Download as pdf or txt
Download as pdf or txt
You are on page 1of 78

DOCUMENT CHANGE RECORD

Revision Date Change Description Author

AA1 28-04-2016 Creation Samir GUERNINE


Document Revision upgraded to major for
AA 12/07/2016 Doc Control
submission to RAMPED
Document Updated to comply with Ramped
Comments and amended Fiber Optic Cables
AB1 29/03/2017 Osama Hajier
Sections for Pulling and Termination. EHS
Section updated completely.
Document Revision upgraded to major for
AB 07/05/2017 Doc Control
submission to RAMPED
AC1 12/10/2017 Updated as per RAMPED comments Wissam OSTA
Document Revision upgraded to major for
AC 22/10/2017 Doc Control
submission to RAMPED

Method Statement for Installation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the file : M3-TSY-MST-POS00-Y20-000041-AC_ Method Statement for Installation of LV,HV and Fiber
Page 2 of 78
Optic Cable Pulling and Termination
Entity Internal Review

Name Function Date Signature

POS L6
Author Wissam OSTA INSTALLATION 12/10/2017
MANAGER

Verification POS
Aissine DJIAR INSTALLATION 12/10/2017
(Sub-system) MANAGER

Verification TSY
Khodor Kurdi CONSTRUCTION 12/10/2017
(OPC) MANAGER

Verification
Yasser Bettache EHS MANAGER 12/10/2017
(HSE)

Verification POS QUALITY


Munir AHMED 12/10/2017
MANAGER
(Quality)

SENIOR POS
Approbation Amel AKHTAR PROJECT 12/10/2017
MANAGER

Method Statement for Installation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the file : M3-TSY-MST-POS00-Y20-000041-AC_ Method Statement for Installation of LV,HV and Fiber
Page 3 of 78
Optic Cable Pulling and Termination
PURPOSE
This method statement is written in compliance of TSY Quality Control Plan and to define the
working methodology to be implemented safely for the installation (Pulling & Termination / Splicing)
of TSY POS LV,HV and Fibe Optic cable.

SCOPE
This method statement covers the installation of LV,HV and Fiber Optic cables in TPS, LPS, ITPS,
PP and along the lines.
The method is applicable for pulling on cable trays, cable ladders or in cable ducts.

USAGE RESPONSIBILITY
TSY POS Installation Manager is responsible for the update of this document as and when required,
in coordination with the respective TSY Technical Team and Manufacturer’s representative.
Issuance and re-issuance of this document is authorized by TSY Project Manager.

It is the responsibility of the user of this document to ensure they are using the latest version of this
document which is available in ACONEX.

Method Statement for Installation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the file : M3-TSY-MST-POS00-Y20-000041-AC_ Method Statement for Installation of LV,HV and Fiber
Page 4 of 78
Optic Cable Pulling and Termination
Table of Contents

1 REFERENCES ................................................................................................ 7
1.1 Referenced Documents .......................................................................... 7
1.2 Applicable documents ............................................................................ 7
1.3 Applicable standards .............................................................................. 7
2 DEFINITION AND ABBREVIATION ............................................................... 7
2.1 Definitions ................................................................................................ 7
2.2 Abbreviations .......................................................................................... 8
3 MACHIINERY, MATERIAL, AND MANPOWER ............................................ 9
4 PERMIT AND LICENSES ............................................................................. 10
5 FLOW CHART – METHODOLOGY OVERVIEW ......................................... 11
6 METHODOLOGY .......................................................................................... 12
6.1 Pre-requisite / Preparation of the works ............................................. 12
6.2 Preparation of the areas for the cable drums handling .................... 12
6.3 Site delivery ........................................................................................... 12
6.4 Handling and Storage of Cable drums ................................................ 13
6.5 Area preparation for installation.......................................................... 15
6.6 Preparation for the Cable pulling ........................................................ 15
6.7 Selection of Cable drum location ........................................................ 16
6.8 Cable drum setup .................................................................................. 16
6.9 Pulling the Cable ................................................................................... 16
6.10 Pulling the MV Cable using Rail Road Vehicle ................................... 16
6.11 MV Cable junction ................................................................................. 19
6.12 Cable End protection ............................................................................ 20
6.13 Cables fastening ................................................................................... 20
6.14 Cables bending radius.......................................................................... 20
6.15 Cables Identifications ........................................................................... 21
6.16 LV Cable and WireTermination ....................................................... 2121
6.17 MV Cable Termination ......................................................................... 35
7 Fibre Optical (FO) Cable ...................................................................... 41
7.1 Material Receiving and Preservation ................................................. 41

Method Statement for Installation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the file : M3-TSY-MST-POS00-Y20-000041-AC_ Method Statement for Installation of LV,HV and Fiber
Page 5 of 78
Optic Cable Pulling and Termination
7.2 Fibre Optic Cable Installation ............................................................. 42
7.3 Detailed Procedure for Splicing & Termination ................................ 44
7.4 Equipment & Tools used for FO cable Installation, Splicing & Termination ..... 49
8 FINAL INSPECTIONS AND INSTALLATION TESTING ....................... 49
8.1 Inspection method ................................................................................ 49
8.2 Testing method ..................................................................................... 50
9 EHS ......................................................................................................... 52
9 Safety ..................................................................................................... 52
9.1 Contingency Plan ................................... Error! Bookmark not defined.53
9.2 Health and Safety Requirements .......... Error! Bookmark not defined.53
9.3 Risk Assessment Alalysis ..................... Error! Bookmark not defined.54
9.4 Safety Management Plan ....................... Error! Bookmark not defined.54
9.4.1 Potential Risks ....................................... Error! Bookmark not defined.55
9.4.2 Job Safety Analysis ............................... Error! Bookmark not defined.55
9.4.3 EHS Equipments .................................................................................. 55
9.4.4 Safety induction / Toolbox talk ............................................................ 55
9.4.5 Emergency Procedure .......................................................................... 55
9.4.6 Noise Control ......................................................................................... 56
9.4.7 Office and Welfare Equipment ............................................................. 56
9.4.8 Air Quality & Dust Control.................................................................... 56
9.5.9 Waste Management Plan ..................................................................... 57
APPENDIX-------------------------------------------------------------------------------57

Method Statement for Installation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the file : M3-TSY-MST-POS00-Y20-000041-AC_ Method Statement for Installation of LV,HV and Fiber
Page 6 of 78
Optic Cable Pulling and Termination
1 REFERENCES
1.1 Referenced Documents

Aconex Reference Document Title


M3-TSY-MPL-SYS00-M50-00017 [R01] TSY Quality Assurance Plan
M3-TSY-MPL-SYS00-M50-000134 [R02] TSY Quality Control Plan
M3-TSY-FOR-SYS00-M50-000130 [R03] Materiel Inspection Report (MIR)
M3-FST-MPL-EFP00-GEN-000002 [R04] Emergency Response Plan

1.2 Applicable documents

Aconex Reference Document Title


M3-TSY-RGR-SYS00-M10-000183 [A01] TSY System Documentation Deliverable Document
List (SDDDL)*
M3-TSY-ITP-POS00-Y20-000009 [A02] Inspection and Test Plan LV or HV Cable Pulling
M3-TSY-QAR-POS00-M50-000014 [A03] Final installation checklist for LV or HV Cable
Pulling
M3-TSY-MPL-SYS00-S10-000192 [A04] TSY Site Logistic Plan
M3-TSY-STD-SYS00-M20-000001 [A05] TSY-Warehouse Procedure
M3-TSY-EDS-POSML-D40-000001 [A06] MV Cable - Supplier Documentation
M3-TSY-STD-POS00-D40-000001 [A07] Mounting Standard
M3-FST-MPL-EEN00-GNE-000008 [A08] Implementation of Environmental Management Plan

1.3 Applicable standards

Reference Description

* All documents related to cable routing, cable lists and Single Line Diagram.

2 DEFINITION AND ABBREVIATION


2.1 Definitions

Expression Definition
A document that details how a particular task or activity will be carried out in
Riyadh Project Site. It details the possible dangers/risks associated with the
project, the control methods to be used and show how the work will be
managed safely.
Method Statement
A method statement is used to specify the health and safety control measures
needed to control the hazards identified by the risk assessment that has been
carried out for the task or operation.
Method statements are always ‘Site Specific’ and are used to control the

Method Statement for Installation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the file : M3-TSY-MST-POS00-Y20-000041-AC_ Method Statement for Installation of LV,HV and Fiber
Page 7 of 78
Optic Cable Pulling and Termination
operation and to ensure that all concerned are aware of the hazards associated
with the work and the safety precautions that need to be taken.
Method statements are also known as a ‘Safe System of Work’.

2.2 Abbreviations

Acronym Description

AFC Approved For Construction

CB Circuit Breaker

CT Current Transformer

EHS Environmental, Health and Safety

FAST FCC, Freyssinet, Atkins, ALSTOM, Samsung, Strukton, Setec & Typsa

ISO International Organization for Standardization

ITP Installation and Test Plan

ITPS Intermediate Traction Power Substation

JSA Job Safety Analysis

LPS Lighting Power Substation

LV Low Voltage

M Meter unit

mA Milli Ampere unit

Mm Milli meter unit

MSDS Material Safety Data Sheet


MV Medium Voltage
OPC Operations, Planning & Coordination (Alstom, part of TSY)
POS POwer supply Subgroup (Alstom, part of TSY)
PPE Personal Protective Equipment
RAMPED Riyadh Advanced Metro Project Execution and Delivery
TPS Traction Power Substation
Iac Alternative Current
Idc Direct Current

VT Voltage Transformer

FO Fiber Optic

Method Statement for Installation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the file : M3-TSY-MST-POS00-Y20-000041-AC_ Method Statement for Installation of LV,HV and Fiber
Page 8 of 78
Optic Cable Pulling and Termination
3 MACHIINERY, MATERIAL, AND MANPOWER
Machinery List
S/No. Description Quantity
N/A Road Rail Truck for MV cable along the line (unilog for example) 1
N/A Portable Drill 3 minimum
N/A Hammer Drill 3 minimum
N/A Splicing Machine 1 minimum
N/A Meghommeter 5KV 3 minimum
N/A Meghommeter 1000V 3 minimum
N/A Multimeter 3 minimum
N/A Hydraulic crimping head up to 400² 2 minimum
N/A Specific crimping tools 6 minimum
N/A Pin type lug Crimping Tool 6 minimum

Material List
S/No. Description Quantity
N/A 3 T drum jacks 4 sets of two
N/A 5 T drum jacks 3 sets of two
N/A Cable cutter (manual or hydraulic) 5
N/A Cable grip as needed*
N/A Cable pulling device 4
N/A Cable winch with single capstan head 2
N/A Captive rollers with hinged guard as needed
N/A Crowbar 2
N/A Drum axles for above as needed
N/A Fire extinguisher 2
N/A Hand tools box (hammer, measuring tape, metal cutting saw, open as needed
end wrench, ratchet wrench, spirit level, …)
N/A Ladders and/or scaffolding as needed*
N/A Length measuring wheel 2
N/A Nylon slings as needed
N/A Offset bolt cutter (wire mesh) 4
N/A Rope as needed
N/A Shackles as needed
N/A Steel cable rollers / Steel corner rollers as needed*
N/A Walkie talkie 2 sets of four
N/A Cable Lugs as needed
* to be studied with cable routing drawings of each site

Material list Notes :


 All lifting equipements (machine and gear) are bearing proper test certificates.
 Tools list is indicative only, all necessary tools shall be available at sites.
 All equipements / tools, subject to periodic calibration, are calibrated. Certificates will be
submitted before utilization and hard copy of certificates are available at site.

