Professional Documents
Culture Documents
REVIEW 570rev 1
REVIEW 570rev 1
PIPING SYSTEM DAMAGE TYPE – AS PER API 571 (SEE API 571) SUPPLEMENTAL INSPECTION
AREAS OF DETERIORATION FOR PIPING SYSTEMS (SEE API 571) EXAMPLE OF INSPECTION
INJECTION POINTS AND MIX POINTS PERIODIC USE OF RADIOGRAPHY AND THERMOGRAPHY
DEADLEGS CHECK FOR FOULING OR INSTERNAL PLUGGING
CUI INCLUDING ECSCC THERMOGRAPHY TO CHECK FOR HOT SPOTS INS REFRACTORY LINED
SOIL TO AIR INTERFACE AND SOIL CORROSION OF BURRIED PIPE SYSTEMS
LOCALIZED CORROSION VERIFIFYING PREVIOSLY MEASURED DATE ACCURACY
EROSION AND EROSION/CORROSION INSPECTION FOR ENVIRONMENTAL CRACKING AND DAMAGE
ENVIRONMENTAL CRACKING MECHANISM
CORROSION BENEATH LINING AND DEPOSITS ACCOUSTIC EMISSION, ACCOUSTIC LEAK DETECTION AND
FATIGUE CRACKING THERMOGRAHY CAN BE USE FOR REMOTE LEAK DETECTION AND
CREEP CRACKING SUVEILLANCE
FREEZE DAMAGE LOCALIZED EROSION OR EROSION/ CORROSION SHOULD BE INSPECTED
CONTACT POINT CORROSION BY VISUAL INSPECTION
BRITTLE FRACTURE IS FOR ONWER/USER SHOULD BE AWARE FOR THE CML – CONDITION MONITORING LOCATION
POTENTIAL FOR BRITTLE FRACTURE
SPECIFIC AREAS ALONG THE PIPING CIRCUIT WHERE INSPECTIONS ARE
TYPE OF INSPECTION AND SURVEILLANCE CONDUCTED.
VARIES ACCORDING TO ITS LOCATION IN THE SYSTEM.
1) INTERNAL VISUAL INSPECTION SERVICE-SPECIFIC DAMAGE MECANISMS
FOR LARGE DIAMETER LOCALIZED CORROSION
FOR PRESSURE VESSEL INSPECTION
USE OF (RVI) REMOTE VISUAL INSPECTION OR BORROSCOPE CML MONITORING
2) ONSTREAM INSPECTION ( SEE API 574 FOR MORE INFORMATION)
ALL ON-STREAN INSPECTION SHALL BE CONDUCTED BY INSPECTOR SHALL BE MONITORED APPROPRIATELY PLACE CMLS.
OR EXAMINER HIGHER CORROSION RATE OR LOCALIZED CORROSION HAVE MORE CML
MAY BE REQUIRED BY THE INSPECTION PLAN (ITP) USE OF UT, RT AND ELECTROMAGNETIC FOR CML MONITORING
ALL INSPECTION OF THE EXAMINER SHALL BE AUTHORIZED AND THE THINNEST READING OR AN AVERAGE OF SEVERAL MEASUREMENT
APPROVE BY THE INSPECTOR. READING SHALL BE RECORDED AND USE TO CALCULATE CORROSION
TYPE OF MATERIALS RATE
WELDMENTS THE RATE OF CORROSION OR DAMAGE SHALL BE DETERMINED FROM
PIPE JUNCTIONS, NOZZLE, SUPPORT SADDLES, REINFORCING SUCCESSIVE MEASUREMENTS AND THE NEXT INSPECTION
PLATES CML SHOULD BE ESTABLISHED FOR AREAS WITH CONTINUING CUI,
INTERNAL LINING OR CLADDING CORROSION AT SAI INSTERFACES, IMMEDIATELY UPSTREAM AND
PHYSICAL ACCESS AND EQUIPMENT TEMPERATURE DOWNSTREAM OF PIPING MATERIAL CHANGES
LIMITATION OF NDE TO DETECT THE DAMAGE MECHANISM CML SHOULD BE MARKED ON INSPECTION DRAWINGS.
