PT.

WIJAYA KARYA (Persero) Tbk


Gas Engine Power Plant 184 MW, Arun Location Project
WORK PERMIT
INSTALLATION FABRICATED TANK
WORK PERMIT NO : PERSO N IN CHARGE :
PROPOSED BY : SCHEDULE START :
DATE : SCHEDULE FINISH :
NO DESCR
WORK PERMIT MECHANICAL
NO DESCRIPTION WORK PERMIT NO DATE START FINISH STATUS No. PDF Keterangan
Oudner

1 WORK PERMIT GROUNDING ROD INSTALLALTION WIKA/WP/I/058/2015 1/10/2015 1/8/2015 2/8/2015 1 √


2 WORK PERMIT INSTALLATION FABRICATED TANK WIKA/WP/IV/072/2015 4/21/2015 4/22/2015 T&F B 1 √
3 WORK PERMIT INSTALLATION OF HDPE DEEP WATER PIPE WIKA/WP/IV/074/2015 4/23/2015 4/24/2015 UNTIL TESTING B 1 √
WORK PERMIT FIRE FIGHTING PIPE INSTALLATION (ALL
4
AREA)
WIKA/WP/III/070/2015 3/26/2015 3/27/2015 5/27/2015 A 1 √
TILL ALL EH
5 WORK PERMIT HVAC ENGINE HALL INSTALLATION WIKA/WP/IV/078/2015 4/3/2015 4/4/2015
COMPLETED
B 1 √
6 WORK PERMIT INSTALLATION OVER HEAD CRANE WIKA/WP/IV/075/2015 4/24/2015 24-042015 T&F B 1 √
WORK PERMIT FIRE FIGHTING TANK FABRICATING AND
7
INSTALLATION
WIKA/WP/IV/076/2015 4/28/2015 4/28/2015 TILL TESTING B 1 √
8 WORK PERMIT ENGINE INSTALLATION WIKA/WP/077/2015 4/2/2015 TILL PRECOM I 1 √
WORK PERMIT INSTALLATION OG EXHAUST GAS MODULE
9
AND ENGINE AUXILLIARY MODULE
WIKA/WP/IV/073/2015 4/24/2015 4/22/2015 TILL PRECOM B 1 √
TILL HYDROSTATE
10 WROK PERMIT INSTALLATION OF COOLING PIPE SYSTEM WIKA/WP/0-90/VI/2015 6/26/2015 6/26/2015
TEST
B 2 √

TILL ALL SETTLE


11 WORK PERMIT INSTALLATION OF PUMP UNITs WIKA/WP/96/VII/2015 7/3/2015 7/3/2015
AND FOUNDATION
I 2 √
TILL ALL PIPE
12 WORK PERMIT INSTALLATION OF SPRINKLE SYSTEM WIKA/WP/99/VI/2015 7/9/2015 7/10/2015
HYDROTEST
B 2 √
TILL
13 WORK PERMIT INSTALLATION FOR SILENCER OF STACK WIKA/WP/91/VI/2015 6/26/2015 6/26/2015
COMMISIONING
I 2 √
WORK PERMIT INSTALLATION MAINTENANCE WATER
14
TANK
WIKA/WP/95/VI/2015 6/30/2015 6/30/2015 T&F I 2 √
15 WORK PERMIT INSTALLATION CHARGE FILTER WIKA/WP/092/VI/2015 6/26/2015 7/27/2015 T&F I 2 √
WORK PERMIT INSTALLATION OF WATER TREATMENT
16
CONTAINER's
WIKA/WP/VI/089/2015 6/24/2015 6/24/2015 T&F I 2 √
17 WORK PERMIT INSTALLATION OF EXPANSION VESSEL WIKA/WP/093/VI/2015 6/27/2015 6/28/2015 TILL FINISHED ALL I 2 √
WORK PERMIT INSTALLATION OF COMPRESSED AIR
18
SYSTEM
WIKA/WP/VI/088/2015 6/24/2015 6/24/2015 T&F I 2 √
WORK PERMIT INSTALLATION OF FIRE FIGHTING
19
CONTAINER's
WIKA/WP/VI/087/2015 6/24/2015 6/24/2015 T&F 2 √
20 WORK PERMIT INSTALLATION OF RADIATOR ENGINE'S WIKA/WP/IV/079/2015 5/11/2015 5/12/2015 TILL COMPLETED B 2 √
EH1-ED10

PRE-
21 INSTALLATION OF EXHAUST GAS DUCTING WIKA/WP/VIII/103/2015 8/6/2015 8/5/2015
COMMISSIONING
B 2 √
22 COMPACT GAS RAMP INSTALLATION WIKA/WP/IV/079/2015 5/11/2015 5/18/2015 TILL COMPLETED I 2 √
TILL PRE-
23 INSTALLATION OF FUEL GAS PIPING WIKA/WP/VIII/107/2015 8/11/2015 8/5/2015
COMMISSIONING
B 2 √
24 STARTING & INSTRUMENT AIR UNIT WIKA/WP/VIII/112/2015 8/31/2015 8/31/2015 - I 2 √
25 ENGINE, AUXILIARY, EGM PLATFORM WIKA/WP/VIII/111/2015 8/31/2015 8/31/2015 - - 2 √
INSTALLATION OF GAS PRESSURE REDUCTION SYSTEM TILL PRE-
26
(GPRS)
WIKA/WP/IX/115/2015 8/31/2015 8/31/2015
COMMISSIONING
I 2 √

TILL PRE-
27 LUBE OIL CHEMICAL CLEANING (PICKLING) WIKA/WP/IX/118/2015 9/19/2015 9/19/2015
COMMISSIONING
B 2 √

TILL PRE-
28 INSTALLATION OF EXHAUST GAS PIPE INSULATIONS WIKA/WP/IX/119/2015 9/21/2015 9/19/2015
COMMISSIONING
B 2 √