Daily Progress Report (DPR)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Daily Progress Report : - 2014/July/219

Date : 19-Jul-14
Project Name: Godrej Summit, Sector-104, Gurgaon, India Date of Report : 18-Jul-14
Contract: Civil & Finishes Work at Godrej Summit, Sector-104, Gurgaon Contract No.: LOI no.- CGS/25/09/2013/01 Dated. 25.09.2013 (Contract Yet to be signed)

Client: Godrej Premium Builders Private Limited


Project Manager: Feedback Infra Private Limited
Main Contractor: Simplex Infrastructures Limited

Contract Completion Date: 21/Jul/16 No. of Days left to Completion: 736

Weather Report
Temprature 36° C Duration of Rain

Sunny Start Finish Total Duration in Hours


Rainy 10.00am 11.30am 1.30hrs
Rainy

Contractor’s Staff Equipment’s


Remarks
Category Day Night Quantity Status
Working
Project Manager 1 0 Batching Plant 2

Manager 3 0 Tower Cranes 2 Working

Site Engineers 8 0 Transit Mixers 5 Working

Planning Engineer 1 0 Loader 1 Working


Forman’s/Supervisor 8 0 Loader cum Excavator 2 Working
QS & Billing 3 0 Hydra 1 Working

QA/QC 8 0 Boom Placer 1 Working

Surveyor 3 0 Concrete Pump 2 Working


Mechanical/Electrical 11 0 Bar Bending Machine 6 Working
Personnel/Admin 2 0 Bar Cutting Machine 5 Working
Technician/Stores 4 0 DG Sets 4 Working
Accounts/Commercial 3 0 Bull Dozer 0 Working
Safety 6 0 Tractor 2 Working
Time Keeper/Admin 1 0 Ambulance 1 Working
Mechanic/Operator/ 24 0
Electrician/ Driver

Area wise Manpower

Shuttering Reinforcement Others Brickworks Remarks


Location
CP HLP BB HLP KHA. KHA. HLP Mas Mas HLP USK
Tower-D 28 30 28 28 5 4 12 18 4
Tower-E 28 30 26 26 5 4 4 5 4
Tower-F 24 26 24 24 5 4 10 20 4
Tower-G 30 30 28 30 5 4 8 10 4
Tower-H 24 26 22 24 5 4 2 4 4
Non Tower (Parcel-1) 30 30 26 26 8 6 4 4 10
Non Tower (Parcel-2) 25 25 22 22 8 6 4 4 8
Quality Lab 3
Store 2
Batching Plant 5
Housekeeping 10
Total 189 197 176 180 49 32 44 65 58
Grand Total 990

Steel Stock at Site :-


Total
Total Requirement Total Receipt Till Total Cosumption Till Total Requirement for Received on Total Received for the
Diameter Consumed Stock at Site
Till Date Yesterday Yesterday the Month Report Day Month
Today
8mm 681.694 553.634 417.320 200 136.314
10mm 688.697 629.937 529.848 100 100.089
12mm 440.267 370.307 320.169 90 20.04 50.138
16mm 693.77 676.770 596.571 130 79.48 80.199
20mm 1195.21 1180.230 1071.657 150 135.02 108.573
25mm 963.485 743.485 721.378 220 22.107
32mm 124.95 99.950 99.950 25 0.000
Total 4788.073 4254.313 3756.893 915 0.00 234.54 0.000 497.420

Page 1 of 2
Daily Progress at Site (Structural Works)
Back Filling Excavation PCC Reinforcement (MT) Formwork (M2) Concrete (M3) Remarks
Location Level
For the Cumm. Till Cumm. Till Cumm. Till Cumm. Till Cumm. Till Cumm. Till
For the Day For the Day For the Day For the Day For the Day
Day date date date date date date

