Professional Documents
Culture Documents
Kepong Bridge
Kepong Bridge
ABSTRACT: Severe cracking in reinforced and/or prestressed concrete structures usually results from the
accumulation of a number of causes, such as errors in structural design, detailing of reinforcement, concrete
composition, concrete curing, overloading under construction, early lowering of falsework, underestimated
thermal loadings, fatigue, and lack of maintenance etc. The paper presents examples of a consistent strategy of
diagnosis and therapy.
49
3 TRACK RECORD OF THE STRUCTURE Expert reports from various parties with various
interpretations finally resulted in inconsistent conclu-
The contract for the flyover structure was awarded in sions about the causes of the cracks and the cracks
May 1999 on a design & built basis. Design was done influence on the structure load bearing capacity.
between July 1999 and August 2001. The construction A major concern of the reports was the sensibility for
started in February 2000 and was completed in April delayed ettringite formation (DEF) in the concrete,
2002. The flyover was opened to traffic in May 2002. where crack growth results from ettringite expansion.
First cracks on the crossheads were observed The observed typical crack patterns, however, could
already during construction. Shortly after opening of not be explained by DEF. Different expert opinions
the bridge for traffic further cracks were developing about the causes of measured test results are a well
and excessively widening. First reports about these known phenomenon both in research and in surveys
cracks are dated back to January 2003 respectively on defects of existing structures. This results from the
November 2003. Detail crack mapping of all 33 piers fact that everybody draws conclusions from the basis
including abutments was subsequently appointed to of his own experience and will only find what he is
a specialist contractor in May 2004, in order to sys- searching for.
tematically have documentation of crack patterns In 2005 key management within JKR changed and
including crack sizes (see figure 2). Various field new Director General, an excellent structural expert
investigations including cover meter tests, verification himself, realized the potential structural risk resulting
of rebar sizes and spacing, core sampling for strength out of this bridge and the structural findings.
tests and monitoring installations were initiated. In October 2005, LAP was appointed for final and
Typical crack patterns consist of detail design for remedial works of the piers on the
basis of a complete critical analysis of design, con-
• two longitudinal (along the direction of the cross struction, material properties and maintenance. At
head) cracks in between the two adjacent bear- the same time the bridge was closed for traffic. The
ings, more or less partitioning the cross head into focus of the remedial design concept was to eliminate
3 segments, potential structural deficiencies, to relief the struc-
• a onionskin shaped crack mesh on the upper flanks tures stresses and to provide appropriate response on
at the cross head centre, partly interconnected in potential DEF occurrence.
transverse direction by cracks on the top surface, The contract for remedial design was awarded
• horizontal cracks over the piers underneath the to a contractor on March 2006. Execution works
onionskin mesh, began after only a one month mobilization period in
• inclined cracks running down the face of the cross April 2006.
beams, and During the following 6 months all 33 T-shaped
• inclined cracks underneath and in the vicinity of piers were structurally rehabilitated, with maximum
the bearings. of 18 piers being remedied simultaneously. Site logis-
tics and strengthening sequence was most challeng-
ing, both for contractor, LAP site supervision and
client, while traffic on highway underneath the bridge
was fully ongoing. The strengthening principles will
be illustrated in chapter 7 in more detail.
In November 2006 the 100% strengthened and
rehabilitated bridge could be reopened to unlimited
side face pier #9, max. crack width 3.2 mm traffic.
50
causes a heat development and distribution within the
member, arising from cement hydration. The applied
concrete mixture proved a high content of Portland
cement which promotes heat development. Tem-
perature gradients from cooling down outer surfaces
exposed to formwork or air while the inner core of the
structure is still hot causes internal tensile stresses,
which may exceed tensile strength of the immature
concrete. Special caution must therefore be under-
taken to control early thermal cracking by providing
sufficient reinforcement in size and arrangement to
control regular crack spacing as well as limit indi-
vidual cracks width. On the other hand concrete mix-
ture must be carefully selected to avoid excessive heat
development, e.g. by using cement with lower hydra-
tion heat development.
