SUMMARY PROGRESS WORK PERCENTAGE PER UNIT AND MANPOWER - IDESIA DASMARINAS Tuesday, March 22, 2022

PHASE 1 PHASE 2
SN ACTIVITIES 1 GAIA 2 GAIA 3 GAIA 4 TALIA 5 TALIA 6 TALIA 7 TALIA 8 TALIA 9 TALIA 1 GAIA 2 GAIA 3 TALIA 4 GAIA 5 GAIA 6 GAIA 7 GAIA 8 GAIA 9 GAIA 10 GAIA 11 GAIA 12 GAIA 13 GAIA 14 GAIA 15 GAIA 16 GAIA 17 GAIA 18 TALIA

BLK 17 LOT 37 BLK 17 LOT 38 BLK 17 LOT 39 BLK 19 LOT 37 BLK 19 LOT 38 BLK 19 LOT 36 BLK 19 LOT 27 BLK 19 LOT 5 BLK 18 LOT 45 BLK 5 LOT 19 BLK 5 LOT 20 BLK 5 LOT 21 BLK 5 LOT 6 BLK 5 LOT 7 BLK 6 LOT 14 BLK 6 LOT 15 BLK 6 LOT 7 BLK 6 LOT 2 BLK 6 LOT 3 BLK 7 LOT 2 BLK 8 LOT 11 BLK 8 LOT 20 BLK 5 LOT 8 BLK 5 LOT 18 BLK 5 LOT 10 BLK 7 LOT 1 BLK 13 LOT 14

1 EXCAVATION 100% 100% 100% 100% 81% 81% 63% 39% 45% 100% 100% 100% 100% 100% 76% 54% 54% 54% 54% 54% 54% 54% 54% 54% 28% 59% 96%
2 SOIL PREPARATION 80% 80% 80% 80% 80% 80% 60% 60% 60% 100% 100% 100% 100% 100% 60% 60% 60% 60% 60% 60% 60% 60% 60% 60% 0% 0% 60%
3 STEEL REINFORCEMENT 79% 79% 79% 65% 65% 65% 53% 53% 53% 100% 100% 100% 100% 100% 22% 15% 21% 15% 14% 8% 8% 8% 14% 22% 45% 80% 14%
4 CONCRETE 78% 78% 78% 58% 58% 47% 39% 39% 39% 100% 100% 100% 100% 100% 17% 12% 12% 8% 8% 0% 0% 0% 8% 14% 0% 0% 8%
5 MASONRY 30% 29% 29% 29% 29% 29% 24% 13% 13% 100% 100% 100% 100% 100% 15% 5% 10% 4% 3% 0% 0% 0% 3% 4% 0% 0% 3%
6 METAL AND ROOFING 19% 12% 0% 0% 0% 0% 0% 0% 0% 100% 100% 100% 37% 37% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
7 PAINT 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 100% 100% 17% 17% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
8 DOORS AND WINDOWS 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 100% 100% 40% 40% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
9 TOILET FIXTURES AND TILES 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
10 PLUMBING AND SANITARY 76% 76% 76% 85% 85% 85% 85% 71% 71% 100% 100% 100% 81% 81% 38% 37% 36% 36% 36% 36% 36% 36% 36% 37% 0% 0% 71%
11 ELECTRICAL 47% 47% 47% 46% 46% 46% 46% 43% 44% 100% 100% 100% 53% 53% 21% 21% 10% 10% 10% 6% 6% 6% 10% 10% 0% 0% 10%
12 FORMS AND SCAFFOLDS 82% 82% 82% 53% 53% 50% 50% 50% 50% 100% 100% 100% 90% 90% 12% 10% 10% 10% 10% 5% 5% 5% 10% 10% 0% 0% 10%

TOTAL WORK PROGRESS 49% 49% 48% 43% 41% 40% 35% 31% 31% 100% 100% 100% 68% 68% 22% 18% 18% 16% 16% 14% 14% 14% 16% 18% 6% 12% 23%

