A Standard Method Statement

TITLE PROJECT: CADANGAN MEMBINA DAN MENYIAPKAN MASJID DAERAH KINTA, BANDARAYA IPOH, PERAK

1. PREPARED BY: NORAIN SYUHADA BINTI ZULHIME 3. DATE: 25 MAY 2022


2. ELEMENT: WALL (UCO SOLID PANEL) 4. PAGE: 1

TASK QUANTITY SEQUENTIAL MACHINERY MANPOWER/ DURATION


NO
DIAGRAM TOOLS LABOUR
1. Make sure the surface is clean as 196.58m²  String  2 Skilled  1 day
site preparation mark the areas  Measuring Labour
with string or oil string and Tape
measuring tape to measure the
position.

2. With the guide of the mark 196.58m²  String  2 Semi-  1 day


earlier, install the bottom track  Measuring Skilled
align with and hold it in place Tape Labour
with small nails or clamps. Then  Screws
screw through the pre-drilled
holes with 1 ½ “screws.
3. Plaster the Sika Ceram 228 at 196.58m²  Trowel  2 Semi-  2 days
only one edge of the panels. Sika Skilled
Ceram 288 was mixed with water Labour
using whisk blender to achieve a
perfect combination. Then, fully
patch the Sika Ceram 288 at one
of the panel’s edges. A moist
sponge was used to flatten excess
Sika Ceram 288.

NO TASK QUANTITY SEQUENTIAL MACHINERY MANPOWER/


DIAGRAM TOOLS LABOUR
4. Next, the panel the panel on 196.58m²  UCO Wall  3 Semi-  3 days
which Sika Ceram 288 has been Panel Skilled
placed is lifted and placed  1" x 2" wood Labour
vertically on the bottom track.
The 1" x 2" wood is used to
support the panels that have been
placed on the bottom track.
5. Then, water levels are used No  Water Level  1 Semi-  1 day
vertically and horizontally to Skilled
check and ensure each panel Labour
placed on the bottom track is in
the proper position.
6. Connecting devices are mounted NO  Drilling  3 Semi-  2 days
on each bottom of the panel for  Hammer Skilled
the purpose of panel rigidity. In Labour
this step, the bottom track is
drilled and fitted with a Y10
grade “7-shape” dowel bar. A
hammer is used to install the Y10
“7-shape” dowel bar on each side
of the bottom corner of the panel.

NO TASK QUANTITY SEQUENTIAL MACHINERY MANPOWER/ DURATION


DIAGRAM TOOLS LABOUR
7. The panels are marked and cut NO  Drilling  2 Skilled  2 days
according to the approved Hammer Labour
drawing measurements for the  Saw
purpose of door and window Machine
openings. The surface of the
panel to be cut is moistened with
water to facilitate the cutting
process using a circular saw
machine.
8. Install of ‘locks’ on each side of NO  Hammer  2 Semi-  2 days
the panel surface and on the top  R6 Skilled
of the panel. a “stapler-shape” Labour
steel reinforcement link of grade
R6 is installed as a ‘lock’ at the
connection between the two
surfaces of the panel that is at the
bottom, middle and top of the
wall.
9. Applying the fiberglass mesh 196.58m²  Fibre Mesh  2 Semi-  1 day
with bitumen between the gap on  Bitumen Skilled
the wall. his step is like gluing Labour
the wall to make it stronger and
tougher for a long time. Bitumen
will provide a water-resistant
wall, so that the rain from outside
can’t go through between the
wall.