ESTIMATED QUANTITIES

Construction of Triple-Barrel Box Culvert


Quezon, Isabela

At Intlet Transition
Class "A"Concrete
Ihead wall = 10.20 x 3.00 x 0.30 = 9.18 cu.m.

Icut-off wall = 16.80 x 1.00 x 0.20 = 3.36 cu.m.

Iflooring = 17.40 + 10.80 x 4.60 x 0.15 = 9.73 cu.m.


2.00

Iside wall = 2.38 + 0.60 x 3.40 x 0.30


2.00
= 1.52 x 2.00 = 3.04 cu.m.

Ifillet = 0.15 x 0.15 x 10.20 = 0.11 cu.m.


2.00

Subtotal = 22.06 cu.m.


At Outlet Transition
Class "A"Concrete
Ohead wall = 10.20 x 3.00 x 0.30 = 9.18 cu.m.

Ocut-off wall = 16.80 x 1.00 x 0.20 = 3.36 cu.m.

Oflooring = 17.40 + 10.80 x 4.60 x 0.15 = 9.73 cu.m.


2.00

Oside wall = 2.38 + 0.60 x 3.40 x 0.30


2.00
= 1.52 x 2.00 = 3.04 cu.m.

Ofillet = 0.15 x 0.15 x 10.20 = 0.11 cu.m.


2.00

Subtotal = 22.06 cu.m.


At Barrel
Class "A"Concrete
Barrel = 10.20 x 2.70 x 10.10 = 88.07 cu.m.
+ 2x 0.15 + 0.25 x 0.20 x 10.10
2.00
- 3.00 x 2.10 x 10.10 x 3.00

Subtotal = 88.07 cu.m.


Total Class"A" concrete = 132.20 cu.m.

Reinforcing Steel Bar (RSB)


W1 = 132.20 x 104.13 = 13,765.85 kgs
Total = 13,765.90 kgs

Lean Concrete
V = 8.08 x 10.20 x 0.05 = 23.02 cu.m.
+ 2x 8.68 + 17.40 x 3.60 x 0.05
2.00
Total = 23.10 cu.m.

Common Earth Excavation


V = 3.60 x 8.08 x 0.50 x 2.00 = 29.09 cu.m.
Total = 29.10 cu.m.

Side Borrow
V = 3.60 x 16.80 x 2.38 x 2.00 = 74.71 cu.m.
- 2x 8.08 + 16.80 x 3.60 x 2.38
2.00 Total = 74.80 cu.m.

S U M M A R Y

Common Earth Excavation = 29.10 cu.m.


Class "A" Conc., 211 kgsc = 132.20 cu.m.
Reinforcing Steel Bars
a. Furnishing & Stockfilling = 13,765.90 kg
b. Cutting, Bending &Placing = 13,765.90 kg
Lean Concrete = 23.10 cu.m.
Side Borrow = 74.80 cu.m.

Prepared by : Checked & Submitted by:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Draftsman II Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
Office of the Municipal Engineer

PROJECT : PROPOSED FENCE FOR BARANGAY CALLANGIGAN


OWNER : LGU - QUEZON, ISABELA
LOCATION : CALLANGIGAN, QUEZON, ISABELA
###

BILL OF QUANTITIES/BILL OF MATERIALS


SUMMARY
DESCRIPTION UNIT QUANTITY UNIT COST AMOUNT
II. EARTHWORKS
Structure Excavation cu.m. 35.00 312.64 10,942.40
Embankment from structure excavation cu.m. 31.00 126.52 3,922.12
Gravel bedding cu.m. 6.40 630.00 4,032.00
III. CONCRETE WORKS
Structural Concrete(Class A, 28 days) cu.m. 9.00 12,551.39 112,962.51
Reinforcing Steel of Reinforced Concrete Structures kgs. 585.47 0.38 222.48
IV. FORMWORKS
Forms sq.m. 167.84 182.44 30,620.73
V. MASONRY WORKS
100 mm CHB (Non load bearing) sq.m. 76.80 429.78 33,007.10
Cement plaster finish sq.m. 102.40 97.05 9,937.92
IV. STEELWORKS
Interlinks sq.m. 77.00 211.05 16,250.85
1 1/4" ∅ GI Pipe ln.m. 128.00 145.73 18,653.44
TOTAL ESTIMATED DIRECT COST 240,551.55
APPROVED BUDGET FOR THE CONTRACT 240,551.55

Prepared by:

ENGR. ERNESTO G. LOPEZ JR.


Draftsman II

Concurred by: Approved by:

HON. MARCELINO MINA HON. BUENVENIDO RUIZ


KAGAWAD, CHAIRMAN COMMITTEE OF INFASTRUCTURE BARANGAY CAPTAIN
Address: Samonte, Quezon, Isabela│Email add: lguquezonisabela@gmail.com │Website: https://quezonisabela.gov.ph
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
Office of the Municipal Engineer

PROPOSED FENCE FOR BARANGAY CALLANGIGAN


ESTIMATED QUANTITIES

FENCE
Fence Length : 65.00 m
No. of Corners : 1.00
Gate Length : 1.00 m
Span per Column : 3.00 m
CHB Height : 1.20 m
Footing Dimension
Depth : 0.80 m
Length : 0.60 m
Width : 0.60 m
Thickness : 0.20 m
Gravel Bedding Thickness : 0.10 m
Column Dimension
Length : 0.20 m
Width : 0.20 m
Height : 2.95 m
Beam Dimension
Width : 0.10 m
Depth : 0.15 m
Wall Footing Dimension
Width : 0.30 m
Depth : 0.20 m

1. C"A"C
Footing
V = Length x Width x Thickness x No. of pcs
V = 0.60 x 0.60 x 0.20 x 24.00
V = 1.73 cu.m.

Column
V = Length x Width x Height x No. of pcs
V = 0.20 x 0.20 x 2.95 x 24.00
V = 2.83 cu.m.

Beam
V = Width x Depth x Length
V = 0.10 x 0.15 x 59.20
V = 0.89 cu.m.

Wall Footing
V = Width x Depth x Length
V = 0.30 x 0.20 x 59.20
V = 3.55 cu.m.

TOTAL = 9.00 cu.m. or Cement 86.00 bags


Sand 9.00 cu.m.
Gravel 5.00 cu.m.

2. RSB
Footing
W = Length x No. of Pcs of RSB 1 side x 2 way x No. of pcs of Footing x Weight of 10mm RSB/m
W = 0.50 x 3.00 x 2.00 x 24.00
W = 72.00 x 0.62
W = 44.35 kgs.

