Environmental Screening Checklist

Name of Subproject: Checking side erosion on right side of Indus River D/S Gajjani Escape.
Proposing Agency: Executive Engineer, D.G.Khan Construction Division, DG Khan Zone

Sub project Location: Area lies in Shadan Lund, Kala, Shah Saddar Din, Pir Adil, Bait Karam Shah, Bait Sawai &
Gajjani etc of Tehsil & District D.G Khan.

Sub Project Objective: The main objective of the project helps to protect D.G.Khan Canal with its system, private
and public precious infrastructures, agriculture lands and so many villages from the river
action.

Subproject description: The contention of project is (1) Constructing guide wall at right bank of Sori Lund flood
(describe here subproject carrying channel. (2) Constructing guide head at existing truncated shank of Gajjani escape.
(3) Constructing guide head spur downstream 6650' from Gajjani escape proposed on the
components and their
right side of the river Indus near Village Shadan Lund, Kala, Shah Saddar Din, Pir Adil,
dimensions/quantum, Bait Karam Shah, Bait Sawai & Gajjani District D.G Khan, act as protection and river
construction and O&M training works. This project protect the Link No.1 and adjoining abadies, furtile land.
activities, major construction
Civil work 702.434 (M)
material required with
approximate quantities, and Contingency+PST 53.676 (M)
other pertinent details):

Estimated Cost: Rs. 820.653 million

Proposed Date of June 2019


Commencement of Work:

Technical Drawing/ Yes  No __


Specifications Reviewed
(circle answer):

Environmental and social setting (describe here the key environmental and social features (land form, land use,
water bodies, flora and fauna, settlements, roads, railway lines, any public buildings, schools, hospitals,
graveyards, etc.) of the area where the subproject would be implemented:
Checklist for subproject related Social and Environmental Issues

Sub project

Checking side erosion on right side of Indus River D/S Gajjani Escape.

Minor Moderat Significant


Issues / e/ / Mitigation Residual
None
Measures Impacts/Notes
Small Medium Large
A. Zoning and land use
planning
1 Will the subproject affect land Limited This project proposed
use zoning and planning or excavation to protect D.G.Khan
conflict with prevalent land Leveling and Canal & its system and
use patterns? restoration of allied abadies.

borrow pit area
Cost is included
in the T.S and
bidding document
2 Will the subproject involve Limited This project is
significant land disturbance or excavation proposed for
site clearance? Leveling and protection of
 restoration of site D.G.Khan Canal & its
system, adjoining
abadies and furtile
public land
3 Will the subproject land be There is no
subject to potential encroachment
encroachment by urban or involved.

industrial use or located in an
area intended for urban or
industrial development?
B Utilities and Facilities

4 Will the subproject require the Designated camp Earthwork, stonework


setting up of ancillary site pitching on apron
facilities? Awareness raising involved in the work.
of labor

Restoration of
camp site after
completion of the
project
5 Will the subproject make There would be no
significant demands on need of large scale

utilities and services? camps, so very little
demand of utilities
6 Will the subproject require Designated camp As the contractor will
significant levels of site need less workers,
accommodation or service Restoration of therefore, large scale
amenities to support the  camp site after camp is not required
workforce during construction completion of the
(e.g., contractor will need project
more than 20 workers)?
C Water and Soil Contamination

7 Will the subproject require  Awareness raising Only earth work &
large amounts of raw materials of drivers for stone is involved in
or construction materials? using roads the project, which will
Limited be directly placed.
excavation
Minor Moderat Significant
Issues / e/ / Mitigation Residual
None
Measures Impacts/Notes
Small Medium Large
Leveling and
restoration of

borrow pit area


with compaction
at site
8 Will the subproject generate Controlled These structures need
large amounts of residual disposal of waste earthwork, stonework
wastes, construction material  material on agreed only.
waste or cause soil erosion? site

