Pandit Deendayal Energy University

School of Technology
Assignment I 2 I

B. Tech. Civil Engineering

Semester – VII

Course Name : Construction Project Management

Instructions:
1. Solve all the questions.
2. Make full page neat diagrams using pencils and pens should be used for labelling purposes
3. Upload the completed assignment on MS Teams as RollNumber_CPM_A2
4. Marking shall be done on (a) Correctness and (b) Neatness
5. Last Date for Assignment Submission is 1st December 2022.

Q-1 Answer the following

1. Draw the Network diagram from the following


activities.
2. Perform forward and backward pass computations
3. Calculate the critical path duration
4. Calculate EST, LST, EFT and LFT
5. Calculate total float, free float, Independent float
and Interference float

Q-2 Answer the following


1) Draw the PERT network for this project
2) Find the expected duration and variance for each
activity
3) Determine the critical path and expected project
length
4) Tabulate the total floats for each activity
5) Prepare the activity schedule for the project
6) Calculate the standard deviation and variance of the
project length
7) What is the probability of project completion in-?

(a) atleast four weeks later than expected time


(b) no more than 2 weeks later than the expected time
(c) If the project completion duration is 27 weeks, what is the
probability of not meeting the due date.
(d) What due date has a 92.5% chance of completing the
project.

Q-3 Solve the following project network crashing problem.


Q-4 Solve the following project network crashing problem. Consider indirect expenses of Rs
6,000/day. Calculate the optimal project duration corresponding to the lowest project cost.
Plot the final results graphically.

Q-5 Table Q4.1 gives the budgeted monthly cash-flow requirements for a construction project.
At the end of October 2006, the total actual project expenditure is reported as Rs 114 lakh
and the project progress is reported as 50 per cent.
Draw an S-curve for cumulative cash flows for the project and calculate cost and schedule
performance indices as at the end of October 2006. What is the delay in the project as on
date in number of months?
Q -6

Q-7 Describe the different types of risks which affect construction projects.
Q-8 Discuss the different ways for mitigating construction risks.
Q-9 You are building a toll road
H,M,L correspond to three different traffic volumes conditional on the state of the
economy (According to your Expert)
Your Initial Investment = $1,000,000

Will You Invest?


Why or Why Not?