Professional Documents
Culture Documents
Daily Progress Report (DPR)
Daily Progress Report (DPR)
Daily Progress Report (DPR)
Date : 19-Jul-14
Project Name: Godrej Summit, Sector-104, Gurgaon, India Date of Report : 18-Jul-14
Contract: Civil & Finishes Work at Godrej Summit, Sector-104, Gurgaon Contract No.: LOI no.- CGS/25/09/2013/01 Dated. 25.09.2013 (Contract Yet to be signed)
Weather Report
Temprature 36° C Duration of Rain
Page 1 of 2
Daily Progress at Site (Structural Works)
Back Filling Excavation PCC Reinforcement (MT) Formwork (M2) Concrete (M3) Remarks
Location Level
For the Cumm. Till Cumm. Till Cumm. Till Cumm. Till Cumm. Till Cumm. Till
For the Day For the Day For the Day For the Day For the Day
Day date date date date date date
Tower-D
7th Floor Columns 20.9 2 20.00 40 240
7th Floor Slab 20.9 30 180
Tower-E
4th Floor Columns 12.05 39.00 700 99.50
4th Floor Slab 12.05 25.00 1200 152.00
5th Floor Columns 12.05 4 29.10 35 415
5th Floor Slab 12.05 3 18.00 20 710
Tower-F
6th Floor Columns 17.95 40.00 710 71.00
6th Floor Slab 17.95 25.00 1155 119.00
7th Floor Columns 17.95 3 29.50 40 450
7th Floor Slab 17.95 2.5 13.50 25 365
Tower-G
4th Floor Columns 12.05 30.00 670 50.00
4th Floor Slab 12.05 25.50 1440 60.00
5th Floor Columns 12.05 5 20.00 25 335
5th Floor Slab 12.05 2.5 2.50 40 480
Tower-H
3rd Floor Columns 9.1 31.00 700 32.000 80.50
3rd Floor Slab 9.1 25.30 1240 65.500 151.50
4th Floor Columns 12.05 4.5 14.50 30 430
4th Floor Slab 12.05 2 12.50 25 485
NON TOWER AREA PARCEL 1
Retaining wall Basement 80 539.5 18.5 1.2 69.17 128 4192 16.000 649.00
Footing & Pedestal Basement 594 2356.5 83 51.37 1303.15 691.51
Column Basement 2.5 108.20 60 2138.14 4.500 219.75
Slab 172.62 5929 1503.00
Grade Slab & Drain Basement 105.75 21.43 203.50
NON TOWER AREA PARCEL 2
Retaining wall Basement 459 542 7 64.58 2200 472.00
Footing & Pedestal Basement 417 589.65 42.3 37.45 729.67 355.50
Column Basement 65.97 791.45 114.20
Slab 78.00 2330 837.00
Pump Room/water tank Basement 975 5.5 6.50 200 55.00
Grade Slab & Drain Basement 26 4.00
TOTAL 0 1550 0 5002.65 0 1251.8 33.2 2520.38 498 79677.41 118.000 19967.95
Physical Progress (Columns)
For the Cumulative Total Balance as on
Description Unit
Day Till date Quantity Dated
SIL Inhouse RMC
Previous
Sr. No. Grade Cummulative
Cummulative
Tower-B (First Floor) Previous Day For the Month Previous Day For the Month
Tower-D
G.F. Slab 0.25 152.55 237.139
1st Floor 3.2 144.191 228.089
2nd Floor 6.15 4.44 31 14
Tower-E
G.F. Slab 0.25 8.742 86.456 26 44.5
Tower-F
G.F. Slab 0.25 94.75 178.4
1st Floor 3.2 59.52 48 217
Tower-G
G.F. Slab 0.25 69.112 166.894
Tower-H
G.F. Slab 0.25
Hindrances if any:
Comments by Client:
Page 2 of 2