Environmental Screening Checklist
Environmental Screening Checklist
Name of Subproject: Checking side erosion on right side of Indus River D/S Gajjani Escape.
Proposing Agency: Executive Engineer, D.G.Khan Construction Division, DG Khan Zone
Sub project Location: Area lies in Shadan Lund, Kala, Shah Saddar Din, Pir Adil, Bait Karam Shah, Bait Sawai &
Gajjani etc of Tehsil & District D.G Khan.
Sub Project Objective: The main objective of the project helps to protect D.G.Khan Canal with its system, private
and public precious infrastructures, agriculture lands and so many villages from the river
action.
Subproject description: The contention of project is (1) Constructing guide wall at right bank of Sori Lund flood
(describe here subproject carrying channel. (2) Constructing guide head at existing truncated shank of Gajjani escape.
(3) Constructing guide head spur downstream 6650' from Gajjani escape proposed on the
components and their
right side of the river Indus near Village Shadan Lund, Kala, Shah Saddar Din, Pir Adil,
dimensions/quantum, Bait Karam Shah, Bait Sawai & Gajjani District D.G Khan, act as protection and river
construction and O&M training works. This project protect the Link No.1 and adjoining abadies, furtile land.
activities, major construction
Civil work 702.434 (M)
material required with
approximate quantities, and Contingency+PST 53.676 (M)
other pertinent details):
Environmental and social setting (describe here the key environmental and social features (land form, land use,
water bodies, flora and fauna, settlements, roads, railway lines, any public buildings, schools, hospitals,
graveyards, etc.) of the area where the subproject would be implemented:
Checklist for subproject related Social and Environmental Issues
Sub project
Checking side erosion on right side of Indus River D/S Gajjani Escape.
7 Will the subproject require Awareness raising Only earth work &
large amounts of raw materials of drivers for stone is involved in
or construction materials? using roads the project, which will
Limited be directly placed.
excavation
Minor Moderat Significant
Issues / e/ / Mitigation Residual
None
Measures Impacts/Notes
Small Medium Large
Leveling and
restoration of
14 Is the subproject located close to Execution of work before Sub project is located along
groundwater sources, surface the monsoon season the river side 2 km away
water bodies, water courses or from abadies
Precautionary measures
wetlands? for the safety of workers