Column
W = Length x No. of Pcs of RSB x No. of pcs of Column x Weight of 10mm RSB/m
W = 3.09 x 4.00 x 24.00 x 0.62
W = 182.43 kgs.

Beam
Main bars W = Length x No. of Pcs of RSB x Weight of 10mm RSB/m x Wasteage Factor
W = 64.12 x 2.00 x 0.62 x 1.05
W = 82.95 kgs.
Ties W = Length x No. of Pcs of RSB x Weight of 10mm RSB/m
W = 0.27 x 161.00 x 0.62
W = 26.78 kgs.

Wall Footing
Main bars W = Length x No. of Pcs of RSB x Weight of 10mm RSB/m x Wasteage Factor
W = 64.12 x 2.00 x 0.62 x 1.05
W = 82.95 kgs.
Ties W = Length x No. of Pcs of RSB x Weight of 10mm RSB/m
W = 0.42 x 215.00 x 0.62
W = 55.62 kgs.

Interlinks Hook bars


Vertical W = Length x No. of Pcs of RSB x No. of spans x Weight of 10mm RSB/m
W = 1.20 x 2.00 x 21.33 x 0.62
W = 31.54 kgs.
Horizontal W = Length x No. of Pcs of RSB x No. of spans x Weight of 10mm RSB/m
W = 3.00 x 2.00 x 21.33 x 0.62
W = 78.85 kgs.

TOTAL = 585.47 kgs. or 257.00


pcs 10mm dia. RSB

3. CHB
A = Length x Height
A = 64.00 x 1.20
A = 76.80 sq.m. or 960.00 pcs

4. Gravel Bedding
V = Length x thickness
V = 64.00 x 0.10
V = 6.40 cu.m. or 80.00 pcs

5. Structure Excavation
V = Length x Width x depth
V = 64.00 x 0.60 x 0.90
V = 35.00 cu.m. or 438.00 pcs

6. Structure Backfill from excavation


V = Excavation - Vol of Footing - Vol of Column neck - Vol of buried CHB Wall
V = 35.00
- 1.73
- 0.58
- 2.56
V = 31.00 cu.m. or 388.00 pcs

7. 1 1/4" ∅ GI Pipe
L = Length/span x no. of pcs/span x No. of spans
L = 3.00 x 2.00 x 21.33
L = 128.00 ln.m. or 22.00 pcs

8. 4"x4" Interinks
A = Height x Length x No. of spans
A = 1.20 x 3.00 x 21.33
A = 77.00 sq.m. or 13.00 pcs

9. Forms
A = Area of Column, Footing, Beam and Wall Footing
A = 56.64 + 46.08 + 23.68 + 41.44
A = 167.84 sq.m. or 28.00 pcs

10. Cement Plaster Finish


A = Area of exposed CHB Wall
A = 0.80 x 64.00 x 2.00
A = 102.40 sq.m. or 18.00 pcs

Prepared by: Concurred by:

Engr. ERNESTO G. LOPEZ JR.


Draftsman II KAGAWAD, CHAIRMAN COMMITTEE OF INFRA.

Approved by:

HON. RUIZ
BARANGAY CAPTAIN

Address: Samonte, Quezon, Isabela│Email add: lguquezonisabela@gmail.com │Website: https://quezonisabela.gov.ph


Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

DERIVATION OF UNIT COST


CONSTRUCTION SURVEY
PROPOSED FENCE FOR BARANGAY CALLANGIGAN

I. Daily Rates to be used.


Basic ACA/ 12% GSIS TOTAL
DESIGNATION Philhealth Pag-Ibig Fund SG
Rate PERA Gov't. Share
1 Engineer 1,047.45 90.91 13.07 125.69 4.55 1,281.67 /day 14
2 Engineering Asst. A 784.31 90.91 9.66 94.12 4.55 983.55 /day 10
3 Driver 631.36 90.91 7.39 75.76 4.55 809.97 /day 7
4 Survey Aide A 587.31 90.91 6.82 70.48 4.55 760.07 /day 6
5 Utility Worker 409.09 90.91 5.11 49.09 4.55 558.75 /day 1

II. Equipment Rental

EQUIPMENT RENTAL FUEL CONSUMPTION


1 Pick-Up 4x4 313.95 /hr. 8.00 lit/hr.
note: Cost of Fuel = 41 /liter

*Assumptions:
1. Establishment of Vertical & Horizontal Control is a one-time activity.
2. The Conduct of Profile and Cross Section Survey shall be at least once a month which shall serve as a
basis in the preparation of Monthly Statistical Report/Status Report as a requisite for Contract Billing, Monthly
Progress Report and other similar report which survey results maybe needed. Profile & Cross Section Survey
may be conducted as often as needed depending on the needed data to be gathered.
3. For presentation, profile & cross section survey shall be conducted on (1) Stake-Out Surveys (2) Once a month
in a year.
No. of Surveys = 1 Profile & Cross-Section Surveys
PROGRAMMED LENGTH OF ROAD : 2.00 km.
A. ESTABLISHMENT OF VERTICAL & HORIZONTAL CONTROL
Length of Canal : 2.10 km.
Capability : 5 km./day
Cycle Time:
2.10 km.
No. of Days = = 0.42 days
5 km./day
25 km x 1 day
Travel Time = = 0.13 days
25 kph x 8 hr
Total Number of Days = 0.55 days
say 0.50 days
or in Hours = 4.00 hours
1. Labor
1- Engineer x 1,281.67 /day x 0.50 days = 640.84
1- Instrumentation x 983.55 /day x 0.50 days = 491.78
1- Survey Aide x 760.07 /day x 0.50 days = 380.04
1- Driver x 809.97 /day x 0.50 days 404.99
5- Utility Worker x 558.75 /day x 0.50 days = 1,396.88
Total Labor Cost = 3,314.51
2. Equipment Utilization
utilized = Pick-Up 4x4
rental = 313.95 /hr.

Page 8
Fuel = 8.00 lit/hr x 41.00 /lit. 4.00 hrs. = 1,312.00
Spare Parts = 313.95 /hr. x 4.00 hrs. = 1,255.80

SUMMARY
a. Labor = 3,314.50
b. Spare Parts = 1,255.80
c. Fuel = 1,312.00
UNIT COST = 5,882.30

B. PROFILE SURVEY
Length of Canal : 2.00 km.
Capability : 2 km./day
Cycle Time:
2.00 km.
No. of Days = = 1.00 days
2 km./day

25 km x 1 day
Travel Time = = 0.13 days
25 kph x 8 hr
Total Number of Days = 1.13 days
say 1.50 days
or in Hours = 12.00 hours
1. Labor
1- Engineer x 1,281.67 /day x 1.50 days = 1,922.51
1- Instrumentation x 983.55 /day x 1.50 days = 1,475.33
1- Survey Aide x 760.07 /day x 1.50 days = 1,140.11
1- Driver x 809.97 /day x 1.50 days 1,214.96
5- Utility Worker x 558.75 /day x 1.50 days = 4,190.63
Total Labor Cost = 9,943.52

2. Equipment Utilization
utilized = Pick-Up 4x4
rental = 313.95 /hr.
Fuel = 8.00 lit/hr x 41.00 /lit. x 12.00 hrs. = 3,936.00
Spare Parts = 313.95 /hr. x 12.00 hrs. = 3,767.40

SUMMARY
a. Labor = 9,943.52
b. Spare Parts = 3,767.40
c. Fuel = 3,936.00
UNIT COST = 17,646.92

C. CROSS SECTION SURVEY


Length of Canal : 2.00 km.
Capability : 0.4 km./day
Cycle Time:
2.00 km.
No. of Days = = 5.00 days
0.4 km./day
25 km x 1 day
Travel Time = = 0.13 days
25 kph x 8 hr
Total Number of Days = 5.13 days
say 5.50 days
or in Hours = 44.00 hours
1. Labor
1- Engineer x 1,281.67 /day x 5.50 days = 7,049.19
1- Instrumentation x 983.55 /day x 5.50 days = 5,409.53
1- Survey Aide x 760.07 /day x 5.50 days = 4,180.39
1- Driver x 809.97 /day x 5.50 days 4,454.84

Page 9
5- Utility Worker x 558.75 /day x 5.50 days = 15,365.63
Total Labor Cost = 36,459.56

Page 10
2. Equipment Utilization
utilized = Pick-Up 4x4
rental = 313.95 /hr.
Fuel = 8.00 lit/hr x 41.00 /lit. x 44.00 hrs. = 14,432.00
Spare Parts = 313.95 /hr. x 44.00 hrs. = 13,813.80

SUMMARY
a. Labor = 36,459.56
b. Spare Parts = 13,813.80
c. Fuel = 14,432.00
UNIT COST = 64,705.36
D. PLOTTING AND COMPUTATION
1. Profile
Length of Canal : 2.00 km.
1. Materials/Office Supplies
Cross Section Paper = 150.00 /km. x 2.00 km. = 300.00
Data Book = 50.00 /km. x 2.00 km. = 100.00
Miscellaneous = 45.00 /km. x 2.00 km. = 90.00
Total Materials Cost 490.00
2. Labor
Length of Canal : 2.00 km.
Capability : 8 km./day
Cycle Time:
2.00 km.
No. of Days = = 0.25 days
8 km./day
Total Number of Days = 0.25 days
say 0.50 day
1- Engineering Asst. A x 1,281.67 /day x 0.50 days = 640.84
Sub-Total = 640.84
SUMMARY
a. Materials Cos = 490.00
b. Labor Cost = 640.84
UNIT COST = 1,130.84

2. Cross-Section
Length of Canal : 2.00 km.
1. Materials/Office Supplies
Cross Section Paper = 350.00 /km. x 2.00 km. = 700.00
Data Book = 75.00 /km. x 2.00 km. = 150.00
Miscellaneous = 55.00 /km. x 2.00 km. = 110.00
Total Materials Cost 960.00
2. Labor
Length of Canal : 2.00 km.
Capability : 0.4 km./day
Cycle Time:
2.00 km.
No. of Days = = 5.00 days
0.4 km./day
Total Number of Days = 5.00 days
say 5.00 day
1- Engineering Asst. A x 1,281.67 /day x 5.00 days = 6,408.35
Sub-Total = 6,408.35
SUMMARY
a. Materials Cos = 960.00
b. Labor Cost = 6,408.35
UNIT COST = 7,368.35

Page 11
SUMMARY FOR PROFILE AND CROSS-SECTION SURVEY
Materials/Office
a. = 1,450.00 /survey x 1 surveys = 1,450.00
Supplies
b. Labor = 53,452.26 /survey x 1 surveys = 53,452.30
c. Spare Parts = 17,581.20 /survey x 1 surveys = 17,581.20
d. Fuel = 18,368.00 /survey x 1 surveys = 18,368.00
UNIT COST = 90,851.50

RECAPITULATION (inclusive of item "A")


Materials/
a. Office = 1,450.00
Supplies
b. Labor = 56,766.80
d. Spare Parts = 18,837.00
e. Fuel = 19,680.00
UNIT COST = 96,733.80

Prepared by: Checked and Submitted by:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer A Acting Municipal Engineer

Page 12
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROGRAM OF WORK/BUDGET COST

Project : PROPOSED FENCE FOR BARANGAY CALLANGIGAN


Location :
Station Limits : STA. 0+000 - STA. 2+000
Appropriation :
Source of Fund :

DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT


A. OTHER GENERAL REQUIREMENTS 1.00 L.S. 324,885.85 324,885.85
B. EARTHWORKS 1.00 L.S. Err:509 Err:509
C. SUBBASE AND BASE COURSE 1.00 L.S. Err:509 Err:509
D. SURFACE COURSE 1.00 L.S. Err:509 Err:509
E. CHB CANAL LINING 1.00 L.S. 2,782,155.15 2,782,155.15
TOTAL CIVIL WORKS COST Err:509

BREAKDOWN OF EXPENDITURES
AS SUBMITTED AS SUBMITTED
1. Labor Err:509 A. Total Direct Cost Err:509
2. Materials Err:509 B. OCM & Profit Err:509
3. Rental of Equipment Err:509 C. Value Added Tax Err:509
4. Provisional Sum D. Total Construction Cost
5. OCM & Profit Err:509 E. Eng'g & Admin. Overhead, %
6. Value Added Tax Err:509 F. RROW Acquisition
7. EAO, % G. Contingency 2,372,253.88
8. RROW Acquisition
9. Contingency 2,372,253.88
10. TOTAL ESTIMATED COST Err:509 H. TOTAL ESTIMATED COST Err:509

Prepared by: Recommending Approval:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer

Approved by:

Hon. JIMMY S. GAMAZON JR.


Municipal Mayor
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED FENCE FOR BARANGAY CALLANGIGAN

APPROVED BUDGET FOR THE CONTRACT


DESCRIPTION QTY UNIT ESTIMATED DIRECT COST OCM & PROFIT VAT TOTAL INDIRECT COST TOTAL COST
A. OTHER GENERAL REQUIREMENTS 1.00 L.S.
371,262.40 49,445.20 2,472.30 51,917.50 423,179.90
B. EARTHWORKS 1.00 L.S.
Err:509 Err:509 Err:509 Err:509 Err:509
C. SUBBASE AND BASE COURSE 1.00 L.S.
Err:509 Err:509 Err:509 Err:509 Err:509
D. SURFACE COURSE 1.00 L.S.
Err:509 Err:509 Err:509 Err:509 Err:509
E. CHB CANAL LINING 1.00 L.S.
Err:509 Err:509 Err:509 Err:509 Err:509
TOTAL Err:509 Err:509 Err:509 Err:509 Err:509

Prepared by: Recommending Approval:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer

Approved by:

Hon. JIMMY S. GAMAZON JR.


Municipal Mayor
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED FENCE FOR BARANGAY CALLANGIGAN

APPROVED BUDGET FOR THE CONTRACT


DESCRIPTION QTY UNIT UNIT COST ESTIMATED DIRECT COST OCM & PROFIT VAT TOTAL INDIRECT COST TOTAL COST

A. OTHER GENERAL REQUIREMENTS

A.1.4(1) Provision of Progress Photographs 1.00 ea. 15.75 15.75 - 15.75

B.5 Project Billboard / Signboard 1.00 L.S. 3,720.00 3,720.00 744.00 223.20 967.20 4,687.20

B.7(2) Occupational Safety and Health Program 1.00 L.S. 242,050.00 242,050.00 48,410.00 2,420.50 50,830.50 292,880.50

A.4. Mobilization and Demobilization 1.00 L.S. 27,302.40 27,302.40 - - - 27,302.40

TOTAL OF PART A 273,088.15 51,797.70 324,885.85

B. EARTHWORKS

B.1. Clearing and Grubbing Err:509 sq.m. 15.40 Err:509 3.10 1.00 Err:509 Err:509

B.2. Common Excavation Err:509 cu.m. 116.50 Err:509 23.30 7.00 Err:509 Err:509

B.4. Foundation Fill Err:509 cu.m. 462.40 Err:509 106.30 19.60 Err:509 Err:509

B.5. Disposal of excess materials - cu.m. 193.80 - 38.80 11.60 - -

TOTAL OF PART B Err:509 Err:509 Err:509

D. SURFACE COURSE

D.1. Portland Cement Concrete Pavement, 0.23m. THK. 1.73 cu.m. 7,604.30 13,140.23 1,520.90 222.50 3,012.60 16,152.83

D.1. RSB Furnishing and Stockpilling Err:509 cu.m. 58.60 Err:509 11.70 0.60 Err:509 Err:509

D.1. RSB Cut, Bend & Place Err:509 cu.m. 11.90 Err:509 2.40 0.70 Err:509 Err:509

TOTAL OF PART D Err:509 Err:509 Err:509

E. TRIPLE-BARREL BOX CULVERT

E.1. Structure Excavation 29.10 cu.m. 87.40 2,543.34 17.50 5.30 663.48 3,206.82

E.2. Class "A" Concrete 132.20 cu.m. 9,130.30 1,207,013.79 1,826.10 214.20 269,725.01 1,476,738.80

E.3. RSB Furnishing and Stockpilling 13,765.90 cu.m. 58.60 806,681.74 11.70 0.60 169,320.57 976,002.31

E.4. RSB Cut, Bend & Place 13,765.90 cu.m. 11.90 163,814.21 2.40 0.70 42,674.29 206,488.50

E.5. Lean Concrete 23.10 cu.m. 1,532.60 35,403.06 306.50 19.30 7,525.98 42,929.04

E.6. Structural Backfill 74.80 cu.m. 841.20 62,921.76 168.20 17.20 13,867.92 76,789.68

TOTAL OF PART E 2,278,377.90 503,777.25 2,782,155.15

GRAND TOTAL Err:509 Err:509 Err:509

Prepared by: Recommending Approval:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Draftsman II Municipal Engineer

Approved by:

Hon. JIMMY S. GAMAZON JR.


Municipal Mayor
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

Base Data of Hauling Distances of Construction Materials

Hauling Distances (km.)


Type I Type II Type III Type IV Type V
Base Cost/ Good Poorly
Item Description Source Location Unit Good Poorly
Quarry Fee Maintained Maintained Manual Total
Maintained Maintained
Concrete/ Concrete/ Gravel Road Gravel Road Hauling Distance
Asphalt Asphalt
1 Cement Roxas, Isabela 276.00 bag 22.00 - - 1.00 23.00
2 Form Lumber Roxas, Isabela 55.00 bd. Ft. 22.00 - - 1.00 23.00
3 1/2" Marine Plywood Roxas, Isabela 850.00 pc. 22.00 - - 1.00 23.00
4 Reinforcing Steel Bar Roxas, Isabela 55.00 kg.
5 Common Wire Nail Roxas, Isabela 90.00 kg. 22.00 - - 1.00 23.00
6 Tie Wire Roxas, Isabela 100.00 kg.
7 Plain GI Sheet Roxas, Isabela 65.00 lin.m. 22.00 - - 1.00 23.00
2 Sand & Gravel Pinukpok, Kalinga Quarry 120.00 cu.m. 51.00 - - 2.00 53.00
9 Boulder Pinukpok, Kalinga Quarry 150.00 cu.m. 53.00 - - 5.00 58.00
10 Concrete Hollow Blocks
10 a. 4" THK Roxas, Isabela 12.00 pc. 22.00 - - 1.00 23.00
12 b. 5" THK Tuguegarao City 15.00 pc. 22.00 - - 4.00 0.30 26.30
13 GI Pipes, 2" Diameter Tuguegarao City 55.00 lin.m.
22.00 - - 4.00 0.30 26.30
14 PVC Pipe, 2" Diameter Tuguegarao City 42.00 lin.m.
15 Gabion (1m x 1m x 2m) Manila 2,500.00 pc.
550.00 - - 4.00 0.30 554.30
16 Mattress (.3m x 2m x 6m) Manila 2,800.00 pc.
17 Coconet CGN 400 Manila 85.00 sq.m.
550.00 - - 4.00 0.30 554.30
18 Vetiber Grass Manila 75.00 sq.m.
11 Steel Paving Forms 4"x10"x10'x1/8" Roxas, Isabela 780.00 pc. 22.00 - - 1.00 23.00
11 Road Form Stakes Roxas, Isabela 780.00 pc. 22.00 - - 1.00 23.00

Prepared by: Approved by:


Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG
Engineer Acting Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

DERIVATION OF UNIT COST


(FORCE ACCOUNT WORKS)

II. Equipment Rental


"Schedule "B" of the Revised Rental Rates"
EQUIPMENT RENTAL FUEL CONSUMPTION
1 160 HP DOZER 1,303.34 /hr. 17.00 lit/hr.
2 LOADER 1.0 m3 734.09 /hr. 9.00 lit/hr.
3 6X6 CARGO TRUCK 304.23 /hr. 15.00 lit/hr.
4 1 BAGGER MIXER 99.14 /hr. 1.26 lit/hr.
note: Cost of Fuel = 41 /liter
III. Hauling of Construction Materials
1. Cement
Hauling from Source to Dumpsite
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 304.23 /hr.
Labor per day = 5 - Laborers x /day = - /day
Base Cost = 276.00 /bag
Capacity of Truck = 150 bags/trip
Capability of five (5) Laborers
Loading = 300 bags/hr
Unloading = 300 bags/hr
a. Hauling from Source To Dump Site
Cycle Time
with load = 22.00 kms. / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = - kms. / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / 25.00 km./hr. = 0.04 hrs./trip
Loading = 150 bags/trip / 300 bags/hr = 0.50 hrs./trip
Unloading = 150 bags/trip / 300 bags/hr = 0.50 hrs./trip
total time = 2.21 hrs./trip
EQUIPMENT:
41.00 lit/hr x 1.21 hrs/trip x 41 /liter
Fuel = = 13.53 /bag
150 bags/trip
304.23 /hr. x 2.21 hrs/trip
Spare Parts = = 4.48 /bag
150 bags/trip
note: Time for Loading & Unloading and Manual Hauling were excluded from the fuel consumption.
Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 558.75 /day
Capability : 1 bag/trip
Cycle Time
with load = - kms. / 2.00 km./hr. = - hrs./trip
T-V
without load = - kms. / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
SUMMARY:
Base Cost = 276.00 /bag
Fuel Cost = 13.53 /bag
Spare Parts = 4.48 /bag
TOTAL = 294.01 /bag
6. Sand and Gravel
a. Quarrying
Utilized : 160 HP Dozer
Production : 65 cu. m./hr.
Rental : 1,303.34 /hr. (incl. Fuel & operator)
EQUIPMENT:
17.00 lit/hr x 41 /liter
Fuel = = 10.72 /cu.m.
65 cu. m./hr.
1,303.34 /hr.
Spare Parts = = 20.05 /cu.m.
65 cu. m./hr.

b. Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 734.09 /hr. (incl. Fuel & operator)
EQUIPMENT:
9.00 lit/hr x 41 /liter
Fuel = = 6.71 /cu.m.
55 cu. m./hr.
734.09 /hr.
Spare Parts = = 13.35 /cu.m.
55 cu. m./hr.

c. Hauling
c.1. Hauling from Quarry Site to Dumpsite
AHD = 53.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 51.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 2.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 304.23 /hr.
Labor per day = 5 - Laborers x /day = - /day
Base Cost = 120.00 /cu.m.
Capacity of Truck = 4 cu.m./trip
Capability of five (5) Laborers
Cycle Time
with load = 51.00 kms. / 35.00 km./hr. = 1.46 hrs./trip
T-I
without load = 51.00 kms. / 45.00 km./hr. = 1.13 hrs./trip
with load = - kms. / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = - kms. / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = 2.00 kms. / 20.00 km./hr. = 0.10 hrs./trip
T-IV
without load = 2.00 kms. / 25.00 km./hr. = 0.08 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 2.89 hrs./trip
EQUIPMENT:
15.00 lit/hr x 2.77 hrs/trip x 41 /liter
Fuel = = 425.96 /cu.m.
4 cu.m./trip
304.23 /hr. x 2.89 hrs/trip
Spare Parts = = 219.59 /cu.m.
4 cu.m./trip

SUMMARY:
SAND GRAVEL
Base Cost = 120.00 /cu.m. = 120.00 /cu.m.
Fuel Cost = 425.96 /cu.m. = 425.96 /cu.m.
Spare Parts = 219.59 /cu.m. = 219.59 /cu.m.
TOTAL = 765.55 /cu.m. = 765.55 /cu.m.

SUMMARY

Base Hauling Cost


Materials
Cost Labor Depreciation Spare Part Fuel Total
1 Cement 276.00 - - 4.48 13.53 294.01
2 Sand 120.00 - - 219.59 425.96 765.55
3 Gravel 120.00 - - 219.59 425.96 765.55
IV. Items of Works
A. CONCRETING WORKS
1. Class "A" Reinforced Concrete (Road concreting, Brgy Road)
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 9.50 2,622.00 - - 42.53 128.55
Sand 0.45 54.00 - - 98.81 191.68
Gravel 0.90 108.00 - - 197.63 383.36
TOTAL 2,784.00 - - 338.98 703.60

c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
9.50 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 1.583 hr./cu.m.
60 min./hr.
Fuel = 1.26 lit./hr. x 1.5833 hr./cu.m. x 41 /liter = 81.80 /cu.m.
Spare Parts = 99.14 /hr. x 1.5833 hr./cu.m. x = 156.97 /cu.m.

SUMMARY
a. Materials = 2,784.00 /cu.m.
c. Depreciation = - /cu.m.
d. Spare Parts = 495.95 /cu.m.
e. Fuel = 785.39 /cu.m.
UNIT COST = 4,065.34 /cu.m.

Prepared by: Recommending Approval:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer
DERIVATION OF UNIT COST
(ABC/EPC/UCD)
PROPOSED FENCE FOR BARANGAY CALLANGIGAN
I. DAILY RATES TO BE USED

DESIGNATION DAILY RATE


1. Foreman 700.00 /day
2. Carpenter 550.00 /day
3. Mason 550.00 /day
4. Steelman 550.00 /day
5. Licensed Blaster 650.00 /day
6. Heavy Equipment Operator 650.00 /day
7. Light Equipment Operator 500.00 /day
8. Driver 500.00 /day
9. Safety Officer 850.00 /day
10. First Aider 550.00 /day
11. Laborer 400.00 /day

