LBC CyberVault - Implementation Project Plan - Draft 2.0
LBC CyberVault - Implementation Project Plan - Draft 2.0
Mode Complete
1 85% 1 Cyber Resiliency Project - PHASE 1 ( until Use case testing) 151 days Mon 20-06-22
2 0% 1.1 External Dependencies 0 days Fri 30-09-22
3 0% 1.1.1 ALDM project completion 0 days Fri 30-09-22
4 100% 1.2 Initiation Phase 151 days Mon 20-06-22
5 100% 1.2.1 KICK OFF CALL AND CREATE PROJECT PLAN 151 days Mon 20-06-22
6 100% 1.2.1.1 Assign Kyndryl Project manager & resources 7 days Mon 20-06-22
7 100% 1.2.1.2 Working session with existing Account teams, 5 days 6 Wed 22-06-22
Resiliency Team on initial assessment
8 100% 1.2.1.3 Project Kick-off call 20 days 6 Wed 22-06-22
9 100% 1.2.1.4 Review all data collection information collected 1 day 8 Thu 23-06-22
during Pre-sales (Baseline Review)
10 100% 1.2.1.5 Set up reoccurring meeting with Kyndryl Project 1 day 9 Fri 24-06-22
Team to define service requirements and scope
11 100% 1.2.1.6 Develop Over all Project plan draft 5 days 9 Fri 24-06-22
12 100% 1.3 Milestone: Initiation Phase Completed 0 days Thu 30-06-22
13 100% 1.4 PROCUREMENT 68 days Mon 20-06-22
14 100% 1.4.1 Dell HW 63 days Mon 20-06-22
15 100% 1.4.1.1 Place requests/PO and Orders with all Approvals 18 days Mon 20-06-22
16 100% 1.4.1.1.1 Dell 9400 Data Domain 360 TB (Includes 5 days Mon 20-06-22
Hardware and Software Maintenance)
17 100% 1.4.1.1.2 VXRail compute 5 days Mon 20-06-22
18 100% 1.4.1.1.3 Dell Power Edge R340 5 days Mon 20-06-22
19 100% 1.4.1.1.4 Powerswitch S5448F - For Vault connectivity 5 days Mon 20-06-22
20 100% 1.4.1.1.5 S5212F Switches 5 days Mon 20-06-22
Page 1
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
21 100% 1.4.1.1.6 Nexus Network Switch from Bank ( temp solution) 5 days Mon 20-06-22
22 100% 1.4.1.1.7 CyberSense Licenses 5 days Mon 20-06-22
23 100% 1.4.1.1.8 Vendor to provide ship dates 7 days 22 Tue 05-07-22
24 100% 1.4.1.2 Receive Hardware 34 days Fri 29-07-22
25 100% 1.4.1.2.1 Dell 9400 Data Domain 360 TB (Includes 0 days Fri 29-07-22
Hardware and Software Maintenance)
26 100% 1.4.1.2.2 VXRail compute 0 days Tue 06-09-22
27 100% 1.4.1.2.3 Dell Power Edge R340 0 days Tue 06-09-22
28 100% 1.4.1.2.4 Powerswitch S5248F - For Vault 0 days Mon 19-09-22
connectivity(temp solution)
29 100% 1.4.1.2.5 S5212F Switches 0 days Tue 06-09-22
30 100% 1.4.1.2.6 N3200 Network Switch 0 days Mon 22-08-22
31 100% 1.4.1.2.7 CyberSense Licenses 0 days Fri 12-08-22
32 100% 1.4.2 Milestone: All Dell Hardware received 0 days 24 Mon 19-09-22
33 100% 1.4.3 2 Firewalls 43 days Mon 20-06-22
34 100% 1.4.3.1 Pricing 1 day Mon 20-06-22
35 100% 1.4.3.2 Kyndryl Approval 8 days 34 Tue 21-06-22
36 100% 1.4.3.3 Proccess PO 1 day 35 Wed 06-07-22
37 100% 1.4.3.4 Vendor to provide ship dates 5 days 36 Thu 07-07-22
38 100% 1.4.3.5 Vendor to ship ordered HW (Assumption 5w TBC) 5 wks 37 Thu 14-07-22
39 100% 1.4.4 Milestone: 2 Firewalls received 0 days 38 Thu 18-08-22
40 100% 1.4.5 Dell BOM Review 57 days Tue 05-07-22
41 100% 1.4.5.1 Conduct a call with Resiliency NB Architect to 1 day Tue 05-07-22
validate Dell BOMs (2 calls)
Task Manual Task Deadline
Page 2
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
42 100% 1.4.5.2 Provide discrepancy in the Dell BOMs vs. the 15 days 41 Thu 07-07-22
proposed solution ( if any found)
