Method Statement Title: GPUMP ROOM GENERAL CONSTRUCTION WORK METHOD STATEMENT
Method Statement No. : WMS - 002
ENDORSED BY
Position Name Signed Date Signature
APPROVED BY
Signed by Project Manager Signed by Project Director
Note:
This document is controlled in soft copy. Any hard copies
seen are uncontrolled unless chopped with Red Control
Stamp.
HARD COPY CONTROL STAMP
OPR-WMS-005
Dec 2019 Page 1 of 24
Logos property India
Work Method Statement
Contents
1. Scope
2. References
3. Terminology
4. General Method Statements
4.1.1. Earthwork Excavation...........................................................................................3
4.1.6. Concreting........................................................................................................... 8
4.1.7. Masonry.............................................................................................................. 9
4.1.8. Plastering.......................................................................................................... 11
4.1.10. Reinforcement....................................................................................................13
5. Responsbility Matrix
6. Quality Inspection And Test Plan
7. Precautionary measures for COVID-19
1 SCOPE
The method statement covers the requirement of the construction of General Builders Work
and related construction activities
2 REFERENCES
1. Technical Specifications
2. Contract Document
3. Construction Drawings
4. Technical Specifications and latest relevant codes.
OPR-WMS-005
Dec 2019 Page 2 of 24
Logos property India
Work Method Statement
3 TERMINOLOGY
Work permit for the concerned work will be obtained and the work will be as per safe work
method statement.
Site clearance such as clearing shrubs, roots, small trees, wild growth and local humps and
debris.
Setting out the work to profile and making the site suitable for marking the layout of building
by suitable survey equipments.
Providing and constructing of permanent grid points with brick pillars placed sufficiently away
from building line.
Providing and construction of bench mark pillar as per engineer incharge instruction.
Final trimming will be done manually and clearing out all loose earth.
The depth of excavation will be under check by our engineer. Utmost care will be taken to
prevent excess excavation.
In deep excavation suitable earth drain all-round the excavated area will be provided and sub
soil water will be bailed out.
For non-stable soil condition, suitable shoring & dewatering all-round the excavated area will
be provided.
OPR-WMS-005
Dec 2019 Page 3 of 24
Logos property India
Work Method Statement
If the subsoil is in loose condition necessary shoring and strutting with suitable material will
be provided to protect the excavation where ever required.
If obtain rock during the earth work excavation, mechanical / electrical rock breaker will be
used for dismantling the rock.
If subsoil water is very high, well point dewatering system will be provided to keep the
foundation in dry condition.
Safe movement in and out of the foundation will be ensured by providing ladles support.
Excavated earth will be transported by tippers and dumped in inside the site premises as
directed by engineer incharge.
Back filling will be done in layers of 150mm to 250mm and compacted by earth rammer to
required compaction.
Each layer of filling will be brought to the specified line, levels and to the required proctor
density.
a. Shoes / Gumboot
b. Helmet
c. Gloves
d. Reflective jacket
a. Excavator
b. Tipper
c. Spaddle
Documents required
a. Work permit
b. Checklist
OPR-WMS-005
Dec 2019 Page 4 of 24
Logos property India
Work Method Statement
Check the Cutting & Dismantling area, Depth as per specification & client requirements.
Check whether Floor cutting machines used are in proper condition and required check are
done.
Check whether all the required work specific PPEs are provided to the workers.
Following PPE will be issued to Labour’s for floor cutting & dismantling.
a. Shoes / Gumboot
b. Helmet.
c. Gloves
Check the Cutting & Dismantling area, Depth as per specification & client requirements.
Check whether Floor cutting machines used are in proper condition and required check are
done.
Check whether all the required work specific PPEs are provided to the workers.
OPR-WMS-005
Dec 2019 Page 5 of 24
Logos property India
Work Method Statement
The back filled around the column and along the plinth beam will be treated with the soil
poison.
Concrete debris, timbers and other materials will be removed from the excavated area before
backfilling.
The entire floor surface will be impregnated with soil toxicants to make a chemical barrier
between the soil and floor.