II. LIST OF EQUIPMENT TO BE UTILIZED


Note: Rental Rates used are based on Operated Hour of the ACEL Rates (includes cost of operation).
OPERATED
EQUIPMENT RENTAL MODEL/MAKE BARE MONTH RENTAL
RENTAL RATE
1 160 HP DOZER 2,257.00 KOMATSU D65E-8 3,233.00 /hr. 293,436.00 /month
2 BACKHOE 1.0 m3 2,886.00 KOMATSU PC-220-5A 3,494.00 /hr. 375,232.00 /month
3 LOADER 1.0 m3 1,746.00 CAT 908 1,746.00 /hr. 226,980.00 /month
4 GRADER, 100-125 HP 1,658.00 KOMATSU GD510-R 1,658.00 /hr. 215,501.00 /month
5 VIB. COMPACTOR, 8 TONS 1,616.00 DYNAPAC CA152D 1,616.00 /hr. 210,067.00 /month
6 CRANE, 25 TONS 1,384.00 ALL MODELS 1,384.00 /hr. 179,894.00 /month
7 PILE HAMMER (SINGLE ACTING) 1,608.00 DELMAG D46-13 (W/O CRANE) 1,608.00 /hr. 209,040.00 /month
7 PILE DRIVING HYDRAULIC 1,800.00 AKP300 HYDRAULIC TYPE 1,800.00 /hr. 233,948.00 /month
4 DUMP TRUCK, 4 m3 877.00 ALL MODELS 1,087.00 /hr. 114,036.00 /month
10 WATER TRUCK, 5000 LIT CAP. 1,672.00 3000 - 5000 LIT. ALL MODELS 1,672.00 /hr. 217,360.00 /month
5 6X6 CARGO TRUCK 920.00 6-8 TONS CAP. ALL MODEL 920.00 /hr. 119,652.00 /month
6 LOW BED TRUCK 1,620.00 ALL MODELS 1,620.00 /hr. 210,636.00 /month
12 TRANSIT MIXER, 4.0 cu.m. 1,151.00 3.5 - 4.5 CU.M. ALL MODELS 1,151.00 /hr. 149,604.00 /month
13 601 cfm COMPRESSOR 1,367.00 ALL MODELS 1,367.00 /hr. 177,749.00 /month
14 ROCK DRILL MACHINE 243.00 ALL MODELS 243.00 /hr. 31,603.00 /month
7 4" Æ CENTRIFUGAL PUMP 466.00 ALL MODELS 466.00 /hr. 44,730.00 /month
8 1 BAGGER MIXER 172.00 ALL MODELS 172.00 /hr. 22,308.00 /month

III. HAULING OF COSTRUCTION MATERIALS


A. Cement
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost = 235.00 /bag
Capacity of Truck = 150 bags/trip
Capability of five (5) Laborers
Loading = 300 bags/hr
Unloading = 300 bags/hr
a. Hauling from Source To Dump Site
Cycle Time
with load = 22.00 kms. / / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip

Page 21
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 150 bags/trip / / 300 bags/hr = 0.50 hrs./trip
Unloading = 150 bags/trip / / 300 bags/hr = 0.50 hrs./trip
total time = 2.21 hrs./trip

920.00 /hr. x 2.21 hrs./trip


Equipment Cost = = 13.54 /bag
150 bags/trip
2,000.00 /day x 2.21 hrs./trip
Labor Cost = = 3.68 /bag
8 hr/day x 150 bags/trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 1 bag/trip

Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /bag
8 hr/day x 1 bag/trip

SUMMARY
1 Base Cost = 235.00 /bag
2 Hauling
a. Equipment Cost = 13.54 /bag
b. Labor Cost = 3.68 /bag
Total Hauling Cost = 17.22 /bag
5% VAT for Hauling Cost = 0.86 /bag
TOTAL COST = 253.08 /bag
say 253.10 /bag
B. Lumber
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost = 58.00 /bd.ft.
Capacity of Truck = 4,000 bd.ft./trip
Capability of five (5) Laborers
Loading = 4,000 bd.ft./trip
Unloading = 4,000 bd.ft./trip
a. Hauling from Source To Dump Site
Cycle Time
with load = 22.00 kms. / / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 4000 bd.ft./trip / / 4000 bd.ft./trip = 1.00 hrs./trip
Unloading = 4000 bd.ft./trip / / 4000 bd.ft./trip = 1.00 hrs./trip
total time = 3.21 hrs./trip
920.00 /hr. x 3.21 hrs./trip
Equipment Cost = = 0.74 /bd.ft.
4000 bd.ft./trip
2,000.00 /day x 3.21 hrs./trip
Labor Cost = = 0.20 /bd.ft.
8 hr/day x 4000 bd.ft./trip

Page 22
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 25 bd.ft./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /bd.ft.
8 hr/day x 25 bd.ft./trip

SUMMARY
1 Base Cost = 58.00 /bd.ft.
2 Hauling
a. Equipment Cost = 0.74 /bd.ft.
b. Labor Cost = 0.20 /bd.ft.
Total Hauling Cost = 0.94 /bd.ft.
5% VAT for Hauling Cost = 0.05 /bd.ft.
TOTAL COST = 58.99 /bd.ft.
say 59.00 /bd.ft.
C. 1/2" Marine Plywood
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost = 820.00 /pc.
Capacity of Truck = 250 pc./trip
Capability of five (5) Laborers
Loading = 250 pc./hr
Unloading = 250 pc./hr
a. Hauling from Source To Dump Site
Cycle Time
with load = 22.00 kms. / / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 250 pc./trip / / 250 pc./hr = 1.00 hrs./trip
Unloading = 250 pc./trip / / 250 pc./hr = 1.00 hrs./trip
total time = 3.21 hrs./trip
920.00 /hr. x 3.21 hrs./trip
Equipment Cost = = 11.80 /pc.
250 pc./trip
2,000.00 /day x 3.21 hrs./trip
Labor Cost = = 3.21 /pc.
8 hr/day x 250 pc./trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 1 pc./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /pc.
8 hr/day x 1 pc./trip

Page 23
SUMMARY

1 Base Cost = 820.00 /pc.


2 Hauling
a. Equipment Cost = 11.80 /pc.
b. Labor Cost = 3.21 /pc.
Total Hauling Cost = 15.01 /pc.
5% VAT for Hauling Cost = 0.75 /pc.
TOTAL COST = 835.76 /pc.
say 835.80 /pc.

D. RSB, CWN & Tie Wire


AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost :
RSB = 58.00 /kg.
CWN = 100.00 /kg.
Tie Wire = 100.00 /kg.
Capacity of Truck = 6,000 kg./trip
Capability of five (5) Laborers
Loading = 6,000 kg./trip
Unloading = 7,000 kg./trip
a. Hauling from Source To Dump Site
Cycle Time
with load = 22.00 kms. / / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 6000 kg./trip / / 6000 kg./trip = 1.00 hrs./trip
Unloading = 6000 kg./trip / / 7000 kg./trip = 0.86 hrs./trip
total time = 3.06 hrs./trip
920.00 /hr. x 3.06 hrs./trip
Equipment Cost = = 0.47 /kg.
6000 kg./trip
2,000.00 /day x 3.06 hrs./trip
Labor Cost = = 0.13 /kg.
8 hr/day x 6000 kg./trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 30 kg./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /kg.
8 hr/day x 30 kg./trip

Page 24
SUMMARY

RSB CWN Tie Wire


1 Base Cost = 58.00 100.00 100.00 /kg.
2 Hauling
a. Equipment Cost = 0.47 0.47 0.5 /kg.
b. Labor Cost = 0.13 0.13 0.1 /kg.
Total Hauling Cost = 0.60 0.60 0.6 /kg.
5% VAT for Hauling Cost = 0.03 0.03 0.0 /kg.
TOTAL COST = 58.63 100.63 100.63 /kg.
say 58.60 100.60 100.60 /kg.

