Construction Management project

Graduation Project Report


Spring 2022

“MID TOWN MALL-SOLO”

Prepared by Group (4):

Ali Nasreldein Saad 75335


Ahmed Safwat 70586

Khaled Abdelrahman 64156


Ayman Ehab 64644

Ahmed Gamal 58726

Adel Gamal 75319

SUPERVISED BY:

DR. SHADY DOKHAN


Table of content

Chapter1:PROJECTSCOPE............................................................4
1.1 PROJECT LOCATION.....................................................................5

1.2 PROJECT DESCRIPTION...............................................................6

1.2.1 Project Information......................................................................7

1.2.2 Project consists of.........................................................................7

1.2.3 Graduation ProjectScope.............................................................8

1.3 PROJECT STAKEHOLDERS.......................................................10


1.4 WORK BREAKDOWN STRUCTURE.........................................11
1.5 PROJECT CHARTER ...................................................................12

Chapter 2: CONTRACT ANALYSIS........................................16


2.1 INTRODUCTION ..........................................................................17

2.2 TYPE OF TENDERS…..................................................................18

2.3 TYPES OF CONTRACT .............................................................18

2.4 Parties of the contract :..............................................................18

2.5 CONTRACT VS FIDIC .................................................................19

Chapter 3: WBS & ACTIVITY LIST........................................48


3.1 WORK BREAKDOWN STRUCTURE (WBS) ...........................49

3.2 Primavera ………............................................................................52

3.3 ACTIVITY LIST ............................................................................54

Chapter 4: CONSTRUCTION METHOD STATEMENT………63


4.1 CONSTRUCTION STRATEGY ......................................................................64

4.2 ALTERNATIVES ..............................................................................................69

MID TOWN MALL – SOLO 2


4.3 METHOD STATEMENT..................................................................................71

Chapter 5: RISK MANAGEMENT.......................................90


4.1 CONSTRUCTION STRATEGY ......................................................................91

4.2 ALTERNATIVES ..............................................................................................95

Chapter 6: QUANTITY SURVEYING ................................96

MID TOWN MALL – SOLO 3


Chapter (1)

Project Scope

1.1 Project Location

1.2 Project Descrption

1.3 Project stakeholders

1.4 Project WPS

1.5 Project data

MID TOWN MALL – SOLO 4


1.1 Project Location

Midtown Mall – Solo is located in The new


administration capital (8A) R7 It is directly on Bin Zayed
road at the corner of the New Cathedral (Birth of Christ
Cathedral) and only 20 minutes away from the center of
New Cairo.

MID TOWN MALL – SOLO 5


1.2 Project Description
1.2.1Project information:
Midtown Mall – Solo is a service project to provide life
needs to all residents of the new administration capital
and mid solo compound, also the mall provides
commercial and administrative units for sale, contain
restaurants and cafes to serving units owners of the
compound.
the Mall located in the new administration capital (8A)
R7 district in front of cathedral of nativity of Christ and
martyrs’ square
The contract works include: -
- Concrete Skelton (Earthworks, Buildings works, Steel works).
- Electromechanical works (firefighting, elevators work).
- Finished works.

• The mall is consisting of 3 roofs: basement and first and


second floor and roof
• The net area of the mall is 26.630 m²
• the buildings area 2200 m² about 20% of total area and the
rest landscapes and pools
• Commercial units’ area starts from 75m² to 265m²
• Administrative units’ area starts from 125m² to 402m²
• Kids area to entertain client’s kids
• Mall contain mosque and pharmacy opens 24 H and
gymnasium and meetings rooms

MID TOWN MALL – SOLO 6


1.2.2 Project Consist of
1. Midtown solo compound
2. Midtown solo Mall

1.5 Project data

Project name Mid-town solo Mall

Start date 1/10/2020

Finish date 31/8/2022

Amon for real estate


Owner
developments

Project contractor Redcon construction co.

Project consultant Better home

Contract type Lump sum

MID TOWN MALL – SOLO 7


1.3 Project Stakeholders

Amoon for real estate


Owner
development

Owner
Better Home
consultant

Main contractor Redcon

MID TOWN MALL – SOLO 8


contractual Milestone: -

MID TOWN MALL – SOLO 9


BOQ contents and budget detailed: -

Earthworks 2.297.150 LE
Concrete works 91.124.670 LE
Buildings works 7.543.670 LE
Steel works 1.967.694 LE
Isolation works 4.804.780 LE
Finishings works 82.779.527 LE
Windows and doors work 1.504.078 LE
Bathrooms accessories works 139.170 LE
Firefighting works 11.405.053 LE
Elevators works 2.508.000 LE
Mechanical works 9.532.110 LE
Electrical works 18.708.787 LE
Electricity rooms 3.479.955 LE
Fence and gates 3.525.876 LE
Total Budget 241.320.520 LE

Works that finished by subcontractor: -


Glass processor
Aluminum fabricator
Isolation works

MID TOWN MALL – SOLO 10


1.4 Work Breackdown Structure

MID TOWN MALL – SOLO 11


MID TOWN MALL – SOLO 12
PROJECT DESCRIPTION

The net area of the mall is 26.630 m² the buildings area 2200 m² about 20%
of total area and the rest landscapes and pools.
The mall is consisting of 3 roofs: basement and first and second floor
Consist of administrative and commercial units.
Commercial units’ area starts from 75m² to 265m².
Administrative units’ area starts from 125m² to 402m².
There are garages to park cars and Kids area to entertain client’s kids.
Midtown contain about 24000m² landscape to entertain clients and provide
gorgeous view.
Mid town contain restaurants and cafes to serving units owners of the
compound.
Mall contain mosque and pharmacy opens 24 H and gymnasium and
meetings rooms.

MID TOWN MALL – SOLO 13


PROJECT GOALS

The importance of this mall is to serve the residents of midtown


compound and whole the new administration city as it considers
a new capital in the future
This project helps in revitalizing tourism and the economy

In scope :-
-Mid-Town solo mall

Out of scope :-
-Mid-Town solo compound

MID TOWN MALL – SOLO 14


ASSUMPTION AND CONSTRAINS

-EASY OF OBTAINING PERMITS

. - QUALIFIED CONTRACTORS ARE AVAILABLE AND INTERESTED IN THE


PROJECT.

- CLIENT DELIVERABLE WILL BE MADE ON TIME ACCORDING TO SCHEDULE.

- AVAILABILITY OF WATER AND ELECTRICITY SOURCE.

CONSTRAINS: -

- MILESTONES DATES MUST BE FOLLOWED

. - THE COMPLETION OF THE PROJECT MUST BE ON TIME 8/10/2021.

MID TOWN MALL – SOLO 15


Chapter (2)

CONTRACT ANALYSIS

2.1 INTRODUCTION

2.2 TYPE OF TENDERS

2.3 TYPES OF CONTRACT

2.4 Parties of the contract

2.5 CONTRACT VS FIDIC

MID TOWN MALL – SOLO 16


2.1 Introduction:
Contract Analysis Aims to compare project contract with standard
contract form to know what risks might arise. The standard form we
follow is “YELLOW FIDIC 2017“

2.1.1 FIDIC:

FIDIC aims to represent globally the consulting engineering field by


promoting the interests of firms/engineers supplying technology-based
intellectual services for the built and natural environment.

2.1.2 Types of FIDIC:

The most common types:

Red book:

for Construction projects designed by the employer in this contract form,


the contractor constructs the works in the accordance with a design
provided by the owner

Yellow book:

for Design-Build projects. In this Type the contractor design and


construct the works in the accordance with the owner.

Green book:
for short-form agreements: Recommended for building or engineering
works of small capital value.

Silver book

In this form, the contractor is responsible for the design and the execution
of the project with little involvement from the employer.

MID TOWN MALL – SOLO 17


2.2 Tender:

Direct order tenders:

• A direct order is given to a selected contractor to carry out the


work on a certain basis.

This type of tender:

• facilitates changing orders during the contract


• fulfillment.

2.3 Parties Of the contract:

First • Amoon Real Estate &


Party Tourism Development

Second • Redcon Construction


Party Co

2.4 Contract Type:

Cost Plus (Design-Build)

MID TOWN MALL – SOLO 18


2.5 Contract Analysis:

Contract Yellow FIDIC Clauses: Priority of Comment Risk


Clause Documents (1.5)
)1-‫(بند‬ The Contract Documents are to be considered as
mutually explanatory of one another. In the
‫العقد‬ event of a conflict, the priority of the documents
ً‫تعتبر المقدمة جزء اليتجزا‬ shall be according as follows:
‫من العقد؛ كما ان مرفقات‬ (a) the Contract Agreement.
(b) the Letter of Acceptance.
‫العقد والمنوه عليها في‬
(c) the Letter of Tender.
‫صلب العقد هي كذلك جزء‬ (d) the Particular Conditions Part A – Contract
‫من العقد وال يعمل بهذا‬ Data.
‫العقد بدونها‬. (e) the Particular Conditions Part B – Special
Provisions. Fair and
(f) these General Conditions. Similar
(g) the Specification.
(h) the Drawings.
(i) the Schedules.
(j) the JV Undertaking (if the Contractor is a JV).
(k) any other documents forming part of the
Contract.
If a Party detects an uncertainty or discrepancy,
that Party must notify the Engineer promptly,
describing the Issue. the Engineer shall concern
the necessary clarification or instruction.

MID TOWN MALL – SOLO 19


Contract Clause Yellow FIDIC Clauses: Care and Supply Comment Risk
of Documents (1.8)
Each of the Contractor’s Documents shall be in the custody and care of
) 2 - ‫( بند‬ there is a
the Contractor, unless and until submitted to the Engineer. The risk to the
‫الغرض من العقد‬ Contractor shall supply to the Engineer one paper-original, one
contractor
‫قيام الطرف الثانى بتنفيذ‬ electronic copy (in the form as specified in the Employer’s Requirements
or, if not stated, a form acceptable to the Engineer) and additional paper Fidic Was in the event
‫األعمال المشار إليها كمقاول‬
ً ‫عام لصالح الطرف االول طبقا‬ copies (if any) as stated in the Contract Data of each of the Contractor’s more that he is
‫لألسعار والشروط الموضحة‬ Documents. Descriptive not aware
‫وطبقا ً للرسومات والمواصفات‬ The Contractor shall keep at all times, on the Site, a copy of: of all the
‫الهندسية وجداول الكميات وباقي‬ (a) the Contract;
plans and
‫مستندات االعمال؛ ويقر الطرف‬ (b) the records under Sub-Clause 6.10 [Contractor’s Records] and
‫الثاني بأنه قد عاين موقع العمل‬ Sub-Clause 20.2.3 [Contemporary records]; specificatio
‫وأنه قد اطلع على كافة‬ (c) the publications (if any) named in the Employer’s Requirements; ns and does
‫المخططات والمواصفات‬ (d) the Contractor’s Documents; and not inspect
‫الخاصة والعامة لجميع األعمال‬ (e) Variations, Notices and other communications given under the the site so
‫المطلوبة وكذلك األعمال‬ Contract.
‫االخرى المرتبطة بها وانه قد قام‬ that he
The Employer’s Personnel shall have right of access to all these
‫بدراستها وتحديد أسعاره بناء‬ documents does not
‫ وأنه اليجوز إجراء‬.‫على ذلك‬ during all normal working hours, or as otherwise agreed with the have to
‫أى تعديل عليها اال بعد الحصول‬ Contractor carry out
‫على موافقة كتابية من الطرف‬ If a Party (or the Engineer) becomes aware of an error or defect (whether
‫أي شروط مقدمة من‬.‫األول‬ additional
of a technical nature or otherwise) in a document which was prepared by
‫الطرف الثاني بالعرضين المالي‬ (or on behalf of) the Contractor for use in the execution of the Works, the
work and
‫والفني ال يُعتد بها والعبرة بالعقد‬ bear its
Party (or the Engineer) shall promptly give a Notice of such error or
.‫ومستندات التعاقد ومالحقه فقط‬ cost
defect to the other Party (or to the Parties). The Contractor shall then
. promptly rectify the error or defect at the Contractor’s risk and cost. (threat)
.