Manpower List
S/No. Job Title Quantity

Method Statement for Installation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 02/04/2017
POS00-Y20-000041 Revision : AB1
Name of the file : M3-TSY-MST-POS00-Y20-000041-AB1_ Method Statement for Installation of LV,HV and
Page 9 of 78
Fiber Optic Cable Pulling and Termination
N/A Foreman 1
N/A Team leader 2
N/A Skilled workers 4
N/A Unskilled workers 10
The quantity of workers and number of teams may vary according to the sizes of the works to be
carried out in each work location.

Manpower list Notes :


 Truck and/or crane driver present during handling and safety trained in addition to their valid
certificate.
 Standard Personal Protective Equipment’s (PPE) to be worn at all times.
 All lifting process will be fully commanded by lifting supervisor. Signalman will be performing
the eye to eye hand signal on ground floor.
 All certificates will be submitted before the actual lifting date and provide personal hard copy
at site at all times for any clarification.

4 PERMIT AND LICENSES


Necessary permit shall be obtained and provided by OPC team to the Site supervisor prior to start
of the activity defined in this method statement.
It is Site supervisor / Foreman responsibility to get all permits.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 10 of 78
and Fiber Optic Cable Pulling and Termination
5 FLOW CHART – METHODOLOGY OVERVIEW

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 11 of 78
and Fiber Optic Cable Pulling and Termination
6 METHODOLOGY
6.1 PRE-REQUISITE / PREPARATION OF THE WORKS
 The site should be compliant and inspections should have been carried out in stations and
technical rooms (TPS, LPS, PP and ITPS).
 Access is granted to full cable routing (multitubular, pulling chambers, rooms, ...).
 The cable trays are installed.
 Site access for cables drums delivery.
 Temporary site storage area (drums, jacks, pulling device,..).
 No parallel works in the pulling area. Special attention to potential activity above the area.
 When applicable Traffic Management specific procedure is approved and available on site.
 Installation and cable routing stamped AFC drawings/ documents should be available on site
and kept at easily accessible point.
 Approved Method statement should be available at site kept at easily accessible point.

Note :
Based on reference documents, the Site Supervisor / Foreman will issue a detailed material request
few working days prior expected delivery date (more information in document [A05]).
The list is submitted to the Storekeeper to prepare the shipment for site delivery.

6.2 PREPARATION OF THE AREAS FOR THE CABLE DRUMS HANDLING


 Clearance of area(s) to be used during handling operations.
 Demarcation and protection by means of temporary tape barriers of the area around the
material handling location.

Note :
Standby all needed tools to receive materials.

6.3 SITE DELIVERY


Cables and drums should be checked upon receipt for any type of damage. Deliveries should be
checked, based on the Site Supervisor / Foreman material request. Missing or damaged items
should be re-ordered by the Site Supervisor / Foreman.
The cables should not be unpacked until pulling.

The delivery can be done using the rail / road truck (figure 01), or using traffic road underneath the
viaduct, the drums are then hoisted on the viaduct level using a crane (figure 02).

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 12 of 78
and Fiber Optic Cable Pulling and Termination
Figure 01 – Rail / road drums delivery Figure 02 – Traffic road drums delivery

6.4 HANDLING AND STORAGE OF CABLE DRUMS


To avoid personal injury or damage to the cable and reels, follow guidelines below on handling and
storage of cable upon receipt at the job site.
 Do not allow the reels to drop from the delivery truck during the unloading process (figure 3).
 When a forklift is used, the forks must support both reel flanges (figure 4).

YES
NO

Figure 03 – Drop from truck strictly forbidden Figure 04 – Forks support both reel flanges

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 13 of 78
and Fiber Optic Cable Pulling and Termination
 Reels can be hoisted by lifting on a metal shaft of sufficient size and strength placed through
the center hole of the reel.
 Handling with a crane should be performed with a lifting rod crossing the drum centre, lifted from
both ends by two slings; it must have equal length of rod out of the drum on each side (figure 5).

PROHIBITED GOOD
Figure 05 – It is absolutely prohibited to put the slings on the battens.

YES

 Handling equipment must not come in contact with the cable.


 For short distances and for small or middle-sized sections, reels should only be rolled in the
direction shown (Drum may be marked with a directional arrow and phrase such as "Roll This
Way" to indicate the proper direction to roll it) or in the direction opposite to the direction that the
cable is wrapped on the reel. Rolling drums in the wrong direction can cause the cable to become
loosen on the reel, which may cause problems during cable reeling out in installation.
 Do not allow reels to roll uncontrolled as they may roll into or over objects, damaging the cable or
causing personal injury. When rolling drums down inclines, the incline should be as gradual as
possible and control of the drum must be maintained.
 For safety reasons, the cable drum must be blocked with shims after handling (figure 6).

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 14 of 78
and Fiber Optic Cable Pulling and Termination
Figure 06 – Shims in both or needed side.
A special care must be taken when choosing a location for cable storage. Select an area where the cable
will be protected from falling objects, excessive heat, or chemicals, etc., resulting in potential damage.
Cable drums should be stored on a dry surface. Store the drums on a flat area and avoid any roughness
of the surface likely to damage the battens (refer to manufacturer data sheet for more information [A06]).

Cable drums must be placed in a vertical position and never laid on flange.

6.5 AREA PREPARATION FOR INSTALLATION


Work area should be checked for hazard frees and be corrected if required all along the path.
Internal part of the ducts / trays / ladders must be carefully cleaned before pulling, so that no
pebbles or sharp objects might damage the cables. The cable pits should be free of debris, clean
and dry.
The temporary opening protection should be kept until installation.
The cable ducts / trays / ladders must never be used as a walkway.

6.6 PREPARATION FOR THE CABLE PULLING


 The Site Supervisor should establish that the environmental conditions within the routes and
the installation methods to be used are suitable for the cable to be installed:
 Installation of the cable pulling devices.
 To verify the cable pulling accessories
 Drawings and erection standards to be checked (particularly the drum number allocation with
the cable list)
 Access to the selected stations granted for cable pulling and cleared.
 To check if the cable gutters (covers removed) / ducts and cableways underneath of the
station platform are obstruction free.
 Installation of the cable rollers where required (figure 7).
 Ensure that all necessary guards, protective structures and warning signs are used to
provide a safe and secure working site.

Figure 07 – Type of Cable rollers can be used.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 15 of 78
and Fiber Optic Cable Pulling and Termination
6.7 SELECTION OF CABLE DRUM LOCATION
 Nearest possible to one of the cable ends.
 Place the cable drum(s) in an accessible zone.
 Do not unwind cable near installations in operation.

6.8 CABLE DRUM SETUP


 Use a pair (or more while several cables are pulled in parallel) of appropriates jack stands: they
comprise screw cylinders or hydraulic control horses (figure 8).

Figure 08 – Drum mounted on Jack stand

 The crossbar chosen must withstand the weight of the cable drum (from 3 T to 6 T).
 Lubricate between axis and cylinder when needed.
 Remove protection (wooden battens) very carefully. This must be done near the place where
cable laying is going to be performed. Pull out nails with a nail catcher. Pick nails fallen on
the ground to avoid injuries to persons and vehicle tyre puncture.
 Particular care should be taken regarding the cable insulating sheath protection to avoid
damage.

6.9 PULLING THE CABLE


 Mark the cables with an identification label before installation (retracing and routing at
termination points will be easy).
 The label can be written down on the cable jacket with a suitable pen or marker. Once the
cable is pulled and formed into the panel or outlet the label must be placed at each end.
 Use 2 persons (or more if required) to reel out cables (figure 9):
o 1 person (or more) to pull the cable in.
o 1 person to act as a break on the drum to avoid damaging the cable due to overrun
of the reel.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 16 of 78
and Fiber Optic Cable Pulling and Termination
Figure 09 – Reel out the Cables

Conventional and Mechanised processes:


Generally used for small cables or short length link:
 Arrange men all along the cable path so that the cable shall be carried (it must never be
drawn on the ground).
 A man or suitable rollers shall be placed at each level or direction change.
 These rollers should be properly spaced dependent on the size and weight of the cable to
prevent the cable from sagging and dragging during the pull (figure 10).
 When required (For locations like depots, pulling pits shall be needed at turning points when
the distance between source and the connecting point is more), the cable must be drawn
outside of the cable duct / tray / ladder (figure 11).
 Once the cable is pulled, the cable must be:
o Attached with tie in clover formation.
o Removed from the rollers and laid in the cable tray.
 Do not allow the cables to drop in the cable duct / tray / ladder as this may damage the cable
and/or the cable duct / tray / ladder.
 Special care must be taken at cable first penetration into cable conduits (figure 12).

Figure 10 – Rollers Figure 11 – Cable drawn outside

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 17 of 78
and Fiber Optic Cable Pulling and Termination
Figure 12 – Cable first penetration
Partly mechanised process:
Due to the length of some cable pulls and the cable weight (or conduit pathway) a great deal of
force can be required and a cable-pulling winch with traction force limitation device must be used in
addition to pulling team (refer to manufacturer data sheet for more information [A06]).

A fish-tape is used to pull the winch wire through the conduit. It can be done manually or via
pressurized air method using foam rat or ball attached to a pull string (figure 13).

Step 1- pull the fish-tape

Step 2 – pull the winch wire

Step 3 – cable pulling

Figure 13 – Steps of mechanised pulling process.

When pulling cables: respect minimum bending radius and maximum pulling forces for the cables
(refer to manufacturer data sheet for more information [A06]).

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 18 of 78
and Fiber Optic Cable Pulling and Termination
Cables will require a wire mesh grip and/or pulling eye to be attached to the leading end of the cable
core(s) (figure 11).

Figure 14 – Clamp Pulling Grip & Pulling Eye.

Whenever it is required to pull 3 single cores of HV cables through the same pipe duct, appropriate
clamp pulling grip will be used. All cables will be pulled at the same time.

