Professional Documents
Culture Documents
Work Permit Mechanical
Work Permit Mechanical
PRE-
21 INSTALLATION OF EXHAUST GAS DUCTING WIKA/WP/VIII/103/2015 8/6/2015 8/5/2015
COMMISSIONING
B 2 √
22 COMPACT GAS RAMP INSTALLATION WIKA/WP/IV/079/2015 5/11/2015 5/18/2015 TILL COMPLETED I 2 √
TILL PRE-
23 INSTALLATION OF FUEL GAS PIPING WIKA/WP/VIII/107/2015 8/11/2015 8/5/2015
COMMISSIONING
B 2 √
24 STARTING & INSTRUMENT AIR UNIT WIKA/WP/VIII/112/2015 8/31/2015 8/31/2015 - I 2 √
25 ENGINE, AUXILIARY, EGM PLATFORM WIKA/WP/VIII/111/2015 8/31/2015 8/31/2015 - - 2 √
INSTALLATION OF GAS PRESSURE REDUCTION SYSTEM TILL PRE-
26
(GPRS)
WIKA/WP/IX/115/2015 8/31/2015 8/31/2015
COMMISSIONING
I 2 √
TILL PRE-
27 LUBE OIL CHEMICAL CLEANING (PICKLING) WIKA/WP/IX/118/2015 9/19/2015 9/19/2015
COMMISSIONING
B 2 √
TILL PRE-
28 INSTALLATION OF EXHAUST GAS PIPE INSULATIONS WIKA/WP/IX/119/2015 9/21/2015 9/19/2015
COMMISSIONING
B 2 √