MID TOWN MALL – SOLO 20


Contract Clause Yellow FIDIC Clauses: Advance Comment Risk
Payment (14.2)
) 3 - ‫( بند‬ If no amount of advance payment is stated in the - The FIDIC -There is no
Contract Data, this Sub-Clause shall not apply. After risk to the
‫شروط السداد‬ agrees with the
receiving the Advance Payment Certificate, the Employer contractor
‫ دفعة مقدمة مقابل خطاب‬%15- shall make an advance payment, as an interest-free loan contract, but
except in the
‫ضمان بنكي غير مشروط ويخفض‬ for mobilisation and design. The amount of the advance the contract is event of a
‫بنفس النسبة من حجم العمل‬ payment and the currencies in which it is to be paid shall explained delay in the
‫بالمستخلصات المعتمدة على أن يتم‬ be as stated in the Contract Data.
more in terms project
‫استرداد قيمة الدفعة المقدمة بالكامل‬ 14.2.1 Advance Payment Guarantee
of time (Opportunity)
‫) شهر من بداية المشروع‬21( ‫بعد‬ The Contractor shall obtain (at the Contractor’s cost) an
Advance Payment Guarantee in amounts and currencies -Fidic Was more - There is no
‫وتصرف بعد عمل محضر استالم‬ risk to the
equal to the advance payment, and shall submit it to the Descriptive The
‫الموقع وتقديم أصل بوليصة التأمين‬ contractor
Employer with a copy to the Engineer. This guarantee FIDIC gave a
‫على المشروع (طبقا ً لالشتراطات‬ except in the
shall be issued by an entity and from within a country (or
‫" تشمل مدة‬2" ‫الموضحه بملحق‬ other jurisdiction) to which the Employer gives consent,
period of 7 case of
)‫ سنة ضمان على األعمال‬+ ‫المشروع‬ and shall be based on the sample form included in the days to present incomplete or
.‫وتقديم تحليل أسعار بنود المقايسة‬ tender documents or on another form agreed by the proof of its invalid works
.‫ مستخلصات حسب نسب اإلنجاز‬- Employer (but such consent and/or agreement shall not (Opportunity)
veracity
‫ جميع االسعار المتفق عليها‬- relieve the Contractor from any obligation under this
)‫(والموجوده بالمقايسة المرفقة بالعقد‬ Sub-Clause). The Contractor shall ensure that the
‫تشمل كافة االستقطاعات والضرائب‬ Advance Payment Guarantee is valid and enforceable
‫والتأمينات االجتماعية وضريبة القيمة‬ until the advance payment has been repaid, but its
‫المضافة والنولونات وكارتات الطرق‬ amount may be progressively reduced by the amount

.‫للمياه والمواد والمعدات وخالفه‬ repaid by the Contractor as stated in the Payment
Certificates. If the terms of the Advance Payment
‫ التأمين الجارى على االعمال وقيمته‬-
Guarantee specify its expiry date, and the advance
‫ يعلى على المستخلصات الجارية‬%5
payment has not been repaid by the date 28 days before
‫طبقا ً لتقدم األعمال ويرد خالل شهر‬
the expiry date: (a) the Contractor shall extend the
‫من عمل محضر االستالم االبتدائي‬
validity of this guarantee until the advance payment has
.‫لألعمال‬ been repaid; (b) the Contractor shall immediately submit
‫ يقوم الطرف الثانى بسداد‬-5% ‫من‬ evidence of this extension to the Employer, with a copy
‫إجمالى العقد كتأمين نهانى لألعمال‬ to the Engineer; and (c) if the Employer does not receive
)‫(بخطاب ضمان بنكى غير مشروط‬ this evidence 7 days before the expiry date of this
‫وذلك قبل الشروع في تنفيذ العقد على‬ guarantee, the Employer shall be entitled to claim under
‫ان يرد هذا التأمين بعد مضى عام من‬ the guarantee the amount of advance payment which
.‫عمل محضر اإلستالم االبتدائى‬ has not been repaid. When submitting the Advance
Payment Guarantee, the Contractor shall include an
application (in the form of a Statement) for the advance
payment.

MID TOWN MALL – SOLO 21


Contract Clause Yellow FIDIC Clauses: Right to Comment Risk
Vary (13.1)
)4 – ‫(بند‬ Variations may be initiated by the Engineer under Fidic Was Risk to the
Sub-Clause 13.3 [Variation Procedure] at any time more contractor
‫قائمة الكميات‬ before the issue of the Taking-Over Certificate for Descriptive. because these
‫ الكميات الواردة بجداول الكميات‬.1 the Works. Other than as stated under Sub-Clause The modifications
‫تقريبية الغرض منها بيان حجم األعمال‬
‫بصفة عامة وستتم المحاسبة على الكميات‬ 11.4 [Failure to Remedy Defects], a Variation shall contractor affect the
‫النهائية للحصر الهندسي الفعلي المعتمدة‬ not comprise the omission of any work which is to could Claim duration of
.‫والمنفذة لألعمال‬ be carried out by the Employer or by others unless an Extension the project
otherwise agreed by the Parties. The Contractor of time and (Threat)
‫ يحق للطرف االول قبل او اثناء تنفيذ‬.2
‫االعمال ان يعدل في االعمال المطلوبة او‬ shall be bound by each Variation instructed under cost due to the
‫في اي بند من البنود بالزيادة او النقصان‬ Sub-Clause 13.3.1 [Variation by Instruction], and employer’s
‫كما يكون له الحق في حذف او إضافة‬ shall execute the Variation with due expedition and Variances In
‫بعض االعمال فى نفس نطاق بنود التعاقد‬ without delay, unless the Contractor promptly gives the quantities
‫ من مجموع قيمة‬25% ‫وذلك في حدود‬
‫العقد وبنفس االسعار المنصوص عليها‬ a Notice to the Engineer stating (with detailed or the
‫بجدول الكميات وقت التعاقد وفى حاله‬ supporting particulars) that: (a) the varied work was construction.
‫ من‬15% ‫حذف بنود اعمال اكثر من قيمه‬ Unforeseeable having regard to the scope and the owner
‫اجمالى قيمه العقد يستحق الطرف الثانى‬ nature of the Works described in the Employer’s cannot ask for
‫تعويضا عن نسبه األرباح نتيجه هذا‬
‫إيجذف ويتم االتفاق عليها بين الطرفين في‬ Requirements; (b) the Contractor cannot readily Editing the
‫حينها‬ obtain the Goods required for the Variation; (c) it basic
‫ بعض االعمال (غرف الخدمات‬.3 will adversely affect the Contractor’s ability to elements in
‫بالبدروم) ضمن بنود التعاقد خالل مده‬ comply with Sub-Clause 4.8 [Health and Safety the project.
‫سنه الضمان وبنفس أسعار التعاقد‬
Obligations] and/or Sub-Clause 4.18 [Protection of this was fully
the Environment]; (d) it will have an adverse Mentioned In
impact on the achievement of the Schedule of the FIDIC.
Performance Guarantees; or (e) it may adversely
affect the Contractor’s obligation to complete the
Works so that they shall be fit for the purpose(s) for
which they are intended under Sub-Clause 4.1
[Contractor’s General Obligations].
Promptly after receiving this Notice, the Engineer
shall respond by giving a Notice to the Contractor
cancelling, confirming or varying the instruction.
Any instruction so confirmed or varied shall be
taken as an instruction under Sub-Clause 13.3.1
[Variation by instruction].

MID TOWN MALL – SOLO 22


Contract Clause Yellow FIDIC Clauses: Comment Risk
Commencement of Works
(8.1). & Time for
Completion (8.2)
)5 – ‫(بند‬ 8.1: The Engineer shall give a Notice As stated in the The time
FIDIC Contract schedule
‫البرنامج الزمني لتنفيذ األعمال‬ to the Contractor stating the
Commencement Date, not less than the owner/engineer represents a
‫ يتعين على الطرف الثاني (الشركة‬.1
14 days before the Commencement had to inform the threat to the
‫المنفذة) ان يقوم بتقديم البرنامج الزمتى‬
‫المفصل لألعمال للمراجعة واالعتماد من‬ Date. Unless otherwise stated in the contractor with the contractor
‫قبل الطرف األول طبقا ً للتواريخ المذكورة‬ Particular Conditions, the Commencement because in
‫) بدون تأخير مبرر ومعتمد‬6( ‫بالملحق‬ Commencement Date shall be within Date,14 days the event of
‫من الطرف األول وان ينجز االعمال‬ 42 days after the Contractor receives
‫الموكلة إليه كما بالعقد وقائمةالكميات‬ before the any delay
the Letter of Acceptance. The
.‫ضمن مدة االنجاز المحددة‬ Commencement whether in
Contractor shall commence the
Date, stated in the submitting
‫ يعثبر تقديم البرنامج الزمنى شرطا من‬.2 execution of the Works on, or as soon
Contract, the the time
‫شروط التعاقد يلتزم الطرف الثاني‬ as is reasonably practicable after, the
‫باحترامه على ان يتم تقديمه بحد اقصى‬ Commencement Date and shall then
owner/engineer schedule to a
‫) يوما من توقيع العقد للمراجعه‬21( proceed with the Works with due Informed 21days maximum of
‫واالعتماد؛ وفى حاله اعادته من الطرف‬ expedition and without delay Before. Contractor 21 days or
‫ على‬:‫األول للطرف الثاني بمالحظات‬ gets enough time submitting
‫الطرف الثاني تالفى تلك المالحظات‬ 8.2: The Contractor shall complete
‫واعادة تقديمه للطرف األول خالل ستة‬ the whole of the Works, and each to be prepared. executive
‫ايام من تاريخ استالم الطرف الثاني تلك‬ Section (if any), within the Time for drawings to
‫المالحظات وفى حالة تاخر الطرف الثاني‬ Completion for the Works or Section be approved
‫عن تلك المده فى التقديم تطبق عليه غرامه‬ by the
(as the case may be), including
‫بواقع الفان جنيه مصرى عن اليوم الواحد‬
.‫وبحد اقصى ثالثون ألف جنيها‬ completion of all work which is stated consultant or
in the Contract as being required for carrying out
‫ يقوم البرنامج الزمنى على طريقه‬.3 the Works or Section to be considered the works
‫علميه معروفة ومعدالت عمل وموارد‬ to be completed for the purposes of mentioned in
‫يوافق عليهاالطرف األول ويبين بطريقه‬ taking over under Sub-Clause 10.1
‫تخطيطيه مواعيد تنفيذ جميع االعمال‬ the contract a
[Taking Over the Works and Sections].
‫المقترحة لجميع انشطة البنود الرئيسيه‬ fine is
‫وعليه ايضا بيان العماله واطقم التنفيذ‬ applied to the
.‫والمعدات التي سيتم استخدامها‬ contractor
‫ على الطرف الثاني اعداد البرنامج‬4 (threat)
‫الزمنى باستخدام أحدث اصدارات برنامج‬
(Primavera-P6) ‫الحاسب اآللي‬
‫ يجب ان يوضح البرنامج الزمنى‬.5
‫تواريخ تقديم الطرف الثاني للرسومات‬

MID TOWN MALL – SOLO 23


‫التنفيذية والتوريدات واعتمادات‬
‫االستشارى واستالمه لالعمال‬
‫والمواد والرسومات التفصيلية لما يتم يذه‬
‫بالفعل وخطه تقديم العينات لالعتماد على‬
‫ان يكون التقويم المستخدم ألنشطة‬
‫االعتماد من‬
‫قبل االستشارى ‪ 5‬ايام عمل فى االسبوع‪.‬‬