The chemicals used for the treatment will be chloropyriphos 20% or 50% EC and the
application will be dilute one part of chemical 20%/50EC with 19/49 parts of water to get 1%
emulsion and in accordance with IS: 6313 and manufacture specification.
Rodding / Drilling shall be made at an equal spacing of 150mm c/c for a depth of 300mm and
the soil toxicant will be injected at the floor and wall junctions.
External perimeter area is covered by the same above method at an spacing of 1m c/c instead
of 150mm
The treatment will be carried out by an approved specialized agency on prior approval.
a. Shoes / Gumboot
b. Helmet
c. Rubber Gloves.
d. Nose mask.
e. Reflective jackets
a. Spray pan
OPR-WMS-005
Dec 2019 Page 6 of 24
Logos property India
Work Method Statement
b. Mixing drum
Documents required
a. Work permit
b. Checklist
Filling will be done in layers of 150mm to 250mm thickness, spread evenly with dozer or
plover.
Filled approved quality earth, lime sand , Granular Sub Base & M- Sand will be watered
(optimum quantity) and compacted by 10T vibromax roller to achieve the required proctor
density.
All layer of filling will be brought to the specified line, levels and to the required proctor
density.
The layer. shall be rolled including premixing in well graded crushed stone aggregate, with
watering and spreading by to required profile and compacting with vibratory roller.
a. Shoes / Gumboot
b. Helmet.
c. Gloves.
d. Goggles
OPR-WMS-005
Dec 2019 Page 7 of 24
Logos property India
Work Method Statement
Walk way will be done by steel grills or plywood board with both end rigid support and tied
properly.
Steel measurement box with MS pipe handle will be used for pouring aggregates in the
machine bucket watertight steel bond will be used for conveying concrete.
a. Shoes / Gumboot
b. Helmet
c. Gloves.
4.1.6 CONCRETING
Cement used for construction will be ordinary Portland cement 43 Grade conforming to IS:
8112.
Coarse graded sand will be used for all concrete works conforming to IS: 383.
Machine crushed coarse graded aggregate will be hard broken blue granite of 20mm and
down size conforming to IS: 383.
Material will be collected as and when required with a minimum stock required for 15 days of
work.
Water used for mixing and curing will be tested in accordance with IS 456.
Nominal mix such as 1:2:4, 1:3:6, 1:4:8 and 1:5:10 proportions will be used in specified
location.
PCC work will be supplied by RMC Plant. The placed concrete will be rammed and finished
to required level and surface.
Concrete will be poured with proper compaction using mechanically operated needle
vibrators.
OPR-WMS-005
Dec 2019 Page 8 of 24
Logos property India
Work Method Statement
Mix design will be done by approved agency and will be on prior approval from Engineer-in-
charge.
RCC used for foundation and super structure will be either cast-in-suit or by RMC.
Weigh batch equipment will be used for design mix concrete. Inspection of concrete will be
done by as per related check card listed in PQP.
Testing will be done at site lab or authorized testing laboratory. Aggregate sieves and
crushing strength machine will be at site to test the size of aggregate and strength of concrete.
All concrete works will be cured for the required number of days from the date of placement
of concrete for compressive strength 7 days & 28 days.
If any honey combs or any other quality based issues observed, suitable repair and
rectification method will be submitted and carried out with prior approval.
a. Shoes / Gumboot
b. Helmet
c. Gloves
d. Reflective jacket
4.1.7 MASONRY
The average thickness of both vertical and horizontal mortar joints is to be 10mm exclusive of
any key in the joint surface of the unit.
All blocks and previous day’s work shall be wetted before commencing/resuming new work.
The blocks should have minimum compressive strength of 5.5N/Sqmm conforming to IS 2185.
Blocks walls are to be built from undamaged blocks in stretcher bond unless otherwise
specified. Half blocks and special blocks are to be used as required to ensure correct bonding.
Maximum height of the masonry work will be of 1m per day with cement mortar 1:5
The work is to be carried out course by course not leaving any part more than 800 mm lower
than another.
