Professional Documents
Culture Documents
Gujarat Technological University
Gujarat Technological University
___________
MARKS
Q.1 (a) What are the construction management functions (field functions) during the 03
construction phase of a project?
(b) Draw a CPM (AOA) Network Diagram for following Project Data. 04
Activity IPA Duration (Weeks)
A - 5
B - 7
C - 3
D A 6
E A, B 9
F A, B, C 4
(c) Draw a CPM-AON network for following project data and find out the floats 07
available for all the activities
Activity IPA Duration Activity IPA Duration
(weeks) (weeks)
A - 4 G C, D, E 6
B - 6 H C, F, G 4
C A,B 5 I G 7
D A, B 4 J H, I 3
E A, B 5 K H, I 5
F C, D 3 L J, K 3
Draw the linked bar chart for the project data also.
Q.2 (a) Can the critical path in a project change during the life of the project? How can 03
such a thing happen? Give an example.
(b) Explain the main differences between the standard node diagram and 04
precedence diagrams.
(c) For the following Data, draw a network diagram (AOA) and find out project 07
completion time and critical activities.
Activity IPA Duration (Weeks) Total Cost (Rs)
A - 4 4000
B - 5 20000
C A 3 6000
D A 2 10000
E B, C 6 9000
F D 8 8000
G D, E 3 6000
H F,G 2 10000
OR
1
(c) Draw a network Diagram (AON) for the data given in Q.2 (c) and find out 07
project completion time, critical activities and floats.
Q.3 (a) A multi-story building construction involves 5 major operations (A, B, C, D and 03
E) in series with their duration and respective resource requirement for each
operation are given below. The total number of floors in the building are 10.
Using Line of Balance (LOB) concept, schedule the project. Use a minimum
buffer of 1 weeks between operations.
(c) Draw the network for the following project. Perform the CPM calculations on 07
the basis of the most likely durations. Pick the longest three paths. Calculate the
expected duration and the standard deviation for each path. Considering all three
paths, what is the duration of the project with at least a 90% confidence level?
Fifteen days after the start of the project, the following information is received:
Activity A- Completed 2 days later than planned.
Activity B- Completed on time.
Activity C- Started; 4 days left.
Activity D- Completed. Took 5 days to finish.
Activity E- Completed.
Activity F- Canceled.
Activity G- Started 3 days late. Project manager hopes to cut 1 day of its
duration.
Activity K- Added. Duration = 4 days. IPA = C.
Activity L- Added. Duration = 3 days. IPA = K, G.
Activity I- Adjusted: IPA = L.
Draw the updated network. Calculate the new project completion date. Check
whether any change in the critical path occurred.
Q.5 (a) Explain, why time-cost trade-off is necessary? 03
(b) Discuss various ways to reduce the activity duration. 04
(c) The data regarding the requirements of manpower for the various activities is 07
given in the table below. Carryout the resources allocation levelling for the
project.
3
OR
Q.5 (a) What is cash flow in construction management? 03
(b) What are the benefits for the projects having good cash flow? 04
(c) Activity details of a project is given below. Decide on the priority of the activity 07
for crashing. Justify on your priority list
Activity Normal Crash Normal Cost Crash Cost
Duration Duration
A 4 2 15000 18000
B 6 3 12000 13000
C 5 4 10000 16000
D 8 5 5000 9000
***********************
4
5