43 100% 1.4.5.3 Order for missing parts (if any found) 40 days Thu 28-07-22
44 100% 1.4.5.3.1 Obtain Business approval 1 day 42 Thu 28-07-22
45 100% 1.4.5.3.2 Obtain Business Legal approval 1 day 44 Fri 29-07-22
46 100% 1.4.5.3.3 Create CRs for each Schedule 1 day 45 Tue 02-08-22
47 100% 1.4.5.3.4 Approve CRs (multiple layers of approvers) 1 day 46 Wed 03-08-22
48 100% 1.4.5.3.5 Create WWCTs for each approved CR 1 day 47 Thu 04-08-22
49 100% 1.4.5.3.6 Approval of WWCTs (multiple layers of approvers)2 days 48 Fri 05-08-22
50 100% 1.4.5.3.7 PO issued to the vendor for each WWCT 4 days 49 Tue 09-08-22
51 100% 1.4.5.3.8 Vendor to acknowledge receipt of POs 1 day 50 Mon 15-08-22
52 100% 1.4.5.3.9 Vendor to provide ship dates 5 days 51 Tue 16-08-22
53 100% 1.4.5.3.10 Vendor to ship ordered HW (Assumption 4w TBC) 23 days 52 Tue 23-08-22
54 100% 1.4.6 Milestone: Missing ( if any) Equipment Received 0 days 43 Fri 23-09-22
55 100% 1.5 Planning Phase 59 days Fri 24-06-22
56 100% 1.2.2 Introduction call with client 0.5 days Wed 29-06-22
57 100% 1.5.2 Develop Project Plan 46.5 days Fri 24-06-22
58 100% 1.2.4 Develop Draft Project plan for DRaaS tracking 5 days Fri 24-06-22
59 100% 1.5.2.2 Meet with Dell PM to adjust/confirm project plan 2 days Thu 30-06-22
60 100% 1.5.2.3 Update project plan (1st tracking release) 3 days 59 Mon 04-07-22
61 100% 1.5.2.4 Update project plan (2nd tracking release) 4 days 60 Thu 07-07-22
62 100% 1.5.2.5 Finalize project plan and generate a final baseline 2 wks 61,23,37,101 Thu 14-07-22
(final release with confirmed shipment dates)
Page 3
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
63 100% 1.5.3 Milestone: Project Plan (Schedule) finalized & baseline 0 days 57 Tue 30-08-22
created
64 100% 1.5.4 Develop/Approve Solution Design (TSD) 52 days Tue 05-07-22
65 100% 1.5.4.1 Deep Dive Technical Workshop Session 1 day Tue 05-07-22
66 100% 1.5.4.2 Provide access to the Dell design tool 1 day 65 Wed 06-07-22
67 100% 1.5.4.3 Kyndryl to populate the online Dell PEQ template 20 days Thu 07-07-22
68 100% 1.5.4.3.1 VxRail PEQ 20 days 66 Thu 07-07-22
69 100% 1.5.4.3.2 Dell Server PEQ 20 days 66 Thu 07-07-22
70 100% 1.5.4.3.3 Dell Switch PEQ 20 days 66 Thu 07-07-22
71 100% 1.5.4.3.4 Data Domain PEQ 20 days 66 Thu 07-07-22
72 100% 1.5.4.3.5 Networker PEQ 20 days 66 Thu 07-07-22
73 100% 1.5.4.4 Dell PEQ review/confirmation by Dell SMEs 0 days 67,101 Tue 23-08-22
74 100% 1.5.4.5 Develop TSD 1st draft 4 days 65 Wed 06-07-22
75 100% 1.5.4.6 Develop CyberVault NW/FW solution design 2 days 74 Wed 06-07-22
76 100% 1.5.4.7 TSD 1st Draft review call 1 day 74,75 Tue 19-07-22
77 100% 1.5.4.8 Updates to draft based on review 3 days 76 Wed 20-07-22
78 100% 1.5.4.9 TSD 2nd Draft review call 1 day 77 Tue 02-08-22
79 100% 1.5.4.10 Updated based on TSD 2nd Draft 3 days 78 Wed 03-08-22
80 100% 1.5.4.11 Milestone: TSD is ready for client & Dell review 0 days 79 Fri 05-08-22
81 100% 1.5.4.12 Send TSD copy for the Bank call review 3 days 80 Mon 08-08-22
82 100% 1.5.4.13 Send TSD copy for the Dell review 1 day 80 Mon 08-08-22
83 100% 1.5.4.14 TSD 1st review with LBC 1 day Tue 16-08-22
84 100% 1.5.4.15 Update TSD based on LBC review 2 days 83 Wed 17-08-22
Page 4
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
85 100% 1.5.4.16 Provide CyberVault Subnet 48 days 65 Wed 06-07-22