TYPE OF DAMAGE MECHANISM ON THE PIPING SYSTEM SAME LOCATION
3) THICKNESS MEASUREMENT INSPECTION AND VARIUS NDE
CML ALLOCATION
EXAMINATION
VERIFY THE THICKNESS OF PIPING COMPONENTS
HIGHER POTENTIAL FOR CREATING A SAFETY OR ENVIRONMENTAL
CALCULATE THE CORROSION RATE AND RAMAINING LIFE
EMERGENCY LEAK
THICKNESS MEASUREMENT SHALL BE OBTAIN BY THE INSPECTOR
HIGHER EXPECTED CORROSION RATE
OR EXAMINER
HIGHER LOCALIZED CORROSION
THICKNESS MEASUREMENT ARE TAKEN WHILE PIPING IS ON-
HIGHER CUI
STREAM
HIGHER CORROSION RATE
THE INSPECTOR SHOULD CONSULT WITH A CORROSION SPECIALIST
HIGHER SHORT/ LONG TERM RATE OR MAXIMUM RATIOS
WHEN THE SHORT-TERM CORROSION RATE CHANGE
LONG STRAIGHT- RUN PIPING SYSTEM
SIGNIFICANTLY FROM THE PREVIOUS IDENTIFIED RATE TO
DETERMINE THE CAUSE
CONDITION MONITORING METHODS
4) EXTERNAL VISUAL INSPECTION
DETERMINE THE CONDITION OF THE OUTSIDE OF THE PIPING,
RT
INSULATION SYSTEM, PAINTING, AND COATING SYSTEM
TO CHECK FOR SIGNS OF MISALIGNMENT PRT IS PREFFERED FOR SMALL BORE PIPING (SBP)
CHECK FOR VIBRATION AND LEAKAGE FOR PIPE DIAMETERS OF NPS 1 AND SMALLER
CHECK PIPING SUPPORT AND HANGER PRT IS PREFERRED FOR SBP WHERE DIGITAL ULTRASONIC THICKNESS
INCLUDE CUI GAUGING (DUT) ARE NOT VERY RELIABLE.
5) VIBRATING PIPING AND LINE MOVEMENT SURVEILLANCE – PIPING ENG’R PRT IS VERY OFTEN THE TECHNIQUE OF CHOICE ON NPS 8 AND UNDER
AND INSPECTION PERSONNEL WHEN LOCALIZED CORROSION IS SUSPECTED.
SHOULD REPORT VIBRATING OR SWAYING
RESULT OF LIQUID HAMMERING
FATIGUE CRACKING
UT- ASME SECTION V ARTICLE 23 AND SECTION SE-797 THICKNESS MEASUREMENT UT ANGLE BEAM EXAMINERS
NPS 2 AND BELOW MAY REQUIRE SPECIALIZED EQUIPMENT (MINIATURE THE OWNER/USER SHALL SPECIFY INDUSTRY QUALIFIED UT ANGLE BEAM
PROBE OR CURVED SHOES EXAMINERS
MEASUREMENT ARE TAKEN ABOVE 150 F (65 C) INSTRUMENTS, DETECTION OF INTERIOR SURFACE (ID) BREAKING FLAWS WHEN
COUPLANTS, AND PROCEDURES SHOULD BE USED THAT WILL RESULT IN INSPECTING FROM THE EXTERNAL SURFACE OD.
