Assignment 3 - Fall 2020 - Model Answer
Assignment 3 - Fall 2020 - Model Answer
Problem 1:
Problem 2:
a) Multiple Activity Chart:
c) Utilization Factor:
Utilization Factor
Utilization Factor
calculations
Loader (18 / 22 ) * 100% 81.8 %
Truck 1 (22/ 22 ) * 100% 100 %
Truck 2 (22 / 22 ) * 100% 100 %
Truck 3 (22 / 22 ) * 100% 100 %
Bulldozer (12/ 22) * 100% 54.5 %
Cairo University
STRN 224: Construction Project Management
Fall-2020
Assignment 3-Model Answer
Problem 3:
a) Multiple Activity Chart:
c) Utilization Factor:
d) Without redrawing the multiple activity chart, calculate the utilization factor for each equipment and the two crews, in case a second
truck is brought to site.