86 100% 1.5.4.16.1 Discuss/review CV Subnet requirements 4 days 65 Wed 06-07-22
87 100% 1.5.4.16.2 Create CV subnet requirements -First Draft 1 day 86 Tue 12-07-22
88 100% 1.5.4.16.3 First Call with Client NW SME to review Subnet 1 day 87 Wed 13-07-22
requirements
89 100% 1.5.4.16.4 Fill Compliance Questionnaire 3 days 88 Thu 14-07-22
90 100% 1.5.4.16.5 Second Call with Client NW SME to review Subnet 1 day 88SF+7 days Thu 21-07-22
requirements
91 100% 1.5.4.16.6 Update Questioannire and Requirements 5 days 90 Fri 22-07-22
92 100% 1.5.4.16.7 3rd Call with Client NW SME to review Subnet 1 day 90SF+7 days Fri 29-07-22
requirements
93 100% 1.5.4.16.8 Client sign-off 30 days 90,92 Tue 02-08-22
94 100% 1.5.4.16.9 Provide Ips 5 days Tue 02-08-22
95 100% 1.5.4.16.9.1 Switches 5 days 92 Tue 02-08-22
96 100% 1.5.4.16.9.2 VxRail 5 days 92 Tue 02-08-22
97 100% 1.5.4.16.9.3 PowerEdge Servers 5 days 92 Tue 02-08-22
98 100% 1.5.4.16.9.4 Data Domain 5 days 92 Tue 02-08-22
99 100% 1.5.4.16.9.5 Networker 5 days 92 Tue 02-08-22
100 100% 1.5.4.17 Dell resources assignment & planning calls 17 days Mon 22-08-22
101 100% 1.5.4.17.1 Assign resources For Vxrail, Switches, DD and 1 day Mon 22-08-22
PowerEdge and consultants
102 100% 1.5.4.17.2 Handover call between consulting teams and 1 day 101SS Mon 22-08-22
Deployment team
103 100% 1.5.4.17.3 Workshop with Dell -1 (TSD 1st Review) 1 day 101SS,82 Mon 22-08-22
Page 5
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
104 100% 1.5.4.17.4 Workshop with Dell -2 (TSD 2st Review) 1 day 103FS+1 day Wed 24-08-22
105 100% 1.5.4.17.5 Workshop with Dell -3 1 day 104FS+1 day Fri 26-08-22
106 100% 1.5.4.17.6 Confirm/Approve the TSD from Dell (To prepare 3 days 105 Mon 29-08-22
for ARB approval)
107 100% 1.5.4.17.7 Planning call For Switches 1 day 106 Thu 01-09-22
108 100% 1.5.4.17.8 Planning call for Vxrail Nodes 1 day 107 Fri 02-09-22
109 100% 1.5.4.17.9 Planning call for PowerEdge Servers 1 day 107 Fri 02-09-22
110 100% 1.5.4.17.10 Planning call for Data Domain 1 day 109 Tue 06-09-22
111 100% 1.5.4.17.11 Planning call for Networker (backup Software) 1 day 109 Tue 06-09-22
112 100% 1.5.4.17.12 Second Planning call for the Switches to review 1 day 95,107 Fri 02-09-22
the design document, finalize it and confirm site
113 100% 1.5.4.17.13 readiness
Second Planning call for the Vxrail Nodes to 1 day 96,112 Tue 06-09-22
review the design document, finalize it and
114 100% 1.5.4.17.14 confirmPlanning
Second site readiness
call for the PowerEdge Servers 1 day 97,113 Wed 07-09-22
to review the design document, finalize it and
confirm site readiness
115 100% 1.5.4.17.15 Second Planning call for Data Domain to review 1 day 98,114 Thu 08-09-22
the design document, finalize it and confirm site
116 100% 1.5.4.17.16 readiness
Second Planning call for Networker to review the 1 day 99,115 Wed 14-09-22
design document, finalize it
117 100% 1.5.4.18 Send Package and schedule Architecture review 1 day 80,106 Wed 14-09-22
118 100% 1.5.4.19 TSD ARB review/approval 1 day 117 Fri 16-09-22
119 100% 1.5.5 Milestone : Completion of LLD/TSD 0 days 118 Fri 16-09-22
120 62% 1.6 Implementation of CyberVault Environment 117 days Thu 30-06-22
121 91% 1.6.1 Hardware Installation 92 days Thu 30-06-22
Page 6
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
122 100% 1.6.1.1 Send request to DELL to provide Power, Cabling & 1 day Thu 30-06-22