9 Will the subproject result in Careful handling Project involves


potential soil or water of earth material mainly earth work,
contamination (e.g., from oil, during working stonework so no such

grease and fuel from Usage of concrete chance of soil or water
equipment yards)? base or drip pans contamination
to avoid spills
10 Will the subproject lead to Dust will be For vegetation & dust
contamination of ground and controlled by control, management
surface waters by herbicides water sprinkler practices will be

for vegetation control and Covering of tarpal exercised & no
chemicals (e.g., calcium on tractor trolleys chemical will be used
chloride) for dust control?
11 Will the subproject lead to an Management Project is located along
increase in suspended practices will be river side
sediments in streams affected exercised

by road cut erosion, decline in 1% cost has been
water quality and increased allocated for tree
sedimentation downstream? plantation
12 Will the subproject involve the Not applicable

use of chemicals or solvents?
13 Will the subproject lead to the Leveling & Barren land is
destruction of vegetation and restoration of available along the
soil in the right-of-way, equipment yard/ project site
borrow pits, waste dumps, and borrow pits area Vegetative plants and
equipment yards? Strictness on some trees will be

digging earth in saved from cutting or
the right-of-way damages Digging of
Allocation of 1% earth in the right-of-
plantation cost in way will be avoided
PCI
14 Will the subproject lead to the Limited Barren land is
creation of stagnant water excavation available along the
bodies in borrow pits, quarries, Leveling and project, it will be
etc., encouraging for mosquito restoration of leveled after work
breeding and other disease borrow pit area by Digging of earth in the
vectors? the contractor. If right-of-way will be
 contractor fails to avoided
level the borrow
pit area, the
equivalent cost
will be deducted
from final bill
Minor Moderat Significant
Issues / e/ / Mitigation Residual
None
Measures Impacts/Notes
Small Medium Large
D. Noise and air pollution
hazardous substances
15 Will the subproject increase Using strict Sub project is located
the levels of harmful air standards for along the abadies
emissions? maintenance of
machinery
Sprinkling of

water to avoid air
pollutants
Prohibition on
burning of waste/
fuel wood
16 Will the subproject increase Sub project area is

ambient noise levels? away from abadies.
17 Will the subproject involve the Not applicable
storage, handling or transport 
of hazardous substances?
18 Will the construction activities Proper marking & Sub project area is
cause safety and health hazard sign boards at site away from abadies.
for the nearby population  Strict rules for the
drivers on access
roads
19 Will the construction activities Proper marking & Only earth work and
cause safety and health hazard sign at site stonework are
for the construction workers Use of personal involved therefore, the
 protective contractor will need
equipments (PPE) less workers
Arranging medical
treatment facility
E. Fauna and Flora
20 Will the subproject involve the Avoid disposal of Sub project area is
disturbance or modification of untreated away from abadies.
existing drainage channels contaminants/

(rivers, canals) or surface waste materials
water bodies (wetlands, into the canal or
marshes)? other water bodies
21 Will the subproject lead to the Avoid hunting & Project area does not
destruction or damage of pouching have such ecosystem
terrestrial or aquatic Restriction of
ecosystems or endangered 
labor within area
species directly or by induced Ensure safety to
development? habitat of fauna
22 Will the subproject lead to the Project does not have
disruption/destruction of any wildlife habitant
wildlife through interruption
of migratory routes, 
disturbance of wildlife
habitats, and noise-related
problems?
F. Destruction / Disruption of
Land and Vegetation
23 Will the subproject lead to  This project is river
unplanned use of the training and flood
Minor Moderat Significant
Issues / e/ / Mitigation Residual
None
Measures Impacts/Notes
Small Medium Large
infrastructure being protection work.
developed?
24 Will the subproject lead to Leveling & For provision of earth
long-term or semi-permanent restoration of work, there will be
destruction of soils in cleared equipment yard/ minor temporary
areas not suited for borrow pits area impact on barren land
agriculture? Strictness on which will be restored

digging earth in after work
the right-of-way Digging of earth in the
Allocated 1% right-of-way will be
plantation cost in avoided
PCI
25 Will the subproject lead to the These works involved
interruption of subsoil and restoration which will

overland drainage patterns (in not create drainage
areas of cuts and fills)? problem.
26 Will the subproject lead to Repair & For carrying earth
landslides, slumps, slips and maintenance of work, minor temporary
other mass movements in road  roads by the impact may occur on
cuts? contractor roads