Where pulling attachments are used on the conductors, cover them with rubber-like or plastic tapes
to prevent scoring of the cable ducts / trays / ladders and installation sheaves during a cable pull.
The reel will generally be placed on reel jacks with an axle of sufficient size and strength to allow
the reel to turn freely with a minimum of friction.
Communications (talkie-walkies or similar) should be established between the pulling end of the run
and the reel end of the run.
The cable should be pulled at a constant speed during the pull.
Note: As per supplier documentation (M3-TSY-EDS-POSML-D40-000001), the cable is
manufactured to hold up to 90 degrees temperature, therefore, it will not be affected by the high
temperature that Riyadh region is usually exposed to in certain times. Moreover, in most of the
times, where the temperature is exceedinig the bareable limit, the external cable pulling activity will
be carried out in the early morning or at night in order to avoid bad temperature effects on the
cables and pulling procedure.

6.10 PULLING THE MV CABLE USING RAIL ROAD VEHICLE


Pulling of MV cables in MV ducts along the track side is carried using a Rail Road Vehicle. Please
refer to Document no. (M3-TSY-MST-POSML-Y10-000001-AA_Method Statement for MV Cable
Pulling using Road Rail Vehicle) for more details.

6.11 MV CABLE JUNCTION


When cable length between 2 substations (or 2 switching devices) is above cable drum maximum
capacity, it will be required to install cable junction box.
Those MV cable links are manufactured with special MV junction kit.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 19 of 78
and Fiber Optic Cable Pulling and Termination
When heat shrink material is necessary to fabricate those junctions, a heating device is required.
When a gas heating device will be used appropriate EHS document will be issued (i.e. hot work
permit, fire permit).
Operation has to be done imperatively by a workers cerfified by the junction kit supplier.
Proposed cable jointers qualifications will be submitted prior to work commencing on site
For Mv, through joints will not be allowed in feeder cables where adequate manufacturer's lengths
are available. Where a joint is necessary, it has to be made inside boxes, handholes or manholes
For Mv, Sample site constructed cable terminations and throughjoints are to be submitted prior to
commencing work on site. Samples are to be constructed in the presence of the Engineer and are
to be available for test and inspection in accordance with manufacturer's recommendation
6.12 CABLE END PROTECTION
During cable pulling, when cables are not properly terminated, cable ends must be protected from
dust or water using provisional end caps.
Plastic end covers are recommended for use both in open air and on underground power
distribution cables with PVC, lead or XLPE sheaths, aluminium or steel armoured. As a result,
plastic end covers on every non-terminated end will be utilized to protect the cable from dust or
water

6.13 CABLES FASTENING


Proper cable clamping should be done with nonmagnetic collars, non-metallic straps or plastic
collars on all length of cable trays according to mounting standard. Distances between clamps will
be as the below figure:

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 20 of 78
and Fiber Optic Cable Pulling and Termination
6.14 CABLES BENDING RADIUS
The maximum permissible bending radius for any cable shall not exceed the value mentioned in the
supplier data sheet and recommendation. Below is an example of the maximum bending radius for
2 types of cables. For all the other cable, please check the respective data sheet for each.

- 1.4m for MV cable 1×300 Cu/XLPE/CW/LSHF-FR


- 1.2m for MV cable 1×150 Cu/XLPE/CW/LSHF-FR
- 1.17m for MV cable 1×120 Cu/XLPE/CW/LSHF-FR

6.15 CABLES IDENTIFICATIONS


Cable labels must be installed at each end according to approved "cable marking principle" and as
per the specification 16050
Nevertheless, a provisory label could be installed at this stage of the work; definitive labels being
installed when the connections are made.
Tags should be provided to identify cable or circuit number and conductor size in accordance with
the Schedules

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 21 of 78
and Fiber Optic Cable Pulling and Termination
6.16 LV CABLES & WIRES TERMINATION
Definitions:
Crimping is joining two pieces of metal (special connector) or other ductile material (usually a wire
and a metal plate) by deforming one or both of them to hold the other. The bend or deformity is
called the crimp.

Crimping is done under special a process, which results cannot be directly checked by a
nondestructive test, after its achievement. The consequences of a special Process application
failure will appear during the product life.

Crimping quality can and must be checked visually after the crimping process.

Certification of tool (prior to the crimping) is also part of the quality test.

Crimping Key Elements:


1) Wire/Cable (Conductor)

2) Terminal (Contact)

3) Crimping tools

4) Other accessories

List of Material Tools:

The material, tools and other accessories required related to Crimping process is as listed
in table below:

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 22 of 78
and Fiber Optic Cable Pulling and Termination
Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 23 of 78
and Fiber Optic Cable Pulling and Termination
Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 24 of 78
and Fiber Optic Cable Pulling and Termination
Description of Tools:

Cutting Tools
Hand Cutter:

The use of hand strippers is a common method for wire preparation for low volumes or field repairs.
Select the suitable cutter according to the wire/cable type (copper or aluminum, solid or stranded,
etc.) and section.

Most common hand strippers are:

Stripping Tools
Hand Strippers, or Operator Assisted Semi-Automatic/Automatic Strippers are used to remove
insulation from the ends of the wire.

Hand Strippers

The use of hand strippers is a common method for wire preparation for low volumes or field repairs.

Many of the mechanical strippers used in wire preparation have sharp edges and should be
handled‎carefully.‎In‎addition,‎it’s‎important‎to‎avoid‎contact with the heating element of thermal strippers.

Most common hand strippers are following described.

1- Round Wire Stripper


This is a triple action tool, cutting longitudinally for end stripping, spiral for end stripping and
midspan cuts, and circular for jacket removal

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 25 of 78
and Fiber Optic Cable Pulling and Termination
2- Manual Wire Strippers
The wire is placed in the correct diameter hole at the specified strip length. The handles of the tool
are then closed and the insulation is stripped by pulling the wire and the tool apart.

3- Automatic Wire Strippers


They‎‎require ‎no‎“cocking”‎or‎‎setting.‎Its‎‎triple‎‎action ‎of ‎clamping the wire, cutting the insulation, and
stripping it, is automatically timed and performed with one squeeze on the handles. Length of strip is
regulated by amount of wire extending beyond the blades. Wire size is shown beneath each
stripping hole. After the stripping action, a partial release of pressure on the handles opens jaws
and wire is removed. Full release of pressure returns the tool to the starting position, ready for next
strip.

Crimping Tools
 Manual crimping tools (hand crimpers) are generally used to crimp small quantities of
terminals
 Manual crimping tools are intended for low volumes or field repairs. These tools are not
intended for production use. The repetitive use of these tools should be avoided.
 Manual crimping tools may have dies that are part of the tool, or dies that are
interchangeable. It important to select the proper crimper and proper die for a given job.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 26 of 78
and Fiber Optic Cable Pulling and Termination
 Choose the correct crimper opening for the gauge of wire to be crimped. Manual crimpers
should be calibrated at regular intervals. These tools are usually calibrated using gauge pins
to measure the distance between the crimping heads or indenters (depending on the type of
tool being calibrated). Make sure the crimping tool in use has a calibration sticker

Hydraulic Crimping Tool for LV cables

TERMINALS & CONTACTS:

General Description:

Terminals are designed to connect a cable or wire to a screw or mating termination. The most
common types include ring, pin, blade, male/female, spade, etc.

Procedure:
1- Cable Preparation:
This section provides requirements and acceptance criteria for preparation of cables and wires.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 27 of 78
and Fiber Optic Cable Pulling and Termination
 To avoid damaging the conductor during stripping, the blades of the stripping tools should be
adapted according to the conductor diameter and the thickness of insulation.
 Stripping faults are often caused by inappropriate handling, incorrect adjustment of the
stripping tool, damaged stripping blades of the stripping tool.
 Strand damage can lead to degraded performance. The number of damaged (scraped,
nicked or severed) strands in a single wire shall not exceed the limits of the below Table:
Allowable Strand Damage.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 28 of 78
and Fiber Optic Cable Pulling and Termination
2- Cable Stripping
Stripping (a wire/cable) consists of removing a portion of the wire jacket, without damaging the
underlying conductor or the rest of the insulation.

The strip length is determined by measuring the exposed conductor strands after the insulation is
removed. The strip length determines the conductor brush length when the insulation position is
centered.

One ‎strip‎‎length‎‎doesn’t ‎fit ‎all‎‎terminals ‎and‎‎contacts. Strip length is important because it provides a
good conductor and insulation fit to the terminal. A good strip also offers strain relief for vibration
protection in the field.

Follow the Table of Primary tools required for Crimping for using stripper for appropriate diameter of
wire/cable.

For proper crimping, follow the instructions regarding stripping length. Terminal specification sheets
so that the terminal is properly applied to the wire/cable

Example of instructions for stripping length

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 29 of 78
and Fiber Optic Cable Pulling and Termination
Differentiate terminal crimp barrel length

After crimping: The conductor (strands) should be visible between the crimp barrel and the insulation grip.

Figure shown crimping

The end of the crimped conductor should protrude out of the front end of the crimp barrel. The
mating or termination area shall not be hindered.

End of the crimping

3- Cable Crimping
For manual crimping operations prior to wire/cable insertion, the operator shall examine the
crimp contacts. Contacts that show the following conditions shall not be used:

 Cracks in the plating or base metal.


 Cracks in the insulating material (only for pre/fully-insulated terminals).
 Tarnishing or discoloration of the plating.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 30 of 78
and Fiber Optic Cable Pulling and Termination
Plating removal or flaking.
Out-of-roundness of the wire well entrance.
Exposed base metal.
Cumulative trauma disorders can result from the prolonged use of manually powered
hand tools. Hand tools are intended for occasional use and low volume applications. A
wide selection of powered application equipment for extended-use, production
operations is available
For Insulated closed Barrel Terminals, the following general crimping tool is utilized:

A general crimping tool for close barrel terminal details

STEPS:
1- Strip the wire according to the dimension provided in the manufacturer datasheet being
careful to avoid nicking or cutting the conductor(s).

2- Open the tool jaws by closing the tool handles until the ratchet releases, and then allow the
handles to open fully.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 31 of 78
and Fiber Optic Cable Pulling and Termination
3- Place the terminal in the jaws holding the wire barrel in place between indenter and nest
and against the stop (see figure below).
4- Close the tool handles until the product is held firmly in place. DO NOT deform the wire
barrel.
5- Insert properly stripped wire(s)/cable into the wire barrel until its tops (see figure below).

6- Complete the crimp by closing the tool handles until the ratchet releases.
7- Release the tool handles, allow the handles to open fully, and remove the crimped product.
8- Remove the crimped terminal from the tool and check it
Each tool has three insulation adjustment positions to adjust the wire insulation grip: 1-Small, 2-
Medium, and 3-Large. To determine the proper insulation crimp setting, proceed as follows:

 Insert the adjustment pin into Position 3.