Space requirements for the Dell HW
123 100% 1.6.1.2 Provide Power & Space requirements for the Dell HW3 days 122 Fri 01-07-22
124 100% 1.6.1.3 Submit a DC Space plan request to DCS team 10 days 123 Wed 06-07-22
125 100% 1.6.1.4 Ensure power and space available and ready in DC 12 days 118,124,65 Mon 19-09-22
126 100% 1.6.1.5 Send request to DELL to provide list of Names & 1 day 125SS Mon 19-09-22
contacts for the Dell resources who will participate
in the Dell HW installation
127 100% 1.6.1.6 Identify Dell resources (Names & Contacts) 3 days 126 Tue 20-09-22
128 100% 1.6.1.7 Arrange DC access for Dell Tech. 0 days 127,23 Thu 22-09-22
129 100% 1.6.1.8 Provide DC access to Dell team 2 days 128 Fri 23-09-22
130 100% 1.6.1.9 S5248 Switch configuration( temp set up) 2 days 125 Thu 06-10-22
131 75% 1.6.1.10 Firewall installation and cabling 15 days 39,125,54 Thu 06-10-22
132 75% 1.6.1.11 Firewall configuration to allow Vault-Prod traffic 10 days 131 Fri 14-10-22
133 99% 1.6.1.12 Rack, stack, cable, power on and configure for 10 days Fri 21-10-22
EMC/Dell Hardware
134 100% 1.6.1.12.1 Powerswitch S5248F ( temp solution) 5 days 129,132,32 Fri 21-10-22
135 100% 1.6.1.12.2 Nexus Network Switch from Bank ( temp solution) 1 day 134 Mon 31-10-22
136 100% 1.6.1.12.3 Vxrail Servers 1 day 135 Tue 01-11-22
137 100% 1.6.1.12.4 PowerEdge Servers 1 day 136 Wed 02-11-22
138 100% 1.6.1.12.5 Data Domain 1 day 137 Thu 03-11-22
139 100% 1.6.1.13 Setup connectivity between equipment 5 days 133,131,132 Fri 04-11-22
140 0% 1.6.2 Milestone: HW and Firewall installation completed and 0 days 121 Thu 10-11-22
ready for configuration
Page 7
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
141 49% 1.6.3 Cyber Vault Build and config 27 days Fri 21-10-22
142 100% 1.6.3.1 AD and DNS configuration and NTP set up 5 days 125,132 Fri 21-10-22
143 100% 1.6.3.2 Configure ESXi Host/s(VxRail Servers) 3 days 133SF+1 day,125,142 Fri 28-10-22
144 100% 1.6.3.3 Build and configure RHEL Virtual machines needed 2 days 143,142 Wed 02-11-22
for Cyber Vault solution
145 100% 1.6.3.4 Build and configure Windows jump server Virtual 1 day 144,142 Fri 04-11-22
Machine needed for Cyber Vault solution
146 0% 1.6.3.5 Secondary AD/ DNS 7 days 142,144 Wed 16-11-22
147 0% 1.6.3.6 Implementation Airgap Automation Workflow 5 days 145 Mon 07-11-22
148 50% 1.6.3.7 Install Cyber Recovery & Cyber Sense Application 5 days 133,125,142 Fri 04-11-22
149 50% 1.6.3.8 Configure Cyber Recovery & Cyber Sense Application12 days 148,142 Mon 14-11-22
150 0% 1.6.4 Milestone : Hardware Built and Cyber Sense config 0 days 141 Tue 29-11-22
Completed
151 50% 1.6.5 Configure Production & Vault data domain 15 days Tue 01-11-22
152 50% 1.6.5.1 Identify Mtrees For test case 15 days Tue 01-11-22
153 50% 1.6.5.2 Setup Replication Link between Production DD and 4 days 147 Mon 14-11-22
vault DD
154 0% 1.6.6 Data Vaulting 18 days Wed 23-11-22
155 0% 1.6.6.1 Create Test Case Mtree in Prod DD 7 days Wed 23-11-22
156 0% 1.6.6.1.1 Submit Change ticket to create prod Mtree 1 day 152 Wed 23-11-22
157 0% 1.6.6.1.2 Approve Change Ticket 3 days 156 Thu 24-11-22
158 0% 1.6.6.1.3 Create Mtree on the Prod DD (DD9900) & backup 3 days 157 Tue 29-11-22
the 2 Applications
159 0% 1.6.6.1.4 Milestone: Mtrees Configured 0 days 158 Thu 01-12-22
Page 8
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