27 Will the subproject lead to Not applicable


erosion of lands receiving

concentrated outflow carried
by covered or open drains?
28 Will the subproject lead to Sprinkling of Vegetative plant &
health hazards and water to avoid trees are present
interference of plant growth dust
adjacent to roads by dust Awareness raising

raised and blown by vehicles? of staff including
drivers for safe
movement along
roads
G. Cultural Property
29 Will the subproject have an Project does not have
impact on archaeological or such kind of structures

historical sites, including
historic urban areas?
30 Will the subproject have an Project does not have
impact on religious such kind of structures

monuments, structures and/or
cemeteries?
31 Have Chance Finds Operational manual for
procedures been prepared for  implementation of
use in the subproject? work will be utilized
H. Expropriation and Social
Disturbance
32 Will the subproject involve Leveling and No. such, because this
land expropriation or restoration of project involves

demolition of existing borrow pit area restoration of spurs
structures?
33 Will the subproject lead to Only earth work is
induced settlements by  involved therefore, the
Minor Moderat Significant
Issues / e/ / Mitigation Residual
None
Measures Impacts/Notes
Small Medium Large
workers and others causing contractor will need
social and economic less labors
disruption?
34 Will the subproject lead to Designated area Only earthwork stone
environmental and social for camp site work is involved
disturbance by construction Avoid therefore, there would
camps? unnecessary be no disturbance on
interaction of setting up of low scale
labor with the camp

local community
Strict watch on
labor for not
damaging
ecosystem of the
area
II. Siting Related Issues

Don’t Residual Impacts/Notes


Issues Yes No Mitigation Measures
Know
1 Does the subproject require land Not Required

acquisition?

2 Will the subproject require There will be no relocation


permanent or temporary of settled people along spurs

relocation/ resettlement of local
people?

3 Will any structures or assets e.g There will be no damage to


crops be removed or acquired on  structures along the spurs
permanent or temporary basis?

4 Will the subproject lead to There will be no issue during


negative impacts on people's  execution for the movement
daily movements of people

5 Will the subproject negatively Involvement of the local


impact livelihoods [Note: public in the project activity
Describe separately if YES]  as labor (semi-skilled or
unskilled) will be positive
impact

6 Is the sub project located on land This project is involved


with contested ownership?  restoration work, no new
land required.

7 Is the sub project located in an



area with security problems

8 Is the sub projected located on Restoration will be done on


land reclaimed from floods ( the existing river training work.

ownership here may be
contested)

9 Is the subproject located in an


area with designated natural 
reserves?

10 Is the subproject located in an


area with unique natural 
features?

11 Is the subproject located in an


area with endangered or

conservation-worthy
ecosystems, fauna or flora?

12 Is the subproject located in an


area falling within 500 meters of
national forests, protected areas,
wilderness areas, wetlands, 
biodiversity, critical habitats, or
sites of historical or cultural
importance?
Don’t Residual Impacts/Notes
Issues Yes No Mitigation Measures
Know
13 Is the subproject located in an
area which would create a
barrier for the movement of 
conservation-worthy wildlife or
livestock?

14 Is the subproject located close to Execution of work before Sub project is located along
groundwater sources, surface the monsoon season the river side 2 km away
water bodies, water courses or  from abadies
Precautionary measures
wetlands? for the safety of workers

15 Is the subproject located in an


area with designated cultural
properties such as 
archaeological, historical and/or
religious sites?

16 Is the subproject in an area with


religious monuments, structures 
and/or cemeteries?

17 Is the project located in an area


from where people have been 
displaced?

18 Is the project located in an area


where IDPs are temporarily 
settled?

19 Is the project in a politically



sensitive area?

20 Is the subproject in a polluted or



contaminated area?

21 Is the subproject located in an


area of high visual and 
landscape quality?

22 Is the subproject located in an


area susceptible to landslides or 
erosion?

23 Is the subproject located in an



area of seismic faults?

24 Is the subproject located in a Project is near to populated



densely populated area? area/ city

25 Is the subproject located on



prime agricultural land?

26 Is the subproject located in an



area of tourist importance?

27 Is the subproject located near a



waste dump?
Don’t Residual Impacts/Notes
Issues Yes No Mitigation Measures
Know
28 Does the subproject have access

to potable water?

29 Is the subproject located far (1-2



kms) from accessible roads?

30 Is the subproject located in an



area with a wastewater network?

31 Is the subproject located in the



urban plan of the city?

32 Is the subproject located outside Project is located on state



the land use plan? land

Signed by Project Manager:

Title:

Date:

Signed by Safeguard Focal Person:

Title:

Date: