Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

Concrete Repair, Rehabilitation and Retrofitting II – Alexander et al (eds)

© 2009 Taylor & Francis Group, London, ISBN 978-0-415-46850-3

Diagnostic analysis and therapy of severely cracked bridges

Hans-Peter Andrä & Markus Maier


Leonhardt, Andrä und Partner, Stuttgart, Germany

ABSTRACT: Severe cracking in reinforced and/or prestressed concrete structures usually results from the
accumulation of a number of causes, such as errors in structural design, detailing of reinforcement, concrete
composition, concrete curing, overloading under construction, early lowering of falsework, underestimated
thermal loadings, fatigue, and lack of maintenance etc. The paper presents examples of a consistent strategy of
diagnosis and therapy.

1 INTRODUCTION The spans were erected with an overhead erection


gantry where the segments are dry jointed and the
Severe structural defects in buildings are generally spans post tensioned with external prestressing cables
due to the accumulation of poor design, poor con- within the void of the box.
struction and construction material and poor mainte- The 33 piers consist of two types of reinforced
nance. The predominant cause is human error, which concrete substructures. Pier #19 and Pier #23 are twin
can only be reduced by means of thorough failure column portal frames supported on pile caps founded
mode and effect analyses (FMEA). on bored cast in place piles.
Human error often results from carelessness, All other piers are T-shaped piers (see figure 1).
disregard, insufficient knowledge, underestimat- The column cross section is orthogonal, the width
ing of decisive influences, blind faith in computer across the flats amounts to 3.62 m. The columns range
analysis, lack of plausibility checks and inad- from 1,5 m to 16 m in height and are supported on
equate time and cost pressures. Preemptive risk 8 m × 8 m square and 3 m deep pile caps which are
analyses by independent reviewers and checkers founded on 4 bored cast in place piles with 1,8 m diam-
as well as site supervision and continuous moni- eter. Each column supports a 18.65 m long cross head
toring can significantly reduce the risk of error which is cantilevering out on both sides about 7.50 m.
accumulation. The cross heads depth varies from 2 m at the tip to 3,5 m
Severe cracks in the cross heads of the T-shaped at the column face, with an overall width of 4 m.
piers of the Kepong Flyover in Kuala Lumpur are a These cantilever crossheads are the focus of the
typical result of the accumulation of such errors. Les- case study, which is presented within this paper.
sons learned from these errors are described in detail
as follows.

2 DESCRIPTION OF THE STRUCTURE

The Kepong Flyover is a dual three-lane elevated car-


riageway as a part of the exterior highway system of
Middle Ring Road II (MRRII) in Kuala Lumpur. The
overall length of the superstructure is 1537 m between
abutments.
The cross section consists of twin precast match
cast single cell box girders which are 11,5 m wide
between barriers with an overall depth of 2,50 m.
The bridge has 34 spans constructed by a span by
span construction method. The 45,2 m long spans are
simply supported with a continuous link slab at the
piers to provide continuity of the running surface.
Movement joints are provided at every fifth pier. At
each pier each box is supported on two bearings, one Figure 1. Kepong Flyover Viaduct at Middle Ring Road 2
underneath each web. in Kuala Lumpur, Malaysia.

49
3 TRACK RECORD OF THE STRUCTURE Expert reports from various parties with various
interpretations finally resulted in inconsistent conclu-
The contract for the flyover structure was awarded in sions about the causes of the cracks and the cracks
May 1999 on a design & built basis. Design was done influence on the structure load bearing capacity.
between July 1999 and August 2001. The construction A major concern of the reports was the sensibility for
started in February 2000 and was completed in April delayed ettringite formation (DEF) in the concrete,
2002. The flyover was opened to traffic in May 2002. where crack growth results from ettringite expansion.
First cracks on the crossheads were observed The observed typical crack patterns, however, could
already during construction. Shortly after opening of not be explained by DEF. Different expert opinions
the bridge for traffic further cracks were developing about the causes of measured test results are a well
and excessively widening. First reports about these known phenomenon both in research and in surveys
cracks are dated back to January 2003 respectively on defects of existing structures. This results from the
November 2003. Detail crack mapping of all 33 piers fact that everybody draws conclusions from the basis
including abutments was subsequently appointed to of his own experience and will only find what he is
a specialist contractor in May 2004, in order to sys- searching for.
tematically have documentation of crack patterns In 2005 key management within JKR changed and
including crack sizes (see figure 2). Various field new Director General, an excellent structural expert
investigations including cover meter tests, verification himself, realized the potential structural risk resulting
of rebar sizes and spacing, core sampling for strength out of this bridge and the structural findings.
tests and monitoring installations were initiated. In October 2005, LAP was appointed for final and
Typical crack patterns consist of detail design for remedial works of the piers on the
basis of a complete critical analysis of design, con-
• two longitudinal (along the direction of the cross struction, material properties and maintenance. At
head) cracks in between the two adjacent bear- the same time the bridge was closed for traffic. The
ings, more or less partitioning the cross head into focus of the remedial design concept was to eliminate
3 segments, potential structural deficiencies, to relief the struc-
• a onionskin shaped crack mesh on the upper flanks tures stresses and to provide appropriate response on
at the cross head centre, partly interconnected in potential DEF occurrence.
transverse direction by cracks on the top surface, The contract for remedial design was awarded
• horizontal cracks over the piers underneath the to a contractor on March 2006. Execution works
onionskin mesh, began after only a one month mobilization period in
• inclined cracks running down the face of the cross April 2006.
beams, and During the following 6 months all 33 T-shaped
• inclined cracks underneath and in the vicinity of piers were structurally rehabilitated, with maximum
the bearings. of 18 piers being remedied simultaneously. Site logis-
tics and strengthening sequence was most challeng-
ing, both for contractor, LAP site supervision and
client, while traffic on highway underneath the bridge
was fully ongoing. The strengthening principles will
be illustrated in chapter 7 in more detail.
In November 2006 the 100% strengthened and
rehabilitated bridge could be reopened to unlimited
side face pier #9, max. crack width 3.2 mm traffic.

4 LOADING HISTORY OF THE CROSS HEADS

The cross heads carry the superstructure dead load


and final stage live loads (vertical and horizontal).
During construction, the gantry loads in addition to
the superstructure dead load are a major, sometimes
even governing load case.

4.1 Thermal loading due to curing of (mass)


concrete
top and bottom faces pier #32, max crack width 3.0 mm
The pouring in one shot of the massive cross-section
Figure 2. detailed scaled crack mapping of all crosshead of the crossheads with 4.00 m in width and 3.50 m
surfaces. in depth and the subsequent curing of the concrete

50
causes a heat development and distribution within the
member, arising from cement hydration. The applied
concrete mixture proved a high content of Portland
cement which promotes heat development. Tem-
perature gradients from cooling down outer surfaces
exposed to formwork or air while the inner core of the
structure is still hot causes internal tensile stresses,
which may exceed tensile strength of the immature
concrete. Special caution must therefore be under-
taken to control early thermal cracking by providing
sufficient reinforcement in size and arrangement to
control regular crack spacing as well as limit indi-
vidual cracks width. On the other hand concrete mix-
ture must be carefully selected to avoid excessive heat
development, e.g. by using cement with lower hydra-
tion heat development.