160 0% 1.6.6.2 Data Seeding & DD replication 13 days Wed 30-11-22
161 0% 1.6.6.2.1 Submit change ticket for Networker tasks (e.g. 1 day 149 Wed 30-11-22
Agent installation)
162 0% 1.6.6.2.2 Approve Change Ticket 3 days 161 Thu 01-12-22
163 0% 1.6.6.2.3 Use the Networker software to configure Prod 2 days 162 Tue 06-12-22
backups - Adding users, policies, add devices,
schedule policies, alertes etc..
164 0% 1.6.6.2.4 (Production)Networker agent installed on all 3 days 162 Tue 06-12-22
servers/VMs to be included into the Cyber Vault
165 0% 1.6.6.2.5 Create CRQ for transfer of back-ups to the DD94003 days 163,158,164 Fri 09-12-22
166 0% 1.6.6.2.6 Start mtree replication for the test case Mtree 3 days 165 Wed 14-12-22
from Prod (DD9900) to Vault DD9400
167 0% 1.6.7 Milestone: Data Seeding and replication complete. 0 days 154,151 Fri 16-12-22
Cyber Vault Environement Ready
168 100% 1.7 REDDI VPN IMPLEMENTATION 13 days Wed 30-11-22
169 100% 1.7.1 Create list of endpoint names & IP addresses 2 days 149 Wed 30-11-22
170 100% 1.7.2 Request REDDI Account Codes 2 days 169 Fri 02-12-22
171 100% 1.7.3 Complete VPN Boarding form 2 days 170 Tue 06-12-22
172 100% 1.7.4 Implement VPN Firewall 2 days 171 Thu 08-12-22
173 100% 1.7.5 Establish VPN 2 days 172 Mon 12-12-22
174 100% 1.7.6 VPN Testing 1 day 173 Wed 14-12-22
175 100% 1.7.7 Request Socks ID's 1 day 174 Thu 15-12-22
176 100% 1.7.8 Test REDDI Access 1 day 175 Fri 16-12-22
177 100% 1.8 Milestone: REDDI remote access network available 0 days 176 Fri 16-12-22
Page 9
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
178 0% 1.9 MONITORING PHASE (MILAN VPN) 11 days Wed 30-11-22
179 0% 1.9.1 Complete Data Gathering Spreadsheet 1 day 149 Wed 30-11-22
180 0% 1.9.2 Collect Dell devices MIP files and send to Milan team 1 day 179 Thu 01-12-22
181 0% 1.9.3 Set up site to site VPN connection 2 days 179 Thu 01-12-22
182 0% 1.9.4 Set up IP address NATing 4 days 181 Mon 05-12-22
183 0% 1.9.5 Configure SNMP traps 4 days 181 Mon 05-12-22
184 0% 1.9.6 Set up agent within DRaaS OS (ITM) 4 days 181 Mon 05-12-22
185 0% 1.9.7 Perform first ITM discovery of devices 4 days 181 Mon 05-12-22
186 0% 1.9.8 Set up Tivoli consoles 2 days 185 Fri 09-12-22
187 0% 1.9.9 Configure management FW for monitoring 1 day 186 Tue 13-12-22
188 0% 1.9.10 Configure Events and Email notification 1 day 187 Wed 14-12-22
189 0% 1.10 Milestone: Monitoring operational 0 days 178 Wed 14-12-22
190 81% 1.11 Testing Phase 117 days Fri 22-07-22
191 89% 1.11.1 Test preparation & Documentation 53.25 days Fri 22-07-22
192 100% 1.11.1.1 Identify Test participants (LBC, Kyndryl & Dell) 2 wks Tue 02-08-22
193 88% 1.11.1.2 Scope 53.25 days Fri 22-07-22
194 100% 1.11.1.2.1 Identify Unix Apps 2 wks Fri 22-07-22
195 100% 1.11.1.2.2 Identify Windows Apps 2 wks Fri 22-07-22
196 100% 1.11.1.2.3 develop Test Scenarios 5 wks Fri 22-07-22
197 100% 1.11.1.2.4 confirm Success criteria 5 wks Fri 22-07-22
198 100% 1.11.1.2.5 Develop test document 1st draft 25 days Fri 22-07-22
199 50% 1.11.1.2.6 Review test document with LBC 20 days 198 Mon 29-08-22
Page 10
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
200 50% 1.11.1.2.7 finalize test document 10 days 199 Tue 13-09-22
201 0% 1.11.2 Milestone: Test document is ready (Participants, Scope 0 days 193 Tue 11-10-22
success crieria, etc..)