51
Maximum crosshead cantilever bending moment
e.g. results to:
52
5.1 Strut and tie model versus FE analysis A comparison between the results of a finite ele-
ment analysis and a strut and tie model is shown in
Due to the fact that the loads are not applied as line Figs. 5 and 6. Even though both approaches provide
loads across the section but in terms of single loads equal results in terms of equilibrium, the finite ele-
along the edges of the cantilever, the internal load ment analysis requires a significant amount of inter-
path actually corresponds to a strut and tie space pretation and is much more susceptible to human
frame with compression and tensile forces in three error than the strut and tie model. The finite element
directions. This space frame reproduces the load path analysis should rather be used as a tool to verify
from the bearings through the cross head to the pier the alignment of the strut and tie model. Detailing
junction and through the pier and the raft into the according to the strut and tie model however is quite
piles. The space frame model includes both the glo- simple, and the necessity of reinforcement in three
bal force actions and the internal thrust actions due dimensions is obvious.
to the local deviation of the load path. Both compres- An erroneous interpretation of the finite analysis
sion struts and tensile ties need to be analyzed and all model could suggest that transverse reinforcement
tensile forces need to be covered by properly detailed between the bearings and splitting reinforcement
and anchored reinforcement. underneath the bearings would not be needed because
“The Art of Detailing”, published by the late Pro- the concrete tensile stresses are low. The integral of
fessor Fritz Leonhardt [1] more than 40 years ago these stresses however results in large forces. FE
describes the engineering concept of strut and tie analysis determines the governing tensile stresses
modeling in detail. Structural design on the basis of in a concrete zone which is pre-cracked due to ther-
strut and tie modeling has now been incorporated in mal reasons and which is considerably intersected by
the relevant provisions of Eurocode 2. the reinforcement, Fig. 7. Due to this intersection of
rebars there is virtually no concrete section left which
could transfer tensile stresses. This does not comply
with the suppositions of the FE analysis.
The superposition of individually negligible hori-
zontal loadings from bearing friction, braking, wind,
horizontal temperature gradients etc. add up to sig-
nificant stresses and result in fatigue failure of non
reinforced concrete sections. The sudden and brittle
collapse of the bridge seat of the Reichsbruecke in
Vienna 1976, Fig. 8, demonstrates that this may hap-
pen even after years of operation.
The lack of sufficient transverse reinforcement
and of proper splitting reinforcement is responsible
for the two longitudinal separating cross head cracks
and the diagonal cracks underneath the bearings.
Blind faith in even highly sophisticated FE compu-
Figure 5. Finite Element Analysis of the cross head. ter analyses implies significant risk potentials.
53
Figure 9. Reinforcement of the cross beam.
54
corresponds to a volume of some 5% ettringite per 5. Add lacking vertical reinforcement legs, adhe-
cubic metre of concrete on the average. Contrasted with sively bonded within concrete member to take
an average pore volume of 13%, the maximum amount the tensile component forces, resulting from lap-
of ettringite that can be formed is significantly smaller splice action according Figure 10.
than the total pore volume. Damages of the concrete 6. Placing of self compacting concrete to close
texture due to DEF are therefore very unlikely. the highly reinforced lap-splice area in order to
There is no doubt however that the ingress of achieve best bond conditions for load transfer
moisture and water into concrete cracks due to ten- within lap splice.
sile stresses promotes the local accumulation of 7. Apply moderate permanent post-tensioning force
newly formed ettringite on the flanks of these cracks. for crack control by 18 externally bonded CFRP
Recrystallized ettringite is thus seen not as the cause tendons, each stressed to 400 kN.
of damage but rather as its consequence. 8. Seal and finish the surface for waterproofing
Due to defective piping of the drainage of the reasons to take necessary actions in terms of sus-
bridge superstructure over the piers, the crossbeams pected DEF problems.
were regularly flooded and wetted in the rainy sea-
son. In addition, the local humidity is very high.