‫‪MID TOWN MALL – SOLO‬‬ ‫‪24‬‬


Contract Clause Yellow FIDIC Clauses: General Comment Risk
Design Obligations (5.1)
)1/6- ‫( بند‬ The Contractor’s Documents shall comprise The required There is a
the documents: (a) specified in the period is 21 risk to the
‫الرسومات التنفيذية و‬ Employer’s Requirements; (b) required to days for FIDIC, contractor if
‫اعتماد المواد‬ satisfy all permits, permissions, licences and
but the contract there is a
other regulatory approvals which are the
allows five delay in its
‫يقوم الطرف الثاني بتقديم الـ‬ Contractor’s responsibility under Sub-Clause
)SHOP DRAWINGS( months, and the delivery or if
1.13 [Compliance with Laws]; and (c)
‫واعتماد المواد الخاصة بالمشروع‬ two stipulated it does not
‫على أن يتم االنتهاء من تقديمها كامله‬ described in Sub-Clause 5.6 [As-Built
‫في موعد أقصاه خمسه أشهر من‬ Records] and Sub-Clause 5.7 [Operation and that it be within conform to
‫تاريخ التعاقد لالعتماد من استشاري‬ the specified the
Maintenance Manuals]. 5.2.1 Preparation by
‫المشروع او المفوض منه باالعتماد‬
‫وتعتبر المدة المشار إليها‬ Contractor Unless otherwise stated in the period of the specification
Employer’s Requirements, the Contractor’s contract. s required in
.‫ داخل المدة الزمنية لتنفيذ العقد‬Documents shall be written in the language
Not mentioned the contract
‫ في حاله تأخر الطرف الثاني‬.2 for communications defined in Sub-Clause The contract (threat)
SHOP ( ‫وعدم التزامه بتقديم ال‬ 1.4 [Law and Language]. The Contractor
‫) في الميعاد المحدد‬DRAWINGS deals with this
shall prepare all Contractor’s Documents,
‫بالجدول الزمنى يحق للطرف األول‬ point in more
‫توقيع غرامة وقدرها (مائة جنيها عن‬ and any other documents necessary to
‫كل لوحه متأخرة عن التقديم في‬
detail.
complete and implement the design during
‫الميعاد المحدد يوميا) وبحد أقصى‬ execution of the Works and to instruct the As for the
‫خمسمائة ألف جنيها مصريا‬ contract, it is
‫ثم يحق للطرف االول حينها تكليف‬ Contractor’s Personnel. The Employer’s
‫مكتب استشاري بإعداد هذه‬ Personnel shall have the right to inspect the required that
SHOP )‫الرسومات‬ preparation of all these documents the contractor
‫ (وخصمها من‬DRAWINGS
‫مستحقات الطرف‬ (including any investigation, modelling and be as built
‫الثاني وبدون الرجوع إليه ويكون‬ testing), wherever they are being prepared. according to a
‫ بالعمل بهذه‬١ ‫الطرف الثاني ملزم‬ 5.2.2 Review by Engineer In this Sub-Clause
.‫الرسومات‬ certain level,
5.2.2: - “Review Period” means the period
while fidic
‫ يتعهد الطرف الثاني بالعمل‬.3 not exceeding 21 days, or as otherwise
Building ” ‫بمنظومه ال‬ leaves the
stated in the Employer’s Requirements,
Information Modeling contractor free
‫ وطبقا للخطة المقدمة من‬BIM“ calculated from the date on which the
‫الطرف الثاني‬ Engineer receives a Contractor’s Document
to choose the
(BEP) ‫للطرف األول لالعتماد‬ and a Contractor’s Notice; - “Contractor’s level of
‫من حيث‬BIM Execution Plan
Document” excludes any of the Contractor’s development,
‫تسمية المستندات والملفات‬

MID TOWN MALL – SOLO 25


) MODELS, NAMING, Documents which are not specified in the which is an
CONVENTION, WORK Employer’s Requirements or these
‫ ) وذلك لتبادل‬INSTRUCTION advantage for
‫ لتحقيق‬18177, 0/1317 ‫ملفات‬ Conditions as being required to be the contractor
‫أقصى استفادة في التنسيق بين‬ submitted for Review, but includes all
‫المعماري واإلنشائي واعمال‬
from the point
documents on which a specified
‫على أن يكون‬. ‫الكهروميكانيكا‬ of view of
400/450‫مستوى التطوير‬ Contractor’s Document relies for
fidic.
“ level of development” completeness; and - “Contractor’s Notice”
model & ‫للـ‬LOD means the Notice which shall state that the
‫والمقدمة من الطرف‬documents
‫ويتم‬. ‫الثاني للطرف االول لالعتماد‬ relevant Contractor’s Document is
‫) بمستوى‬AS BUILT( ‫عمل ال‬ considered by the Contractor to be ready for
Level of )LOD 500( Review under this Sub-Clause 5.2.2 and for
development
use, and that it complies with the
Employer’s Requirements and these
Conditions, or the extent to which it does
not do so. If the Employer’s Requirements
or these Conditions specify that a
Contractor’s Document is to be submitted to
the Engineer for Review, it shall be
submitted accordingly, together with a
Contractor’s Notice.
The Contractor shall prepare, and keep up-
to-date, a complete set of
“as-built” records of the execution of the
Works, showing the exact as-built
locations, sizes and details of the work as
executed by the Contractor.
The format, referencing system, system of
electronic storage and other
relevant details of the as-built records shall
be as stated in the Employer’s

MID TOWN MALL – SOLO 26


‫‪Contract Clause‬‬ ‫‪Yellow FIDIC Clauses‬‬ ‫‪Comment‬‬ ‫‪isk‬‬

‫( بند ‪) 2/6‬‬ ‫‪Not mentioned‬‬ ‫‪Not mentioned‬‬ ‫‪There is a risk‬‬


‫‪but the contract‬‬ ‫‪to the‬‬
‫اكتشاف التعارض بعد‬ ‫‪obliges the‬‬ ‫‪contractor‬‬
‫‪contractor to‬‬ ‫‪because when‬‬
‫توقيع العقد‬
‫‪know the problem‬‬ ‫‪there are‬‬
‫‪-1‬فى حالة اى تعارض بين مستندات‬ ‫‪and try to solve it‬‬ ‫‪additional‬‬
‫التعاقد المختلفة ولم يتم حسم هذا‬ ‫‪works not‬‬
‫التعارض صراحة فى اى تعليمات‬ ‫‪mentioned in‬‬
‫كتابية؛ فعلى الطرف الثاني قبل البدء‬
‫فى العمل ان يطلب التوقيع من مدير‬ ‫‪the contract‬‬
‫المشروع الذي سوف يقوم بدوره‬ ‫‪they will be‬‬
‫باصدار قراره النهائى كتابيا للطرف‬ ‫‪implement at‬‬
‫الثاني‪.‬‬ ‫‪the expense of‬‬
‫‪-2‬إذا فشل الطرف الثاني فى‬ ‫‪the‬‬
‫اكتشاف او ابالغ مثل هذا التعارض‬ ‫‪consideration‬‬
‫أثناء فترة التنفيذ وبالتالي وجد ان‬ ‫)‪(threat‬‬
‫األعمال قد مقبولة من مدير‬
‫المشروع؛ فسوف يقوم الطرف الثاني‬
‫على حسابه الخاص باعادة تنفيذ او‬
‫استبدال اوتغيير هذه األعمال حسب‬
‫ما يقررمدير المشروع فى هذا الشأن‬
‫بدون اى مدد اضافية عن زمن تنفيذ‬
‫المشروع او اية مصاريف اضافية‬
‫نتيجة االعتمادات المسبقة‪.‬‬

‫‪MID TOWN MALL – SOLO‬‬ ‫‪27‬‬


Contract Clause Yellow FIDIC Clauses: Comment Risk
Contractor’s Equipment
(4.17)
) 7 - ‫( بند‬ The Contractor shall be responsible for all Whether the Risk to the
Contractor’s Equipment. When brought on contract or fidic, contractor
to the Site, Contractor’s Equipment shall
‫تجهيزات‬ they require the because the
be deemed to be exclusively intended for contractor to entire
)Mobilization(‫الموقع‬
the execution of the Works. The Contractor prepare the entire Mobilization is
‫على الطرف الثاني تجهيز الموقع‬-1 shall not remove from the Site any major site on the
‫من (مكاتب وكرفانات ومولدات‬ items of Contractor’s Equipment without contractor
‫وغرف اجتماعات واطقم التنفيذ و‬ the Engineer’s consent. However, consent within a period
‫ الخ) خالل شهر واحد من تاريخ‬.....
‫التعاقد طبقا ً للخطة المعتمدة من قبل‬ shall not be required for vehicles of time
.‫الطرف األول‬ transporting Goods or Contractor’s specified by
Personnel off Site. the owner
In addition to any Notice given under Sub- (Threat)
Clause 4.16 [Transport of Goods], the
Contractor shall give a Notice to the
Engineer of the date on which any major
item of Contractor’s Equipment has been
delivered to the Site This Notice shall be
given within 7 days of the delivery date,
shall identify whether the item of
Contractor’s Equipment is owned by the
Contractor or a Subcontractor or another
person and, if rented or leased, shall
identify the rental or leasing entity.

MID TOWN MALL – SOLO 28


Contract Clause Yellow FIDIC Clauses: Comment Risk
Transport of Goods (4.16)
)8 - ‫( بند‬ brought on to the Site, Contractor’s FIDIC is required A risk for the
Equipment shall be deemed to be for a specific contractor to
‫المواد‬ exclusively intended for the execution of period of time, bear all risks
the Works. The Contractor shall not which is 7 days, such as damage
‫على (الطرف الثاني) ان بقوم‬ remove from the Site any major items of to wait for the or theft of
‫بمعرفته وعلى حسابه بتدبير كافة‬ Contractor’s Equipment without the engineer materials
‫المواد والمهمات التي تخص تنفيذ‬
Engineer’s consent. However, consent shall )Threat)
)‫أعماله؛ وعلى (الطرف االول‬
‫تخصيص مكان في موقع العمل يكون‬ not be required for vehicles
‫تحت تصرف الطرف الثاني لتشوين‬ transporting Goods or Contractor’s
‫المواد والمهمات االزمة لالعمال‬ Personnel off Site .In addition to any
ً‫على ان يكون الطرف الثاني مسئوال‬
Notice given under Sub-Clause 4.16
‫عن جميع االخطار الناتجة عن ذلك‬
‫وكذلك حراسة هذة التشوينات وال‬ [Transport of Goods],
‫يسمح له بسحب المواد المشونه‬ the Contractor shall give a Notice to the
‫ونقلها خارج الموقع اال بموافقه كتابية‬ Engineer of the date on which any major
‫من مهندس الطرف االول والتعليمات‬
item of Contractor’s Equipment has been
‫والقواعد المعمول بها بجهاز‬
.‫العاصمة االدارية للتنمية العمرانية‬ delivered to the Site .
This Notice shall be given within 7 days of
the delivery date, shall identify whether the
item of Contractor’s Equipment is owned
by the Contractor or a Subcontractor or an
other person and, if rented or leased, shall
identify the rental or leasing entity

MID TOWN MALL – SOLO 29


Contract Clause Yellow FIDIC Clauses: Comment Risk
Protection of the Environment
(4.18)
)9 - ‫(بند‬ The Contractor shall take all necessary Whether contract No risk If the
measures to; (a) protect the environment or fidic contractor is
‫المخلفات‬ (both on and off the Site); (b) comply with They obligate the unable to remove
the environmental impact statement for the contractor to it or delays its
‫الطرف الثاني إزالة جميع المخلفات‬ Works (if any); and (c) limit damage and reduce deal with removal
‫التي تنتج عن تنفيذ اعماله اوال بأول‬ nuisance to people and property resulting waste and get ride according to
‫و نقلها للمقالب العمومية وكذلك تسليم‬
from pollution, noise and other results of the of it government law,
‫جميع االماكن الثي كان تيال ا او‬
‫التشوين او التركيب خالبة و نظيفة‬ Contractor’s operations and/ or activities. Contract clauses the owner can
‫وذلك طبقا للقواعد المعمول بها‬ The Contractor shall ensure that emissions, remove it with
‫بجهاز العاصمة االدارية للثنمية‬ surface discharges, effluent and any other his own
‫العمرائية و إال جاز ( الطرف االول‬
pollutants from the Contractor’s activities knowledge.
‫) إزالتها بمعرفتة وعلي حساب‬
‫الطرف الثاني بعد اخطاره كناب‬ shall exceed neither the values indicated in
‫بإزالتها وخالل بومين وعلى الطرف‬ the Employer’s Requirements nor those (Opportunity)
‫الثاني االحتفاظ ببونات وايصاالت‬ prescribed by applicable Laws.
‫توريد المخلفات لمقالب العاصمة‬
‫وعمل كشف بها وتسليم نسخه‬
‫للطرف األول مع المستخلص‬
. ‫الشهري‬