4.2 Loading during erection of the superstructure


The superstructure was erected using an overhead
erection gantry. The gantry was supported on the
cross head and carried the load of the precast super-
structure elements which were attached and winched
up into position. Once all 15 segments with a weight Figure 3. principle sketch of erection stage with rear and
of 80.8 tons each were in position and adjusted for front gantry support.
fit, line and level the external post-tensioning was
applied. Upon completion of stressing the completed
superstructure was lowered onto the piers transferring
the superstructure load from the gantry supports to torsion and high out of balance bending moments
the permanent bearings. especially at the front gantry support during the erec-
After completion of the first superstructure, the tion of the first superstructure. However since the
gantry was shifted in transverse direction to the adja- gantry progressed span by span, each pier suffers
cent carriageway for the erection of the second super- clockwise torsion from front gantry support during
structure in the same span using the same erection erection of this span, while suffering anticlockwise
sequence. Upon completion of the second superstruc- torsion from rear gantry support during erection of
ture the gantry was launched forward to the next pier next span.
for the next span erection. This cycle was then repeated
starting from abutment A in the north and then pro- 4.3 Loading transferred from the superstructure
ceeded until the entire viaduct was completed. while “in-service”
The crossheads are more or less symmetrically
loaded due to superstructure dead loads in the final British Standard BS 5400 was applied for the bridge
stage. In the erection stage however they are loaded design.
by high out of balance loads as well as Torsion result- The design loads for the in-service condition
ing from the rear and font gantry nose beam supports. include dead load from superstructure and superim-
(see figure 3). posed dead load comprising from asphalt surface and
The overall weight of 15 segments per span sums parapets as well as live loads resulting from HA, and
up to 1212 tons, the overall erection gantry tonnage HB 45 units load design vehicles both for serviceabil-
sums up to 617 tons which is about half of the super- ity state (SLS) and ultimate limit state (ULS) with its
structures weight. load combinations as specified in BS 5400.
The maximum loading coming from rear and front The bridge is 11.50 m wide between the kerbs,
gantry support occurs just prior to placement of post- which acc. BS5400 corresponds to four notial design
tensioned box girder onto the final bearings, i.e. when lanes, although each deck of the bridge will actually
the completed box girder is still fully supported by the only be used as a three lane deck.
gantry. The total weight which is resting on the cross- Figure 4 shows the governing HA/HB45 load
heads gantry support locations short before lowering arrangement on a single span, which generates worst
down the assembled superstructure to the final bear- case supporting forces to be transferred onto the bear-
ings sums up to 1829 tons. ing pads, which in turn generates maximum cross-
Both gantry supports are eccentric to centerlines of heads in service stresses (bending, out of balance
the piers, therefore the gantry loadings generate high moments, shear and torsion).

51
Maximum crosshead cantilever bending moment
e.g. results to:

due to dead loads MDead = 76.50 MNm


due to live loads MLive = 31.50 MNm
total Mtot = 108.00 MNm

Horizontal loadings depend on and result from the


bearing lay out of the superstructure. Thermal elonga-
tion/shrinkage creating bearing friction forces as well
as other horizontal loadings due to acceleration/brak-
ing and wind are minor load effects, but these effects
must not be neglected. The resulting stresses are
superimposed by other horizontal local stresses such
splitting or spalling stresses underneath the bearings.
The accumulated stresses are of critical magnitude if
no adequate reinforcement is provided.
This is even more important for cyclic loadings.
Both vertical loads coming from live load design
vehicles as well as horizontal loads resulting from
bearing pattern are considered to be cyclic.

4.4 Effects of the load history on the observed


cracks
Both thermal effects and construction loadings had
not been sufficiently addressed in the design. Ther-
mal effects result in a mesh of micro cracks, weak-
ening the complete crossbeam envelope and in DEF
vulnerability.
The inclined shear cracks at the cross beam faces
are due to underestimated torsion loadings during
construction.
Ignorance of construction loadings and final
material composition is a general problem, because
concrete composition according to local availability
and construction equipment are not fully known in
the design phase or because there is a discontinuity in
the interface between design and construction. This
discontinuity between design and construction gener-
ally results from contractual liability reasons and not
from engineering reasons.
Contracts and attitudes between the parties
involved which disregard the success of the project as
a whole imply significant risk potentials.

5 DESIGN AND DETAILING OF THE CROSS


HEADS

The structural system of the T shaped pier seems to


be quite simple. Bending moments and shear forces
at governing sections can be determined and designed
for by hand calculation.
The determination of internal stresses resulting
Figure 4. Governing vehicle load arrangement for 4 notial from the local application and introduction of the
design lane analysis and resulting supporting forces on bearing forces into the cross head section however is
bearings. rather complex.

