Week 2 (24th October 2022)

Quantity and Cost Estimations (CE-323)


3rd Year - Fall 2022

Lecture # 3-4 Boundary Wall

1. Work out the volume for Excavation.


2. Work out the volume of 1:4:8 lean concrete.
3. Calculate the number of blocks (12”x9”x6”) required for the boundary wall
construction.
4. Calculate the volume of backfill needed.

********************************************************************************************

Department of Civil Engineering Course Instructor


Dr. Rana Rab Nawaz Ahmed
Week 2 (24th October 2022)

Load Bearing Structure

Required Tasks:

1. Work out the volume for Excavation.


2. Work out the volume of 1:4:8 lean concrete.
3. Work out the 1:3:6 block masonry up to G.L.
4. Work out the 1:3:6 block masonry between G.L and P.L.
5. Calculate the volume of backfill needed.
6. Calculate the quantities of D.P.C provided over block masonry at P.L

********************************************************************************************

Department of Civil Engineering Course Instructor


Dr. Rana Rab Nawaz Ahmed