SOG CONCRETE SOG CONCRETE SOG CONCRETE


FIRE WALL FIRE WALL FIRE WALL FIRE WALL FIRE WALL FIRE WALL
SOG CONCRETE PREPARATION, PREPARATION, PREPARATION,
EXTENSION EXTENSION EXTENSION EXTENSION EXTENSION EXTENSION FINISHED PUNCH FINISHED PUNCH FINISHED PUNCH ON HOLD FOR ON HOLD FOR GROUND FLR GROUND FLR GROUND FLR GROUND FLR GROUND FLR GROUND FLR RETURNED TO RETURNED TO GROUND FLR
REMARKS ROOFING WORKS ROOFING WORKS ROOFING WORKS POURING AND ELEC. AND ELEC. AND ELEC. AND
REMAINING REMAINING REMAINING REMAINING REMAINING REMAINING LIST INSPECTION LIST INSPECTION LIST INSPECTION ROOF WORKS ROOF WORKS BLOCKWORKS BLOCKWORKS BLOCKWORKS BLOCKWORKS BLOCKWORKS BLOCKWORKS RLB RLB BLOCKWORKS
CHB LAYOUT PLUMBING PLUMBING PLUMBING
BLOCKWORKS BLOCKWORKS BLOCKWORKS BLOCKWORKS BLOCKWORKS BLOCKWORKS
LAYOUT LAYOUT LAYOUT
ROOF ROOF ROOF ROOF ROOF ROOF ROOF ROOF ROOF
SOG CONCRETE SOG CONCRETE SOG CONCRETE
THIS WEEK TARGET ACTIVITY 03 INSTALLATION INSTALLATION INSTALLATION INSTALLATION INSTALLATION INSTALLATION INSTALLATION INSTALLATION INSTALLATION PUNCH LIST PUNCH LIST PUNCH LIST ON HOLD FOR ON HOLD FOR RETURNED TO RETURNED TO
BLOCKWORKS BLOCKWORKS BLOCKWORKS BLOCKWORKS BLOCKWORKS POURING. POURING. POURING. BLOCKWORKS BLOCKWORKS BLOCKWORKS
21 - 03 27 2022 AND PLASTER AND PLASTER AND PLASTER AND PLASTER AND PLASTER AND PLASTER AND PLASTER AND PLASTER AND PLASTER RECTIFICATION RECTIFICATION RECTIFICATION ROOF WORKS ROOF WORKS
BLOCKWORKS BLOCKWORKS BLOCKWORKS
RLB RLB
WORKS WORKS WORKS WORKS WORKS WORKS WORKS WORKS WORKS

ON HOLD FOR ON HOLD FOR


2ND FLR 2ND FLR 2ND FLR 2ND FLR 2ND FLR 2ND FLR 2ND FLR 2ND FLR
ROOF WORKS ROOF WORKS
SCAFFOLD, SCAFFOLD, SCAFFOLD, SCAFFOLD, SCAFFOLD, SCAFFOLD, SCAFFOLD, SCAFFOLD,
NEXT WEEK TARGET ACTIVITY EXTERIOR WALL EXTERIOR WALL EXTERIOR WALL EXTERIOR WALL EXTERIOR WALL EXTERIOR WALL EXTERIOR WALL EXTERIOR WALL EXTERIOR WALL FINAL PUNCHLIST FINAL PUNCHLIST FINAL PUNCHLIST REPAIR FOR REPAIR FOR RETURNED TO RETURNED TO
ELEC/PLUMBING ELEC/PLUMBING ELEC/PLUMBING ELEC/PLUMBING ELEC/PLUMBING BLOCKWORKS BLOCKWORKS BLOCKWORKS ELEC/PLUMBING ELEC/PLUMBING ELEC/PLUMBING
03 28 - 04 03 2022 PLASTERING PLASTERING PLASTERING PLASTERING PLASTERING PLASTERING PLASTERING PLASTERING PLASTERING TURN OVER TURN OVER TURN OVER MINOR WORKS MINOR WORKS
LAYOUT, RSB LAYOUT, RSB LAYOUT, RSB LAYOUT, RSB LAYOUT, RSB LAYOUT, RSB LAYOUT, RSB
RLB RLB
LAYOUT, RSB
AND PAINT AND PAINT
LAYOUT LAYOUT LAYOUT LAYOUT LAYOUT LAYOUT LAYOUT LAYOUT
PRIMER PRIMER