ACCURATE MEASUREMENTS AT THE HIGHER TEMPERATURES DETECTION CHARACTERIZATION OR THROUGH WALL SIZING OF DEFECT
FACTORS THAT CAN CONTRIBUTE TO REDUCE ACCURACY OF
ULTRASONIC MEASUREMENTS INCLUDE THE FLOWING CUI INSPECTION
a) IMPROPER CALIBRATION
b) EXTERNAL COATING OR SCALE INSPECTION FOR CUI SHALL BE CONSIDERED FOR EXTERNALLY-
c) PROBE ORIENTATION INSULATED CARBON AND LOW ALLOY PIPING OPERATION
d) SUBSURFACE MATERIAL FLAWS(LAMINATION) HISTORY OF CUI
e) TEMP. ABOVE 150 F (65 ) VISUAL CONDITION
f) RESOLUTION OF SCREEN EVIDENCE OF FLUID LEAKAGE
g) LESS THAN 3.2MM FOR TYPICAL DTG WHETHER THE PIPING SYSTEMS ARE IN INTERMITTENT SERVICE
h) TO MUCH OR LITTLE COUPLANT CONDITION/AGE OF THE EXTERNAL COATING, IF KNOWN
EVIDENCE OF AREAS WITH WET INSULATION
OTHER NDE TECHNIQUES FOR PIPING SYSTEMS POTENTIAL FOR THE TYPE OF INSULATION TO ABSORB/ HOLD MORE
WATER
MAGNETIC PARTICLE EXAMINATION LOW POINT OF SAGGING LINES
a) FOR CRACKS AND LINEAR DISCOUNTINUITIES THAT EXTEND BOTTOM OF VERTICAL PIPE
TO THE SURFACE
PROXIMITY TO EQUIPMENT THAT COULD INCREASE THE LOCAL
b) FERROMAGNETIC MATERIALS
HUMIDITY
c) ASME SECTION V ARTICLE 7
AREAS WHERE TEMPERATURE REGIMES ARE MOVING INTO AND OUT OF
LIQUID PENETRANT EXAMINATION
THE CUI
a) FOR DISCLOSING CRACKS, POROSITY OR PINHOLES THAT
EXTEND TO THE SURFACE MIXING POINT INSPECTION
b) FOR OUTLINING OTHER SURFACE IMPERFECTIONS,
ESPECIALLY IN NONMAGNETIC MATERIALS MIXING POINT ARE LOCATION IN PIPING SYSTEMS WHERE TWO OR
c) ASME SECTION V ARTICLE 6 MORE DIFFERENT STREAMS MEET
RT
a) FOR DETECTING INTERNAL IMPERFECTION SUCH AS INJECTION POINT INSPECTION
POROSITY, WELD SLAG INCLUSIONS, CRACK AND THICKNESS
COMPONENTS ARE SOMETIMES SUBJECT TO ACCELERATED OR LOCALIZED CORROSION
b) ASME SECTION V ARTICLE 2 FROM NORMAL TO ABNORMAL OPERATING CONDITION
ULTRASONIC FLAW UPSTREAM LIMIT 12 IN (300MM) OR 3X PIPE DIAMETER, WHICHEVER IS
a) FOR DETECTING INTERNAL AND SURFACE BREAKING CRACKS GREATER
AND OTHER ELONGATED DISCONTINUITIES DOWNSTREAM 25FT (706MM) BEYOND THE FIRST CHANGE IN FLOW
b) ASME SECTION V ARTICLE 4,5 AND 23 DIRECTION, WHICHEVER IS LESS
ALTERNATING CURRENT FLUX LEAKAGE EXAMINATION PREFFERED NDE IS RT AND UT
a) FOR DETECTING SURFACE-BREAKING CRACKS AND
ELONGATED DISCONTINUITIES PRESSURE TESTING OF PIPING SYSTEMS
EDDY CURRENT EXAMINATION
b) FOR DECTECTING LOCALIZED METAL LOSS, CRAKING, AND PRESSURE TESTING ARE NOT NORMALLY CONDUCTED AS PART OF A
ELONGATED DISCONTINUITIES ROUTINE INSPECTION
c) ASME SECTION V ARTICLE 8 PRESSURE TESTING REQUIREMENTS FOR REPAIR, ALTERATION AND RE-
FIELD METALLOGRAPHIC REPLICATION RATING
a) OTHER NAME REPLICA AFTER ANY HEAT TREATMENT
b) FOR IDENTIFYING METALLURGICAL CHANGES AN ENGINEER SHOULD BE CONSULTED WHEN PRESSURE TESTING
ACCOUSTIC EMISSION EXAMINATION ENTIRE PIPING CIRCUIT
a) FOR DETECTING STRUCTURALLY SIGNIFICANT DEFECTS DESIGN OF SUPPORT NEED TO REVIEW BY ENGINEER
b) ASME SECTION V ARTICLE 11 AND 12 THE OWNER/USER IS CAUTIONED TO AVOID EXCEEDING 90% OF THE
THERMOGRAPHY SPECIFIED MINIMUM YIELD STRENGTH
a) FOR DETERMING TEMPERATURE OF COMPONENTS,
BLOCKAGES, DEBRIS/SEDIMENT LEVEL AND FLOW TEST FLUID
VERIFICATION
LEAK TESTING THE TEST FLUID SHOULD BE WATER UNLESS THERE IS THE POSSIBILTY OF
a) FOR DETECTING THROUGH-THICKNESS DEFECTS DAMAGE DUE TO FREEZING
b) ASME SECTION V ARTICLE 10 IF LIQUID IS FLAMMABLE, FLASHING POINT SHALL BE AT LEAST 120 F
GUIDED WAVE EXAMINATION (49 C)
a) FOR DETECTION OF METAL LOSS PIPING SHOULD BE THOROUGHLY DRAINED (ALL HIGH POINT VENTS
SHOULD BE OPEN DURING DRAINING). AIR BLOWN OR OTHERWISE
SUFACE PREPARATION FOR NDE DRIED.
IF PORTABLE WATER IS NOT AVAILABLE, WATER HAVING LOW CHLORIDE
IMPORTANT FOR VISUAL, SURFACE PREPARATION WIRE BRUSHING, BLASTING, LEVEL HIGHER PH (>10) TO REDUCE PITTING AND MICROBIOLOGICALLY
CHIPPING, GRINDING OR A COMBINATION INDUCED CORROSION
IF VALVE IS SUSPTECTED OF CORROSION-EROSION, THICKNESS READING
SHOULD BE CONDUCTED ON THE BODY BETWEEN THE SEATS
PNEUMATIC PRESSURE TESTING CHECKING THE FLAPPER IS FREE TO MOVE
THE FLAPPER STOP SHOULD NOT HAVE WEAR BEYOND TOLERANCE
MAY BE USED WHEN IT IS IMPRACTICABLE TO HYDROSTATICALLY THE FLAPPER NUT SHOULD BE SECURED TO THE FLAPPER BOTT TO
TESTING DUE TO TEMPERATURE, STRUCTURAL, OR PROCESS AVOID BACKING OFF INSERVICCE
LIMITATIONS.
IN-SERVICE INSPECTION OF WELDS
TEST TEMPERATURE AND BRITTLE FRACTURE CONSIDRATIONS
INSPECTION FOR PIPING WELD IS FOR NEW CONSTRUCTION, REPAIR OR
EXPOSED TO TEMPERATURES BELOW THEIR TRANSITION TEMPERATURE ALTERATION
PRESSURE GREATER THAN 25% OF THE REQUIRED HYDROSTATIC TEST WELD ARE OFTEN INSPECTED FOR CORROSION AS A PART OF A
PRESSURE OR 8 KSI OS STRESS RADIOGRAPHIC PROFILE INSPECTION OR AS A PART OF INTERNAL
TO MAXIMIZE THE RISK OF BRITTLE FRACCTURE DURING A PRESSURE INSPECTION.