MID TOWN MALL – SOLO 30


Contract Clause Yellow FIDIC Clauses: Comment Risk
Engagement of Staff and
Labour (6.1) , Health and
Safety of Personnel (6.7)
) 10 - ‫( بند‬ 1-Not Mentioned 1 not mentioned The contractor
but its important bears all the
2-(6.1) Except as otherwise stated in the To complete the risk because he
‫االيدي العاملة‬
Specification, the Contractor shall make work without is responsible
‫يقدم الطرف الثاني كل مايلزم من‬ arrangements for the engagement of all problems and to for the
‫ايدي عاملة للقيام بتنفيذ االعمال‬ Contractor’s Personnel, and for their perfection efficiency of
‫المطلوبة منه علي أكمل وجه ويكون‬
payment, accommodation, feeding, the work to be
‫مسئوالً عن؛‬
‫ان يكونوا من ذوي الخبرة‬-1 transport and welfare. 2 both contract carried out the
‫والكفاءة الفنية الكافيه للقيام باألعمال‬ and fidic They payment of
‫موضوع هذا العقدر‬ 3,4- (6.7) In addition to the requirements of oblige the workers wages
Sub-Clause contractor to pay and
‫ دقع أجور عماله وتعويضاتهم‬-2
‫وعالجهم عن اي حوادث تحدث لهم‬ the workers’ compensation
‫بالموقع وكذاك تأمين وسائل‬ 4.8 [Health and Safety Obligations], the wages and and the
‫المواصالت والسكن لهم‬ Contractor shall at all times take all provide their payment of
necessary precautions to maintain the supplies in full fines resulting
‫ اتباع قواعد السالمة واألمن‬-3
‫الصناعي داخل المواقع وتطبيق‬ health and safety of the Contractor’s from not
1981 ‫ لسئة‬137 ‫وانفاذ القانون‬ Personnel. In collaboration with local 3,4 both contract following the
‫الخاص بالسالمة والصحة المهنية‬ health authorities, the Contractor shall and fidic They rules of
‫(االمن الصناعي) وكافه االشتراطات‬
ensure that: (a) medical staff, first aid oblige the security and
‫الخاصه بجهاز العاصمة االدارية‬
.‫للتنمية العمرائية‬ facilities, sick bay, ambulance services and contractor Safety safety
any other medical services stated in the rules, but unlike (threat)
‫ سالمه تنزيل وتخزين واستخدام‬-4 Employer’s Requirements are available at the fidic contract,
‫المواد الخاصة به في الموقع وتعيين‬
all times at the Site and at any they are not
‫حارس لها إذا لزم االم‬
accommodation for Contractor’s and required by a
‫ على الطرف الثانى تسوية‬-5 Employer’s Personnel; and (b) suitable specific law
‫أوضاع العمالة المؤقتة (العمالة الغير‬ arrangements are made for all necessary
‫منتظمة) طبقا لمتطلبات مكتب العمل‬
welfare and hygiene requirements and for 5 not mentioned
‫قبل المطالبة باى مستحقات وذلك‬
‫طبقأ ً القرار وزارة القوى العاملة‬ the prevention of epidemics. The but its important
9‫ و‬8‫ و‬7‫ و‬6 ‫ مادة‬329 ‫والهجرة رقم‬ Contractor shall appoint a health and safety To complete the
‫وإيفاد الطرف األول ما يفيد ذلك‬ officer at the Site, responsible for work without
maintaining health, safety and protection problems and to
against accidents. This officer shall: (i) be perfection
qualified, experienced and competent for
this responsibility; and (ii) have the

MID TOWN MALL – SOLO 31


authority to issue directives for the purpose
of maintaining the health and safety of all
personnel authorised to enter and/or work
on the Site and to take protective measures
to prevent accidents. Throughout the
execution of the Works, the Contractor
shall provide whatever is required by this
person to exercise this responsibility and
authority.

5- Not Mentioned

MID TOWN MALL – SOLO 32


Contract Clause Yellow FIDIC Clauses: Comment Risk
Assignment (1.7)
) 11 - ‫( بند‬ Neither Party shall assign the whole or any FIDIC was A risk to the
‫التنازل عن المشروع‬ part of the Contract or any benefit or interest moderate to the contractor if he
in or under the Contract. However, either goes bankrupt or
Contractor,
‫ال يحق للطرف الثاني التنازل عن‬ Party: (a) may assign the whole or any part has accumulated
‫هذا العقد ويعتبر ال تم ذلك دون اخذ‬ of the Contract with the prior agreement of
allowing him to works and he
‫موافقة الطرف االول وللطرف االول‬ the other Party, at the sole discretion of such assign but only needs to
‫ان يتخذ ما يراه مناسبا لحفظ حقوقه‬
‫دون ان يكون للطرف الثاني الحق‬ other Party; and (b) may, as security in under certain withdraw and an
‫في المطالبة بأي تعويضات او مبالغ‬ favour of a bank or financial institution, conditions, and advantage for the
.‫او أي شئ آخر‬ assign the Party’s right to any moneys due, owner so that his
does not
or to become due, under the Contract without works do not
eliminate his
the prior agreement of the other Party. stop suddenly
liability to the and therefore
owner delay in
implementing
them
(Threat)

MID TOWN MALL – SOLO 33


MID TOWN MALL – SOLO 34
Contract Clause Yellow FIDIC Clauses: Progress Comment Risk
Reports (4.20) , Delay Damages (8.8)

) 13 - ‫( بند‬ 1- Monthly progress reports, in the format The contractor


stated in the Employer’s Requirements (if bears all the
‫الدفعات‬ not stated, in a format acceptable to the
risk because
Engineer), shall be prepared by the
when there are
‫يتم صرف دفعات شهرية (خالل‬. .1 Contractor and submitted to the Engineer.
‫ يوم عمل من تاريخ تقديم‬30 Each progress report shall be submitted in fines they are
‫فقات) للطرف‬, ‫المستخلص كامل‬ one paper-original, one electronic copy and Fair and Similar deducted from
‫الثاني وذلك بموجب مستخلصات‬
‫تحرر‬ additional paper copies (if any) as stated in the extracts
‫بواسطة الطرف الثاني مرفق بها‬ the Contract Data. The first report shall (threat)
‫دفاتر الحصر وتعتمد من مهندس‬ cover the period up to the end of the first
‫ مدير مشروع‬/ ‫االشراف الهندسي‬ month following the Commencement Date.
.‫الطرف االول‬
Reports shall be submitted monthly
‫ يحق (للطرف االول) في ان‬.2 thereafter, each within 7 days after the last
‫يخصم من مستحقات الطرف الثاني‬ day of the month to which it relates.
‫اية مبالغ قد تكون مستحقة السداد فيما‬ Reporting shall continue until the Date of
‫يخص غرامات مستحقات اخري‬
‫على (الطرف الثاني) قبل عمالة او‬ Completion of the Works or, if outstanding
‫قبل الغير يصدر بها حكم قضائي في‬ work is listed in the Taking-Over Certificate,
‫هذا الشأن على ان يتم ابالغ الطرف‬ the date on which such outstanding work is
.‫الثاني بذلك‬ completed. Unless otherwise stated in the
‫ من المتفق عليه ان اية دفعة يتم‬.3 Employer’s Requirements, each progress
ً‫صرفها للطرف الثاني ال تعد قبوال‬ report shall include: (a) charts, diagrams and
‫من (الطرف االول) عن االعمال‬ detailed descriptions of progress, including
‫المنفذة او التشوينات المورده ولكن‬ each stage of design, Contractor’s
‫العبره بتسليم االعمال واعتمادها من‬
‫قبل الطرف األول او من يمثله او‬ Documents, procurement, manufacture,
.‫استشاري المشروع‬ delivery to Site, construction, erection,
testing, commissioning and trial operation;
‫يتم صرف دفعة تشوينات للخامات‬..4 (b) photographs and/or video recordings
‫(الحديد والخامات الرئيسية‬
75% ‫للتشطيبات) بنسبة تساوى‬ showing the status of manufacture and of
‫(خمسة وسبعون بالمائة) من قيمة‬ progress on and off the Site; (c) for the
‫الخامات‬ manufacture of each main item of Plant and
‫طبقا ً لفاتورة الشراء وعلى أرضي‬ Materials, the name of the manufacturer,
‫المصنع (بالنسبة لخامه الحديد) وقت‬
‫الشر اء بعد موافقة الطرف األول‬ manufacture location, percentage progress,
‫عليه كتابيا ً على النموذج المعد لذلك‬ and the actual or expected dates of: (i)
.*»‫ولكل طلبيه على حده‬ commencement of manufacture, (ii)
Contractor’s inspections, (iii) tests, and (iv)
shipment and arrival at the Site; (d) the

MID TOWN MALL – SOLO 35


details described in Sub-Clause 6.10
[Contractor’s Records]; (e) copies of quality
management documents, inspection reports,
test results, and compliance verification
documentation (including certificates of
Materials); (f) a list of Variations, and any
Notices given (by either Party) under Sub-
Clause 20.2.1 [Notice of Claim]; (g) health
and safety statistics, including details of any
hazardous incidents and activities relating to
environmental aspects and public relations;
and (h) comparisons of actual and planned
progress, with details of any events or
circumstances which may adversely affect
the completion of the Works in accordance
with the Programme and the Time for
Completion, and the measures being (or to
be) adopted to overcome delays. However,
nothing stated in any progress report shall
constitute a Notice under a Sub-Clause of
these Conditions
2- If the Contractor fails to comply with Sub-
Clause 8.2 [Time for Completion], the
Employer shall be entitled subject to Sub-
Clause 20.2 [Claims For Payment and/or
EOT] to payment of Delay Damages by the
Contractor for this default. Delay Damages
shall be the amount stated in the Contract
Data, which shall be paid for every day
which shall elapse between the relevant
Time for Completion and the relevant Date
of Completion of the Works or Section. The
total amount due under this Sub-Clause shall
not exceed the maximum amount of Delay
Damages (if any) stated in the Contract Data.
These Delay Damages shall be the only
damages due from the Contractor for the
Contractor’s failure to comply with Sub-
Clause 8.2 [Time for Completion], other than

MID TOWN MALL – SOLO 36


in the event of termination under Sub-Clause
15.2 [Termination for Contractor’s Default]
before completion of the Works. These
Delay Damages shall not relieve the
Contractor from the obligation to complete
the Works, or from any other duties,
obligations or responsibilities which the
Contractor may have under or in connection
with the Contract. This Sub-Clause shall not
limit the Contractor’s liability for Delay
Damages in any case of fraud, gross
negligence, deliberate default or reckless
misconduct by the Contractor.

MID TOWN MALL – SOLO 37


Contract Clause Yellow FIDIC Clauses: Delay Damages Comment Risk
(8.8) , Termination for Contractor’s Default
(15.2)
) 15 - ‫( بند‬ 1-If the Contractor fails to comply with Sub-Clause 8.2 Full risk
[Time for Completion], the Employer shall be entitled to the
subject to Sub-Clause 20.2 [Claims For Payment and/or contractor
‫جزاءات التاخير‬
EOT] to payment of Delay Damages by the Contractor for any
‫ إذا تأخر الطرف الثاني في إتمام‬.1 for this default. Delay Damages shall be the amount delays,
‫االعمال وتسليمها حسب المراحل‬ stated in the Contract Data, which shall be paid for Fair and for
ً ‫المحددة بالبرنامج الزمني وطبقا‬
every day which shall elapse between the relevant Similar example,
‫) لكل‬6( ‫للتواريخ المذكورة بالملحق‬
‫مرحلة على توقيع غرامه تأخير على‬ Time for Completion and the relevant Date of fines of 1
‫ عن كل‬%1 ‫الطرف الثانى بنسبة‬ Completion of the Works or Section. The total amount percent
‫اسبوع تأخير او عشرة االف جنيها عن‬ due under this Sub-Clause shall not exceed the from each
‫كل يوم (ايهما أكبر) بما ال يتجاوز‬
maximum amount of Delay Damages (if any) stated in stage for
‫ من قيمة االعمال المتأخره لكل‬%10
.‫مرحلة على حدة‬ the Contract Data. These Delay Damages shall be the each week
only damages due from the Contractor for the of delay.
‫ يحق للطرف االول توقيع جزاء‬.2 Contractor’s failure to comply with Sub-Clause 8.2 )Threat)
‫(قابل للرفع حال تالفيه) حسب رأى‬
[Time for Completion], other than in the event of
‫الطرف االول وذلك على الطرف الثانى‬
‫طبقا للحاالت المذكوره‬ termination under Sub-Clause 15.2 [Termination for
‫(سحب االعمال) باالضافه الى‬16 ‫ببند‬ Contractor’s Default] before completion of the Works.
‫إذا ما أهمل او تقاعس في اصالح ايه‬ These Delay Damages shall not relieve the Contractor
‫عيوب تشوب اعماله خالل مده التنفيذ‬
from the obligation to complete the Works, or from any
‫او اهمال تعليمات الطرف االول فيما‬
‫يخص اعمال السالمه والصحه المهنيه‬ other duties, obligations or responsibilities which the
‫أو مراقبه الجودة وذلك باتخاذ االجراء‬ Contractor may have under or in connection with the
‫التصحيحي الالزم فى مده اقصاها ثالثه‬ Contract. This Sub-Clause shall not limit the
‫ايام من تاريخ اعالمه واال جاز للطرف‬
Contractor’s liability for Delay Damages in any case of
‫االول توقيع غرامه تقدر ب‬
ً ‫ (عشرة االف جنيها‬10000.00 fraud, gross negligence, deliberate default or reckless
‫اسبوعيا) وتكرر وتتضاعف حال‬ misconduct by the Contractor.
‫استمرارها أو تكرارها لحين ازاله‬