Water and moisture induced ettringite formation thus 7.2 Installation of tie-frame
expanded the original excessive cracking from struc- Since no vertical support was accepted, to relieve the
tural deficiencies. structure during strengthening, an external tie-frame
Ettringite formation can be stopped after elastic was installed, which could be stressed up to 18 MN.
grouting of the existing cracks and waterproofing of This external horizontal force introduction on the end
the pier head surface. faces of the crossbeam allowed a stepwise relieve of
the internal reinforcement stresses, without chang-
ing the statical system. The total resultant force of
7 REHABILITATION the external tie-frame was at same level than the top
tension force within the reinforcement layers result-
7.1 General ing out of cantilever bending moment. The tie-frame
together with end buttress including working platform
Since the identified main crack patterns were with a total weight of 80 tons were lifted in one piece
addressed to have systematic structural causes, and during night (Fig. 11).
since every pier was built according the same draw- Immediately after the tie-frame and the buttresses
ing, it was required to apply strengthening and reha- were installed in final position, the tie-frame stressing
bilitation procedures to every pier, regardless of the works commenced. Strands aligned within the main
present degree of cracking excess. It would have chords of the tie-frame were stressed to 65% UTS to
been only a matter of time, once cracking excess secure the structure.
would have propagated, since the stability could only
be explained by assuming concrete tensile strength,
which is not known as a reliable concretes property 7.3 Grouting of detected cracks
while bearing cyclic loadings. All cracks were grouted with epoxy resin. The
Following was the sequence of strengthening pro- grouting works were carried out sequentially and
cedure for each and every pier: directionally from the bottom of the cross-head to
the top. At some piers the epoxy resin could easily be
1. Securing the crossbeam structure with a temporary,
pumped at the onion shell-like cracks over a length of
horizontal and external tie-frame to release the
4 m through the complete pier section.
bending stresses by temporary post-tensioning up
The maximum quantity which was pumped into
to 18 MN stressing force. The tie-frame was at same
one packer was about 60 litres which was an indica-
time providing the working platform. Temporary
tion of –beside cracks-poorly compacted concrete as
vertical supports were not accepted, since the high-
well as presence of large honey combs.
way below the bridge must be in full operation.
2. Grouting of all detected cracks with epoxy resin to
fill the voids. 7.4 Transverse post-tensioning
3. Transverse post-tensioning of crossheads with
prestressing bars to compensate the lack of trans- A total of 15 nos. of prestressing bars per pier diam-
verse reinforcement and to stress cracks faces of eter 32 and 40 mm respectively were to be installed to
longitudinal cracks against grout. cater for insufficient transverse reinforcement below
4. Replacing and removal of highly and undefined the bearings.
cracked concrete within lap-splice area down to The location of the existing reinforcement was
3rd layer of lap-splice reinforcement by means of checked to identify the optimized coring location in
hydro-water-jetting. order to avoid, cutting or damaging of existing vertical
55
For structural safety reasons the lap splice was
opened in two steps: First opening of the centre sec-
tion with a width of 2 m and repair of that section
(Area I). Then opening of the adjacent areas followed,
each with an approximate width of 1m (Area II).
A high pressure water jetting unit was set up below
the flyover serving two demolition areas simulta-
neously. The area of the lap splice was completely
covered to prevent parts from falling onto the traf-
fic below the flyover structure. Specially designed
temporary drain channels were installed to collect the
waste water and divert it to a collection tank for sub-
sequent cleaning purposes.
Initially, the concrete cover was removed by
water jetting to expose the top reinforcement bars.
Figure 11a. External tie-frame stressed up to 18MN, to 250 mm deep pilot holes each with a spacing of
relieve the structure during strengthening, allowed to open 250 mm were drilled around the perimeter of Area 1.
the lap splice. These pilot holes helped to speed up and control the
consistency of the water jetting process. Finally all
bars with diameter 40 mm were fully exposed with
a minimum clearance of 20 mm to all sides. For
proper bonding purposes all rebar was cleaned of
cement slurry and loose particles. A full lap-splice
mapping followed.
The main purpose of the remedial exercise was to
repair the deficiencies in the lap splice area. All of the
T40 rebar were generally lapped in a vertical manner
at the maximum bending moment area.
