Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

PROJECT NAME

Document No:
Metod Statement for Rev : 0
Excavation & Backfilling Date:
Page 1 of 8

METHOD STATEMENT FOR

EXCAVATION AND BACKFILLING

Revision Record
PROJECT NAME

Document No:
Metod Statement for Rev : 0
Excavation & Backfilling Date:
Page 2 of 8

1. This cover page is a record of all revisions of the document identified above by number and title. All
previous cover pages are hereby superseded and are to be destroyed.

2. The contractor has the full right to modify, amend or change Method Statement and supporting
documents as required or as deemed necessary. All such documents will be submitted to the
“CONSULTANT” for approval.

Prepared Approval for


Rev Date Reviewed by Description & page Number of Revision
By Issuance by

Contents

1.0 Purpose

2.0 Scope

3.0 References

4.0 Definitions and Abbreviations

5.0 Responsibilities
PROJECT NAME

Document No:
Metod Statement for Rev : 0
Excavation & Backfilling Date:
Page 3 of 8

6.0 Materials

7.0 Equipment & Tools

8.0 Safety & Health

9.0 Procedure

10.0 Attachments

1.0 PURPOSE
The purpose of this method statement is to clarify excavation and backfilling works to be carried out for the project .
2.0 SCOPE
This method statement covers general excavation works for foundations and other structures requiring straightforward excavations. It generally encompasses
the following:

o Machineries for earthwork, delivery, transportation, handling and storing at site.

o Survey

o Stockpiling and disposal of excavated material

o All necessary safety measures

o Testing, preparing ground surface to final grade and levels

.
3.0 REFERENCES
 Project specifications

 Contract Drawings

 Approved Shop Drawings

 NOC from the Concerned Authority


PROJECT NAME

Document No:
Metod Statement for Rev : 0
Excavation & Backfilling Date:
Page 4 of 8

 Project Quality Plan


4.0 DEFINITIONS& ABBREVIATIONS
PM: CONTRACTOR’sProject Manager
CM: CONTRACTOR’s Construction Manager
PE: CONTRACTOR’s Project Engineer
SE: CONTRACTOR’s Site Engineer
QCE: CONTRACTOR’s Quality Control Engineer
QA QC: Quality Assurance and Quality Control
HSE: Health Safety Environment
5.0 RESPONSIBILITIES

 Project Manager is responsible for overall project execution, quality and safety. Adopt a leading role with respect to Contractor’s quality and safety
procedures. The PM is responsible for the overall implementation of this method statement. The Project Manager shall ensure that the key personnel
are well aware of the specifications and method statement.

 CM / Project Engineer shall arrange all materials, equipment, safety related items & manpower & direct the Site Engineers & Foremen to resort
appropriate action for the smooth execution of the works.

 Safety Engineer shall be responsible for safe working environment & conditions. Coordinate with Site Engineer to identify potential hazards before
works and advise methods of safe working from new developments.

 Surveyor shall be responsible for setting out for levels, layout, and lines & establish top levels. Ensuring setting out books are properly maintained and
filed when completed. To coordinate with the CONSULTANT surveyor in determining coordinates, levels, and limits.

 QA/QC Engineer shall be responsible for ensuring that execution of works are complying with approved method statement; specifications, approved
shop drawings and ensure ITR are submitted based on ITP requirements.

 Site Engineer shall ensure that all works are carried out according to approved shop drawings. He shall direct the surveyor for the setting out lines &
levels in concurrence from the Construction Manager/Senior Civil Engineer.

 MEP Coordinator / Engineer shall be responsible for proper execution of MEP works involved before, during and after the works.
6.0 MATERIALS

 Approved Materials for backfilling


7.0 EQUIPMENTS& TOOLS
Below is the equipment involved in the subject works included the following:
 Excavator

 Power shovel
 Motor Grader

 Dump Truck
 Plate and Roller Compactor

 Front End Loader


 JCB`

 Water Tanker

 Hand tools (Shovels, Spade, rake etc.)

 Dewatering Equipment (if required)


 Total station, level

 Shoring materials (if required)


The capacity / size and quantity of the above equipment shall be judged in accordance with site conditions, requirements, and availability at the time of
execution.
8.0 SAFETY & HEALTH

 Site HSE Management shall be applied.

 All personnel involved will use necessary PPE as required such as safety helmet, glasses,
coverall, shoes, gloves, ear plugs etc.
PROJECT NAME

Document No:
Metod Statement for Rev : 0
Excavation & Backfilling Date:
Page 5 of 8

 HSE officer to ensure that excavated area is barricaded. Adequate warning tapes and
warning signs are provided. All access from adjacent play ground to extension area shall be
closed and monitored.
 Though the excavation is minor in nature a hazard analysis table is attached for excavation
activities. All major possible risks/ hazards are highlighted.
 The workers will be made aware of safety requirements related to this activity through
daily tool box and safety talk.

 All required work permits will be acquired and kept available at respective work site
hanged clearly in plastic folders.

 Safety notice board will be installed.


9.0 PROCEDURE
EXCAVATION:

 Ensure the availability and validity of documents such as Excavation Permits, NOC and approved drawings.

 Ensure the availability of MEP clearance, risk assessment, shoring and dewatering permits etc.

 Before commencement of work ascertain the nature and location of all existing (above and underground) services on site by visual survey or by

reviewing the service layout drawing.

 If any protection, rerouting, termination or removals of services are required for the smooth processing of work, it shall be discussed and written

approval shall be obtained from the Engineer as appropriate.

 The surveyor will set out line / coordinates as per relevant construction drawings.

 The surveyor will inform area / excavation foreman of these lines & levels.

 Banks man will be deployed with all mechanical excavation equipment & dump trucks to guide the operators.

 The excavation / area foreman will direct the excavation equipment in an agreed sequence.

 Dumping of unsuitable material will be done to disposal point, as notified by CLIENT & material fit for backfilling will be stock piled separately at a

suitable agreed location.

 Barricading of the excavated area will be done as work proceeds.

 Where ever there are chances of sliding, the sides of excavation will be sloped

 The bottom of all excavated areas shall be trimmed, leveled and rammed.

 While excavation is in progress, excavation area foreman will continuously monitor the level to avoid over excavation.

 The surveyor will check the lines & levels upon completion of excavation.

 Upon acceptance of survey, the area will be released for subsequent activities.

 If excavation goes below the adjacent structures, shoring will be carried out.

BACKFILL & FILL:

 CM/PE will ensure that particular area/structure has been cleared for backfilling by QC department.

 Upon approval for backfilling the PE will instruct concerned foreman to conduct this activity.

 The backfill material will be sourced from suitable stock pile or from excavated material.

 The backfill material will be placed in layers according to the specification.

 The layer will be moisturized and compacted.

 Generally compaction will be done by rollers / compactors.


PROJECT NAME

Document No:
Metod Statement for Rev : 0
Excavation & Backfilling Date:
Page 6 of 8

Compaction must be monitored and judged by regular tests for density which should not

be less than 95% Maximum Dry Density.

Once test results are satisfactory to the specification subsequent layer shall be precede.

In narrow places and corners where roller can’t reach, a plate compactor shall be used to

complete the job.

Precede the subsequent layer with the same procedure until the required level obtained.

 Upon completion of backfill activity, the area will be cleaned of waste materials.

 Safety barriers will be removed to safety store.

10.0 ATTACHMENTS

 ITP

 Checklist
Risk Assessment

You might also like