E. Plain GISheet
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00

Utilized : 6x6 Cargo Truck with five (5) Laborers


truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost : 70.00 /lin.m.
Capacity of Truck = 6,000 lin.m./trip
Capability of five (5) Laborers
Loading = 6,000 lin.m./trip
Unloading = 6,000 lin.m./trip

a. Hauling from Source To Dump Site


Cycle Time
with load = 22.00 kms. / / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 6000 lin.m./trip / / 6000 lin.m./trip = 1.00 hrs./trip
Unloading = 6000 lin.m./trip / / 6000 lin.m./trip = 1.00 hrs./trip
total time = 3.21 hrs./trip
920.00 /hr. x 3.21 hrs./trip
Equipment Cost = = 0.49 /lin.m.
6000 lin.m./trip
2,000.00 /day x 3.21 hrs./trip
Labor Cost = = 0.13 /lin.m.
8 hr/day x 6000 lin.m./trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 25 lin.m./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /lin.m.
8 hr/day x 25 lin.m./trip

SUMMARY

1 Base Cost = 70.00 /lin.m.


2 Hauling
a. Equipment Cost = 0.49 /lin.m.
b. Labor Cost = 0.13 /lin.m.
Total Hauling Cost = 0.63 /lin.m.
5% VAT for Hauling Cost = 0.03 /lin.m.
TOTAL COST = 70.66 /lin.m.

Page 25
say 70.70 /lin.m.

F. Sand and Gravel


1 Quarrying
Utilized : 160 HP Dozer
Production : 65 cu. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)
Equipment
3,233.00 /hr
Cost = = 49.74 /cu. m
65 /cu. m./hr.

2 Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 1,746.00 /hr. (incl. Fuel & operator)
Equipment
1,746.00 /hr
Cost = = 31.75 /cu. m
55 /cu. m./hr.

3 Hauling
AHD = 53.00 kms. (TABUK CITY, KALINGA QUARRY) Speed (kph)
with Load w/o Load
Type of Road : Type I = 51.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 2.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilize Dump Truck (6W)
Capacity : 4.00 cu.m./trip
truck rental = 1,087.00 /hr.
Quarry Pit Fee : 120.00 /cu.m.

a. Hauling from Source To Dump Site


Cycle Time
with load = 51.00 kms. / / 35.00 km./hr. = 1.46 hrs./trip
T-I
without load = 51.00 kms. / / 45.00 km./hr. = 1.13 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 2.00 kms. / / 20.00 km./hr. = 0.10 hrs./trip
T-IV
without load = 2.00 kms. / / 25.00 km./hr. = 0.08 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 2.89 hrs./trip
1,087.00 /hr. x 2.89 hrs./trip
Equipment Cost = = 784.58 /cu.m.
4 Dump Truck (6W)
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 0.027 cu.m./trip
Cycle Time
with load = - km. / / 2.00 km./hr. = - hrs./trip
without load = - km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /cu.m.
8 hr/day x 0.027 cu.m./trip

4 Screening of Aggregates
Capability
Sand = 6.00 cu. m./day
Gravel = 4.00 cu. m./day
1 -Laborers @ 400.00 /day

400.00 / day
Sand = = 66.67 /m3
6.00 m3/day
400.00 / day
Gravel = = 100.00 /m3
4.00 m3/day

Page 26
SUMMARY
SAND GRAVEL
1 Quarry Pit Fee = 120.00 /m3 = 120.00 /m3
2 Quarrying = 49.74 /m3 = 49.74 /m3
3 Loading = 31.75 /m3 = 31.75 /m3
4 Hauling = 784.58 /m3 = 784.58 /m3
5 Screening = 66.67 /m3 = 100.00 /m3
Total = 1,052.73 /m3 1,086.06 /m3
Plus: 5% VAT = 52.64 /m3 54.30 /m3
2% Excise Tax = 21.05 /m3 21.72 /m3
TOTAL COST = 1,126.42 /m3 = 1,162.09 /m3
say 1,126.40 /m3 say 1,162.10 /m3

G. 4" CHB
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost = 11.00 /pc.

Capacity of Truck = 600 pc./trip


Capability of five (5) Laborers
Loading = 600 pc./hr
Unloading = 600 pc./hr
a. Hauling from Source To Dump Site
Cycle Time
with load = 22.00 kms. / / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 600 pc./trip / / 600 pc./hr = 1.00 hrs./trip
Unloading = 600 pc./trip / / 600 pc./hr = 1.00 hrs./trip
total time = 3.21 hrs./trip
920.00 /hr. x 3.21 hrs./trip
Equipment Cost = = 4.92 /pc.
600 pc./trip
2,000.00 /day x 3.21 hrs./trip
Labor Cost = = 1.34 /pc.
8 hr/day x 600 pc./trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 4 pc./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /pc.
8 hr/day x 4 pc./trip
SUMMARY
1 Base Cost = 11.00 /pc.
2 Hauling
a. Equipment Cost = 4.92 /pc.
b. Labor Cost = 1.34 /pc.
Total Hauling Cost = 6.25 /pc.
5% VAT for Hauling Cost = 0.31 /pc.
TOTAL COST = 17.57 /pc.
say 17.60 /pc.

Page 27
H. Steel Paving Forms 4"x10"x10'x1/8"
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00

Utilized : 6x6 Cargo Truck with five (5) Laborers


truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost : 260.00 /lin.m.
Capacity of Truck = 6,000 lin.m./trip
Capability of five (5) Laborers
Loading = 6,000 lin.m./trip
Unloading = 6,000 lin.m./trip

a. Hauling from Source To Dump Site


Cycle Time
with load = 22.00 kms. / / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 6000 lin.m./trip / / 6000 lin.m./trip = 1.00 hrs./trip
Unloading = 6000 lin.m./trip / / 6000 lin.m./trip = 1.00 hrs./trip
total time = 3.21 hrs./trip
920.00 /hr. x 3.21 hrs./trip
Equipment Cost = = 0.49 /lin.m.
6000 lin.m./trip
2,000.00 /day x 3.21 hrs./trip
Labor Cost = = 0.13 /lin.m.
8 hr/day x 6000 lin.m./trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 25 lin.m./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /lin.m.
8 hr/day x 25 lin.m./trip

SUMMARY

1 Base Cost = 260.00 /lin.m.


2 Hauling
a. Equipment Cost = 0.49 /lin.m.
b. Labor Cost = 0.13 /lin.m.
Total Hauling Cost = 0.63 /lin.m.
5% VAT for Hauling Cost = 0.03 /lin.m.
TOTAL COST = 260.66 /lin.m.
say 260.70 /lin.m.