Tower-D
7th Floor Columns 20.9 2 20.00 40 240
7th Floor Slab 20.9 30 180
Tower-E
4th Floor Columns 12.05 39.00 700 99.50
4th Floor Slab 12.05 25.00 1200 152.00
5th Floor Columns 12.05 4 29.10 35 415
5th Floor Slab 12.05 3 18.00 20 710
Tower-F
6th Floor Columns 17.95 40.00 710 71.00
6th Floor Slab 17.95 25.00 1155 119.00
7th Floor Columns 17.95 3 29.50 40 450
7th Floor Slab 17.95 2.5 13.50 25 365
Tower-G
4th Floor Columns 12.05 30.00 670 50.00
4th Floor Slab 12.05 25.50 1440 60.00
5th Floor Columns 12.05 5 20.00 25 335
5th Floor Slab 12.05 2.5 2.50 40 480
Tower-H
3rd Floor Columns 9.1 31.00 700 32.000 80.50
3rd Floor Slab 9.1 25.30 1240 65.500 151.50
4th Floor Columns 12.05 4.5 14.50 30 430
4th Floor Slab 12.05 2 12.50 25 485
NON TOWER AREA PARCEL 1
Retaining wall Basement 80 539.5 18.5 1.2 69.17 128 4192 16.000 649.00
Footing & Pedestal Basement 594 2356.5 83 51.37 1303.15 691.51
Column Basement 2.5 108.20 60 2138.14 4.500 219.75
Slab 172.62 5929 1503.00
Grade Slab & Drain Basement 105.75 21.43 203.50
NON TOWER AREA PARCEL 2
Retaining wall Basement 459 542 7 64.58 2200 472.00
Footing & Pedestal Basement 417 589.65 42.3 37.45 729.67 355.50
Column Basement 65.97 791.45 114.20
Slab 78.00 2330 837.00
Pump Room/water tank Basement 975 5.5 6.50 200 55.00
Grade Slab & Drain Basement 26 4.00
TOTAL 0 1550 0 5002.65 0 1251.8 33.2 2520.38 498 79677.41 118.000 19967.95
Physical Progress (Columns)
For the Cumulative Total Balance as on
Description Unit
Day Till date Quantity Dated
SIL Inhouse RMC
Previous
Sr. No. Grade Cummulative
Cummulative
Tower-B (First Floor) Previous Day For the Month Previous Day For the Month

Columns First Lift No 69 69 0 1 PCC M7.5 365.8 69.00 365.80


Non Tower (Parcel-1) 2 PCC M10 1032.1 1032.10
Columns First Lift No 3 185 261 76 3 M-25 20184.75 81.50 1328.00 20266.25
Columns Second Lift No 2 155 261 106 4 M-30 103 103.00 103.00
Non Tower (Parcel-2) 5 M-35 488.5 270.00 488.50
Columns First Lift No 90 165 75 6 M-40 1216.8 36.50 91.50 1253.30
Columns Second Lift No 80 165 85 7 M-45 1523 10.00 1523.00
Cummulative (CUM) 24913.95 118.00 1871.50 0.00 0.00 25031.95
Daily Progress at Site (Finishing Works)
Brickwork 230 MM Brickwork 115 MM Plaster Remarks
Location Level
For the Cumm for Cumm for the Cumm for the
For the Day For the Day
Day the Month Month Month

Tower-D
G.F. Slab 0.25 152.55 237.139
1st Floor 3.2 144.191 228.089
2nd Floor 6.15 4.44 31 14
Tower-E
G.F. Slab 0.25 8.742 86.456 26 44.5
Tower-F
G.F. Slab 0.25 94.75 178.4
1st Floor 3.2 59.52 48 217
Tower-G
G.F. Slab 0.25 69.112 166.894
Tower-H
G.F. Slab 0.25

Hindrances if any:

Comments by Client:

Prepared By:- Checked by :-


Mr. Shankar B. Banerjee Mr. Pushpendu Bhattacharya
Planning Engineer Project In-Charge
Simplex Infrastructures Ltd. Simplex Infrastructures Ltd.

Page 2 of 2