MID TOWN MALL – SOLO 38


‫ العيب او المخالفه اسبوعيا ً طبقا لمكاتبه‬2- Termination of the Contract under this Clause shall not
.‫ من الطرف االول تفيد بذلك‬prejudice any other rights of the Employer under the Contract
‫ من قبل جهاز العاصمة االدارية للتنمية‬or otherwise. 15.2.1 Notice The Employer shall be entitled to
‫العمرانية‬
give a Notice (which shall state that it is given under this Sub-
‫ يتحمل (الطرف الثاني) كافة‬.3 Clause 15.2.1) to the Contractor of the Employer’s intention to
‫الجزاءات التي توقع على الطرف االول‬ terminate the Contract or, in the case of sub-paragraph (f), (g)
‫المشروع في حالة تاخره عن تنفيذ‬ or (h) below a Notice of termination, if the Contractor:
‫االعمال باالضافة الي ما جاء‬ (a) fails to comply with: (i) a Notice to Correct; (ii) a binding
agreement, or final and binding determination, under Sub-
‫او الجهات السيادية والحكومية وكذلك‬
Clause 3.7 [Agreement or Determination]; or (iii) a decision of
‫العمالء المشترين للوحدات‬
‫ بالنقطة االولى من هذا البند او اخالله‬the DAAB under 21.4 [Obtaining DAAB’s Decision] (whether
.‫ بشروط او مواصفات هذا العقد‬binding or final and binding) and such failure constitutes a
material breach of the Contractor’s obligations under the
Contract; (b) abandons the Works or otherwise plainly
demonstrates an intention not to continue performance of the
Contractor’s obligations under the Contract; (c) without
reasonable excuse fails to proceed with the Works in
accordance with Clause 8 [Commencement, Delays and
Suspension] or, if there is a maximum amount of Delay
Damages stated in the Contract Data, the Contractor’s failure
to comply with Sub-Clause 8.2 [Time for Completion] is such
that the Employer would be entitled to Delay Damages that
exceed this maximum amount; (d) without reasonable excuse
fails to comply with a Notice of rejection given by the Engineer
under Sub-Clause 7.5 [Defects and Rejection] or an Engineer’s
instruction under Sub-Clause 7.6 [Remedial Work], within 28
days after receiving it; (e) fails to comply with Sub-Clause 4.2
[Performance Security]; (f) subcontracts the whole, or any part
of, the Works in breach of Sub-Clause 4.4 [Subcontractors], or
assigns the Contract without the required agreement under
Sub-Clause 1.7 [Assignment]; (g) becomes bankrupt or
insolvent; goes into liquidation, administration,
reorganisation, winding-up or dissolution; becomes subject to
the appointment of a liquidator, receiver, administrator,
manager or trustee; enters into a composition or arrangement
with the Contractor’s creditors; or any act is done or any event
occurs which is analogous to or has a similar effect to any of
these acts or events under applicable Laws; or if the
Contractor is a JV: (i) any of these matters apply to a member
of the JV, and (ii) the other member(s) do not promptly
confirm to the Employer that, in accordance with Sub-Clause
1.14(a) [Joint and Several Liability], such member’s obligations

MID TOWN MALL – SOLO 39


under the Contract shall be fulfilled in accordance with the
Contract; or (h) is found, based on reasonable evidence, to
have engaged in corrupt, fraudulent, collusive or coercive
practice at any time in relation to the Works or to the
Contract.

MID TOWN MALL – SOLO 40


Contract Clause Yellow FIDIC Clauses: Comment Risk
Delay Damages (8.8)

)16/1( ‫بند‬ If the Contractor fails to comply FIDIC obliges the The
with Sub-Clause 8.2 [Time for contractor to what contractor
‫باعتبار أن الطرف االول هو الطرف األول‬ Completion], the Employer shall be was stipulated in bears all the
‫والمسئول عن حسن تنفيذ االعمال وإنجازها‬ entitled subject to Sub-Clause 20.2 the contract in risk because
ً ‫في موعدها؛ كما انه يتضرر ماديا ومعنوبا‬
‫نتيجة اي تقصير أو تأخير او مخالفة في‬ [Claims For Payment and/or EOT] terms of delay in the event
‫ الخ؛ لذا فإنه يحق له وحسب‬... ‫المواصفات‬ to payment of Delay Damages by penalties or of a default
‫تقديره وحده سحب االعمال من الطرف الثاني‬ the Contractor for this default. Delay compensations, or violation
‫وإخطاره بذلك بأي وسائل االتصال دون‬ Damages shall be the amount stated because the owner in the
‫حاجة الي إنذار أو إجراء قانوني وذلك في‬
:‫االحوال التالية على سبيل المثال ال الحصر‬ in the Contract Data, which shall be is the biggest specifications
paid for every day which shall victim of the the owner
‫ أيام‬7 ‫ إذا توقف عن العمل كليا مدة‬.1 elapse between the relevant Time for delay and the The has the right
‫متواصلة دون توضيح خطي يقبله الطرف‬ Completion and the relevant Date of cases of to withdraw
.‫االول‬
Completion of the Works or Section. termination of the the works
‫ إذا السحب من العمل او تركه الي سبب‬.2 The total amount due under this contract are from him
‫من االسباب مثل؛ االفالس؛ االعسار أو ما‬ Sub-Clause shall not exceed the identical between (threat)
.‫شابه‬ maximum amount of Delay the fidic and the
‫ إذا استعمل الغش أو التالعب في المواد أو‬.3 Damages (if any) stated in the contract
.‫في أي تعامل مع الطرف االول‬ Contract Data. These Delay
(16/2) ‫بند‬ Damages shall be the only damages
due from the Contractor for the
‫باعتبار أن الطرف االول هو الطرف األول‬ Contractor’s failure to comply with
‫والمسئول عن حسن تنفيذ االعمال وإنجازها‬
‫في موعدها؛ كما انه يتضرر ماديا ومعنويا‬ Sub-Clause 8.2 [Time for
‫نتيجة اي تقصير أو تأخير او مخالفة في‬ Completion], other than in the event
‫ الخ؛ لذا فإنه يحق له وحسب‬,.. ‫المواصفات‬ of termination under Sub-Clause
‫تقديره وحده سحب االعمال من الطرف الثاني‬ 15.2 [Termination for Contractor’s
‫وإخطاره بذلك بأي وسائل‬
‫االتصال بسرعه تصحيح اوضاعه خالل‬ Default] before completion of the
‫اربعه عشر يوما والتى تعتبر بمثابة انذار اول‬ Works. These Delay Damages shall
‫وذلك في االحوال التالية على سبيل المثال ال‬ not relieve the Contractor from the
:‫الحصر‬ obligation to complete the Works, or
‫ إذا تأخر في بدء االعمال أو أظهر تباطؤ‬.1 from any other duties, obligations or
‫في تنفيذها بما يؤثر على امكانية تنفيذ‬ responsibilities which the Contractor
.‫المشروع في الموعد المحدد‬ may have under or in connection
with the Contract. This Sub-Clause
‫ إذا أخل بأي شرط في العقد أو أهمل في‬.2
.‫التزاماته المقررة فيه‬ shall not limit the Contractor’s
liability for Delay Damages in any
‫ إذا رفض أو تجاهل تنفيذ التعليمات‬. 3 case of fraud, gross negligence,
,‫الصادرة البه من الطرف االول‬ deliberate default or reckless
misconduct by the Contractor.

MID TOWN MALL – SOLO 41


‫‪ .4‬رفض أو تجاهل تنفيذ التعليمات والقواعد‬
‫واالشتراطات الخاصه بجهاز العاصمة‬
‫االدارية للتنمية العمرانية‪.‬‬

‫وفى حاله عدم استجابه الطرف الثانى‬


‫لتصحيحع اوضاعه بعد انتهاء مهله ال (‪14‬‬
‫يوم) بسبعه ايام تعتبر هذه المدة (‪ 7‬ايام)‬
‫بمثابة االنذار الثاني‬
‫ويحق للطرف االول حينها سحب اال‬
‫االعمال‬

‫‪MID TOWN MALL – SOLO‬‬ ‫‪42‬‬


Contract Clause Yellow FIDIC Clauses Comment Risk

) 17 - ‫( بند‬ If the Contractor fails to carry out any Fidic was specific There is a risk
obligation under the Contract the Engineer about those cases, but to the contractor
‫نتائج سحب االعمال‬ may, by giving a Notice to the Contractor, both law 182 and because if the
require the Contractor to make good the contract was not fully representative
‫في حالة قيام الطرف االول بسحب‬ failure and to remedy it within a specified descriptive of the second
‫االعمال الي سبب من االسباب‬ time (“Notice to Correct” in these party does not
‫الموضحة في البند السابق يتم‬
Conditions). The owner has the right attend or refuse
‫اخطار الطرف الثاني بإيقافه عن‬
‫العمل ويحرر محضر جرد‬ -1The Notice to Correct shall: to terminate the to sign the
‫باالعمال التي ثمت وكذا المواد‬ (i) describe the Contractor’s failure . contractor's contract in minutes of
‫والمعدات التي أحضرها الطرف‬ (ii) state the Sub-Clause and/or provisions 8 cases stipulated in the withdrawal of
‫الثاني بالموقع وذلك خالل ثالثة‬
of the Contract under which the Contractor FIDIC contract: works he will
‫ايام من تاريخ إيقافه عن العمل‬
‫ويوقع علي المحضر مندوب من‬ has the obligation. 5of them have bear all the
‫كل الطرفين؛ واذا لم يحضر‬ (iii) specify the time within which the conditions, including damages,
‫مندوب الطرف الثاني أو رفض‬ Contractor shall remedy the failure, which the warning expenses and
‫التوفيع علي المحضر يقوم الطرف‬
shall be reasonable, taking due regard the notification. If the additional cost
‫آالول باثبات ذلك بالمحضر‬
‫ويخطر به الطرف الثاني علي‬ nature of the failure and the work and/or same mistake is that may result
‫عنوانه ويعتبر ذلك ملزما ً للطرف‬ other action required to remedy it.after repeated, the owner from that
‫الثاني؛ و يكون للطرف االول‬ Notice 14 Day as a time limit to Waiver the has the right to (threat)
‫الحق في ان يكمل وينهي االعمال‬
site. terminate the contract
‫موضوع العقد بمعرفته وعلى‬
‫حساب الطرف الثاني باي وسيلة‬ a) fails to comply. and receive the site
‫يراها الطرف االول؛ ويتحمل‬ (b) abandons the Works or otherwise plainly within 14 days.
‫الطرف الثاني كافة االضرار‬ demonstrates an intention not to continue In the remaining three
‫والمصاريف والتكاليف االضافية‬
performance of the Contractor’s obligations of these cases, the
‫التي قد تنجم عن ذلك ؛ ويحق‬
ً ‫للطرف االول اتخاذ مايراه مناسبا‬ under the Contract . owner has the right to
‫من االجراءات التالية على سبيل‬ (c) without reasonable excuse fails to terminate the contract
: ‫المثال ال الحصر‬ proceed with the Works by Clause 8 without warning and
[Commencement, Delays, and Suspension] without a warning
‫ وقف أي مستحقات او‬.1
‫محتجزات للطرف الثاني وبدء‬ (d) without reasonable excuse fails to letter or notification
‫احتساب غرامة تأخير حتى يتم‬ comply with a Notice of rejection given by of handing over the
‫تكليف طرف ثالث بتكملة االعمال‬ the Engineer under Sub-Clause 7.5 [Defects site after 14 days and
.‫وانهائها‬
and Rejection] expelling the
‫ منع عمال وأفراد الطرف الثاني‬.2 (e) fails to comply with Sub-Clause 4.2 contractor and seizing
.‫من الدخول الي الموقع‬ [Performance Security]. its equipment
• Rescinding the contract and receiving
‫ اسناد االعمال المتبقية الي‬.3
the site without warning or time limit.
‫مقاول آخر على حساب الطرف‬
.‫الثاني مهما كانت فروق االسعار‬