Partitions shall be 10 mm thick unless otherwise noted. Partitions having lavatories or other
plumbing fixtures secured to them back to back (or approximately so) are to be a minimum of
200 mm thick. Solid concrete masonry units shall be built in where full units cannot be used
or where needed for the fixing of accessories. Bells or hubs of pipes must be completely
enclosed.
All connections between block walls or partition and concrete or steel columns are to be
reinforced at maximum 400 mm centers by galvanized metal or stiffeners for columns in
block work except noted on approved drawings.
Internal walls shall be built-up to leave 20mm joint between the top of the wall grout or
partition and the soffit of the slab. The joint should be filled by Class M6 mortar. Where
concrete slabs are supported on block work. The top of block should be fully grouted or solid
block shall be provided to void any mortar slip between ceiling and top of the wall.
In the following situations, the cavities of hollow block walls are to be filled solid with Class
M6 mortar.
Jambs of all openings
Ends, angles and junctions of walls and partitions
Junctions of walls and partitions with the stiffeners for column in block work
At sills
At tops of partitions, if so specified
Immediately following setting, brush exposed surfaces free of mortar or other foreign matter.
All block work shall be kept covered with wet hessian cloth or other approved material for a
minimum of 3 days.
Curing of the built-up wall shall be ensured by monitoring and recording the curing time.
a. Shoes
b. Helmet
c. Gloves.
d. Safety belt.
OPR-WMS-005
Dec 2019 Page 10 of 24
Logos property India
Work Method Statement
4.1.8 PLASTERING
Button marks will be provided using cement mortar before starting the work.
Thickness more than 20mm will be done in 2 coats of minimum 12 hours interval.
Approved brand Cement used will be 43/53 Grade Ordinary Portland cement.
Plastering used will be sieved sand free from organic material, clay and dust.
Sign board indicating the mix proportion will be laid near the mixing platform.
The gauged materials (ie.) cement and sand will be mixed dry through and then water will be
added gradually.
Wet mixing will be continued till the mix is homogeneous and of uniform colour.
150mm wide GI chicken mesh to a required width will be provided at the junctions of
concrete and brick work.
Mortar will be firmly applied, spread evenly well pressed into the joints, rubbed smoothened
with straight edge, wooden float and trowel and smooth finished as per engineer incharge
requirement.
The plastered surface will be wet for a period of 7 days by spraying water and the same will
be monitored by recording.
a. Shoes
b. Helmet
c. Gloves.
OPR-WMS-005
Dec 2019 Page 11 of 24
Logos property India
Work Method Statement
d. Safety belt.
Sand gravel mix in 1:1 proportion will be prepared for a thickness of 200mm.
150mm Channel will be fixed over the PCC as form work to form panel. The top level of the
channel will be maintained to finished floor level.
Dowel bar will be inserted through holes provided in the form work (ie) 16mm dia @500mm
c/c in 2 layers.
Nito floor hard top standard (FOSROC) @ 3.5kg/Sqm will be spread over the concrete by
manually after the dewatering process completion.
Rough finishing and smooth finishing will be done by using power floater and power trowel.
Expansion and isolation pad of specified thickness will be used for expansion and isolation
joint in floors. Care will be taken to make sure that expansion pad does not deform during
concreting process.
Following PPE will be issued to Labour’s for Vaccum Dewatering Flooring Work.
e. Shoes
OPR-WMS-005
Dec 2019 Page 12 of 24
Logos property India
Work Method Statement
f. Helmet
g. Gloves.
h. Safety belt.
4.1.10 REINFORCEMENT
Reinforcement steel of grade Fe 500 will be conforming to high yield strength deformed
bars conforming to IS: 1786.
Reinforcement steel received at site shall be stacked over wooden pieces elevated from
ground level.
Shop drawing for all reinforcement will be submitted and approved by the Engineer-in-
charge according to the schedule of work.
Bar bending schedule will be submitted for approval along with the concreting checklist
for approval prior to the work.
The area to receive reinforcement will be thoroughly cleaned. No debris will be left on
the surface.
While placing the reinforcement, approved make cover block to required size will be
placed. Rods will be spread and tied with 18G GI wire double twisted ensuring 100%
binding in all junctions of bars.
