Professional Documents
Culture Documents
Bond Analysis
Bond Analysis
Bond Analysis
This paper compares standard forms for three types of surety bonds: bid bond, performance bond and labour and material payment bond. Standard forms from Public Works and Government Services Canada (PWGSC) and Canadian Construction Documents Committee (CCDC) are presented and compared. Similarities and differences between these standard forms and their impacts to the project and project management are discussed.
Surety Bonds
A surety bond is not an insurance policy. It is an agreement between the owner (obligee) and the bonding company (surety), in which the bonding company guarantees that the contractor (principal) will perform the obligation written in the contract. The format of surety bonds are typically the same, where an obligee, a surety, a principal need to be identified, the purpose and the total amount of payment also need to be clearly stated, the conditions of each bond may vary depend on specific projects. The bond must be signed, sealed and delivered to all parties in order to make it enforceable.
Both versions require the bond to be signed and sealed by the principal and the surety, and the date of the bond also needs to be specified. However, PWGSC requires the date of the bond (signed and sealed) to be filled out at almost the beginning of the form, and then requires a witness to sign off the form with the principal and the surety at the bottom of the form where it says signed, sealed and delivered as a confirmation of the delivery, but the identity of the witness is not specified. CCDC requires attorney in fact representing the principal and the surety to sign off as a confirmation of the bond being signed and sealed.
Bid Bond
A bid bond is normally issued with other bidding documents by the surety to the obligee to guarantee that once the principal is accepted for the lowest bid, it will enter into the formal contract with the obligee. If the principal fails to enter the formal contract, then the surety will pay a full or partial forfeiture to the obligee as the penalty. The conditions between the two versions are quite different. PWGSC requires 60 days from the closing date of the tender for the principal to accept the bid, and within 14 days from the day he accepts the bid, the principal should prepare further contractual documents (a performances bond and a labour and material payment bond) and security specified at the beginning of the form. PWGSC also specified the amount of performance bond and labour and material payment bond to be each in the amount of 50% of the contract price. In comparison, CCDC is more flexible in terms of timing. It only requires the date to be specified by the obligee. According to PWGSC, the obligee cannot sue the surety within 12 months from the date of the bond, where CCDC only ask for 7 months. Typically, government funded projects are limited strictly by budget and time. Therefore it is reasonable that PWGSC clearly specifies the timeline and the amount of the security. On the other hand, CCDCs bid bond form is more flexible in timing and it will be suitable for different types of projects, no matter what type of formal contract is used.
Performance Bond
A performance bond is also a written agreement submitted to the obligee by the surety at the time of signing the formal contract in order to ensure the principal fulfill its obligations specified in the contract. If the principal defaults, the surety will be liable for: 1. remedy the default; 2. complete the contract ; 3. obtain bids from other contractors for the completion of the contract and make money available to the owner up to the penal sum of the bond to pay any differences in price; 4. pay the penal amount of the bond to the owner. (ALG-LAW1000, 2011) 2|Page
CCDCs performance bond provides exact conditions as the ones mentioned above, whereas PWGSCs version defines the condition differently. PWGSC specifically defines conditions when the work is not taken out of the principals hands, the surety shall remedy the default; when the work is taken out of the principals hands, the surety will act under the obligees supervision to choose another contractor to complete the work. If the cost of completion exceeds the contract price, then the surety is liable for paying all excess costs until completion of the contract, and only if the obligee is satisfied with the final product, then the surety will get paid for the excess amount. The reason that PWGSCs performance bond has very specific conditions is because government funded projects need to be protected and finished on time. If the government is frequently left with unfinished projects, the excess amount of cost due to contractors default will become a heavy burden on all taxpayers.
3|Page
One condition CCDCs form specified is that the surety will not take advantage of article 2365 of the Civil Code of the Province of Quebec. This is to avoid the possibility of a surety termination by an act or an omission of a claimant.
Conclusion
This paper compared bid bonds, performance bonds, labour and material payment bonds drafted by PWGSC and CCDC. Their similarities and differences are analysed and also their impacts to the project and project management are discussed. In general, due to the nature of these two different entities, forms drafted by PWGSC aids to help and protect government funding projects, whereas forms drafted by CCDC are more flexible and can be used in any type of projects.
References
ALG-LAW1000. 2011. Types of Bonds. Retrieved from http://bb.embanet.com/webapps/blackboard/execute/displayLearningUnit?course_id=_9425_1&co ntent_id=_496494_1 CCDC. (2002). A guide to construction surety bonds. Standard Construction Document. Retrieved from http://bb.embanet.com/webapps/blackboard/execute/displayLearningUnit?course_id=_9425_1&co ntent_id=_496494_1 CCDC. (2011). About CCDC. http://www.ccdc.org/about/index.html Wikipedia. (2011). Public Works and Government Services Canada. Retrieved from http://en.wikipedia.org/wiki/Public_Works_and_Government_Services_Canada
4|Page