 Position the receptacle into the jaws as described.
 Insert an UNSTRIPPED wire into just the insulation barrel of the receptacle. Crimp the
receptacle and remove it from the jaws.
 Check the insulation support by bending the wire back and forth once. The insulation barrel
should retain grip on the wire insulation. If the wire pulls out, move the insulation adjustment
pin to the next smaller position (2) and perform another test crimp. If the wire does not
pullout, the pins are properly adjusted.
Move the insulation adjustment pin as necessary until the desired insulation grip is obtained. The
crimp should hold the wire insulation firmly without cutting into it.

For uninsulated closed lugs, the following hydraulic crimping tool is utilized:

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 32 of 78
and Fiber Optic Cable Pulling and Termination
This hydraulic hand tool has a stationary lever and a movable lever. These levers are compressed
to pump hydraulic fluid behind the ram, moving it forward and thereby closing the dies. After the
crimping is complete, the movable lever is turned to depress the plunger. The moving die retracts to
its original position, completing the crimping cycle

STEPS:
1- Press head latch and open crimping head.
2- Pull back the die latch and turn thumb knob until desired die size appears. (Embossed wire
size appears on side of each die position.).
3- Rotate thumb knob left or right until die latch locks die wheel in desired position.
4- Close head.

5- Strip wires as per manufacturer datasheet.


6- Insert terminal or splice in upper die.
7- Pump movable lever until moving (lower) die grips terminal or splice.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 33 of 78
and Fiber Optic Cable Pulling and Termination
8- Insert stripped wire into wire barrel of terminal or splice.
9- Continue pumping moveable lever. A slight click may be heard, indicating the pump has
shifted into the high-pressure stage. Continue pumping moveable lever. When dies have
bottomed,‎an‎audible‎“pop”‎will‎be‎heard.‎This‎indicates‎that‎the‎crimp‎is‎complete.‎
10- Retract movable die by turning movable handle (to actuate striker), compress levers to
depress plunger. Movable die will now retract.
11- Remove crimped terminal or splice.

12- Inspect crimp for the following criteria:


 Centering of crimp (crimp may be off center but not off end of wire barrel).
 Wire size being used matches wire range stamped on die position and terminal.
 End of wire is flush with or extends slightly beyond end of wire barrel.
 There are no nicked or missing strands.

A figure shown crimping procedure

General Note: Tighten electrical connectors and terminals including screws and bolts, in accordance
with manufacturers published torque-tightening values

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 34 of 78
and Fiber Optic Cable Pulling and Termination
6.17 MV CABLES TERMINATION

MV cable termination procedure requires a very qualified, trained, and certified technician. Below
is a step by step procedure for MV cable terminations:
 Cable cut lengths should be sufficient to terminate cable in the panel however avoid
unnecessary long cuts.
 Prepare adequate holes in the gland plats, Gland the cables taking care the grounding
connection.
 Cable termination shall be done by certified terminator according to termination type
recommended procedure. As there is Plug In Type Termination, so the cables will be
terminated as per the Supplier (3M) recommended procedure for which the steps are as
under:
 Align cable and fix with clamp observing smallest admissible bending radius (15 x outer
diameter of cable
 Cut off cable rectangular with a saw if possible and do not damage insulation screen when
removing conductive tape
 Use cleaning solvents for cleaning the cable the core insulation can usually be cleaned by
means of dry cleaning cloths.
 Check while fixing the cable below the bushing it has to be observed that the cable runs
along the axis of the bushing after completed installation of the termination
 Cut back outer sheath by measure “A“ observing to leave sufficiently long screen wires (see
figure). Cut off tape wrapping and counter helix at the end of the outer sheath.
A = L; min. 203 mm
 Clean outer sheath and apply 1st layer of sealing tape. Bend back screen wires and press
them into the sealing tape all along the circumference. Apply 2nd layer of sealing tape onto
the screen wires and press it against screen wires
 Cut-back conductive tape at the end of outer sheath.
 Remove fix-bonded insulation screen up to 20 –25 mm from the end of outer sheath with a
round stripping tool.
 If remainders of the insulation screen are still existing, then remove carefully with attached
emery cloth without leaving any residues
 Check the transition from the insulation screen to the surface of the stripped core is even
and smooth.
 Cut off core 203 mm before end of outer sheath.
 Cut back core insulation by 85 mm and slightly chamfer edge of insulation. Wrap end of
conductor with self- adhesive plastic tape and clean core insulation
 Check correct position of pressure disc and pressure spring according to the manufacturer
recommendation and push fixing flange over cable.
 Grease core insulation and bottom area of insulator boring with installation paste and push
over insulator up to the shoulder. Remove self-adhesive plastic tape.
 Push stop disc and cone clamp onto compression sleeve. Check contact ring with regard to
correct position of laminated contact and push onto cone clamp.
 Fix cone clamp and contact ring by 2 or 3 hammer blows on the attached impact device

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 35 of 78
and Fiber Optic Cable Pulling and Termination
 Turn knurled adjusting ring of the hand-operated compression tool to the left as far as
possible with the tool levers open. Place corresponding compression piece onto spindle and
suspend halves onto the tool.
 Open halves, suspend behind stop disc and seal with fixing ring while observing that the
silicone body is not stuck between the halves.
 Turn knurled adjusting ring of the compression tool to the right as far as possible with the
tool levers open.
 Press contact ring onto cone clamp. Remove hand-operated compression tool.
 Push insulator toward the stop disc up to the shoulder.
 Clean bushing and insulator. Grease bushing and insula- tor thin and evenly with installation
paste.
 Plug cable connection into bushing up to the shoulder. Fix cable with clamp after correct
installation of cable connection.
 Check pressure disc and pressure spring with regard to correct position. Push up fixing
flange, press on and fix with screws.
 Collect screen wires and cut to length. Compress cable lug and screw on.
 Fix Cable tag.
 Connect the ground connections.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 36 of 78
and Fiber Optic Cable Pulling and Termination
Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 37 of 78
and Fiber Optic Cable Pulling and Termination
Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 38 of 78
and Fiber Optic Cable Pulling and Termination
Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 39 of 78
and Fiber Optic Cable Pulling and Termination
Termination on GIS:

This kind of equipment is a compact multicomponent assembly, enclosed in a ground metallic


housing where bus bars, circuit breakers, isolators and instrument transformers are installed ,
having as primary insulation medium a compressed gas – sulfur hexafluoride (SF6) – that assure
the phase to ground insulation.

GIS are provided with cable termination enclosures where cable terminations will be installed.

Main features of GIS cable terminations are:

 Cable lug
 Box body
 Reliable support insulator – High grade, non-tracking, epoxy insulators provide excellent
mechanical and electrical characteristics. The insulators are compatible with SF6 gas by-
products, ensuring long life of the termination. Design of the insulators also allows for an
optional cable shield break.
 Filling compound
 Stress control cone with bundle tape.
 Rigid cable support – The connector is locked in position by a threaded hood at the top of
the support insulator. Electrical connection between the GIS and termination should not be
subjected to the mechanical forces from the cable.
 Positive sealing system – A double “O” ring sealing system is used to seal between the
termination oil compartment and the GIS SF6 compartment. Fully retained gaskets are
compressed to seal the interior of the termination from the atmosphere.
 Earthing clamp.

The below figure shows a scheme of GIS cable termination:

GIS cable termination scheme

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 40 of 78
and Fiber Optic Cable Pulling and Termination
Proper tools and accessories are required for termination for GIS installation:

 Panduit pliers – for installation of bundle tape around stress cone.


 Circlip pliers – for installation of top fitting.
 Adapter flange.
 Top fitting removal kit.
 Re-assembly kit
 Earthing kit.
 Screen connection

7 FIBER OPTICAL(FO) CABLE


7.1 Material Receiving and Preservation:
The quality inspector shall inspect all fiber optic cable and cable accessories to be installed during
receiving at warehouse in accordance with purchase orders, company and project requirements,
additionally shall ensure the proper preservation of them as follow:

 All Incoming material shall be visually inspected for damage and project specification non-
conformance
 The cable drums shall be stored on a flat and firm surface
 When placing drums on uneven or sloping ground, take necessary precaution against
rolling. Ensure appropriate stopping devices (like scotch blocks) are available
 Cable drums shall not be stacked on top of each other
 Always check the weight of the drum to ensure the lifting device has the required capacity
 Always lower the drums gently onto the ground or transport tray. Never drop drums. Avoid
impact, which may damage the drums
 The drums shall be restrained from rolling on or off the truck. This shall be ensured by
placing wooden wedges or similar blocks under them on either sides of the point of contact
 Accessories include Fiber Optic connector and terminal kits, FO cutting and splicing
equipment, FO cable straps and ties, FO cable testing equipment, etc..
 The manufacturer's storage, handling and preservation instructions to be followed.
 All empty drums shall be removed from the site as and when they become empty
and returned to store for disposal
 Cable reels shall be stored away from open flame, fire, arc welding, brazing, grinding and
other sources of high heat or ignition.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 41 of 78
and Fiber Optic Cable Pulling and Termination
7.2 Fibre Optic Cable Installation:
Prior starting the installation, testing, termination and splicing activities, the following verifications
shall be conducted to ensure the compliance of project requirements in accordance with
applicable Inspection and Test Plans:

 Ensure that all drawings/documents are latest revision and available prior to commencement
of any work.
 Verify and mark the location of cable on each cable tray/containment where the FO cables
will be installed. Cable number should mark as per the latest cable routing plan and cable
list details.
 Check materials for damage before transporting to the work area. All materials of doubtful
condition or quality shall be immediately segregated from the job site.
 Ensure that all materials and tools/equipment needed to complete the work are available at
work areas.
 Quality Control inspector shall inspect the materials prior installation – fiber optic
system materials shall conform to all applicable requirements, standards, and specifications
prior to release to be used as part of the work

During Installation and cable pulling, the following precautions shall be carried out:

 It needs to be handled appropriately to ensure the long-term life of the cable.


 The Mechanical cable pulling which shall be well calibrated and the pulling tension
shall be strictly observed as per the cable manufacturer’s recommendations.
 The cable shall not be dragged along the ground or trench as this may cause abrasion and
damage to the outer sheath and may result in kinks in the cable, if it gets stuck in debris,
rock or similar.
 Always ensure that there are enough people available to hold the cable so that it does not
drag along the ground.
 No traffic of whatever nature shall be permitted to cross over the cables.
 No construction plant, trucks or even light vehicles shall be allowed to drive over the cable.
 Personnel shall not be permitted to step on the cables.
 When the cable is being uncoiled, care shall be taken to ensure that the coils left on the
drum do not cross over one another.
 Cutting of Fiber Optic cable for splicing is normally not allowed.
 Where it is absolutely necessary to cut the cable at terminations, both ends of the cut cables
shall be sealed with temporary insulation tapes in order to keep moisture and dirt away from
the fibers and prevent the filling compound escaping.
 Jacks and spindle shall be used for cable installation.
 The spindle must be equipped with two cones and two collars. The cones are
pushed into the space between the spindle hole and the spindle, and the collars
which have locking screws, keep the cones in place. This arrangement prevents the
drum from sliding along the spindle.
 Decide whether the cable can be pulled in one stage or more than one stage

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 42 of 78
and Fiber Optic Cable Pulling and Termination
 Cable drum set-up location and the direction of pulling are decided and the drum is either
loaded in drum frame and spindle or in Cable Jacks & spindle.
 The cable jacks shall be on level and firm surface and restrained from moving while
the cable is being pulled.
 The drum should be rotated in the direction of the arrow indicated on the drum flange.
 At least 300 mm clearance shall be maintained between the bottom of the cable drum and
the ground surface during cable pulling.
 The cable should leave the drum from top
 At the pulling end of the cable, a quick break swivel configured for the pulling tension as
recommended by the cable manufacturer shall be attached which will break in case
of pulling tensile load of the cable exceeds.
 This swivel also helps in preventing the twisting of the cable during cable pulling
 Cutting the cable to facilitate convenient cable installation is not allowed. Cutting of cable will
introduce additional joints, which will lead to increase of Link Loss
 Flag signals (Red & Green) may be used for stopping and starting the cable pulling
operations.
 The pulling tension should be uniform throughout and jerking the cable while pulling should
be avoided
 An up to date cable drum traceability record will be kept to identify where each drum
length has been installed

Note: During FO cable pulling, the bending radius limitation will be taken in consideration as the
following:
The curve radius shall be greater than 10 times the outer diameter of the cable (say for outer
diameter 50mm then curve radius must be greater than 500mm). Make sure that while the cable
bends in curves/track crossings, the total surface of the cable should be rested on the
ground properly.

The optical fibre cable conduit shall comply with internal diameter 20 and external 25 minimum
bending radius 140 mm

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 43 of 78
and Fiber Optic Cable Pulling and Termination
7.3 DETAILED PROCEDURE FOR SPLICING AND TERMINATION
A splice may be considered as two or more conductors joined with a suitable connector,
reinsulated, reshielded and rejacketed with compatible materials. applied over a properly
prepared surface. There are two methods of fiber optic splicing, fusion splicing & mechanical
splicing, Fusion Splicing will be used.
 Fusion splicing: Fusion splicing is the process of fusing or welding two fibers together
usually by an electric arc. Fusion splicing is the most widely used method of splicing as it
provides for the lowest loss and least reflectance, as well as providing the strongest and
most reliable joint between two fibers.
 Mechanical splicing: A mechanical splice is a junction of two or more optical fibers that are
aligned and held in place by a self-contained assembly (usually the size of a large
carpenter's nail). The fibers are not permanently joined, just precisely held together so that
light can pass from one to another

When splicing the fibers optic cables, verify the followings:

 The installation site must be kept dry and clean for the entire duration of the splicing
operation
 The splicer is following the manufacturer's instruction for the splicing equipment being used.
 The splicer is using an approved buffer stripper.
 The fiber coating stripper used shall be approved for the specific size fiber being stripped.
 Verify that Splicing equipment is approved fusion splicing equipment
 To minimize damage to the bare fibre, avoid excessive wiping (more than five times). Before
cleaving, wipe the fibre twice with a new tissue dampened with 90% grade alcohol to remove
any coating debris from the stripped fiber.
 Verify that only appropriate cleaving tool is being used to cleave the fibre. Hand scribes shall
not be used for cleaving.
 Verify that dispose of bare fibre is being properly handled by using the sticky side of a piece
of tape to pick up and discard any loose ends in a container. Scrap pieces of fibre shall be
cleaned up from the work site and properly discarded before leaving a work site.
 Handle unprotected glass fibers carefully to avoid introducing flaws such as scratched or
broken fibers.

The Fiber Optic Cable need to be spliced as per the following steps:

METHOD FOR STRIPPING

• Strip fiber cable jacket. Strip back about 3 meters of fiber cable jacket to expose the fiber loose
tubes or tight buffered fibers.

• Use cable rip cord to cut through the fiber jacket.

• Then carefully peel back the jacket and expose the insides.

• Cut off the excess jacket.

• Clean off all cable gel with cable gel remover.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 44 of 78
and Fiber Optic Cable Pulling and Termination
• Separate the fiber loose tubes and buffers by carefully cutting away any yarn or sheath.

• Leave enough of the strength member to properly secure the cable in the splice enclose.

• Strip fiber tubes. For a loose tube fiber cable, strip away about 2 meters of fiber tube using a
buffer tube stripper and expose the individual fibers.

• Clean cable gel. Carefully clean all fibers in the loose tube of any filling gel with cable gel
remover.

• Secure cable tubes. Secure the end of the loose tube to the splice tray and lay out cleaned and
separated fibers on the table. Strip and clean the other cable tube’s fiber that is to be spliced, and
secure to the splice tray.

• Strip first splicing fiber. Hold the first splicing fiber and remove the 250µm fiber coating to expose
5cm of 125um bare fiber cladding with fiber coating stripper tool. For tight buffered fibers, remove
5cm of 900µm tight buffer first with a buffer stripping tool, and then remove the 5cm of 250µm
coating.

• Place the fusion splice protection sleeve. Put a fusion splice protection sleeve onto the fiber being
spliced.

• Clean the bare fiber. Carefully clean the stripped bare fiber with lint-free wipes soaked in isopropyl
alcohol.

• After cleaning, prevent the fiber from touching anything

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 45 of 78
and Fiber Optic Cable Pulling and Termination
CLEAVING

• With a high precision fiber cleaver, cleave the fiber to a specified length according to your fusion
splicer’s manual.

• Prepare second fiber being spliced. Strip, clean and cleave the other fiber to be spliced.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 46 of 78
and Fiber Optic Cable Pulling and Termination
FUSION SPLICING

Some of the general steps with full automatic microprocessor control splicing machines shall

be as under:

• Hands shall be thoroughly washed prior to commencing this procedure.

• The clean bare fibre shall be dipped in the beaker of ethyl alcohol of the ultrasonic cleaver and
ultrasonic clever switched on for 5-10 seconds.

• The bare fibre shall then be placed inside ‘V’ groove of the splicing machine by opening clamp
handle, in such a way so that 1 mm gap is available between the electrodes and the end of fibre
being spliced and heat shrink protector inserted.

• The same procedure shall be repeated for other fibre.

• The start button on the splice controller shall be pressed.

• The machine shall pre-fuse set align both in ‘X’ and ‘Y’ direction and then finally fuse the fibre.

• The splice shall be inspected on monitor provide on the fusion splicing machine, there shall be no
nicking; bulging and cores are adequately aligned. The above procedure shall be repeated if the
splice is not visually good looking.

• The heat shrink protector shall be slid over the splice and tube shall be placed in tube heater.
Heating shall be considered complete when soft inner layer is seen to be ‘oozing’ out of the outer
layer of the protector.

• The above steps shall be repeated for other fibres.

• Place splice into splice tray. Carefully place the finished splice into the splice tray and loop excess
fiber around its guides. Ensure that the fiber’s minimum bending radius is not compromised

For termination, carefully insert the bare fiber into the connector until it meets the preloaded fiber
stub

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 47 of 78
and Fiber Optic Cable Pulling and Termination
Cable Mode Numer of Cores Core Connectors
Type Type Diameter

Single Single 4 9/125 None


loose Mode (micron) -
tube standard OS1

Duplex Multi-mode 2 62,5/125 1 duplex SC in both


Zip Cord (micron) –
sides
(Type 1) standard
OM1

Duplex Single 2 9/125 2 simplex SC in one


Zip Cord Mode (micron) -
side,
standard OS1
(Type 2)
2 simplex ST in the
other side

Duplex Single 2 9/125 2 simplex SC in one


Zip Cord Mode (micron) -
side,
standard OS1
(Type 3)
1 duplex SC in the
other side

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 48 of 78
and Fiber Optic Cable Pulling and Termination
7.4 Equipment & Tools used for FO cables installation, splicing and terminations:

 Hand Gloves
 Safety Goggles
 Dust Mask & Cap.
 Air Blower.
 Optical Time Domain Reflect meter with built in Power Meter.
 Optical Power Laser Source.
 Single Mode Patch Cords.
 Splicing Machine
 Stripping Tool
 Cleaving Tool
 fiber adapter
 FOC Technicians tool kit
 Quick Break Swivels
 Cable socks (pulling sleeve)
 Cable rollers.
 FOC Drum Jack & spindle.
 Fusion splicing machines shall be kept in proper working condition. Regular
maintenance in accordance with the machine manufacturer’s

8 FINAL INSPECTIONS AND INSTALLATION TESTING


8.1 INSPECTION METHOD
During cable pulling process, special care will be taken to avoid any damage to the outer sheet.
Random visible checks are conducted along the entire length. Any physical damage to the outer
sheet will be immediately reported by any member of the pulling team to the cable pulling
supervisor.
The damaged severity will be analysed and appropriated action will be taken accordingly.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 49 of 78
and Fiber Optic Cable Pulling and Termination
Site Inspection will be conducted as part of Power Supply Site Quality Plan, in order to ensure that
cables are properly installed according to relevant Method Statement and Technical specification.

8.2 TESTING METHOD


Continuity and insulation checks will be performed on the cables before connections.
A record sheet is filled and submitted to the Supervisor (confer to the ITP [A02]).
The following values will be the acceptance criteria for cable testing:

S/N Cable Type Acceptance Criteria

1 MV Cables 5000V < 10 MOHM

2 LV / PTR / NTR Cables 1000V < 1 MOHM

3 Control Cables 500V < 1 MOHM

Note: HI-POT test will be carried out for MV cables as per approved documents (M3-TSY-PRO-
POSML-T20-022031) MV cable – SAT Procedure.
Note: As per supplier recommendation and in orde to avoid any damage to the cables, Hi-pot test
will be carried out only one time before preparation for energizing and after termination.

Fiber Optic cables testing:


Splice loss measurements shall be made between the end terminal points both at 850 & 1300 nm
for backbone multimode fibers and 1310 & 1550nm for backbone single mode fibers. The overall
link loss (dB) and optical length for each fiber are directly obtained from the OTDR Trace.

OTDR Testing: OTDR – Optical Time Domain Reflectometer, is a device that can identify
performance-inhibiting factors like bad or dirty connections, plots the backscattered signal power as
a function of distance withen the fiber. It easily locates all events (bend, bad splices, etc.) that
contribute to the overall loss and calculates the overall reflectance level. In addition, the OTDR
accurately measures the fibers length, so cuts or misrouted connections can be found.
Note: Piror to the FOC cable pulling, pre-installation tests will be conducted without fail and
post instalaltion test will be done after pulling.

Steps:

 Connect one end of the cord to the launching port of the OTDR and the other end to the
terminal number 1 at the ODF in terminal station A.
 Turn on the OTDR and leave it for some time for stabilization.
 Follow the instruction manual to operate the OTDR
 Acquisition parameters are generally selected by the OTDR in the auto configuration
mode.
 Set the wavelength at 850nm.
 Press the start button and wait for averaging and display of the final trace.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 50 of 78
and Fiber Optic Cable Pulling and Termination
 The trace gives an indication of the splice distances and its losses from the measuring end
terminal A in this case
 Slope of the trace gives an indication of the attenuation of the fiber. The horizontal
scale is a measure of the power loss in dB.
 Change the range and/or pulse width manually if required and repeat the test in order
to get a clear and smooth trace. Save the trace.
 Set the wavelength at 1300nm and repeat the measurement and save the trace.
 The test is repeated for all the fibers in the cable from terminal A
 The same test is repeated from terminal B.
 The test is repeated for 1310 and 1550 nm for single mode fiber
 The average of the test results is calculated and recorded in the relevant test format.
 These results shall be compared with link loss budget. If any abnormal deviations are
found, the cable shall be re-spliced.
 Record the data from the trace to the approved data sheet and calculate the splice losses.

Acceptance Criteria:

The splice losses for individual splices in the cable shall not exceed the limit specified in the
applicable specifications

The length of the fibers indicated in the OTDR trace shall be slightly more than the physical
length of the cable due to helix factoring. The overall link loss indicated in the OTDR trace should
not be taken as the insertion loss of the link. It gives only approximate loss and does not reflect the
actual loss in the working condition. The OTDR trace indicates the distribution of losses
among various segments in the optical path for further analysis.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 51 of 78
and Fiber Optic Cable Pulling and Termination
EHS
9 SAFETY
- Site safety shall refer to the FAST HSE PLAN.
- For this activity, hazard identification and risk assessment procedures should be carried out
for the fixing activities, in order to develop, implement and maintain control measures.
- Risks being identified are:
Task Reference Risks

Lifting of equipment EHS Plan People can be hit and injured by


moving parts of machinery or
dropped or ejected material. Parts of
the body can also be drawn in or
trapped between rollers, belts,
chains and pulley drives.
Sharp edges can cause cuts and
severing injuries, sharp-pointed
parts can stab or puncture the skin,
and rough surface parts can cause
friction or abrasion.
People can be crushed both
between parts moving together or
towards a fixed part of the machine,
wall or other object, and two parts
moving past one another can cause
shearing.
Parts of the machine, materials and
emissions (such as steam or water)
can be hot or cold enough to cause
burns or scalds and electricity can
cause electrical shock and burns.
Equipment or attachments can
become unreliable and develop
faults due to poor or no
maintenance, or machines may be
used improperly through
inexperience or lack of training.
Parts of the equipment may fail and
loads may drop.

Working inside construction EHS Plan Tripping, falling objects etc


site

Works at the Scaffolding EHS Plan Falling from height


Platform

Work with Machinery EHS Plan Electric Shock, Injury


Table 1: Risk identifications in Tasks involved

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 52 of 78
and Fiber Optic Cable Pulling and Termination
9.1 Contingency Plan
For any unforeseen situations or uncertainties which leads to unsafe situation, then the Person-in-
charge should consider the followings:
- Stop work and remove all tools and materials from location
- Report to Engineers, Installation Manager or HSE officers or raise any concern during
meeting etc.

9.2 Health and Safety Requirements


TSY shall ensure the provision of the following HS&E requirements but may not limited to;

 Comply with FAST HSE Plan latest approved copy


 Comply with all Safe Work Procedures of FAST
 Comply and implement all required HSE forms and checklists of FAST
 Safety Induction, TBTs, Job Specific Trainings etc
 Job Specific Risk Assessment
 PPE Mandatory and Job Specific
 Safety Signage
 Safety Coverage by Alstom
 Competent Persons
o Training
o Knowledge, experience, Certification etc
 Emergency Procedures ( refer to SWP-20)
o Fire safety i.e Fire Extinguishers for Type A, B and C fires
o First Aid and Medical Facilities
o Emergency Contact Number i.e 051 510 1411
o Welfare Facilities (as per FAST HSE Plan and SWPs)
 Fork Lift Truck Safety (FLT)
o Certified Operator
o FLT 3rd Party Certified
o Flag Man
o Beacon Lights fixed
o Reverse Beep Alarm
o SWL posted on FLT
o Daily checklist filled by Operator

 Lifting Operations (as per SWP-14 & 15)


o Maximum Weight and associated Lifting Plans, SWPs to use etc
o Crane and Lifting Gears certified by 3rd party…
o Lifting lugs/points tested for lifting empty Silos or full???? Shall be mentioned clearly.
o Area barricading/exclusion zones while lifting, signages, etc

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 53 of 78
and Fiber Optic Cable Pulling and Termination
o Operator, Riggers , Slinger qualified….
o Daily Inspection Checklists and Lifting Plans in place
 Work At Height
o PPE, Harness, double lane yard with shock absorber, Life Lines etc
o Scaffold, Guard Rails, Toe boards, Platform etc, OSHA Standards…..
o Access ladder complying OSHA
o MEWPs, Scissor Lifts if required
o Harnesses etc…
 Electrical Safety (as per FAST SWP-07 & FAST HSE Plan)
o Competent person
o Use of quality electrical cables, socket, plugs, switches etc.
o Color coding of electrical cables, tools etc.
o Grounding of Plant etc.
o Lightning Protection (if required)
o GFCI/ ELCBs
o PPE Job specific
o Lock-Out Tag-Out System
 Plant, Tools and Equipment Safety- (as per SWP-09)
 Lock-Out/Tag-Out ---explain and (as per SWP-16)
o Power shall be disconnected while working on Electric systems using electrical work
permit
o De-Energizing and Lock-Out procedures in place
 Material Storage
 Waste Management and Environmental Safety (as per Environmental Plan)
 COSHH Stores for all chemicals with SDSs available

9.3 Risk Assessment Analysis


Note:-Kindly refer this analytical risk assessment as a draft version actual performed risk
assessment will be done at site safety FAST HSE Plan Rev. 05
Follow Risk assessment form (Template) requirement at time of site execution (see the attachment
RISK assessment)

9.4 SAFETY MANAGEMENT PLAN


The Site Manager is in charge of implementing the Safety Management Plan at areas under his
9.4
responsibility and to maintain his work area as a safe work place following the requirements
described under Safety Management Plan, Environmental Management Plan and its
9.4
complementing Health, Safety and Environment (EHS) Documents. The Site manager shall be
supported by the Safety Team for the implementation and verification of application of best safety
practices in the project.
9.4
According to Safety Management Plan :
9.4
Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
9.4
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 54 of 78
and Fiber Optic Cable Pulling and Termination
9.4
 Job title specific, each responsible person for EHS has certain responsibilities and these are
documented to ensure people are aware of their responsibilities.
 Framework for legislative and contractual EHS documentation :
- Risk assessments.
- Meeting minutes.
- Consultation and communication methods
 General guidelines and references have been made to specific procedures for amendment
purposes.
- Lifting operations.
- Traffic safety.
 Tool box Talk will be made for all teams and operators before the start of any activity.

9.4.1 POTENTIAL RISKS

Refer to annex appendix 3.

9.4.2 JOB SAFETY ANALYSIS

Refer to annex appendix 5.

9.4.3 EHS EQUIPEMENTS

Standard Personal Protective Equipment (PPEs) to be worn by all personnel is:


 Safety Helmet/Gloves
Safety coat / yellow vest and Safety boots / shoes.

9.4.4 SAFETY INDUCTION / TOOLBOX TALK

The person in charge of start of new operations or activity shall conduct a toolbox Talk to workers
before the start of this activity. It will include/understand a presentation of work to be carried out and
procedures of safety installation.
All supervision staff shall receive necessary EHS training in order to lead the construction site
activities. At the end of work, the section engineer shall ensure that all the materials and equipment
were evacuated from site.

9.4.5 EMERGENCY PROCEDURE

The General Emergency procedure is described in document [R04]: Emergency Response Plan.
 Proper safe mean of access egress from and to the working area will be made available at
all time.
 Emergency contact numbers Contact numbers of all emergency supervisors will be
distributed to site personnel (Superintendent, Safety officer, nurse, etc.)

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 55 of 78
and Fiber Optic Cable Pulling and Termination
 Injuries will receive the first aid service and if required, the injured person will be sent to the
hospital.

9.4.6 NOISE CONTROL

The noise level will be maintained to the allowable levels at 85 Dba. When working at night,
measures will be taken to limit the noise and other nuisance. Same shall be performed in
accordance with project EHS Plans and Method Statement. Ref M3-FST-MPL-EEN00-GNE-
000008 AB.

9.4.7 OFFICE AND WELFARE EQUIPMENT

The offices, cloakrooms, toilets and equipment of cleaning will be established along the sites.
The arrangement will be done in a case by case process according to site situation (refer to [A02]

9.4.8 AIR QUALITY & DUST CONTROL

The Contractor shall instigate effective dust suppression measures as may be necessary to
avoid creating dust nuisance arising as a result of the Works on site.
The Contractor shall clearly identify proposed dust control measures intended to be implemented in
detail as a part of a general method statement to be issued.