To prevent the concrete in the splice zone from
spalling off, additional transverse (vertical) reinforce-
ment (U-Bars) needed to be installed as the existing
stirrup reinforcement was insufficient.
To install the additional U-bar reinforcment, holes
were drilled into the concrete between the T40 bars
and bond-anchored with epoxy resin.
Figure 11b. Lifting procedure of 80 tons tie-frame incl.
working platform.
7.6 Pouring and closing lap splice with self
compacting concrete (SCC)
reinforcement bars. The anchorages of the transverse After the U-bars were installed the lap splice area was
stressing bars had to be placed inbetween the gap of closed by self compacting concrete (SCC). SCC was
the 3rd to 4th CFRP tendon layer, later running lon- chosen for the following 5 reasons:
gitudinally on both sides of the cross-head. Therefore
it was extremely important to limit the drilling devia- − The spacing between the spliced bars was expected
tion over the length of 4 m through the crosshead to to vary substantially.
only 20 mm. However this was successfully achieved − The early concrete strength had to be high to
by the competent coring subcontractor. allow re-opening of the flyover soon after concrete
The bars were stressed to 65% UTS, grouted and placement.
final anchor head corrosion protection was applied. − The bonding quality of the concrete has to be
extremely good in the lap splice area.
− Since relatively small concrete quantities were
7.5 Lap splice strengthening required and for quality assurance reasons the
aggregates for the SCC had to be supplied in sacks
The most important remedial work procedure was the and mixed on site.
rehabilitation of the lap-splice. To allow to open the − Requirement of low shrinkage properties.
lap-splice without any vertical support of the canti-
lever ends the temporary prestressing force, horizon- All lap splices had to be concreted during week-
tally introduced by tie-frame jacking was increased to ends when the flyover could be temporarily closed
18MN, which represents the ultimate tensile force of for traffic. to give the SCC sufficient hardening time
the top two reinforcement layers. until reopening of the flyover for traffic.
56
The SCC was mixed on top of scaffolding situated
on top of the flyover. The concrete was discharged
directly from the scaffolding through a PVC-pipe into
the lap-splice area. Because of the required shifting of
the scaffolding the mixer was later on installed on a
truck which could easily service up to 6 piers in one
night.
To achieve the required mix parameters (e.g. fresh
concrete temperature, viscosity, flow spread etc.) it
was important to implement the following additional
measures:
− Cooling of the pre-packed mixture in an air-
conditioned container for about 24 hours.
− Cooling of the water to a predetermined
temperature.
A strict QC/QA procedure was established to
garantee satisfactory SCC properties.
After curing time of the SCC the temporary tie-
frame post-tensioning force was relieved from 18MN
down to 9MN to get the lap-splice activated.
57
The prevention of the errors described requires [3] Fritz Leonhardt, “Vorlesungen über Massivbau, Teil 1,
a fundamental change in economical competition 2, 3”, Springer Verlag, Berlin 1975.
standards. Applied science has to dominate short [4] Leonhardt, Andrä und Partner, “Summary on Investi-
dated profit considerations, not vice versa. gations, Findings and Conclusions Concerning Cracks
in Crossheads at MRR2 in Kuala Lumpur”, Berlin,
Stuttgart, Nov. 2004.
[5] Leonhardt, Andrä und Partner, “Report on Remedial
REFERENCES Detail Design for Main Viaduct Piers P1 to P33 and
Abutment B”, Berlin/Stuttgart, Dec. 2005.
[1] Fritz Leonhardt, “über die Kunst des Bewehrens von [6] Lee Coon Siang, Ismail Mohamad Taib, Dato’ Moha-
Stahlbetontragwerken”, Beton- und Stahlbetonbau, Vol mad Razali b Othman, Causes and Retrofitting for
60, 1965, No. 8, pp. 181–192; No. 9, pp. 212–220. Failure at Kuala Lumpur MRR II Highway Viaduct
[2] Fritz Leonhardt, “Das Bewehren von Stahlbetontrag- Malaysia, IABSE Symposium Lisbon 2005.
werken”, Betonkalender 1971, Wilhelm Ernst & Sohn,
Berlin, Part II, pp. 303–330
58