MID TOWN MALL – SOLO 43


‫ منع افراد الطرف الثاني من‬.4 Agreement with a third party or
‫سحب ايه خامات او معدات من‬ subcontracting without the knowledge of the
‫الموقع لحين فض النزاع طبقا لما‬
owner
‫ حل‬-21( ‫هو مذكور ببند‬
.)‫النزاعات‬ Bankruptcy . Evidence of corruption

MID TOWN MALL – SOLO 44


‫‪Contract Clause‬‬ ‫‪Yellow‬‬ ‫‪Comment‬‬ ‫‪Risk‬‬
‫‪FIDIC‬‬
‫‪Clauses‬‬
‫( بند ‪) 19 -‬‬ ‫‪Not mentioned‬‬ ‫‪Not mentioned but‬‬ ‫‪There is a risk‬‬
‫‪The contract should be‬‬ ‫‪to the‬‬
‫القوانين النافذة‬ ‫‪a decisive reference,‬‬ ‫‪contractor‬‬
‫‪as it stipulates that all‬‬ ‫‪because he‬‬
‫‪ 1‬يلتزم الطرف الثاني بتطبيق كافة القوانين المعسول بها في‬
‫‪laws be followed‬‬ ‫‪bears all‬‬
‫جمهورية مصر العربية وخاصة فيما يتعلق بقوانين العمل‬
‫والعمال والضرائب‬ ‫‪criminal and‬‬
‫والتأمينات واالمن الصناعي واجراءات السالمة من الدفاع‬ ‫‪civil‬‬
‫المدني؛ ويتحمل المسؤولية كاملة امام جهات االختصاص‪.‬‬ ‫‪responsibilities‬‬
‫‪in the event of‬‬
‫‪ .2‬يتحمل الطرف الثاني من تاريخ هذا العقد كافة‬
‫المسئوليات الجنائية اوالمدنية في حالة الحوادث (ال قدر هللا)‬ ‫‪accidents‬‬
‫او الي اسباب اخري والتي قد‬ ‫)‪(threat‬‬
‫تصيب عماله او عمالة الغير او المواد او المعدات ملكه او‬
‫ملك الغير طوال مدة التنفيذ نتيجة قيامه باألعمال الموكلة‬
‫إليه‪.‬‬

‫‪MID TOWN MALL – SOLO‬‬ ‫‪45‬‬


Contract Clause Yellow FIDIC Comment Risk
Clauses
) 20 - ‫( بند‬ Not mentioned It is not very influential, but it
obliges the parties to have all
‫المحل المختار‬ knowledge to ease
‫لالطراف‬ communication between them
‫يعتبر محل إقامة كل من‬
‫الطرفين والمبينين بصدر جميع‬
‫االوراق المرسلة إليه صحيحة‬
‫وقانونية وعليه فإنه في أسبوع‬
.‫على االقل‬

MID TOWN MALL – SOLO 46


Contract Clause Yellow FIDIC Clauses: Comment Risk
Amicable Settlement (21.5)

) 21 - ‫( بند‬ Where a NOD has been given Both parties, Risk to the
under Sub-Clause 21.4 [Obtaining contractor and owner contractor, if
DAAB’s Decision], both Parties
‫حل النزاعات‬ meet to resolve the
any dispute
shall attempt to settle the Dispute occurs and is
dispute amicably and
‫اي نزاع ينشاء بخصوص هذا العقد يتم‬ amicably before the not resolved
‫حله وديا ً في إطار حسن النوايا بما‬ commencement of arbitration. in case of failure an amicably, there
‫يحفظ حقوق الطرفين ; وإن لم يتم‬ However, unless both Parties impartial committee will be a trial
‫التوصل الى حل فيتم اللجوء الى‬
.‫المحاكم المختصه‬ agree otherwise, arbitration may (arbitration council), is
be commenced on or after the appointed to settle (Threat)
twenty-eighth (28th) day after the
disputes in the interest
day on which this NOD was
given, even if no attempt at
of all parties, in
amicable settlement has been consequence, we
made. approve all the
Judgements and the
Requirements they ask
for

MID TOWN MALL – SOLO 47


Chapter 3

WBS & Activity list

3.1 WORK BREAKDOWN STRUCTURE

3.2 Primavera

3.3 ACTIVITY LIST

MID TOWN MALL – SOLO 48


3.1 MIDTOWN – SOLO WBS

MID TOWN MALL – SOLO 49


MID TOWN MALL – SOLO 50
MID TOWN MALL – SOLO 51
3.2 Primavera

MID TOWN MALL – SOLO 52


MID TOWN MALL – SOLO 53
3.3 ACTIVITY LIST

Mid Town Solo


Engineering (AF.022)

Item

Shop Drawings
Civil work
Submits of shop drawings
Approval of shop drawing
Finishing Work
Submits of shop drawings
Approval of shop drawing
MEP
Submits of shop drawings
Approval of shop drawing
AS BUILT DRAWINGS
Civil work
Submits of As built drawings
Approval of As built drawings
Finishing Work
Submits of As built drawings
Approval of As built drawings
MEP
Submits of As built drawings
Approval of As built drawings
foundation
Pc
Shuttering Formwork PC
Pouring PC
De-shuttering formwork & Curing PC
Rc

MID TOWN MALL – SOLO 54


Shuttering Formwork RC
RFT RC
pouring RC
De-shuttering formwork & Curing RC
Concrete Works
Column
Shuttering Formwork columns
RFT columns
pouring columns
De-shuttering formwork & Curing columns
Flat Slab
Shuttering Formwork Flat slab
RFT Flat slab
pouring Flat slab
De-shuttering formwork & Curing Flat slab
Retaining Wall
Shuttering Formwork R.W
RFT R.W
pouring R.W
De-shuttering formwork R.W
Insulation Works
install insulation
Administrative Building
Civil Works
Sub-Structure
Earthwork
excavation earth work
replacement earth work
backfill earth work
foundation
Pc
Shuttering Formwork PC
Pouring PC
De-shuttering formwork & Curing PC
Rc

MID TOWN MALL – SOLO 55


Shuttering Formwork RC
RFT RC
pouring RC
De-shuttering formwork & Curing RC
SOG
Shuttering Formwork RC
RFT RC
pouring RC
De-shuttering formwork & Curing RC
Insulation Works
install insulation
Super-Structure
Ground Floor
Column
Shuttering Formwork columns
RFT columns
pouring columns
De-shuttering formwork & Curing columns
Flat Slab&Beams
Shuttering Formwork Flat Slab&Beams
RFT Flat Slab&Beams
pouring Flat Slab&Beams
De-shuttering formwork & Curing Flat
Slab&Beams
Masonry
Masonry Wall of Ground Floor
First Floor
Column
Shuttering Formwork columns
RFT columns
pouring columns
De-shuttering formwork & Curing columns
Flat Slab Beams
Shuttering Formwork Flat Slab Beams
RFT Flat Slab Beams

MID TOWN MALL – SOLO 56


pouring Flat Slab Beams
De-shuttering formwork & Curing Flat Slab
Beams
Masonry
Masonry Wall of Mezzanine Floor
Second Floor
Column
Shuttering Formwork columns
RFT columns
pouring columns
De-shuttering formwork & Curing columns
Flat Slab Beams
Shuttering Formwork Flat Slab Beams
RFT Flat Slab Beams
pouring Flat Slab Beams
De-shuttering formwork & Curing Flat Slab
Beams
Masonry
Masonry Wall of First Floor
Roof
Column
Shuttering Formwork columns
RFT columns
pouring columns
De-shuttering formwork & Curing columns
Flat Slab Beams
Shuttering Formwork Flat Slab Beams
RFT Flat Slab Beams
pouring Flat Slab Beams
De-shuttering formwork & Curing Flat Slab
Beams
Masonry
Masonry Wall of Roof
FINISHING
Ground Floor
INTERNAL

MID TOWN MALL – SOLO 57


plastering works
Flooring works
Ceiling Gypsum Board
Painting Works
Insulation Works
Wooden Doors& windows
Aluminum Doors& windows
EXTERNAL
plastering works
Painting Works
Aluminum works
First Floor
INTERNAL
plastering works
Flooring works
Ceiling Gypsum Board
Painting Works
Insulation Works
Wooden Doors& windows
Aluminum Doors& windows
EXTERNAL
plastering works
Painting Works
Aluminum works
Second Floor
INTERNAL
plastering works
Flooring works
Ceiling Gypsum Board
Painting Works
Insulation Works
Wooden Doors& windows
Aluminum Doors& windows
EXTERNAL
plastering works

MID TOWN MALL – SOLO 58


Painting Works
Aluminum works
Roof
INTERNAL
plastering works
Flooring works
Ceiling Gypsum Board
Painting Works
Insulation Works
Wooden Doors& windows
Aluminum Doors& windows
EXTERNAL
plastering works
Painting Works
Aluminum works
MEP
Ground Floor
HVAC
Seamless pipes
Duct Works
Isolation Works
Fan coil unit
Air outlet
FIRE SUPPRESION
Install Water pumps
Install Firefighting piped
Controlling Systems
Sprinkles Installation
ELECTRICAL SYSTEM
power
1st Fix for ELECTRICAL Works
2nd Fix for ELECTRICAL Works
Distribution Panel
Accessories
Lighting

MID TOWN MALL – SOLO 59


1st Fix for ELECTRICAL Works
2nd Fix for ELECTRICAL Works
Accessories
PLUMBING
INTERNAL
1st Fix for PLUMBING
2nd Fix for PLUMBING
Accessories
EXTERNAL
Water Distribution
Drainage
First Floor
HVAC
Seamless pipes
Duct Works
Isolation Works
Fan coil unit
Air outlet
FIRE SUPPRESION
Install Water pumps
Install Firefighting piped
Controlling Systems
Sprinkles Installation
ELECTRICAL SYSTEM
power
1st Fix for ELECTRICAL Works
2nd Fix for ELECTRICAL Works
Distribution Panel
Accessories
Lighting
1st Fix for ELECTRICAL Works
2nd Fix for ELECTRICAL Works
Accessories
PLUMBING
INTERNAL

MID TOWN MALL – SOLO 60


1st Fix for PLUMBING
2nd Fix for PLUMBING
Accessories
EXTERNAL
Water Distribution
Drainage
Second Floor
HVAC
Seamless pipes
Duct Works
Isolation Works
Fan coil unit
Air outlet
FIRE SUPPRESION
Install Water pumps
Install Firefighting piped
Controlling Systems
Sprinkles Installation
ELECTRICAL SYSTEM
power
1st Fix for ELECTRICAL Works
2nd Fix for ELECTRICAL Works
Distribution Panel
Accessories
Lighting
1st Fix for ELECTRICAL Works
2nd Fix for ELECTRICAL Works
Accessories
PLUMBING
INTERNAL
1st Fix for PLUMBING
2nd Fix for PLUMBING
Accessories
EXTERNAL
Water Distribution

MID TOWN MALL – SOLO 61


Drainage
Roof
HVAC
Seamless pipes
Duct Works
Isolation Works
Fan coil unit
Air outlet
FIRE SUPPRESION
Install Water pumps
Install Firefighting piped
Controlling Systems
Sprinkles Installation
ELECTRICAL SYSTEM
power
1st Fix for ELECTRICAL Works
2nd Fix for ELECTRICAL Works
Distribution Panel
Accessories
Lighting
1st Fix for ELECTRICAL Works
2nd Fix for ELECTRICAL Works
Accessories
PLUMBING
INTERNAL
1st Fix for PLUMBING
2nd Fix for PLUMBING
Accessories
EXTERNAL
Water Distribution
Drainage

MID TOWN MALL – SOLO 62


Chapter (4)

Construction Method
Statement

4.1 Construction Strategy

4.2 Alternatives

4.3 Method Statement

MID TOWN MALL – SOLO 63


4.1 Construction Strategy

Introduction:

We will discuss the strategy for excavation and wooden wedges for the slabs

The site including mall location:

MID TOWN MALL – SOLO 64


The mall:

The site of the mall divided into six zones for excavation:

Material storage:

There is a way parallel to the mall behind it not in front of the mall

This way used to be the material storage of the whole location construction

The black line is for storage and the red line is an opening between the mall and the
site to make it easier moving between the mall and rest of the site

MID TOWN MALL – SOLO 65


They used to excavate for the first two zones (zone1 and zone2) then the second wo
zones then the third and last two zone in the mall

The way excavated to get the equipment's in and outside from the site for the first two
zones