TEST, THE METAL TEMP SHOULD BE MAINTAIND AS LEAST 3 F (17 C) SEE API 577
ABOVE THE MDMT FOR PIPING THAT IS MORE THAN 2 IN. (5 CM) THICK
CRACK – LIKE FLAWS AND ENVIRONMENTAL CRACKING SHALL BE
10 F (6 C) ABOVE THE MDMT FOR PIPING THAT HAVE A THICKNESS OF ASSESSED BY AN ENGINEER IN ACCORDANCE WITH API 579
2 IN (5 CM) OR LESS PREFERENTIAL WELD CORROSION SHALL BE ASSSESED BY THE
THE TEST TEMPERATURE NEED TO EXCEED 120 F ( 50 C) UNLESS THERE IS INSPECTOR
INFORMATION ON THE BRITTLE CHARACTERISTICS OF THE PIPE.
ISSUES TO CONSIDER WHEN ASSESSING THE QUALITY OF EXISTING
WELDS INCLUDE THE FOLLOWING
PRECAUTIONS AND PROCEDURES
a) ORIGINAL FABRICATION INSPECTION METHOD AND
ACCEPTANCE CRITERIA
IF EXCEED THE SET PRESSURE OF THE PRESSURE RELIEVING DEVICE(PRD),
b) EXTENT, MAGNITUDE, AND ORIENTATION OF IMPERFECTION
THE PPRESSURE RELIEVING DEVICE (PRD) SHOULD BE REMOVED OR
c) LENGTH OF TIME IN SERVICE
BLANKED
d) OPERATING VERSUS DESIGN
AS AN ALTERNATIVE, EACH VALVE DISK SHALL BE HELD DOWN BY A
e) POTENTIAL FATIGUE LOADS
SUITABLY DESIGNED TEST CLAMP
f) POTENTIALFOR IMPACTOR TRANSIENT LOADS
GAGE GLASSES, PRESSURE GAGES, EXPANSION JOINTS, AND RUPTURE
g) POTENTIAL FOR IENVIRENMENTAL CRACKING
DISKS, SHOULD BE REMOVED OR BLANKED.
h) REPAIR HISTORY
i) HEAT TREATMENT HISTORY
PRESSURE TESTING ALTERNATIVES
j) DISSIMILAR METAL
APPROPRIETE NDE SHALL BE SPECIFIED AND CONDUCTED WHEN A k) WELD HARDNESS
PRESSURE TEST IS NOT PERFORMED AFTER A MAJOR REPAIR OR
INSPECTION OF FLANGE JOINT
ALTERATION
FOR SUBSTITUTING NDE PROCEDURES FOR PRESSURE TEST AFTER AN
FLANGE JOINT SHOULD BE EXAMINED FOR EVIDENCE OF LEAKAGE
ALTERATION IS ALLOWED ONLY AFTER THE ENGINEER AND INSPECTOR
HAVE APPROVE
FOR CASES WHERE UT IS USED IN LIEU OF A PRESSURE TEST, THE
OWNER/USER SHALL SPECIFY INDUSTRY-QUALIFIED UT ANGLE BEAM 6.0
EXAMINERS
INTERVAL/FREQUENCY AND EXTENT OF INSPECTION
MATERIAL VERIFICATION AND TRACEABILITY
GENERAL
THE OWNER/USER SHALL ASSESS THE NEED FOR EXTENT OF
APPLICATION OF A MATERIAL VERIFICATION TO ENSURE EQUIPMENT INTEGRITY
CONFIRMATIONOF MATERIALS DISCRIBE IN API 578 ALL PIPING SYSTEMS AND PRD (PRESSURE RELIEVING DEVICE) SHALL BE
THE OWNER/USER AND AUTHORIZED PIPING INSPECCTOR, IN INSPECTED AT THE INTERVALS/FREQUENCIES PROVIDED IN THIS SECTION
CONSULTATION WITH A CORROSION SPECIALIST, SHALL ESTABLISH A SCHEDULED INSPECTIONS SHALL BE CONDUCTED ON OR BEFORE DUE
SCHEDULE FOR REPLACEMENT OF THOSE COMPONENTS UNTIL THE DATE OR CONSIDERED OVERDUE
REPLACEMENT AN INSPECTION DUE
AUTHORIZED INSPECTOR SHALL USE PERIODIC NDE, AS NECESSARY, ON DATE MY BE DETERMINED THROUGH A RISK ASSESSMENT IN API 580
THE IDENTIFIED COMPONENT UNTIL THE REPLACEMENT
OLDER PROCESS UNITS OPERATING ABOVE 500 F (260 C) AND SUBJECT INSPECTION DURING INSTALLATION AND SERVICE CHANGES
