Professional Documents
Culture Documents
Checking Procedure For Plant Layout & Piping
Checking Procedure For Plant Layout & Piping
(b) Make sure pits area arranged on a reclaimed ground and buildings/ large
tanks on a rocky ground.
(c) Regarding safe distance, safe open space, green area and roads, make sure
applicable laws are observed.
(b) Are the entrances for materials, utilities and the exits for products properly
positioned?
(c) For large-scale equipment, make sure its transportation and installation are
well studied.
(e) Make sure fire protection / safety systems are well studied.
(a) Make sure operation, maintenance and safety are well considered in the
layout.
(d) Are machine rooms and control rooms fuctionally arranged? (Check the
shapes and sizes.)
(f) Is the wind direction taken into consideration ( e.g. cooling towers)?
1 of 5
B. Piping Check List
(a) Do the piping specifications comply with applicable laws, codes and
standards?
(b) Isn’t there any problem on the splitting of the procurement and the delivery
date?
(a) Does the piping design reflect fully the special features of the plant?
(b) Have adjustments been made with other departments concerning following
items of Design Job Instruction?
Process design
Equipment design
Electrical and instrumentation design
Structural design
Construction design
(b) Are the routes of high class piping, thick-wall pipes and large-sized pipes
made as shortest as possible?
(a) Are the surface conditions and others of the site satisfactory?
(b) Is there a plan to pave the areas around chemicals and oil systems?
2 of 5
Document Check Items Check
Has there been mutual checking of the important piping with the Process
Department?
Were the clips to support pipes of towers and tanks presented in time for the
schedule of the equipment manufacture?
(a) Is the plan for equipment frames examined from the economical viewpoint?
(b) Is the structure of the pipe rack made to fully reduce the cost? Examination
of horizontal and vertical braces and of a front guard type pipe rack.
(c) Isn’t any floor (wall) opening, insert plate or anything else omitted?
(b) Do the drawings comply with the schedule of the field works?
3 of 5
Document Check Items Check
(f) Are the conditions around the piping of large thermal movement all right?
(g) Have testing and flushing plans been examined from the viewpoint of
construction works?
(j) Have the fabrication drawings of special piping like jacket piping been
prepared?
(l) Are the directions of the discharge points of such as safety valves not
hazardous to operators?
Aren’t any sampling piping or small diameter piping around machine omitted in
the drawings?
(a) Do the piping drawings meet the tracing conditions (measures against
freezing or process demands) ?
(b) Are the drawings sufficient for field workers to do piping work?
(a) Has the take-off of the piping materials been done without any omission,
and ordered?
(b) Do the delivery dates of the materials comply with the schedule of the field
works?
4 of 5
Document Check Items Check
(a) Are the loading data and the test load clear for the design of cross section
area of the skid members?
(b) Have the positions of the instruments been fixed and have the operability
and maintenance been planned?
5 of 5