MID TOWN MALL – SOLO 66


For wooden wedges:

In order they excavate the first two zones they used to start footing in them while the
second two zones are being excavated

MID TOWN MALL – SOLO 67


The contractor don’t have much wooden wedges for all of the site so he starts by the
first and second zone after finishing its excavation to save time as after finishing
excavation for the third and fourth zones the footing will be finished and started with
new excavated zones and so on until they finished excavation and footing for all
zones and starts with the basement slab for the first zones

The footing for the first two zones after being excavated

MID TOWN MALL – SOLO 68


4.2 Alternatives

Concerts:

There are two types:


Made in the site
Ready Mixed Concrete

Made in the site Ready Mixed Concrete

Cost its lower cost than the ready 15-20% more expensive than made in site
mix concrete

For construction its Shorter time, supplied


For construction time it takes ready-to-install
Longer time than ready mix, it is
poured on site On quality its Higher quality than that made
in site, the proportions of the ingredients are
On quality lower quality, the accurately calculated and better finishing
proportions of the ingredients are
not calculated accurately and the The plant used to make test and take the
finishing is poor responsibility for its failure

There should be more than one choice of


The tests make in the site on the plants which supply your ready mix to avoid
contractor responsibility problems delays from plants

MID TOWN MALL – SOLO 69


Criteria of evaluation
1) Cost
2) Time
3) Constructability
4) Transportation
5) Quality
6) Safety
Weight matrix:

B C D E F
A a a-1 a-2 a a-1
B b-1 b-2 B b-1
C c-1 c-1 c
D d-2 d-1
E e-1
F

Criteria weight Made in the Ready


site Mixed
Concrete
score total score total
Cost 20% 3 0.8 2 0.8
Time 20% 1 0.15 2 0.45
Constructability 15% 1 0.10 5 0.5
transportation 10% 1 0.05 1 0.05
Quality 20% 1 0.15 5 0.75
safety 15% 1 0.15 4 0.6
Sum 100% 1.4 2.15 Ready mix gets
the highest
score then we will use it as it’s the best choice of the two

MID TOWN MALL – SOLO 70


4.3 Method Statement

INTRODUCTION:

Method statements are hugely important when it comes to the health and safety of
projects, particularly in the construction industry. These documents are used alongside
risk assessments to make sure certain high-risk tasks and activities involved in a
project are safe. But what is a method statement and why is it important?

Method statements are documenting that detail exactly how to carry out work safely.
When it comes to ensuring building site health and safety, method statements are key.

Purpose of the method of Statement:


• Estimation of the required resources, labor, skills, and duration for individual tasks.

• Plan the activity to be completed efficiently.

• Identifying any interactions among different work tasks.

• Identifying legal requirements.

• Prediction of possible problems.

• Determination of measures to be performed to control the risk.

MID TOWN MALL – SOLO 71


Excavation and shoring:

Team Members and Responsibilities:


• Project Manager: overall responsibility

• Consultant

• Construction Supervisor: Responsible for site works and reports to Construction

Manager.

• Civil Supervisors: Report to Civil Engineer.

• Foreman: Reports to Construction Supervisor.

• Operator: Responsible for the excavator and loader.

• QC Civil Inspector: Reporting to QA Manager

• Driver Responsible to haul and Dump the Surplus.

• Safety manager: make sure that work is happening according to the safety plane

Materials:

• Soil in site

• wood shoring

Equipment:

• Dump truck

• Excavator

• Hydraulic jackhammer

• Loader

MID TOWN MALL – SOLO 72


Procedure :

Excavation in asphalt soil below the foundation level for drainage wells and elevator
wells

All construction elements that need to be drilled according to the dimensions shown
in the paintings for

Recommendations of the soil report prepared by the owner's consultant, or the work
includes reaching the required level with the settlement of the drilling floor and
spraying it with water and compaction to obtain the highest dry density (not less than
98%) with the transfer of drilling output to the inside of the worksite.

And we are the work according to the engineering specifications and the origins of the
industry and the instructions of the supervisory body

[geometric scaling]

• Excavation for the mall is being done for all areas, with soil replacement of 26810,
cubic meters to reach foundation level at (-7.5 m) blew ground zero level

• The excavator will use the approved plan and drawings to know where to dig.

• The compaction test report shall be submitted to the Engineer for approval prior to

• How deep they dig will depend on several factors, like the type of foundation and if
there will be a crawl space or a basement.

• Before the compaction starts, it shall make sure that the excavated level is free from
standing water or excessive moisture content.

• Inspection would be conducted during compaction for checking and approval of the
Engineer.

MID TOWN MALL – SOLO 73


Risks :
• A worker accidentally fell into an excavation

• A worker being trapped by the collapse of an excavation.

• A falling object striking a worker in an excavation.

• A worker in an excavation being exposed to an airborne contaminant.

• A worker being engulfed by the influx of water into the excavation.

In order to manage these risks, the following must also be considered:

• The nature of the excavation

• The type of the excavation work, including the various ways in which that work
could be carried out

• Entry and exit from excavation sites, where applicable.

• For all excavation activities, adequate safety barriers, signboards, andwarning signs
would be used.

MID TOWN MALL – SOLO 74


Reference :

• CHAS

• Wollam construction

• Worksafe

• Specification Book

Backfilling :
Backfilling is the process of putting the soil back into a trench or foundation once
excavation, and the related work has been completed. The backfill process requires
skills and heavy equipment as well as knowledge of the specifications, contract
requirements, and soil conditions

Team Members and Responsibilities:

• Project Manager: overall responsibility

• Consultant

• Construction Supervisor: Responsible for site works and reports to Construction

Manager.

• Civil Supervisors: Report to Civil Engineer.

• Foreman: Reports to Construction Supervisor.

• Operator: Responsible for the excavator and loader.

• QC Civil Inspector: Reporting to QA Manager

• Driver Responsible to haul and Dump the Surplus.

• Safety manager: make sure that work is happening according to the safety plane

MID TOWN MALL – SOLO 75


Materials:

• Soil in site

• Clean sand

Equipment:

• Truck

• Loader

• Manual compactor

Procedure:

Supply and backfilling with clean sand supplied by the owner (Annex 4) between the
bases and pedestals inside and outside the building around the retaining walls,
provided that the sand is free of impurities, foreign materials, backfill products and
large blocks.

Backfilling is carried out using mechanical equipment on layers not exceeding a layer
thickness of 25 cm with compaction with an appropriate tamper that achieves a
maximum dry density of not less than 98%, as well as the upper surface of the filling
level and on the level shown on the plates,

And the item also includes experiments according to the Egyptian code for backfilling
and compaction works, as well as the supply of water workshops at the appropriate
engineering rate and the calculation according to the engineering measurements and
inventory carried out in nature.

And work of all of it in cubic meters in accordance with the approved boards,
engineering specifications, industry assets, and the instructions of the supervisory
body.

MID TOWN MALL – SOLO 76


MID TOWN MALL – SOLO 77
Safety:
• Use appropriate Personal Protective Equipment

Hardhat.

Safety boots.

Overalls.

Ear Protection.

Masks

Safety Glasses

Hand gloves

• All necessary personal/protective equipment (PPE), as well as the harness, be


provided.

• Banks man, wearing distinctive vests, shall be assigned to help operators maneuver
their equipment.

• The equipment operators shall possess the required licenses and certificates

• Generated dust (By the end or equipment operations) shall be controlled by periodic
water spraying.

• The required permit to work by Borsch shall be obtained prior to the commencement
of work.

• The required TSTI will be prepared prior to the commencement of work and
positively implemented.

• The project safety officer is responsible along with the project zone site engineer for
ensuring that all operations are carried out with due regard to the safety of all project
personnel & property.

• No working at height issues anticipated.

• All working activity shall comply with Client Safety Procedure

• First Aid Material

• General management of protection/operation hazards are to be observed

MID TOWN MALL – SOLO 78


Reference:

• Thebalancesmb

• civil-engineers-2020

• Specification Book

Column Works:

Materials:
• Sand

• Gravel

• Cement

•Wood shoring

Equipment:
• Truck

• Concrete Pump

• Concrete Mixer

Procedure:
MID TOWN MALL – SOLO 79
• Supply ready-made steel and concrete for the pillars of the ground floor and the
height indicated in the construction boards. Effort of 300 kg / cm2 using ordinary
Portland cement with a cement content of not less than 350 g / m3 and reinforcing
iron according to what is shown in the shop drawing, rank (60/40) for diameters more
than 8 mm and rank (37). /24) for a diameter of 8 mm.

And using the counter panels used in the implementation of the previous items, with
the same specifications (but the item is not fair faced concrete).

The work includes the supply of all the necessary elements for construction, cod,
programming, casting, mechanical shaking, syringes, and the treatment of their places
with their own restoration materials, in addition to the treatment works (Water /
Masterkure 102 produced by BASF or X-Cure by NCC company) and the work of All
in cubic meters in accordance with the approved plates, engineering specifications and
industry assets.

• Supply ready-made steel and concrete for the wall columns (above the basement
ceiling) and the walls of the fence and the height shown in the construction panels.

An effort of 300 kg / cm2 using ordinary Portland cement with a cement content of
not less than

MID TOWN MALL – SOLO 80


350 kg/m3 with reinforcing steel according to what is shown in the structural plates,
rank (60/40) for more diameters

From 8 mm and the rank of (37/24) to a diameter of 8 mm.

The work includes the supply of all the elements necessary for construction,
codification, milling, casting and mechanical vibrator

(if necessary) and treatment works.

And work of all of it in cubic meters in accordance with the approved boards,
engineering specifications, industry principles, and the instructions of the supervisory
body.

Slab Works :
Materials:
• Sand

• Gravel

• Cement

•Wood shoring

Equipment:
• Truck

• Concrete Pump

• Concrete Mixer

MID TOWN MALL – SOLO 81


Procedure:
• Supply steel and ready-made concrete for ceilings, beams, stairs, basements and
external stairs area Landscape.

At the height indicated on the structural plates

Effort of 300 kg / cm2 using ordinary Portland cement with a cement content of not
less than 375 kg /3 m and reinforcing iron according to what is shown in the structural
panels, rank (60/40) for diameters more than 8 mm and grade (37/24) for a diameter
of 8 mm

And with the same specifications in item [3-8]

The work includes the supply of all the elements necessary for construction,
codification, milling, casting and mechanical vibrator And the drawers for circuits and
the treatment of their places with their own restoration materials, in addition to the
treatment works (Water / Masterkure 102 produced by BASF or X-Cure by NCC).

And work of all of it in cubic meters in accordance with the approved boards,
engineering specifications, industry principles, and the instructions of the supervisory
body.

• Supply ready-made steel and concrete for ceilings and beams of water tanks and
waste water collection tanks in basements and in height • and the level shown in the
construction panels,

Effort 300 kg / cm 2 using resistant Portland cement with a cement content of not less
than 400 kg / m 3 and with reinforcing iron according to what is shown in the
structural panels, rank (60/40) for diameters more than 8 mm and rank (37/24) for a
diameter of 8 mm. And with the same specifications in item (3-8)

The work includes the supply of all the elements necessary for construction,
codification, milling, casting and mechanical vibrator

Shanbers for circuits and treatment works (Water / Masterkure 102 produced by
BASF or X-Cure by NCC)

And work of all of it in cubic meters in accordance with the approved boards,
engineering specifications, industry principles, and the instructions of the supervisory
body

MID TOWN MALL – SOLO 82


Supply steel and ready-made concrete for ceiling and ground floor beams and stairs
from floor to ceiling

On the ground floor.

And the height shown in Civil drawing.

Effort 300 kg / cm 2 using ordinary Portland cement with a cement content of not less
than: 375 kg / m 3 and with reinforcing iron according to what is shown in the
structural panels, rank (60/40) for diameters more than 8 mm and rank (37/24) for a
diameter of 8 mm

Safety:

1. Supervision and Inspection


Practising proper supervision during formwork placement, concrete pouring, and
stripping of formworks is essential for obtaining safety in the use of forms. A
supervisor's task is to ensure the erection of formwork according to the design and
practising a safe erection procedure to avoid overloading of members.

Filed modification in the falsework, forms, or erection procedure should be permitted


unless the form designer is consulted. The exertion of unusual loads shall be
prevented if the formwork system is not designed for such loads.

2. Platforms and Access for Workers


Accessible working platform shall be prepared for works executed at elevated
positions. Long ladder to the tops of falsework needs to have rest or passing platform.
In certain structures such as bridges, it might be necessary to use special scaffolds or
any other suitable equipment for stripping decks and piers forms.