8.5.9 Waste Management Plan


The optimal way to manage waste is to avoid generating it. In some situations the generation of
waste is unavoidable. However, the guiding principles and the philosophy of FAST and all
subcontractors is to ensure that as much as possible, waste generation is reduced.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 56 of 78
and Fiber Optic Cable Pulling and Termination
APPENDIX

Number
N° Appendix Title Reference
of Pages

1 Materiel Inspection Report (MIR) M3-TSY-FOR-SYS00-M50-000130 N/A

2 Final installation check list (part of Inspection and Test M3-TSY-QAR-POS00-M50-000007 4


Plan (ITP))

3 Risk assessment N/A 2

4 Potential hazards N/A 1

5 Job safety analysis N/A 3

6 Depot and line equipment Supplier M3-TSY-EDR-POSTL-PWD-D40- 16


Documentation. 0021559

10

11

12

13

14

15

16

17

18

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 57 of 78
and Fiber Optic Cable Pulling and Termination
APPENDIX 1 – Material Inspection Report (MIR) – Sample

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 58 of 78
and Fiber Optic Cable Pulling and Termination
APPENDIX 2 – Final installation checklist (part of ITP) – Sample

Equipment/System :

Site : Location :
Tag : Serial No. :
Characteristics :

Inspection by
Item
Main Activity Acceptance Criteria Remarks
No Site
CM QC
Sup

1. CABLE PULLING

A VISUAL INSPECTION

As per design
1 Check the cable drums, type of cables and sizes drawings, cable list
and MRIR
Check all tools and machinery to be used in the As per tools and
2
cable pulling machinery list

B INSTALLATION CHECKS

As per approved, MS
Check the work area are hazard free and ready to
1 and Handback from
start the cable pulling
CW to subsystem
As per approved MS,
Check the internal part of multi-tubular are clean Handback from CW
2
prior to cable pulling to subsystem and
mandrill report
As per approved MS
Check the installation of cable trays inside and Handback from
3 substation (TPS/LPS) are completed and CW to subsystem
obstruction free

Check the installation of cable pulling devices and


4 accessories are completed and properly set up As per approved MS
prior to cable pulling

Check the cable conditions to ensure the


5 As per approved MS
insulation is not damage

Check the label or identification on the cable As per approved MS


6
before to pulling the cable and design drawings

Check the respected minimum bending radius and As per manufacturer


7
maximum pulling force for the cables data sheet

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 59 of 78
and Fiber Optic Cable Pulling and Termination
Check the cable label at both ends (temporary As per design
8
labels to be provided) drawing

2. LV CABLE TERMINATION

A VISUAL INSPECTION

Check the materials to be used for termination


1 As per requirements
and jointing of cables
Check all tools and equipment to be used for
2 As per requirements
termination and jointing of cables
As per approved MS
3 Cable Dressing
and Design Drawings
As per approved MS
4 Cable Ties, Cleats
and Design Drawings

B INSTALLATION CHECKS

Continuity and
Check the continuity and insulation of the cable
1 Insulation Test See attached list
prior to termination
Report
Check the installation of cable terminal and As per approved MS
2
jointing kits and Design Drawings

3. MV CABLE TERMINATION AND JOINTING

A VISUAL INSPECTION
Check the materials to be used for termination
1 As per requirements
and jointing of cables
Check all tools and equipment to be used for
2 As per requirements
termination and jointing of cables
As per approved MS
3 Cable Dressing
and Design Drawings
As per approved MS
4 Cable Ties, Cleats
and Design Drawings
B TERMINATION OF CABLES
As per manufacturers
1 Check the cutting of cable as per required length
instruction

As per manufacturers
2 Check the preparation of cables
instruction

As per manufacturers
3 Check the installation and crimping of terminal lugs
instruction

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 60 of 78
and Fiber Optic Cable Pulling and Termination
As per manufacturers
4 Check the installation of shrink tube
instruction

C JOINTING OF CABLES
1 Check the preparation of the cables As per manufacturers
instruction

2 Check the installation and crimping of jointing kits As per manufacturers


instruction

3 Check the installation of shrink tube and heating process As per manufacturers
instruction

Prepared by / Checked by: Witnessed by: Approved by:

POW-CM/Engineer/Supervisor POW-QCE/Inspector Engineer

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 61 of 78
and Fiber Optic Cable Pulling and Termination
APPENDIX 3 – Risk assessment

Risk Assessment LV, HV & Fibre Optic Cable Pulling &


Title: Termination
Risk Assessment
Revision:

Residual Risk
Risk Rating
Who is at Action Rating
Item Hazard Risk Necessary Control Measures
Risk By
S F Rating S F Rating

- Daily tool box talk have to be done

- The worker shall be experienced in handling sharp


edge tools
Sharp Edge
1 Cutters /
knives
Personal Injuries like skin
cut etc.
- General
site workers
5 5
25 - Sharp Tools shall be closed just after the used in a
5 1
5
secured Box

- Safety gloves will be worn during this activity

Electric shock from contact


2 Electricity
with existing services,
lights, temporary panel
boards, etc…
- General
site workers
5 5
25 - Daily tool box talk have to be done 5 1
5

Method Statement for Installation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 02/04/2017
POS00-Y20-000041 Revision : AB1
Name of the file : M3-TSY-MST-POS00-Y20-000041-AB1_ Method Statement for Installation of LV,HV and
Page 62 of 78
Fiber Optic Cable Pulling and Termination
- Battery operated tools shall be used to avoid
Electrocutions
- Alstom
employees
- Defective extension lights and electric hand tools,
power cords and extension leads shall be repaired or
- Site
replaced
visitors

- Portable electric tools, extension lights and cords


should be inspected each time they are issued and
returned. This should be part of a tool store
procedure. All power leads, lights, plugs and
electrical power tools, (except battery operated hand
tools) shall carry the appropriate colour coding for
the inspection period.

- Workers are prone to abuse extension cords by


pulling them over sharp metal objects, hanging
them across equipment, kicking them, or letting them
be run over by industrial equipment

- Only qualified electricians should make repairs and


carry out maintenance checks.

- All extension lights must be fitted with protective


guards
- Do not use any damage or faulty equipment

- Report any damage to the supervisor and ensure it is

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 63 of 78
and Fiber Optic Cable Pulling and Termination
taken out of use until it has been repaired

- Fire Marshalls shall be appointed

- Fire extinguishers are in place and checked

- HSE staff shall generate

and maintain a register or log of all firefighting


equipment on the project site.

- 2 people have to be trained as Fire Warden

Fire (electric default) 5 5


25 - Flammable / combustible material stores shall be in a
5 1
5
segregated area

- Containers of flammable or combustible liquids /


substances will remain tightly sealed except when
poured or applied

- Materials delivered in flammable / combustible


packaging shall be stored away from sources of ignition

- Information and warning signs will be provided across


the worksite

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 64 of 78
and Fiber Optic Cable Pulling and Termination
- All persons working on the track must be trained and
certified to work on tracks (Training had been carried out
in TSY warehouse under FAST HSE supervision on
07/06/2017) (see certificates in appendix 6)

-2 certified Flag men shall be moving all the way with the
moving vehicle (one from the front & one from the back)
- General
site workers
-The vehicle driver shall not move the vehicle without
the order of the flag men

3
Vehicle
Movements
Hit by moving vehicles (rail
roads, cars, etc..)
- Alstom
employees
5 5
25 -Nobody shall be allowed to cross the track within 5
meters of the moving vehicle
5 1
5
-Existing safety arrangements (e.g. fixed warning
- Site systems)
visitors -No one is allowed to sit at the back of the vehicle or
trolleys.
-Wear PPE at all times
-Fix warning signs
-Fix signs showing the “entrance” direction and “leaving
the site direction”
-Fix scotch blocks when trailors are static

Trip hazard
4
and slips
Falling on the ground
- General
3 5
15 - Clean-up of the site frequently
2 2
4
Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 65 of 78
and Fiber Optic Cable Pulling and Termination
site workers
- Trip hazards are removed it and roads are free of
obstacles or hazards and have adequate lighting
- Alstom
employees
- All cables have been arranged in order to not cause
trip hazards
- Site
visitors

- Every equipment, objects and items are attached to the


belt of the safety harness

- Safe area is delimited

- General
site workers - Safety helmet are worn
Equipment,
Equipment, objects, tools,
5
objects, tools,
plants and
items
plants and items falling
from height
- Alstom
employees
5 5
25 - Installation of crash decks over entrances / access
routes where the risk of falling objects is significant
5 1
5
- Site - Installation of catch nets to protect parallel works or
visitors pedestrian routes

- All tools and equipment shall be color coded and


inspected regularly

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 66 of 78
and Fiber Optic Cable Pulling and Termination
- Competent person shall check all equipment and tools
before starting activities

- All work equipment, objects, tools, plants and items


must be kept properly maintained so that its
Equipment,
Equipment, objects, tools, performance does not deteriorate to the extent that it
6
objects, tools,
plants and
items
plants and items are
defected
3 5
15 puts people at risk 3 1
3
- All tools need to be double insolated

- Ensure that there is adequate information, instruction,


training and supervision

- Use of mechanical machine will be done as much as


possible in order to reduce manual handlings

Manual - Muscular / Skeletal - General


7
handling disorder site workers
2 2
4 - Switching the workers using the shovel to allow
enough rest and avoid injury
1 1
1
- If there is a need to move a heavy loads, use more
than 1 worker

- Ensure that the correct handling technique are used


such as keeping the load close to the body, keeping fee

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 67 of 78
and Fiber Optic Cable Pulling and Termination
shoulder width apart and avoid twisting or stooping

- Lift briefing shall be been conducted before starting the


activity
- All items that will be Lifted with the equipment shall be
included in the weight
- Lifting lugs shall be used with the correct shackle(s)
- Lifting lugs shall be free from damage and debris
- The Load shall be checked for loose or unsecured
items that might fall off during the lift
- The capacities of the slings and shackles shall be
Delivery & checked for the Load
- The slings and shackles shall be visually inspected for
unloading of Offloading at numerous defects or damage
equipment and - General - The center of gravity shall be considered when
points, collisions with
8
cable drums construction plant/
site workers 5 5
25 checking the capacities of the sling and shackles
- The Crane shall receive a daily inspection and
5 1
5
using vehicles on site operational check by the Operatorbefore usage
Crane/boom - The ground conditions shall be inspected and
truck determined to be adequate
The Crane and the Operator shall be certified
-The radius of the Lift shall be checked and measured
- The Lifting area shall be free of obstruction, process
equipment, piping, or live electrical lines
- The area under the Lift shall be barricaded, warning
signs displayed or everyone warned to stay away
- There shall be one person designated as the
Slinger/Signaller in charge of the Lifting Operation

- PPE, gloves, hard hat, safety boots


Pulling cables Rotating Machinery - General
site workers
9
during cable
drum rotation &
movement
Strains/lifting/trip/catch
points,
5 5
25 - Only well trained and expert people shall be
allowed to work (Training is carried out under
FAST HSE supervision in TSY Warehouse on
5 1
5
Manual - Alstom 20/06/2017)

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 68 of 78
and Fiber Optic Cable Pulling and Termination
handling/cuts/abrasions employees

- Site
visitors

- Personal injury due to - General


ignoring FAST Safety and site workers - Stop work
Quality rules, regulations - Give warnings or dismissal depending on the action
Ignoring FAST done
- Alstom
10 Safety and
Quality rules,
- Damage due to ignoring
FAST Safety and Quality
employees
5 5
25 - Debriefing with contractors or sub-contractors
5 1
5
regulations rules, regulations leading - Retraining (internal)
to financial and production - Site - Issue warning
loss visitors

- General
- Personal injury due to no site workers
continuous supervision

11
No continuous
supervision - Damage due no
continuous supervision
- Alstom
employees
5 5
25 - Supervision in charge must be on site otherwise the
work have to be stopped until the supervisor is available
5 1
5
leading to financial and
production loss - Site
visitors

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 69 of 78
and Fiber Optic Cable Pulling and Termination
- Drinking water is available

- Sufficient toilets are in place (washing facilities shall be


installed)

- Welfare facilities should be reviewed

- First Aid equipment provided on site shall include


- General
treatment for dehydration e.g. electrolytes.
site workers

- Temperature has to be taken into consideration, a


Heart attack or physical - Alstom
12 Heat
problems employees
5 5
25 thermometer has to be on the site (especially between
12PM and 3PM)
5 1
5
- Site
- Casualty should be stood down from work, removed to
visitors
a cool place and given plenty of fluids contains
electrolytes. Work may be resumed when the medical
attendant establishes that the casualty has recovered
sufficiently

- Switch / rotations between workers need to be done

- A watcher / supervisor has to be present on the site


and to check the behavior of your workers (in case of
any strange behavior because of the heat he can decide
to stop the work for some or all of your workers and to

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 70 of 78
and Fiber Optic Cable Pulling and Termination
bring them to the FAST Medical clinic)

- Emergency numbers (ambulance, fire, police…) have


to be on the Safety board

- The work has to be done under the warehouse at all


the time (nobody has to be directly under the sun)
between 12PM and 3PM

- Rest area with chairs have to be in place

- Bottles of water will be provided to your teams as much


as possible (especially during 12PM and 3 PM)

- Medical staff or first aiders will send regular


communiqués on the subject of heat stress and
inform management of any concerns.