ADDITIONAL ADDITIONAL ADDITIONAL ADDITIONAL ADDITIONAL ADDITIONAL ADDITIONAL ADDITIONAL


RAFTERS AND RAFTERS AND RAFTERS AND RAFTERS AND RAFTERS AND RAFTERS AND MANPOWER. MANPOWER. MANPOWER. MANPOWER. MANPOWER. MANPOWER. MANPOWER. MANPOWER.
ROOF SHEET ROOF SHEET ROOF SHEET RLB MEMO RLB MEMO ADDITIONAL ADDITIONAL ADDITIONAL
ROOF SHEET ROOF SHEET ROOF SHEET ROOF SHEET ROOF SHEET ROOF SHEET AS PER AS PER AS PER CEMENT FOR CEMENT FOR CEMENT FOR CEMENT FOR CEMENT FOR CEMENT FOR CEMENT FOR CEMENT FOR
MATERIALS. MATERIALS. MATERIALS. INSTRUCTION TO INSTRUCTION TO MANPOWER. MANPOWER. MANPOWER. RETURNED TO RETURNED TO
MATERIALS / ACTION NEEDED MATERIALS. MATERIALS. MATERIALS. MATERIALS. MATERIALS. MATERIALS. PUNCHLIST ITEMS PUNCHLIST ITEMS PUNCHLIST ITEMS WALL MORTAR, WALL MORTAR, WALL MORTAR, WALL MORTAR, WALL MORTAR, WALL MORTAR, WALL MORTAR, WALL MORTAR,
CEMENT FOR CEMENT FOR CEMENT FOR CONTINUE WORK CONTINUE WORK CEMENT FOR CEMENT FOR CEMENT FOR RLB RLB
CEMENT FOR CEMENT FOR CEMENT FOR CEMENT FOR CEMENT FOR CEMENT FOR TO RECTIFY TO RECTIFY TO RECTIFY ELEC./PLUMBING ELEC./PLUMBING ELEC./PLUMBING ELEC./PLUMBING ELEC./PLUMBING ELEC./PLUMBING ELEC./PLUMBING ELEC./PLUMBING
PLASTERING PLASTERING PLASTERING ON ROOF ON ROOF WALL MORTAR WALL MORTAR WALL MORTAR
PLASTERING PLASTERING PLASTERING PLASTERING PLASTERING PLASTERING PIPES. RSB FOR PIPES. RSB FOR PIPES. RSB FOR PIPES. RSB FOR PIPES. RSB FOR PIPES. RSB FOR PIPES. RSB FOR PIPES. RSB FOR
2ND FLR 2ND FLR 2ND FLR 2ND FLR 2ND FLR 2ND FLR 2ND FLR 2ND FLR

MRF-008 MRF-008 MRF-008 RETURNED TO RETURNED TO


MRF NO. MRF-0014 MRF-0014 MRF-0014 MRF-0014 MRF-0014 MRF-0014
MRF-0074 MRF-0074 MRF-0074 RLB RLB

STAFFS AND MANPOWER


144 MANPOWER NEED 7 7 7 7 7 7 7 7 7 2 2 7 7 7 7 7 7 7 7 7 7 7

47 ACTUAL MANPOWER 3 3 3 0 0 0 0 0 4 4 4 4 3 1 4 4 3 3 0 0 4

2 ENGINEERS
2 FORMAN
1 SAFETY OFFICER
1 DRAFTSMAN
1 WAREHOUSEMAN
1 DRIVER
3 HAULERS
58 TOTAL
TOTAL PROGRESS PER PHASE NOTES
PHASE 1 ( 9 UNITS) 41% 1 MANPOWER NEEDED ESPECIALLY FOR THE REMAINING AND PRIORITY UNITS
PHASE 2 ( 16 UNITS) 39% 2 MRF PENDING
OVERALL TOTAL 3 PUNCH LIST TO BE RECTIFIED AS PER RLB COMMENTS
40%
( 25 UNITS) 4 ON HOLD ROOFING WORKS ON 2 UNITS AS PER RLB INSTRUCTION
5 2 UNITS ON PRIORITY WORK
TOTAL PROGRESS PER P.O. 6 2 UNITS RETURNED TO RLB ( BLK 5 LOT 10 AND BLK 7 LOT 1 )
P.O. 1 (8 UNITS) 70% 7 3 REMAINING UNITS FOR SOG
P.O. 2 (11 UNITS) 17% 8 URGENT NEED OF WELDERS FOR ROOFING
P.O. 3 (6 UNITS) 40% 9 LAST PROGRESS REPORT 3/18/2022
OVERALL TOTAL
43%
( 25 UNITS)