202 100% 1.11.3 Prepare CV Test VMs in PROD Environment 3 wks 200 Tue 11-10-22
203 0% 1.11.4 Execution & reporting 16 days Mon 19-12-22
204 0% 1.11.4.1 Submit change Ticket 1 day 202,167,159 Mon 19-12-22
205 0% 1.11.4.2 Approve Change Ticket 3 days 204 Tue 20-12-22
206 0% 1.11.4.3 Execute test 10 days 200,205 Tue 27-12-22
207 0% 1.11.4.4 Milestone: Test Execution Complete 0 days 206 Tue 10-01-23
208 0% 1.11.4.5 document results 2 days 206 Wed 11-01-23
209 0% 1.12 Milestone: Use Case Testing completed and Passed 0 days 190 Thu 12-01-23
210 0% 1.13 Milestone: PHASE 1 Completed 0 days 209 Thu 12-01-23
211
212
213
214 0% 2 Final config and Steady State Handover- PHASE 2 ( Tentative)78 days Thu 12-01-23
215 0% 2.1 Procurement 2 days Thu 12-01-23
216 0% 2.1.1 S5448 F Switches 1 day Fri 13-01-23
217 0% 2.1.2 S5212 Switches 1 day Fri 13-01-23
218 0% 2.1.3 Network Switches 2 days Thu 12-01-23
219 0% 2.2 Milestone: Procurement Completed 0 days 244 Wed 15-03-23
220 0% 2.3 Hardwrare Installation 10 days Mon 16-01-23
221 0% 2.3.1 S5448 F Switches 10 days 216 Mon 16-01-23
Page 11
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
222 0% 2.3.2 S5212 Switches 3 days 217 Mon 16-01-23
223 0% 2.3.3 Review DD to DD connecivity and change for 3 days 217 Mon 16-01-23
permanent design,if needed ( Prod clustered pair)
224 0% 2.3.4 Network Switches 3 days 218 Mon 16-01-23
225 0% 2.3.5 Test connectivity 3 days 224 Thu 19-01-23
226 0% 2.4 Milestone: Hardware set up completed 0 days 244 Wed 15-03-23
227 0% 2.5 TSD Development and Approval 18 days Fri 13-01-23
228 0% 2.5.1 Finalize Design 10 days 210,2 Fri 13-01-23
229 0% 2.5.2 Meeting 1 3 days 228 Fri 27-01-23
230 0% 2.5.3 Meeting 2 1 day 229 Wed 01-02-23
231 0% 2.5.4 Meeting 3 1 day 230 Thu 02-02-23
232 0% 2.5.5 ARB Approval 3 days 231 Fri 03-02-23
233 0% 2.6 Milestone: Final/ Permanent Design reviewed and approved0 days 244 Wed 15-03-23
234 0% 2.7 Final configuration 19 days Fri 13-01-23
235 0% 2.7.1 Permanent Set up changes- Network swtich / S5448 switch
10 days 210,2 Fri 13-01-23
236 0% 2.7.2 Initiate the final customization for enabling replicated 3 days 235 Fri 27-01-23
data to the Vault
237 0% 2.7.3 Configure up to four Mtrees to support MVC 3 days 236 Wed 01-02-23
238 0% 2.7.4 Finalize configuration to replicate the defined backups 3 days 237 Mon 06-02-23
to the Vault and validation the replication is working.
