MINUTES OF MEETINGS
MNC THEMEPARK PROJECT
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
I. SUBMISSION
1 GAI - KSO - GEOFORCE to submit action plan per 2 weeks. And provide catch
up program. GAI-KSO- 22-Sep-19
For GAI - Make sure all the STA and Grid Plan mentioned in it. Because KSO v
GEOF 30-Sep-19
want to make sure all the work is on strict schedule.
2 KSO to Submit:
e. Cash Flow Projection
Recent Update : Will be submitted today. 18-Sep-19
MWW suggested the updated schedule refer to KSO realization KSO-GAI 30-Sep-19 v
Also submit it for Earthwork & Macro Drain TBD
3 KSO to submit new schedule regarding the site activity which will be carried out
13-Sept-19
next. KSO v
9-Oct-19
4 KSO to submit brochure & Specification of concrete panel.
Recent Updates : - 18-Sep-19
KSO 7-Oct-19 v
16-Oct-19
10 GAI-KSO-GEOFORCE to submit daily report every day and weekly report every
Monday. All For Info v
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
11 KSO to submit thesettlement reading as attachment on weekly report.
KSO For Info v
2 KSO to Re-do the Subdrain mock up palced in front of MWW Site Office
KSO TBD v
14 All the site work have to follow the approved Shop drawing, Method Statement
and material approval. All contractor to make sure all foreman do the work as the
submitted drawing. ALL For Info v
15 GAI to start the Line B after the DB 5 avoiding the DB5 spring water. GAI 18-Sep-19 v
16 KSO subdrain productivity is approximate 30 m'/ day, so GAI have to provide
area as needed to catch up with KSO schedule.
Recent Update : Since last week they cant achived it, so on this week GAI have to GAI For Info v
prepare for 420 m by this week.
17 With the remaining schedule time (8 weeks), GAI to provide working area for
KSO subdrain work with minimum 200m' per week. GAI For Info v
19 KSO to proceed with the temporary drain before Sediment Trap after the
sediment trap installed. KSO 16-Oct-19 v
21 GAI to open 150 m' work area on B2 until B4 to KSO per Tuesday 15 october 2019.
GAI 15-Oct-19 v
III. SAFETY
1 KSO to aware about sediment trap access road at the northern slope area.
KSO For Info v
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
2 All Contractor have to use name card at site. KSO TBD v
3 KSO to aware on the backfilling slope area KSO For Info v
4 KSO and GAI to maintain the water quality which run to Lido Lake. KSO For Info v
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
4 GAI going to devide the team into day shift and night shift
Recent Update: GAI already started the night shift until 10 pm.
MWW comments: Safety personal must be on site to supervise. ALL TBD v
5 KSO requesting not using DCP and only use field CBR and Sand Cone for
Compaction testing. For Info
GEOFORCE will inform quality inspection as per KSO request. MWW v
9-Oct-19
10 KSO to put settlement monitoring (reference point) at the edge of the slope which
backfill level already finish (1 meter away from the slope every 50 meters). And KSO For Info v
read it every week.
11 Comencement date for bulk earthwork & macro drain start when the CAR release
by MWW. MWW For Info v
12 KSO site activity on Zone E (8 October 2019 10 am) and zone D (7 October 2019 1
pm) stopped due to the villager issue (Ciletuh Hilir and Wates). MWW to take
notes about this. MWW For Info v
13 DEM will meet the villager who stop the site work and consolidate with them.
MWW-DEM For Info v
14 GAI to aware about the nourthern RCP and install more pipes by next
Wednesday and divert the water from toll road directly to the RCP.
GAI to prepare the material 3 more. GAI 15-Oct-19 v
15 AS per GAI meeting with MWW, Saturday 12 october 2019 GAI will mobilize
6 Dump Truck
1 Amphibious Exc GAI 12-Oct-19 v
1 Bull dozer
V. DESIGN ISSUE
1 First Updates: Slurry depth recommendation from GEOFORCE is 3m to 9 m.
Second Updates: GEOFORCE will give the recommendation regarding the soft
soil excavation depth and type of soil to be backfilled starting from area around
DB 5.
Third Updates: Slurry is to be removed until the vegetation layer. Approximate 2-
4 m still same with the GAI contract. ALL 23-Aug-19 v
Recent Updates : Minimum Slurry Excavation based on GEOFORCE
recomendation on last meeting 25 sept 2019
MWW already distribute it to all
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
2 As agreed on todays meeting,
CBR test should reach >= 5%,
50 cm loose thickness,
Tested using Field CBR, DCP test, & Sand Cone test,
Tested every 50 m' grid/radius.
if the CBR did not reach the requirement, test again nearby the point and do the
average. ALL FOR INFO v
Agreed today 25 September 2019 :
1. For the valley area excavation using the GEOFORCE recommendation, its not
require CBR 5%, indeed need flat surface only.
2. For other subgrade besides valley, require CBR 5 %
3 KSO will do the works on buffer area, GEOFORCE will provide the
recommendation regarding the soil stability.
To be Submitted to MWW on 13 september 2019 GEOF-MWW 19-Sep-19 v
recent updates : submitted to KSO by MWW per 19 september 2019 (For Info)
7 For the soil testing, All surface have to be tested wheter its achived the MWW-GEOF-
requirement or not. For Info v
KSO
8 Regarding Buffer Area recommendation, using the excavation recommendation
on 18 sept 2019 by geoforce, for the soil treatment after the slurry soil removed
MWW-GEOF TBD v
still outstanding.
9 As per today KSO already give the DCP vs CBR field result for GEOFORCE and
MWW to study for KSO proposal for using field CBR for soil testing. MWW-KSO-
For Info v
GEOF
10 GEOFORCE will provide the formula regarding DCP CBR calculation. GEOF 2-Oct-19 v
11 KSO and GEOFORCE to join and approved the GAI site handover with MWW ALL 27-Sep-19 v
12 Based on P Tjendra Instruction on site, Subdrain 4 change from 2 pipes to 3 pipes,
Subdrain 5 from 2 pipes to 1 pipe.
MWW instruct to make fish bone on the spring water near the DB 5 and KSO to KSO-MWW For Info v
put it in a drawing.
13 KSO to start the subdrain 5 from STA 0+40 due to the macrodrain path crossing it.
KSO to aware about it. KSO-MWW 16-Oct-19 v
VI. MISC.
1 GEOFORCE to value engineering their recommendation for slope stability at
buffer area and present again to MWW.
Recent Updates: refer to the 8 october recommendation sent by geoforce GEOF For Info v
2 Cut off Progress Claim every 25th per month ALL For Info v
3 SM / CM have to on site everyday ALL For Info v
4 PM and SM / CM have to attend weekly meeting. ALL For Info v
5 Next Meeting on KSO site office ALL For Info v
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
6 KSO to survey existing village access and surrounding area for MWW to consider
and design underpass/boxculvert before backfilling BOH access. 16 ocotber
Recent Updates: Partially next week ALL v
2019
7 KSO still wating for the Draft format of Down Payment and performance bond
from MWW / Owner MWW For Info v