52
5.1 Strut and tie model versus FE analysis A comparison between the results of a finite ele-
ment analysis and a strut and tie model is shown in
Due to the fact that the loads are not applied as line Figs. 5 and 6. Even though both approaches provide
loads across the section but in terms of single loads equal results in terms of equilibrium, the finite ele-
along the edges of the cantilever, the internal load ment analysis requires a significant amount of inter-
path actually corresponds to a strut and tie space pretation and is much more susceptible to human
frame with compression and tensile forces in three error than the strut and tie model. The finite element
directions. This space frame reproduces the load path analysis should rather be used as a tool to verify
from the bearings through the cross head to the pier the alignment of the strut and tie model. Detailing
junction and through the pier and the raft into the according to the strut and tie model however is quite
piles. The space frame model includes both the glo- simple, and the necessity of reinforcement in three
bal force actions and the internal thrust actions due dimensions is obvious.
to the local deviation of the load path. Both compres- An erroneous interpretation of the finite analysis
sion struts and tensile ties need to be analyzed and all model could suggest that transverse reinforcement
tensile forces need to be covered by properly detailed between the bearings and splitting reinforcement
and anchored reinforcement. underneath the bearings would not be needed because
“The Art of Detailing”, published by the late Pro- the concrete tensile stresses are low. The integral of
fessor Fritz Leonhardt [1] more than 40 years ago these stresses however results in large forces. FE
describes the engineering concept of strut and tie analysis determines the governing tensile stresses
modeling in detail. Structural design on the basis of in a concrete zone which is pre-cracked due to ther-
strut and tie modeling has now been incorporated in mal reasons and which is considerably intersected by
the relevant provisions of Eurocode 2. the reinforcement, Fig. 7. Due to this intersection of
rebars there is virtually no concrete section left which
could transfer tensile stresses. This does not comply
with the suppositions of the FE analysis.
The superposition of individually negligible hori-
zontal loadings from bearing friction, braking, wind,
horizontal temperature gradients etc. add up to sig-
nificant stresses and result in fatigue failure of non
reinforced concrete sections. The sudden and brittle
collapse of the bridge seat of the Reichsbruecke in
Vienna 1976, Fig. 8, demonstrates that this may hap-
pen even after years of operation.
The lack of sufficient transverse reinforcement
and of proper splitting reinforcement is responsible
for the two longitudinal separating cross head cracks
and the diagonal cracks underneath the bearings.
Blind faith in even highly sophisticated FE compu-
Figure 5. Finite Element Analysis of the cross head. ter analyses implies significant risk potentials.

Figure 6. Strut and Tie Space Frame Model of the cross


head. Figure 7. Tensile zone in concrete intersected by rebars.

53
Figure 9. Reinforcement of the cross beam.

Figure 8. Collapse of the Reichsbruecke Vienna.

5.2 Detailing of reinforcement


The reinforcement of the crossbeam is shown in Fig. 9.
The top two layers of the crossbeam T40 bars at
a spacing of 120 mm were lapped over the column,
i.e. at the location of maximum bending moments.
The lap length was chosen at its minima allowed acc. Figure 10. Transmission of forces between lapped bars [2].
to BS 5400.
The necessary lap length according to the German
DIN Code and US AASHTO codes in an area with due to this unreinforced section between column and
“unfavourable bond condition”, i.e. “top reinforce- crossbeam.
ment so placed that more than 30.5 cm of concrete
are cast below” would be about 1.8 times longer and
would require transverse stirrups to anchor splitting 6 CONCRETE COMPOSITION
forces from the transmission of the forces between AND MAINTENANCE
the lapped bars. The transmission of the forces from
each bar of approximately 500 kN to the surrounding The 3,5 m by 4,0 m cross-section of the cross head is
concrete induces significant tensile splitting stresses massive concrete section which would have required
normal to the bar axes. particular concrete composition with low cement
Due to the extremely high concentration of lap contents and cooling of the fresh concrete to avoid
splices, the remaining concrete strips between the temperatures of more than 70°C due to the liberated
bars are to small to transfer the high transmission hydration heat.
forces, Fig. 10. Bond failure of this lap splice was High hydration temperatures do not only result in
anavoidable. internal stresses and cause early cracking but also
Locating the laps outside the maximum bending create optimal conditions for ettringite crystalliza-
moment zone and staggering hooked laps accordingly tion. Both primary ettringite formation at the start
would have complied with the art of detailing rules [1]. of hydration and ettringite formation in the hardened
The column bars were not lapped with the cross- concrete texture may occur. The latter is referred to as
beam bars, so that there is no sufficient reinforcement delayed ettringite formation, DEF.
to resist the transfer of the cantilever moment There is a controversial discussion in literature on
between crossbeam and column due to eccentric whether the expansion caused by ettringite was the
crossbeam loadings during construction. Overall sta- primary cause of texture damage or whether it was a
bility is still possible as long as the eccentricity of subsequent manifestation of prior damage. Regarding
the normal force in the column produces a bending the examined concrete composition of the relevant
moment of equal magnitude. Horizontal cracks above piers (maximum cement content 560 kg/m³, SO2 con-
the pier underneath the onionskin mesh however are tent about 3%), the ettringite density of 1,77 g/cm³