239 0% 2.8 Milestone: Final configuration completed 0 days 244 Wed 15-03-23
240 0% 2.9 QRadar 30 days Thu 16-03-23
241 0% 2.9.1 Development 15 days 249,219,226,233,239 Thu 16-03-23
242 0% 2.9.2 Testing 15 days 241 Thu 06-04-23
Page 12
ID Task % WBS Task Name Duration Predecessors Start
Mode Complete
243 0% 2.10 Milestone: QRadar Integrated 0 days 240 Wed 26-04-23
244 0% 2.11 Handover To Steady State 25 days Thu 09-02-23
245 0% 2.11.1 Steady State Processess (FW) 2 days 238,232 Thu 09-02-23
246 0% 2.11.2 Update all documentation(Operations handover, KT) 2 days 238,232 Thu 09-02-23
247 0% 2.11.3 Knowledge transfer from Transition to Steady State 20 days 246 Mon 13-02-23
support (GCC)
248 0% 2.11.4 Confirm acceptance of deliverables from Client 3 days 247 Mon 13-03-23
249 0% 2.12 Milestone: Go-Live 0 days 244 Wed 15-03-23
250 0% 2.13 Service Now Integration 30 days Thu 16-03-23
251 0% 2.13.1 Development 15 days 249,219,226,233,239 Thu 16-03-23
252 0% 2.13.2 Testing 15 days 251 Thu 06-04-23
253 0% 2.14 Milestone: SNOW Integrated 0 days 250 Wed 26-04-23
254 0% 2.15 Closure Activities 3 days Thu 27-04-23
255 0% 2.15.1 Closure Call 1 day 253,243 Thu 27-04-23
256 0% 2.15.2 Release Resources 1 day 255 Fri 28-04-23
257 0% 2.15.3 Closure of project in system 1 day 256 Mon 01-05-23
258 0% 2.16 Milestone:Project Completed and Closed 0 days 254 Mon 01-05-23
Page 13
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Thu 26-01-23
Fri 30-09-22 30-09
Fri 30-09-22 30-09
Thu 26-01-23
Thu 26-01-23
Tue 28-06-22
Tue 28-06-22 DRaaS PM,Account PM
Page 14
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Fri 24-06-22 Kyndryl PM
Fri 24-06-22 Kyndryl PM
Wed 13-07-22 DellEMC
Mon 19-09-22
Fri 29-07-22 29-07
Page 15
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Wed 27-07-22 Dell,RS Architect,RS NW Architect
Fri 23-09-22
Thu 28-07-22 Resiliency Mgmt.
Fri 29-07-22 Kyndryl Legal
Tue 02-08-22 Resiliency Procurement
Wed 03-08-22 Resiliency Mgmt.
Thu 04-08-22 Resiliency Procurement
Mon 08-08-22 Resiliency Mgmt.
Fri 12-08-22 Resiliency Procurement
Mon 15-08-22 HW Vendor
Mon 22-08-22 HW Vendor
Fri 23-09-22 HW Vendor
Fri 23-09-22 23-09
Fri 16-09-22
Wed 29-06-22 Kyndryl,LBC
Tue 30-08-22
Thu 30-06-22 DRaaS PM
Fri 01-07-22 DRaaS PM,Account PM
Wed 06-07-22 DRaaS PM,Account PM,Dell PM
Tue 12-07-22 DRaaS PM,Account PM,Dell PM
Tue 30-08-22 DRaaS PM,Account PM
Page 16
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Tue 30-08-22 30-08
Fri 16-09-22
Tue 05-07-22 Account Architect,RS NW Architect,RS Architect
Wed 06-07-22 RS Architect
Thu 04-08-22
Thu 04-08-22 Dell Architect,RS Architect
Thu 04-08-22 Dell Architect,RS Architect
Thu 04-08-22 Dell Architect,RS Architect
Thu 04-08-22 Dell Architect,RS Architect
Thu 04-08-22 Dell Architect,RS Architect
Tue 23-08-22 23-08
Mon 18-07-22 RS Architect,Account Architect,RS NW Architect
Tue 19-07-22 RS NW Architect
Wed 20-07-22 RS Architect,Account Architect,RS NW Architect
Mon 25-07-22 RS Architect,Account Architect,RS NW Architect
Tue 02-08-22 RS Architect,Account Architect,RS NW Architect
Fri 05-08-22 Dell,RS Architect,Account Architect
Fri 05-08-22 05-08
Wed 10-08-22 RS Architect