- General
- Personal injury due to the
site workers - All documents should be submitted after kick-off
absence of Work without
Work without meeting
Method Statement, Safe
Method
work procedures and plans
13
Statement,
Safe work
procedures - Damage due to Work
- Alstom
employees
5 5
25 - FAST SWPs must be read, understood and explain to
5 1
5
the all team before
and plans without Method Statement,
Safe work procedures and - Site commencing the activities
plans leading to financial visitors
and production loss

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 71 of 78
and Fiber Optic Cable Pulling and Termination
- Daily tool box talk have to be done

- Training must be provided or the evidence of training


should be shown
14
Untrained
workers
Personal injury due to no
training
- General
site workers
5 5
25 - Previous experiences and documents must be ensured
5 1
5
- Safety officer daily inspection checklist have to be
done

- General
site workers

- Competent person shall check PPE prior to use


Personal injury due to - Alstom
15 Defects in PPE
defects PPE employees
5 5
25 - Defects PPE will be remove from the site
5 1
5
- Site
visitors

16
Unprotected
opening / holes
Personal injury due to falls
- General
5 5
25 - Cover open holes with heavy duty steel plate
5 1
5
Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 72 of 78
and Fiber Optic Cable Pulling and Termination
site workers
- All holes have to be signaled
- Alstom
employees

- Site
visitors

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 73 of 78
and Fiber Optic Cable Pulling and Termination
APPENDIX 4 – Potential hazards
Potential Hazards This list may not identify all potential hazards present. Visit the job site to ensure all hazards are identified. If a potential hazard has no impact on the job, mark the box with "N/A" (Not
Applicable.) If a potential hazard does have an impact on the job, tick the relevant box (es) with  and implement appropriate control measures in the JSA.

WORKING AT HEIGHTS WORKING OVER OR NEAR WATER UNDERGROUND SERVICES


 Will personnel be working at height during this task?  Safety Boats  Are there any underground service lines, e.g. water, gas, electricity,
 Life Jackets sewage pipes?
 TRIP HAZARDS HYDROCARBONS/FLAMMABLES FALLING OBJECTS
 Will equipment in use form a trip hazard?  Will equipment need to be drained / purged?  Will personnel be working above where others may pass? Working
 Are there trip hazards in the work area?  Are there highly flammable products in the work area below others?
ASBESTOS DAY/NIGHT TIME OPERATION HYDROGEN SULPHIDE (H2S)
 Will personnel be exposed to asbestos during this task?  Is extra lighting required  Will personal monitors or gas detectors, respiratory protection be
required?
 MANUAL HANDLING LEAD EXCAVATIONS
Are hazardous MH tasks involved? (eg: repetitive or sustained  Do surfaces to be worked on contain lead paint? Are testing kits  Does the work require an excavation to be dug? Specific work planning
use of force, awkward posture, vibration, unstable/unbalanced available? and approvals are required.
loads).
 HUMAN FACTORS  WEATHER NOISE
 Are personnel competent and confident to perform the
task?
 Have weather extremes been considered?  Is there a need for hearing protection in the area?
 Is hearing PPE appropriate and in good condition? Will the work create
 Is fatigue an issue? Are procedures clear and higher noise levels?
understood?
WORKING ON ENERGY SYSTEMS/ENERGY ISOLATION ENVIRONMENTAL  CRANES & LIFTING EQUIPMENT
 Is there potential for contact with live electrical  Have potential spill sources been identified?  Does the lifting activity require a lifting permit?
equipment? Will electrical isolation be required?  Is a banks man overseeing all lifting activities?
 Has the need for drip trays, containment, spill blankets, absorption
 Will mechanical isolation be required? been considered?  Is all lifting equipment certified and colour coded
 Is the equipment to be worked on required to be drained,  Has clean up after the job/housekeeping been considered?  Has lifting over live equipment been considered?
depressurized? Consider air, gas, water, inert, oil,
Hydrocarbons etc.  Does job require waste disposal measures  Is the equipment in good condition (no oil leaks, etc.)?
 Will job require hazardous waste collection and disposal
 Will equipment with stored energy (spring loaded,  Does the equipment have a valid certificate
gravitational) have an impact on the job?
 OCCUPATIONAL HEALTH CONFINED SPACE  TOOLS & EQUIPMENT

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 74 of 78
and Fiber Optic Cable Pulling and Termination
 Have health exposures been considered? (eg: Legionella)  Does the work to be done require confined space entry?  Will a generator, compressor or other mobile equipment be used?
 Is a First Aider available  Are relevant personnel trained in the entry requirements?  Are machine guards in place? Are guards, safety rails, etc in good
 Welfare: drinking water, toilets, shaded areas  Is there a stand-by person condition?
 Biological hazards: untreated sewage water, ..  Is adequate rescue equipment required
 Extreme temperatures
 BARRIERS – TRAFFIC MANAGEMENT WORK AREA HAZARDOUS MATERIALS (COSHH)
 Do barriers need to be erected to exclude non-authorized  Will confined space entry, hot work, other work be occurring nearby?  Will hazardous substances be used? Have the MSDS's been checked?
personnel or vehicles from an area where potential Have the health hazards of the chemical been considered?
hazards exist?  Does work affect other contractors or members of the general public
 Is vehicular and pedestrian traffic segregated
 Is signage/traffic management plan required?
Emergency Response: The JSA should consider egress routes, location of nearest first aid post and compression chamber, alarm, shutdown switch, fire equipment, etc.

APPENDIX 5 – Job safety analysis


Prepared by: Reviewed / Approved by:

Description: Installation of cubicles/panels in TPS,PP,LPS


Duration of the job: Refer to schedule
Permit Required
 5 key steps  Notes
Daily
Hot Work 1. Identify Job to be analysed 
  The JSA must be updated with any additional hazards found during the work.
Excavation 2. Break down job into steps – see page 3
 If any hazard cannot be adequately controlled by the JSA, further Risk
Work on Energy systems 3. Identify hazards for each step 
Assessment & Management Approval is required.
Confined Space Entry 4. Assess the level of risk for each hazard   Existing JSA’s should be reviewed for any hazards; a new JSA should be
 performed in preference to reusing existing analyses.
Diving 5. Develop control actions to reduce risk
 JSA & JSA signing sheet to be filed.
Other: ……………………..

PPE Tools & Equipment needed


Comments (e.g. : progressive history, updates, reviews and reason)
Item  Specify
This covers cubicles/panels installation inside TPS,PP,LPS by power supply and associated Safety shoes/boots 
Refer to chapter 3.1 (Handling equipment)
equipment and tools.
Safety helmet  Refer to chapter 3.2 (tools list)
Safety glasses 
Safety goggles 
Protective clothing n/a

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 75 of 78
and Fiber Optic Cable Pulling and Termination
High visibility vest 
Gloves 
Fall protection 
Hearing protection 
Life jacket n/a
Other: ……………… n/a

JOB SAFETY ANALYSIS Form ID:


Doc ID:
PRE-TASK BRIEFING Date:
Rev: 01
MAIN STEPS OF TASK POTENTIAL HAZARDS AFFECTED CONTROL ACTIONS NEEDED TO REDUCE RISK
Each step is for a specific part of the task. Identify the hazards relating to each step. E/SC/P/O * List the controls required to reduce the risk in each step.

 Heat Stress E/SC  Sufficient potable water


 Employees to be made aware of heat stress by mean of
Working outside toll box talks
 Shaded rest areas to be provided
 No work during summer restricted times
 Overloading E/SC  Lifting Supervisor to coordinate all lifting activity.
 Injury to person and/or damage to  Safety supervisor to be ensures delivery route is safe and
equipment
 Hit by falling object adequate.
 Hand injury  Lifting Supervisor will ensure all lifting gear are in good
conditions and inspected with proper certificates.
Handling; unloading and lifting tasks  Staff training awareness of proper method for handling
the equipment
 Appropriate PPE including safety helmet and reflective
vest must be worn at all times.
 Avoid passing through or standing below lifting activity
On-going.

 Injury to person and/or damage to E/SC  Area to be fenced.


Swaying of load equipment  Conduct briefing and toolbox meeting prior lifting.

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 76 of 78
and Fiber Optic Cable Pulling and Termination
 Tagline to be installed to control loads from swinging.
 Signal man to give signal.
 HIAB or crane operator to avoid sudden movement of
load.
 No worker allowed to station under the load.

For each hazard, indicate who is at risk: employees (E), sub-contractor employees (SC), Members of Public (P), Others (Specify) (O)

JOB SAFETY ANALYSIS Form ID:


Doc ID:
PRE-TASK BRIEFING
Date:
Rev: 01
NAME OF THE SUPERINTENDANT / SUPERVISOR / FOREMAN:
CREW SIGN ON SHEET
NAME SIGNATURE DATE NAME SIGNATURE DATE

Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 77 of 78
and Fiber Optic Cable Pulling and Termination
Method Statement for instullation of LV,HV and Fiber Optic Cable Pulling and Termiantion / M3-TSY-MST- 22/10/2017
POS00-Y20-000041 Revision : AC
Name of the File. : M3-TSY-MST-POS00-Y20-000041-AC_ Depot Method Statement for Installation of LV,HV
Page 78 of 78
and Fiber Optic Cable Pulling and Termination

You might also like