Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 13

Room 204 Cabrera Building II, No.

64 Timog Avenue Diliman, Quezon City 1103


Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/12/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 57.14%
Contractor DUAL AIR INC. Required Completion Rate 50.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 SQ M 0.00%


CONCRETE POURING
CONCRETE PAD 3.72 CU M 0.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
57.14%
457.14%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 6/22/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 58.82%
Contractor DUAL AIR INC. Required Completion Rate 55.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 3.01 SQ M 11.73%


CONCRETE POURING
CONCRETE PAD 3.72 CU M 0.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
58.82%
470.54%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 6/23/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 61.04%
Contractor DUAL AIR INC. Required Completion Rate 55.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 7.01 SQ M 27.31%


CONCRETE POURING
CONCRETE PAD 3.72 CU M 0.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
61.04%
488.35%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 6/24/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 64.41%
Contractor DUAL AIR INC. Required Completion Rate 60.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 13.06 SQ M 50.88%


CONCRETE POURING
CONCRETE PAD 3.72 CU M 0.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
64.41%
515.29%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 6/27/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 67.79%
Contractor DUAL AIR INC. Required Completion Rate 65.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 CU M 0.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
67.79%
542.36%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 6/28/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 82.08%
Contractor DUAL AIR INC. Required Completion Rate 80.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
82.08%
656.64%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/2/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 85.36%
Contractor DUAL AIR INC. Required Completion Rate 65.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 3.29 SQ M 22.93%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
85.36%
682.84%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/5/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 88.62%
Contractor DUAL AIR INC. Required Completion Rate 65.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 6.57 SQ M 45.78%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
88.62%
708.97%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/6/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 92.18%
Contractor DUAL AIR INC. Required Completion Rate 80.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 10.15 SQ M 70.73%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
92.18%
737.48%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/6/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 96.37%
Contractor DUAL AIR INC. Required Completion Rate 85.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 14.35 SQ M 100.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
96.37%
770.93%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/6/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 93.26%
Contractor DUAL AIR INC. Required Completion Rate 90.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 21.07 SQ M 82.08%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 10.15 SQ M 70.73%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
93.26%
746.07%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/15/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 100.00%
Contractor DUAL AIR INC. Required Completion Rate 83.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 25.67 SQ M 100.00%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 14.35 SQ M 100.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
100.00%
800.00%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 8/22/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 100.00%
Contractor DUAL AIR INC. Required Completion Rate 100.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

MASONRY WORKS
CONCRETE POURING 1.92 1.92 0.00 CU M 100.00%
EPOXY PAINT 12.01 12.01 0.00 SQ M 100.00%

100.00%
300.00%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 2
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 4

Melvin Sarcia

Engr. Raymart Dela Cruz


Project In Charge

You might also like