Mon 08-08-22 RS Architect
Tue 16-08-22 LBC
Thu 18-08-22 RS Architect
Page 17
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Tue 13-09-22
Mon 11-07-22 Account Architect,RS Architect,RS NW Architect,Dell Architect
Tue 12-07-22 Account Architect,RS Architect,RS NW Architect,Dell Architect
Wed 13-07-22 Account Architect,RS Architect,RS NW Architect,Dell Architect,LBC NW SME
Page 18
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Wed 24-08-22 RS Architect,Dell SME,Account Architect,RS NW Architect
Fri 26-08-22 RS Architect,Dell SME,Account Architect,RS NW Architect
Wed 31-08-22 Dell SME
Wed 14-09-22
Fri 16-09-22 LBC,Account Architect
Fri 16-09-22 16-09
Fri 16-12-22
Thu 10-11-22
Page 19
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Thu 30-06-22 Account PM
Page 20
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Tue 29-11-22
Thu 27-10-22 RS SMEs
Tue 01-11-22 Dell,RS Architect
Thu 03-11-22 Dell,RS Architect
Tue 22-11-22
Tue 22-11-22 RS Architect,Account Architect,LBC,Kyndryl BaaS
Thu 17-11-22 RS Architect,Dell
Fri 16-12-22
Thu 01-12-22
Wed 23-11-22 Kyndryl BaaS
Mon 28-11-22 LBC
Thu 01-12-22 Kyndryl BaaS
Page 21
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Fri 16-12-22
Wed 30-11-22 Kyndryl BaaS
Fri 16-12-22
Thu 01-12-22 Client Network Specialist
Mon 05-12-22 REDDI Team
Wed 07-12-22 DRaaS SME Local Team,Network Specialist
Fri 09-12-22 Resiliency NW Architect,LBC NW
Tue 13-12-22 Resiliency NW Architect,LBC NW
Wed 14-12-22 Resiliency NW Architect,LBC NW
Thu 15-12-22 Resiliency NW Architect
Fri 16-12-22 GCC Level 1 & 2 Support,Resiliency NW Architect
Fri 16-12-22 16-12
Page 22
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Wed 14-12-22
Wed 30-11-22 DRaaS SME Local Team
Thu 01-12-22 RS Linux,RS Windows
Fri 02-12-22 DRaaS SME Local Team
Thu 08-12-22 RS Italy,DRaaS SME Local Team
Thu 08-12-22 DRaaS SME Local Team
Thu 08-12-22 RS Italy
Thu 08-12-22 RS Italy
Mon 12-12-22 RS Italy,DRaaS SME Local Team
Tue 13-12-22 RS Italy,DRaaS SME Local Team
Wed 14-12-22 DRaaS SME Local Team
Wed 14-12-22 14-12
Thu 12-01-23
Tue 11-10-22
Mon 15-08-22
Tue 11-10-22
Fri 05-08-22 Account Architect
Fri 05-08-22 Account Architect
Fri 26-08-22 Account Architect,Account PM,RS Architect,BaaS
Fri 26-08-22 Account PM,Account Architect,RS Architect,BaaS
Fri 26-08-22 RS Architect
Mon 26-09-22 Account PM,Account Architect,RS Architect,BaaS,LBC
Page 23
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Tue 11-10-22
Tue 11-10-22 11-10
Mon 01-05-23
Fri 13-01-23
Fri 13-01-23
Fri 13-01-23
Fri 13-01-23
Wed 15-03-23 15-03
Fri 27-01-23
Fri 27-01-23
Page 24
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Wed 18-01-23 RS Architect
Wed 18-01-23
Wed 18-01-23
Mon 23-01-23 RS Architect
Wed 15-03-23 15-03
Tue 07-02-23
Thu 26-01-23
Tue 31-01-23 RS Architect
Wed 01-02-23
Thu 02-02-23
Tue 07-02-23 RS Architect
Wed 15-03-23 15-03
Wed 08-02-23
Thu 26-01-23
Tue 31-01-23 RS Architect
Fri 03-02-23
Wed 08-02-23 RS Architect
Page 25
Finish
06 Feb '22 15 May '22 21 Aug '22 27 Nov '22 05 Mar '23 11 Jun '23
F T S W S T M F T S W
Wed 26-04-23 26-04
Wed 15-03-23
Fri 10-02-23
Fri 10-02-23 RS Architect
Fri 10-03-23 RS Architect
Page 26