Rod will be free from grease, bitumen and mud. Laps will be staggered.
a. Shoes
b. Helmet
c. Gloves.
d. Goggles
OPR-WMS-005
Dec 2019 Page 13 of 24
Logos property India
Work Method Statement
Sample mock up will be prepared using approved colour and confirmed for approval of the
same.
Surface to be painting area will be free from mortar or any other impurities.
All patch works will be completed one day before on priority basis.
Second coat putty will be applied over the well dried first coat of putty.
Putty surface rubbing will be done till getting the smooth surface.
One coat of primer and two coat of approved colour, shade and make final paint to be applied
a. Shoes
b. Helmet
c. Gloves.
d. Safety belt.
Sign board will be provided on scaffolding for incomplete scaffolding to avoid worker usage.
OPR-WMS-005
Dec 2019 Page 14 of 24
Logos property India
Work Method Statement
Surface to be painting area will be free from mortar or any other impurities.
All patch works will be completed one day before on priority basis.
Approved make and shade of texture grains coat to be applied over the plastering.
Thickness and shade of texture to be maintained evenly through out the surface of wall.
One coat primer and two coats of approved colour and shade weather shield paint to be
applied over the texture.
Colour and shade will be maintained evenly through out the painting area.
a. Shoes
b. Helmet
Climbing the ladder initially with safety belt with double lanyard for fixing theassembled life
line at the top of the platform on the ladder or structure.
One person will be doing this activity at height. And create on point Anchor from
ladder or structure and release the Grip adjusting rope lanyard to create second
Anchorage on the top of the roof.
Access the roof with the support of Grip adjusting rope lanyard or with the help of
double lanyard.
After securing to the hand rail of ladder (Available anchor over the roof top), mark the first
post position.
Drill holes by placing the roof post and Rivet the posts on to the roof sheet of fix the standing
seam post on seam peak. Taking support from this post move to the next position for fixing
another roof post.
OPR-WMS-005
Dec 2019 Page 15 of 24
Logos property India
Work Method Statement
Repeat the above procedure for further post fixing. At every 15 meters distance and create
another anchor point and install the post and connect the temporary life line on the anchor
post.
After Installing all the Post connect the Shock absorber and Tensioner with wire rope for the
life line installation.
Apply the Tension to the Cable with support of Tensioner and tight the wire until the Tension
indicator touches the L plate and once the line is fixed on the posts, inspects the line for the
proper tension applied.
The inspection of life line system after installation will be carried out for the quality
checks of the products and also the proper installation of the life line. Please view the
below inspection sheet formats.
SAFETY PRECAUTIONS:
For fall Hazards – Always wear safety helmets, safety shoes while working on the
plant and use safety belt with double lanyard connected with anchor point while
working on the roof & heights above 2 mtrs. Use proper rope for lifting the material.
Electrical Hazards –Always use the proper MCB and industrial sockets for the power
cables. Use the proper power cable without any pinholes and joint.
Slip & trip hazards – Use a proper safety shoes and barricade the work area with
barricading tape.
GENERAL CONSIDERATIONS
The priority during the construction is to minimize on-site construction and provide extensive
prefabrication.
OPR-WMS-005
Dec 2019 Page 16 of 24
Logos property India
Work Method Statement
Proper planning during design stage is required, with consideration of column and beam
spacing for the following:
Hoisting of precast facade panel for external walls ensure the steel member sizes are easy to
hoist, manage and install on site other site constraints such as accessibility and limitations of
hoisting equipment’s need to be considered. These constraints may subsequently affect the
sequence of construction for the development.
Fabrication, Erection and approval of Steel Structures shall be in compliance as per IS: 800.
SEQUENCE OF INSTALLATION
Erection of steel column and beams - Temporary bracing was required to ensure
verticality of steel columns when bolt connections from beams to columns were
tightened.
Bolted connection for column to beam with laying of metal decking for second storey
and roof.
Make sure there is space and firmed pathway for truck delivery, crane truck erection
operation. The suitable truck & crane capacity must be clarified (and listed in the equipment
register).