MID TOWN MALL – SOLO 83


Safety signs and barriers should be placed to keep the unauthorized individuals out of
the working area during erection and striping formwork system. Platforms and access
means for worker need to conform with applicable codes such as OSHA
requirements. The provision of accessible and safe working area can be provided if
engineers and experienced field personnel cooperate with each other.

3. Control of Concreting Practices


Controlling concrete pouring is a major factor in the safety plan establishment. The
sequence and rate of concrete placement should consider limitations provided in the
formwork drawings.

While concrete is placed, unbalanced form loading shall be prevented. For


instance, in beam and slab construction, fill the beams first and then work
outward equally on both sides when placing the slab. The stability of the
formwork system can be enhanced in a column-and-slab structure by
concreting the columns at least a day ahead of the slab.

4. Improving Soil Bearing and Bracing


Commonly, the condition of soil is not known when the forms and scaffoldings are
designed; assumed bearing capacity is used. So, it would be the task of contractor to
check whether the bearing capacity of the soil at construction site is greater or smaller
than the one assumed during design stage. If soil bearing capacity is questionable,
then it can be stabilized by tamping or covered with layer of crushed stone.
Formworks shall be designed to prevent progressive collapse due to localized failures.

5. Shoring and Reshoring


Installation of out of plumb shores, bent jacks, and defective timber shall be avoided
otherwise these supporting elements would support only a small portion of design
loads. During Concreting, forms shall be monitored continuously in order to observe
problems and correct them as soon as they arise.

MID TOWN MALL – SOLO 84


Reference:
• Theconstructor.org

• Civil drawings

• Specification Book

Team Members and Responsibilities:


• Consultant

• Construction Supervisor: Responsible for site works and reports to Construction

Manager.

Civil Supervisors: Report to Civil Engineer.

• Foreman: Reports to Construction Supervisor

• Operator: Responsible for pump machine, pump truck

• Labor: Responsible for mixing , placement and shoring

• Safety manager: make sure that work is happening according to the safety plane

Finishing Works :

Materials:
• Portland Cement

• Sand

• coating material

• non-shrinkable material

MID TOWN MALL – SOLO 85


Equipment:
• The scale of water (spirit level)

• Line dory

• Plumb bob

• Mixture plaster machine

• The scale of the thread (shagul)

• Steel brush

• Metal corners

• Fiber network

• Cement cannons or compressors

• Mobile scaffolds

Procedure:

• The categories of plastering, supplying and installing work include the


following:

1- Geometric measurement for all internal and external whitewashing work

2- Unloading and Shake pointing with a depth of 10 mm and all surfaces that will be
implemented

The whiteness on it with a wire brush, as it is free of grease, dust and salts.

3- The roofs of buildings must be covered with water dew before the bleaching, and if
any dry areas appear, they must be re-moistened so that they are all equal in the
degree of water absorption.

4- Fiber network produced by (GEOS---V3-133-A) company in the joints between


buildings and concrete.

Or between new and old walls and in places of electrical pipes, while filling joints
with non-removable material

MID TOWN MALL – SOLO 86


shrinkage;

5- Metal corners from Metal-X company are placed in all corners of the building and
covered with cement mortar (only one stick height) with adjusting their straightness.

6- All surfaces that are whitened must be made on flat surfaces, weighted vertically
and horizontally.

With the scale of the thread (shagul) or the scale of water (spirit level) and aluminum
lead and make the slate from gypsum mortar measuring 10 * 3 cm distributed on
points at distances not exceeding 2 m vertically, horizontally and at the corners and
with the same thickness of the lining layer of the white.

7- Plating works must be done in a clean manner according to the principles of the
industry, and all faces (except for circular ones) must be flat and level, and the angles
are straight and weighted horizontally and vertically, and the whiteness must be
smooth, resistant to cracking, and chemically stable upon hardening.

• Supplying and making a cement roughening bleaching as necessary for the fence,
consisting of two layers, the first is a splatter layer with a thickness of 0.50.cm, a
mortar consisting of (450.0 kg cement / m3 sand) of clean sand and grooves and free
of special impurities (cement cannons or compressors) provided that all surfaces are
covered The work also includes preparing and cleaning the surface of buildings and
concrete elements, as well as water treatment works for the splash for a period of at
least three days.

The second layer, which is the lining layer with a thickness of not less than 2 cm after
the splatter layer has dried and a mortar consisting of (1.00 m 3 sand / 250 kg of
cement). on item

strings and accessories

(Fiberglass net V3-133-A)

From an approved factory, it is necessary to connect the buildings with the concrete
elements, as well as any scaffolding works for the destinations to complete the work,
as well as the work of water treatment of whitewash for a period of three days at least.

And all work according to the flat meter according to the approved boards,
engineering specifications and industry assets

Supervisory instructions.

MID TOWN MALL – SOLO 87


• Supply and making baffles on the facades of gates and fences according to
engineering drawings, with a width of 2 cm and a depth of not less than 1 cm and
according to the approved sample the work includes all the necessary raw materials,
tools, scaffolding and milling with shinbar for shaping and treating letters with
gypsum and white cement to ensure their flatness and complete integrity.

the importance of delivering the work site clean after the end of the activity.

And work of all of it by the linear meter in accordance with the approved boards,
engineering specifications, industry principles, and the instructions of the supervisory
body.

• Supply and making the facades whiteness from a ready-made polymeric mortar
using Marble Orchid (white/gray color) for the need for fences, with the need to adopt
a sample and color before implementation and the work includes all the necessary raw
materials, number and tools with the importance of delivering the work site clean after
End of activity.

And work all of it by flat meter in accordance with the approved boards, engineering
specifications, industry assets, and the instructions of the supervisory body.

Reference:
• Planningengineer.net

• Architectural Drawings

• Specification Book

MID TOWN MALL – SOLO 88


Safety:
• Contractor shall ensure that the machine operators involved must be
experienced/competent persons.

• All PPE is a must in this activity.

• It is to be noted that the special care to be adopted against snake/insects bite.

• During the movement of equipment the operator must blow the horn to caution the
people around.

• All Measuring & Test Equipment’s used must be well maintained.

• All lifting devices & Tolls used shall be well maintained.

• It is to be taken care that no spillage of fuel or lubricants is allowed at the site.

• The contractor shall arrange Regular Toolbox Meeting.

• The contractor shall arrange a First Aid Box at the site.

Team Members and Responsibilities:


• Consultant

• Construction Supervisor: Responsible for site works and reports to Construction

Manager.

Civil Supervisors: Report to Civil Engineer.

• Foreman: Reports to Construction Supervisor

• Operator: Responsible for scaffolding and Cement cannons or compressors

• Labor: Responsible for mixing, placement and bleaching

• Safety manager: make sure that work is happening according to the safety plane

MID TOWN MALL – SOLO 89


Chapter (5)

RISK MANAGEMENT

Risk Identification
5.1

5.2 RBS

MID TOWN MALL – SOLO 90


5.1 Risk Identification

INTRODUCTION :
There are multiple sources of risk. For risk identification, the project team
should review the program scope, cost estimates, schedule (to include
evaluation of the critical path), In addition, historical data from similar
projects, stakeholder interviews, and risk lists provide valuable insight
into areas for consideration of risk. Risk identification is an iterative
process. As the program progresses, more information will be gained
about the program, and the risk statement will be adjusted to reflect the
current understanding. New risks will be identified through the project
life cycle.
Category Risk ID
Engineering E
Administration A
Law and legislation L
Politics P
Management M
Contractual C
Financial F
Social S
Technically T
Construction Co
Safety S

MID TOWN MALL – SOLO 91


Risk Risk Type of Risk Type of
category ID Risk Description Risk
Engineering E1 Delay of and inspection A
monitoring danger occurs
(Engineer) when the engineer
supervising the (Opportunity)
site is late in
monitoring and
inspection.
Administration A1 Owner government The project is
agency owned by a
government
agency, and in
most cases, it is (Opportunity)
easy and quick to
issue permits.
Which will
positively affect
the project
schedule.
Law and L1 Change in Local the Contract
Law follow Law 182.
legislation
There is a
possibility that the
law may change (Opportunity)
under any
circumstances, and
this change It does
not pose a danger
to the contractor,
if the change of
law is risky to the
contractor, we
follow the old law.
Management M1 estimate (Fatal Although it is
Mistake) Difficult, it does
happen. a)
Estimate date.
Failure to estimate (Threat)
time can delay a
change in the
project schedule.
b) Budget,

MID TOWN MALL – SOLO 92


estimate cost and
BOQ. The error in
estimating the
cost. of the project
and any error at
the project budget
can cause a real
threat for the
Contractor, so the
amounts and the
budget must be
accurately
estimated.
M2 Miscommunication Disputes and voids
between the
parties of the
project. can cause (Threat)
the project to stop,
and there will be
changes at the
project schedule.
M3 Change of the The changes at the
board of directors board of directors
greatly affects the
project, the effect (Threat &
is often negative, Opportunity)
and the change can
be positive if the
new board of
directors is able to
manage the project
better.
M4 Delay in Import The project may
Equipment& require imported
materials. equipment and the
(Breakdown). materials, In event
of equipment (Threat)
failure or
resources
damages. There is
a risk of delaying
the arrival of
imported
equipment and

MID TOWN MALL – SOLO 93


materials, which
leads to delays and
changes in the
project schedule
and an increase in
cost.
M5 Project quality the contract was (Opportunity)
standards. direct order.
Accordingly, the
owner is making
sure that the
quality of the
works provided by
the contractor
M6 Shorting in labor The worker's
productivity. failure to work
affects the rate of
productivity, (Threat)
which leads to a
change in the
schedule and an
increase in costs.
Contractual C1 Provisional sum The budget
amount is entered
in the BOQ for a
specific purpose.
A special spend (Opportunity)
that you cannot
take from to pay
for increases in the
costs of other
items in the BOQ.
C2 Termination by Contractor cannot
contractor termination the
contract when
(Threat)
employer delay
the payments.

MID TOWN MALL – SOLO 94


5.2 RBS

MID TOWN MALL – SOLO 95


Chapter (6)

QUANTITY SURVEYING

MID TOWN MALL – SOLO 96


6.1 QUANTITY SURVEYING

PC Number Area M² Volume M³


F1 14 33.6 10.08
F2 30 108 32.4
F3 172 791.2 237.36
F4 38 199.5 59.85
F5 14 79.66 23.898
F6 19 121.8375 36.55125
F7 18 129.015 38.7045
F8 151 1183.84 355.152
F9 18 178.92 53.676
F10 50 522 156.6
F11 2 23.04 6.912
F12 6 40.8 12.24
F13 28 47.88 14.364
Total Vol. 1037.78775 M³

PC

MID TOWN MALL – SOLO 97


RC Number Area M² Volume M³
F1 14 215.6 86.24
F2 30 58.5 23.4
F3 172 464.4 185.76
F4 39 124.8 49.92
F5 14 49.665 19.866
F6 21 86.3625 34.545
F7 18 84.915 33.966
F8 151 798.79 319.516
F9 18 126.27 50.508
F10 50 372 148.8
F11 2 16.74 6.696
F12 6 25.2 10.08
F13 28 36.4 14.56
Total Vol. 983.857 M³

RC

MID TOWN MALL – SOLO 98


Number Dim Area Volume
A1 58 80*30 2400 408
L1 57 60*25 1500 255
L1 1273 60*30 1800 306
Total Number 1388 Total Area , Vol 5700 969 M³

Semmel

MID TOWN MALL – SOLO 99


Column neck Number Area Volume
164 0.18 0.162
63 0.15 0.135
48 0.44 0.396
6 0.78 0.702
10 0.36 0.324
93 0.12 0.108
6 0.81 0.729
27 0.27 0.243
42 0.36 0.324
63 0.15 0.135
20 0.36 0.324
49 0.21 0.189
20 0.3 0.27
19 0.24 0.216
4 0.2 0.18
16 0.385 0.3465
20 0.3 0.27
8 0.36 0.324
20 0.36 0.324
30 0.36 0.324
19 0.24 0.216
2 0.6 0.54
Total Number 749 TotalVolume 6.7815 M³

Column Neck

MID TOWN MALL – SOLO 100


Excavation Backfilling
Area Depth vol. Volume
21409.79 6 128459 PC 1037.7 M³
RC 983.8 M³
Semmel 969 M³
column 6.78 M³
Total Vol 2997.28 M³
Total Backfilling125461 M³

Backfilling