TO SULFIDATION CORROSION, CARBON STEEL PIPING CONTAINING LESS
THAN 0.1 WT % SILICON CAN CORRODE AT SIGNIFICANTLY HIGHER PIPING INSTALLATION
RATES THAN HIGHER SILICON CARBON STEELS
PIPING SHALL BE INSPECTED IN ACCORDANCE WITH CODEOF
INSPECTION OF VALVE CONSTRUCTION REQUIREMENTS
INSTALLATION INSPECTION IS TO VERIFY THAT THE PIPING IS CLEAN AND
THICKNESS MEASUREMENTS ARE NOT ROUTINELY TAKEN ON VALVES IN SAFE FOR OPERATION
PIPING CIRCUITS, THE BODY OF A VALVE IS THICKER THAN THE PIPE VERIFY THAT THE PIPE INSTALL CORRECTLY
SHOP PERSONNEL SHOULD VISUALLY EXAMINE THE VALVE WITH THE CORRECT METALLURGY IS INSTALLED
UNUSUAL PATTERNS OR THINNING SUPPORTS
REPORT THE INFORMATION TO THE INSPECTOR VERIFY THE (PRD) PRESSURE RELIEVING DEVICES SATISFY THE DESIGN
EXAMINED PERIOICALLY FOR THERMAL FATIGUE CRACKING REQUIREMENTS
DOCUMENT
Creating vapors that can collect and form an explosive mixture, such as
C2, C3 and C4.
PIPING SERVICE CHANGE Boiling Point below 50 F (10) or below the operating tempature
Hydrogen sulphide greater than 3 % weight
IF THE SERVICE CONDITION OF THE PIPING SYSTEM ARE CHANGED, IT Hydrofluoric acid
WILL EXCEED THE CURRENT OPERATING ENVELOPE Piping over or adjacent to water and piping over public throughways
a) PROCESS CONTENT
(refer to national or local regulations e.g. department of transportation
b) MAXIMUM OPERATING PRESSURE
coast guard
c) MAXIMUM AND MINIMUM OEPRATING TEMPERATURE
Flammable services operating above their auto-ignition temperature
GENERAL
Services not included in other class are in class 2
Majority of unit process piping and selected offsite piping
FREQUENCY AND EXTENT OF INSPECTION ON PIPING CIRCUIT WHETHER
On site hydrocarbons that will slowly vaporize during release
ABOVE OR BELOW GROUND DEPEND ON THE AFFECTED PIPING AND
Below the boiling point but above the flash point
CONSEQUENCES OF FAILURE
On site hydrogen, fuel gas and natural gas
DEPENDS ON TH DAMAGE MECHANISM
On site strong acids and caustics
DEPENDS ON THE CONSEQUENCE OF FAILURE
Class 3
SETTING INSPECTION INTERVAL WITH RBI
Services that are either flammable but do not significantly vaporize when
ASSESSMENT IN ACCORDANCE WITH API 580
they leak below the flash point
DETERMINE INSPECTION INTERVAL
Flammable but are located in remote areas
DETERMINE INSPECTION DUE DATE
On site hydrocarbons that will not significantly vaporize during release
SETTING INSPECTION INTERVAL WITHOUT THE USE OF RBI Offsite distillate and product lines to and from storage and loading
Tank farm piping
IF RBI IS NOT USED Offsite acids and Caustics
a) THE CORROSION RATE AND REMAINING LIFE CALCULATIONS Off-site hydrogen, fuel gas and natural gas
