Project Cost Estimate-De Weerd (Final) DOE
Project Cost Estimate-De Weerd (Final) DOE
( ILECO-1 )
Tigbauan, Iloilo
December 3, 2022
SUB-TOTAL 10,000.00
ENGR. GC JUNE GARANCHON ENGR. MIGUEL A. PAGUNTALAN JR. OLUMIDE OLUSEYI KUMAPAYI
TSD Manager General Manager Signature Over Printed Name of Applicant
Notes:
1 Installation jobs near LIVE circuit should be conducted during NGCP scheduled BLACK-OUT
2 The Cost of Hauling is applicable only from ILECO-1 main office up to the last accesable road by the
ILECO-1 service vehicle.
3 The consumer is responsible for the Right-of-Way acquisition and line clearing.
4 Only materials and accessories from ILECO-1 such as pole, transformer, and kWhr meter if
applicable) are included in this estimate.
5 Service drop conductor insulated copper wire from transformer bushing to kWhr meter to service entrance
is not included in this cost estimate.
6 The applicant must install a circuit breaker accessible to ILECO-1 line crew.
consumer / accounting / billing / ISD
ILOILO 1 ELECTRIC COOPERATIVE, INC.
( ILECO-1 )
Tigbauan, Iloilo
December 3, 2022
SUB-TOTAL 10,000.00
Notes:
1 Installation jobs near LIVE circuit should be conducted during NGCP scheduled BLACK-OUT
2 The Cost of Hauling is applicable only from ILECO-1 main office up to the last accesable road by the
ILECO-1 service vehicle.
3 The consumer is responsible for the Right-of-Way acquisition and line clearing.
4 Only materials and accessories from ILECO-1 such as pole, transformer, and kWhr meter if
applicable) are included in this estimate.
5 Service drop conductor insulated copper wire from transformer bushing to kWhr meter to service entrance
is not included in this cost estimate.
6 The applicant must install a circuit breaker accessible to ILECO-1 line crew.
consumer / accounting / billing / ISD
ILOILO 1 ELECTRIC COOPERATIVE, INC.
( ILECO-1 )
Tigbauan, Iloilo
December 3, 2022
SUB-TOTAL 10,000.00
ENGR. GC JUNE GARANCHON ENGR. MIGUEL A. PAGUNTALAN JR. LIFEBANK FOUNDATION INC. (JOSEPH PERLAS)
TSD Manager General Manager Signature Over Printed Name of Applicant
Notes:
1 Installation jobs near LIVE circuit should be conducted during NGCP scheduled BLACK-OUT
2 The Cost of Hauling is applicable only from ILECO-1 main office up to the last accesable road by the
ILECO-1 service vehicle.
3 The consumer is responsible for the Right-of-Way acquisition and line clearing.
4 Only materials and accessories from ILECO-1 such as pole, transformer, and kWhr meter if
applicable) are included in this estimate.
5 Service drop conductor insulated copper wire from transformer bushing to kWhr meter to service entrance
is not included in this cost estimate.
6 The applicant must install a circuit breaker accessible to ILECO-1 line crew.
consumer / accounting / billing / ISD
ILOILO 1 ELECTRIC COOPERATIVE, INC.
( ILECO-1 )
Tigbauan, Iloilo
December 3, 2022
SUB-TOTAL 10,000.00
ENGR. GC JUNE GARANCHON ENGR. MIGUEL A. PAGUNTALAN JR. KRIS WYROL JEZ FERNANDEZ ASTROLOGO
TSD Manager General Manager Signature Over Printed Name of Applicant
Notes:
1 Installation jobs near LIVE circuit should be conducted during NGCP scheduled BLACK-OUT
2 The Cost of Hauling is applicable only from ILECO-1 main office up to the last accesable road by the
ILECO-1 service vehicle.
3 The consumer is responsible for the Right-of-Way acquisition and line clearing.
4 Only materials and accessories from ILECO-1 such as pole, transformer, and kWhr meter if
applicable) are included in this estimate.
5 Service drop conductor insulated copper wire from transformer bushing to kWhr meter to service entrance
is not included in this cost estimate.
6 The applicant must install a circuit breaker accessible to ILECO-1 line crew.
consumer / accounting / billing / ISD
ILOILO 1 ELECTRIC COOPERATIVE, INC.