54
corresponds to a volume of some 5% ettringite per 5. Add lacking vertical reinforcement legs, adhe-
cubic metre of concrete on the average. Contrasted with sively bonded within concrete member to take
an average pore volume of 13%, the maximum amount the tensile component forces, resulting from lap-
of ettringite that can be formed is significantly smaller splice action according Figure 10.
than the total pore volume. Damages of the concrete 6. Placing of self compacting concrete to close
texture due to DEF are therefore very unlikely. the highly reinforced lap-splice area in order to
There is no doubt however that the ingress of achieve best bond conditions for load transfer
moisture and water into concrete cracks due to ten- within lap splice.
sile stresses promotes the local accumulation of 7. Apply moderate permanent post-tensioning force
newly formed ettringite on the flanks of these cracks. for crack control by 18 externally bonded CFRP
Recrystallized ettringite is thus seen not as the cause tendons, each stressed to 400 kN.
of damage but rather as its consequence. 8. Seal and finish the surface for waterproofing
Due to defective piping of the drainage of the reasons to take necessary actions in terms of sus-
bridge superstructure over the piers, the crossbeams pected DEF problems.
were regularly flooded and wetted in the rainy sea-
son. In addition, the local humidity is very high.
Water and moisture induced ettringite formation thus 7.2 Installation of tie-frame
expanded the original excessive cracking from struc- Since no vertical support was accepted, to relieve the
tural deficiencies. structure during strengthening, an external tie-frame
Ettringite formation can be stopped after elastic was installed, which could be stressed up to 18 MN.
grouting of the existing cracks and waterproofing of This external horizontal force introduction on the end
the pier head surface. faces of the crossbeam allowed a stepwise relieve of
the internal reinforcement stresses, without chang-
ing the statical system. The total resultant force of
7 REHABILITATION the external tie-frame was at same level than the top
tension force within the reinforcement layers result-
7.1 General ing out of cantilever bending moment. The tie-frame
together with end buttress including working platform
Since the identified main crack patterns were with a total weight of 80 tons were lifted in one piece
addressed to have systematic structural causes, and during night (Fig. 11).
since every pier was built according the same draw- Immediately after the tie-frame and the buttresses
ing, it was required to apply strengthening and reha- were installed in final position, the tie-frame stressing
bilitation procedures to every pier, regardless of the works commenced. Strands aligned within the main
present degree of cracking excess. It would have chords of the tie-frame were stressed to 65% UTS to
been only a matter of time, once cracking excess secure the structure.
would have propagated, since the stability could only
be explained by assuming concrete tensile strength,
which is not known as a reliable concretes property 7.3 Grouting of detected cracks
while bearing cyclic loadings. All cracks were grouted with epoxy resin. The
Following was the sequence of strengthening pro- grouting works were carried out sequentially and
cedure for each and every pier: directionally from the bottom of the cross-head to
the top. At some piers the epoxy resin could easily be
1. Securing the crossbeam structure with a temporary,
pumped at the onion shell-like cracks over a length of
horizontal and external tie-frame to release the
4 m through the complete pier section.
bending stresses by temporary post-tensioning up
The maximum quantity which was pumped into
to 18 MN stressing force. The tie-frame was at same
one packer was about 60 litres which was an indica-
time providing the working platform. Temporary
tion of –beside cracks-poorly compacted concrete as
vertical supports were not accepted, since the high-
well as presence of large honey combs.
way below the bridge must be in full operation.
2. Grouting of all detected cracks with epoxy resin to
fill the voids. 7.4 Transverse post-tensioning
3. Transverse post-tensioning of crossheads with
prestressing bars to compensate the lack of trans- A total of 15 nos. of prestressing bars per pier diam-
verse reinforcement and to stress cracks faces of eter 32 and 40 mm respectively were to be installed to
longitudinal cracks against grout. cater for insufficient transverse reinforcement below
4. Replacing and removal of highly and undefined the bearings.
cracked concrete within lap-splice area down to The location of the existing reinforcement was
3rd layer of lap-splice reinforcement by means of checked to identify the optimized coring location in
hydro-water-jetting. order to avoid, cutting or damaging of existing vertical

55
For structural safety reasons the lap splice was
opened in two steps: First opening of the centre sec-
tion with a width of 2 m and repair of that section
(Area I). Then opening of the adjacent areas followed,
each with an approximate width of 1m (Area II).
A high pressure water jetting unit was set up below
the flyover serving two demolition areas simulta-
neously. The area of the lap splice was completely
covered to prevent parts from falling onto the traf-
fic below the flyover structure. Specially designed
temporary drain channels were installed to collect the
waste water and divert it to a collection tank for sub-
sequent cleaning purposes.
Initially, the concrete cover was removed by
water jetting to expose the top reinforcement bars.
Figure 11a. External tie-frame stressed up to 18MN, to 250 mm deep pilot holes each with a spacing of
relieve the structure during strengthening, allowed to open 250 mm were drilled around the perimeter of Area 1.
the lap splice. These pilot holes helped to speed up and control the
consistency of the water jetting process. Finally all
bars with diameter 40 mm were fully exposed with
a minimum clearance of 20 mm to all sides. For
proper bonding purposes all rebar was cleaned of
cement slurry and loose particles. A full lap-splice
mapping followed.
The main purpose of the remedial exercise was to
repair the deficiencies in the lap splice area. All of the
T40 rebar were generally lapped in a vertical manner
at the maximum bending moment area.
To prevent the concrete in the splice zone from
spalling off, additional transverse (vertical) reinforce-
ment (U-Bars) needed to be installed as the existing
stirrup reinforcement was insufficient.
To install the additional U-bar reinforcment, holes
were drilled into the concrete between the T40 bars
and bond-anchored with epoxy resin.
Figure 11b. Lifting procedure of 80 tons tie-frame incl.
working platform.
7.6 Pouring and closing lap splice with self
compacting concrete (SCC)
reinforcement bars. The anchorages of the transverse After the U-bars were installed the lap splice area was
stressing bars had to be placed inbetween the gap of closed by self compacting concrete (SCC). SCC was
the 3rd to 4th CFRP tendon layer, later running lon- chosen for the following 5 reasons:
gitudinally on both sides of the cross-head. Therefore
it was extremely important to limit the drilling devia- − The spacing between the spliced bars was expected
tion over the length of 4 m through the crosshead to to vary substantially.
only 20 mm. However this was successfully achieved − The early concrete strength had to be high to
by the competent coring subcontractor. allow re-opening of the flyover soon after concrete
The bars were stressed to 65% UTS, grouted and placement.
final anchor head corrosion protection was applied. − The bonding quality of the concrete has to be
extremely good in the lap splice area.
− Since relatively small concrete quantities were
7.5 Lap splice strengthening required and for quality assurance reasons the
aggregates for the SCC had to be supplied in sacks
The most important remedial work procedure was the and mixed on site.
rehabilitation of the lap-splice. To allow to open the − Requirement of low shrinkage properties.
lap-splice without any vertical support of the canti-
lever ends the temporary prestressing force, horizon- All lap splices had to be concreted during week-
tally introduced by tie-frame jacking was increased to ends when the flyover could be temporarily closed
18MN, which represents the ultimate tensile force of for traffic. to give the SCC sufficient hardening time
the top two reinforcement layers. until reopening of the flyover for traffic.

56
The SCC was mixed on top of scaffolding situated
on top of the flyover. The concrete was discharged
directly from the scaffolding through a PVC-pipe into
the lap-splice area. Because of the required shifting of
the scaffolding the mixer was later on installed on a
truck which could easily service up to 6 piers in one
night.
To achieve the required mix parameters (e.g. fresh
concrete temperature, viscosity, flow spread etc.) it
was important to implement the following additional
measures:
− Cooling of the pre-packed mixture in an air-
conditioned container for about 24 hours.
− Cooling of the water to a predetermined
temperature.
A strict QC/QA procedure was established to
garantee satisfactory SCC properties.
After curing time of the SCC the temporary tie-
frame post-tensioning force was relieved from 18MN
down to 9MN to get the lap-splice activated.

Figure 13. Permanent steel buttresses stressed against end


7.7 Permanent longitudinal post-tensioning
faces of crossbeam by 18 Nos. of CFRP tendons.
by CFRP tendons
The cross-heads were permanently prestressed
with 18 Nos. of CFRP tendons, each prestressed to stressing force was simultaneously relieved by dein-
400kN. CFRP-tendons were chosen for the following stallation strand by strand.
reasons: Finally the tie-frame was lowered down. Fig. 13
shows the anchorage detail and the final situation,
− Easy handling of the tendons due to its light where the steel buttress installed on both end faces of
weight. the crossbeam are permanently interconnected by 18
− High durability in the hot and humid climate of post-tensioned CFRP tendons, properly covered and
Malaysia. protected against mechanical impact.
− Easy bonding of the tendons with the surface of the
concrete, which increases the factor of safety dur-
ing the ULS and provides crack control and cracks 8 CONCLUSIONS
width limitation.
Structural design, construction process, selection of mate-
The tension force was applied in incremental steps,
rials and maintenance are susceptible to human error. Thor-
to allow filling the gap behind the CFRP-tendons
ough risk analysis is required to prevent severe defects or
with adhesive. Starting with each 6 CFRP tendons on
failures due to the accumulation of these errors.
side faces the top 6 tendons were installed. During
The paper presents the focuses of a chain of errors
this stressing process, while increasing the permanent
which could have been prevented by means of thor-
CFRP post-tensioning force, the temporary tie-frame
ough failure mode and effect analyses (FMEA).
Dominant errors were
• Imperfect loading assumptions
• Blind application of code provisions
• Blind faith in FE analysis
• Ignorance of the art of detailing
• Inconsistency of the interface between design and
the construction process
• Inadequate material selection
• Inadequate contractual relationships
• Inadequate maintenance.
Even the first steps of the rehabilitation process
Figure 12. Opened lap splice additionally reinforced by were again governed by human error, especially due
vertical U-Bars. to legal and liability reasons.

57
The prevention of the errors described requires [3] Fritz Leonhardt, “Vorlesungen über Massivbau, Teil 1,
a fundamental change in economical competition 2, 3”, Springer Verlag, Berlin 1975.
standards. Applied science has to dominate short [4] Leonhardt, Andrä und Partner, “Summary on Investi-
dated profit considerations, not vice versa. gations, Findings and Conclusions Concerning Cracks
in Crossheads at MRR2 in Kuala Lumpur”, Berlin,
Stuttgart, Nov. 2004.
[5] Leonhardt, Andrä und Partner, “Report on Remedial
REFERENCES Detail Design for Main Viaduct Piers P1 to P33 and
Abutment B”, Berlin/Stuttgart, Dec. 2005.
[1] Fritz Leonhardt, “über die Kunst des Bewehrens von [6] Lee Coon Siang, Ismail Mohamad Taib, Dato’ Moha-
Stahlbetontragwerken”, Beton- und Stahlbetonbau, Vol mad Razali b Othman, Causes and Retrofitting for
60, 1965, No. 8, pp. 181–192; No. 9, pp. 212–220. Failure at Kuala Lumpur MRR II Highway Viaduct
[2] Fritz Leonhardt, “Das Bewehren von Stahlbetontrag- Malaysia, IABSE Symposium Lisbon 2005.
werken”, Betonkalender 1971, Wilhelm Ernst & Sohn,
Berlin, Part II, pp. 303–330

58

You might also like