b) THE PIPING SERVICE CLASSIFICATION Other lower risk hydrocarbon piping that does not fall in class 1,2,4
c) THE APPLICABLE JURISDICTIONAL REQUIREMENTS
d) THE JUDGEMENTAL OF INSPECTOR, PIPING ENGINEER, PIPING Class 4
SUPERVISOR AND MATERIAL SPECIALIST BASE ON OPERATING
CONDITION Service that are essentially non-flammable and nontoxic
e) THE OWNER/USER OR THE INSPECTOR SHALL ESTABLISH Steam and steam condensate
INSPECTION INTERVAL FOR THICKNESS AND VISUAL Air
f) FOR CLASS 1,2,3 THE PERIOD BETWEEN THICKNESS Nitrogen
MEASUREMENTFOR CML OR CIRCUIT SHOULD NOT EXCEED Water, including boiler feed water or stripped sour water
ONE HALF THE REMAINING LIFE OR THE MAXIMUM Lube oil, seal oil
INTERVALS RECOMMENDED IN TABLE 1, WGICH EVER IS LESS Category d services
g) WHENEVER THE REMAINING LIFE IS LESS THAN FOUR YEARS, Plumbing and sewers
THE INSPECTION INTERVAL MAY BE THE FULL REMAINING
LIFE UP TO A MAXIMUM OF 2 YEARS
h) THE INTERVAL IS ESTABLISHED BY THE INSPECTOR OR PIPING
ENGINEER IN ACCORDANCE WITH THE ONWER/USER QA
SYSTEM
GENERAL – the owner/user shall maintain a record of process piping fluids handled,
including their classification.
Class 1
PRD inspection
NOTE Thickness measurements apply to systems for which CMLs have been
established in accordance with 5.6.
a Inspection intervals or due dates for potentially corrosive injection can also
be established by a valid RBI analysis in accordance with API 580. Statistical analysis method
b See API 574 for more information on SAI interfaces.
Probability plots or related tools to establish a representative corrosion,
remaining life remaining life estimate or re-inspection date. PIPING STRESS ANALYSIS
MAWP FOR THE CONTINUED USE OF PIPING SYSTEMS SHALL BE COMPUTER RECORDS – USE COMPUTER BASE SYSTEM FOR STORING
ESTABLISHED USING THE APPLICABLE CODE CALCULATING AND ANALYZING DATA SHOULD BE CONSIDERED
COMPUTATIONS MAY BE MADE FOR KNOWN MATERIALS IS ALL THE a) STORING AND ANALYZING THE ACTUAL THICKNESS READING
FOLLOWING ESSENTIAL COMPLY b) CALCULATING SHORT TERM AND LONG TERM CORROSION RATES
UPPER OR LOWER TEMPERATURE LIMITS FOR SPECIFIC MATERIALS c) RETIREMENT DATES
QUALITY OF MATERIALS AND WORKMANSHIP d) MAWP
INSPECTION REQUIREMENTS e) REINSPECTION INTERVALS
REINFORCEMENT OF OPENINGS f) HIGHLIGHTING AREAS OF HIGH CORROSION RATES
ANY CYCLICAL SERVICE REQUIREMENTS g) PIPING CIRCUITS OVER DUE FOR INSPECTION
FOR UNKNWN MATERIALS COMPUTATION MAY BE MADE ASSUMING h) PIPING CLOSE TO THE MINIMUM REQUIRED THICKNESS AND
THE LOWEST GRADDE MATERIAL AND JOINT EFFICIENCY OTHER INFORMATION
SEE ANNEX D FOR CALCULATION OR EXAMPLE CALCULATION Piping circuit records
RESULTS
CHECKLIST AND NARRATIVE RECORD
LOCATION OF CUI INSPECTION
LOCATION OF NDE
APPROPRIATE ISO
PREHEATING
PWHT