( ILECO-1 )
Tigbauan, Iloilo
December 3, 2022
SUB-TOTAL 10,000.00
ENGR. GC JUNE GARANCHON ENGR. MIGUEL A. PAGUNTALAN JR. VIC BRYAN OCHON
TSD Manager General Manager Signature Over Printed Name of Applicant
Notes:
1 Installation jobs near LIVE circuit should be conducted during NGCP scheduled BLACK-OUT
2 The Cost of Hauling is applicable only from ILECO-1 main office up to the last accesable road by the
ILECO-1 service vehicle.
3 The consumer is responsible for the Right-of-Way acquisition and line clearing.
4 Only materials and accessories from ILECO-1 such as pole, transformer, and kWhr meter if
applicable) are included in this estimate.
5 Service drop conductor insulated copper wire from transformer bushing to kWhr meter to service entrance
is not included in this cost estimate.
6 The applicant must install a circuit breaker accessible to ILECO-1 line crew.
consumer / accounting / billing / ISD
ILOILO 1 ELECTRIC COOPERATIVE, INC.
( ILECO-1 )
Tigbauan, Iloilo
December 3, 2022
SUB-TOTAL 10,000.00
Notes:
1 Installation jobs near LIVE circuit should be conducted during NGCP scheduled BLACK-OUT
2 The Cost of Hauling is applicable only from ILECO-1 main office up to the last accesable road by the
ILECO-1 service vehicle.
3 The consumer is responsible for the Right-of-Way acquisition and line clearing.
4 Only materials and accessories from ILECO-1 such as pole, transformer, and kWhr meter if
applicable) are included in this estimate.
5 Service drop conductor insulated copper wire from transformer bushing to kWhr meter to service entrance
is not included in this cost estimate.
6 The applicant must install a circuit breaker accessible to ILECO-1 line crew.
consumer / accounting / billing / ISD
ILOILO 1 ELECTRIC COOPERATIVE, INC.
( ILECO-1 )
Namocon, Tigbauan, Iloilo
ACCOUNT NO.:
Notes:
1 Installation jobs near LIVE circuit should be conducted during NGCP scheduled BLACK-OUT
2 The Cost of Hauling is applicable only from ILECO-1 main office up to the last accesable road by the
ILECO-1 service vehicle.
3 The consumer is responsible for the Right-of-Way acquisition and line clearing.
4 Only materials and accessories from ILECO-1 such as pole, transformer, and kWhr meter if
applicable) are included in this estimate.
5 Service drop conductor insulated copper wire from transformer bushing to kWhr meter to service entrance
is not included in this cost estimate.
6 The applicant must install a circuit breaker accessible to ILECO-1 line crew.
consumer / accounting / billing / ISD
ILOILO 1 ELECTRIC COOPERATIVE, INC.
( ILECO-1 )
Namocon, Tigbauan, Iloilo
ACCOUNT NO.:
OTHERS
Notes:
1 Installation jobs near LIVE circuit should be conducted during NGCP scheduled BLACK-OUT
2 The Cost of Hauling is applicable only from ILECO-1 main office up to the last accesable road by the
ILECO-1 service vehicle.
3 The consumer is responsible for the Right-of-Way acquisition and line clearing.
4 Only materials and accessories from ILECO-1 such as pole, transformer, and kWhr meter if
applicable) are included in this estimate.
5 Service drop conductor insulated copper wire from transformer bushing to kWhr meter to service entrance
is not included in this cost estimate.
6 The applicant must install a circuit breaker accessible to ILECO-1 line crew.
consumer / accounting / billing / ISD
December 3, 2022
Notes:
1 Installation jobs near LIVE circuit should be conducted during NGCP scheduled BLACK-OUT
2 The Cost of Hauling is applicable only from ILECO-1 main office up to the last accesable road by the
ILECO-1 service vehicle.
3 The consumer is responsible for the Right-of-Way acquisition and line clearing.
4 Only materials and accessories from ILECO-1 such as pole, transformer, and kWhr meter if
applicable) are included in this estimate.
5 Service drop conductor insulated copper wire from transformer bushing to kWhr meter to service entrance
is not included in this cost estimate.
6 The applicant must install a circuit breaker accessible to ILECO-1 line crew.
Cc: consumer / accounting / billing / ISD