Survey the wind direction to have plan for roof material storage and installation direction.
Decide the plan for unloading and material storage. Choose a firm and dry location. Materials
shall be stored in designated areas for each building and clearly identified for their location in
that area.
Make sure that materials supply and storage schedule is appropriate and not conflict with the
installation schedule and other sub-contractors’ schedules.
Register the available power & water supply source locations at the site. Make sure there is a
safe method to lead the supply to the working area.
All delivery to site shall be informed by production people to the site manager 24 hours earlier to
have plan for unloading.
A delivery note is always enclosed with the supplied materials to clarify name of project,
location, building number, type of materials, quantity, date of delivery, etc….
OPR-WMS-005
Dec 2019 Page 17 of 24
Logos property India
Work Method Statement
Upon arrival of materials at the storage yard, the material controller will match delivery notes
and shall verify the consignment. The material controller, then, report to the site supervisor
the received material list and quality condition.
Unloading can be done manually or with cranes. A spreader should be used for lifting long
components. Lifting nylon or cloth belts with suitable SWL shall be used for unloading the
materials to minimize the damage. Be sure to hook belts to component with the right no. of
points and position so that the load of component itself do not damaged or broken.
Always attach a tag line to the lifting component.
All materials receipt at site shall be visually inspected by site supervisor for any damage.
Remedial works to the damage shall be taken immediately, if possible, to avoid any delay to erection.
The structural frames and other parts of the building can be erected in various ways which
will depend on the following key factors:
- The type of structures such as: small clear span, large clear span, low rise building, high
building, taper I structure, open-web structure, etc…
- The sequence/method of erection shall be studied and planned so that execution can be
carried out in a safe, economical and efficient manner.
- There are certain erection practices which are in general use and have proven sound over the
years.
OPR-WMS-005
Dec 2019 Page 18 of 24
Logos property India
Work Method Statement
5 RESPONSBILITY MATRIX
METEC
RESPONSIBILITY
& AUTHORITY
CHART
Sl. Responsibility Authority Remarks
Designation
No.
1 Project Overall Project Execution.
Manager (PM)
Approval of Master Recommendation of sub-
Construction Schedule and contractors / vendors.
Monthly Schedules.
Co-ordination & Approval of sub-
Correspondence with Client. contractor work & invoices
for payment.
Co-ordination with the Decission to accept any
Staff & Mangement. deviations.
Approval of Monthly Giving decisions in co-
Reports to Client and ordination with DPM / Site
percentage progress. Manager.
Cost control of the Project /
Approval of Monthly
Expenses Sheet.
2 Site Manager Assistance to PM in Work allocation of staff in
OPR-WMS-005
Dec 2019 Page 19 of 24
Logos property India
Work Method Statement
Water
absorption,
Bulk density
& Specific
Gravity
Conduct awareness among crew and staff members on how to protect themselves from the
infection of Covid-19 through communication in daily tool box meeting.
Report to be shared with LOGOS/PMC team if any person shows symptoms such as high
body temperature, coughing and difficulty in breathing.
All Staff and workers are instructed to maintain a safe distance of 1 mtr from each other if not
then Face shield must be used.
Key: Level of Significance: Level 1 An impact that could cause pollution or degradation that may have irreversible detrimental
(High Severity) effects on the environment and/or community.
Level 2 An impact that could cause pollution or degradation that may have persistent but reversible
(Medium Severity) detrimental effects on the environment and/or community.
Level 3 An impact that could cause pollution or degradation that may have short term and
(Low Severity) reversible detrimental effects on the environment and/or community.
Aspects Sources Level of Significance Mitigation Plan Responsible By
Noise Construction works in Day Level 2 Noise Monitoring regularly
time
Construction Works in Level 2 Ensure noise works does not
Night hours exceed 75 dB carried on night Project Engineer
Air Quality Cutting Level 2 Project Engineer
Water Quality Level 2 Collection pit Project Engineer & EHS
Manager
Waste Packing of material. Level 2 Reuse and dispose through Project Engineer & Logistic
authorized collector Manager
OPR-WMS-005
Dec 2019 Page 24 of 24