I. Road Form Stakes


AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00

Page 28
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost : 150.00 /pc.
Capacity of Truck = 8,000 pcs./trip
Capability of five (5) Laborers
Loading = 8,000 pcs./trip
Unloading = 8,000 pcs./trip

a. Hauling from Source To Dump Site


Cycle Time
with load = 22.00 kms. / / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 8000 pcs./trip / / 8000 pcs./trip = 1.00 hrs./trip
Unloading = 8000 pcs./trip / / 8000 pcs./trip = 1.00 hrs./trip
total time = 3.21 hrs./trip
920.00 /hr. x 3.21 hrs./trip
Equipment Cost = = 0.37 /pc.
8000 pcs./trip
2,000.00 /day x 3.21 hrs./trip
Labor Cost = = 0.10 /pc.
8 hr/day x 8000 pcs./trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 25 pcs./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /pc.
8 hr/day x 25 pcs./trip

SUMMARY

1 Base Cost = 150.00 /pc.


2 Hauling
a. Equipment Cost = 0.37 /pc.
b. Labor Cost = 0.10 /pc.
Total Hauling Cost = 0.47 /pc.
5% VAT for Hauling Cost = 0.02 /pc.
TOTAL COST = 150.49 /pc.
say 150.50 /pc.

RECAPITULATION
DESCRIPTION UNIT UNIT PRICE
1. Cement P/bag 253.10
2. Sand P/cu. m. 1,126.40
3. Gravel P/cu. m. 1,162.10
4. Reinforcing Steel Bar P /kg. 58.60
5. 1/2 " THK. Plywood P /pc. 835.80
6. Form Lumber P/bd. ft. 59.00
7. CWN P/kg. 100.60
8. Tie Wire P/kg. 100.60
9. 4' THK CHB P /pc. 17.60
10. Plain GI Sheet P/lin.m. 70.70
11. Steel Paving Forms 4"x10"x10'x1/8" P/lin.m. 260.70
11. Road Form Stakes P/pc. 150.50
INDIRECT COST (%) 20%

Page 29
IV. ITEM OF WORK
A. CONCRETING WORKS
2. Class "A" Reinforced Concrete (211 kscm for Road Conreting)
a. Materials
Cement = 9.50 bags /m3 x 253.10 / bag = 2,404.45 /m3
Sand = 0.45 m3 /m3 x 1,126.40 /m3 = 506.88 /m3
Gravel = 0.90 m3 /m3 x 1,162.10 /m3 = 1,045.89 /m3
S.Paving Form = 1.60 lin.m./cu.m. x 260.70 P/lin.m. = 417.12 /m3
R. Form Stake = 2.00 pcs./cu.m. x 150.50 P/pc. = 301.00 /m3
Material Cost . . . . . = 4,675.34 /m3

b. Labor
b.1 Fabrication, Placing & Dismantling of Forms
Capability = 3.50 cu. m./day
2 -Carpenters @ 550.00 /day = 1,100.00 /day
4 -Laborers @ 400.00 /day = 1,600.00 /day
2,700.00 /day

2,700.00 / day
Cost = = 771.43 /m3
3.50 m3/day

b.2 Concreting and Curing


Capability = 3.50 cu. m./day
1 -Foreman @ 700.00 /day = 700.00 /day
2 -Mason @ 550.00 /day = 1,100.00 /day
8 -Laborers @ 400.00 /day = 3,200.00 /day
5,000.00 /day

5,000.00 / day
Cost = = 1,428.57 /m3
3.50 m3/day

c. Equipment Utilization
Utilized : 1 - Transit Mixer
Rental = 1,151.00 /hr. (incl. fuel & operator)
9.50 bags /m3 x 4.00 min./bag
Time of Mixer/day = = 0.63 hrs./m3
60.00 min./hr.

Cost = 1,151.00 /hr. x 0.63 hrs./m3 = 728.97 /m3

SUMMARY
5%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 4,675.30 - 4,675.30 /m3
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 2,200.00 110.00 2,310.00 /m3
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = 729.00 36.45 765.45 /m3
TOTAL DIRECT COST = 7,604.30 146.50 7,750.80 /m3
Plus: 20% OCM & Profit = 1,520.90 76.00 1,596.90 /m3
UNIT COST = 9,125.20 222.50 9,347.70 /m3
say 9,347.70 /m3

1. Class "A" Reinforced Concrete (211 kscm for Siphon/Box Culvert & Other Structures)
a. Materials
Cement = 9.00 bags /m3 x 253.10 / bag = 2,277.90 /m3
Sand = 0.45 m3 /m3 x 1,126.40 /m3 = 506.88 /m3
Gravel = 0.90 m3 /m3 x 1,162.10 /m3 = 1,045.89 /m3
F. Lumber = 25.00 bd. ft./m3 x 59.00 /bd. ft. = 1,475.00 /m3
Plywood = 1.25 pc./m3 x 835.80 /pc. = 1,044.75 /m3
Tie Wire = 1.20 kgs. /m2 x 100.60 /kg. = 120.72 /m2
CWN = 2.00 kgs. /m3 x 100.60 /kg. = 201.20 /m3
Material Cost . . . . . = 6,672.34 /m3

Page 30
b. Labor
b.1 Fabrication, Placing & Dismantling of Forms
Capability = 3.50 cu. m./day
2 -Carpenters @ 550.00 /day = 1,100.00 /day
4 -Laborers @ 400.00 /day = 1,600.00 /day
2,700.00 /day

2,700.00 / day
Cost = = 771.43 /m3
3.50 m3/day

b.2 Concreting and Curing


Capability = 3.50 cu. m./day
1 -Foreman @ 700.00 /day = 700.00 /day
2 -Mason @ 550.00 /day = 1,100.00 /day
8 -Laborers @ 400.00 /day = 3,200.00 /day
5,000.00 /day

5,000.00 / day
Cost = = 1,428.57 /m3
3.50 m3/day

c. Equipment Utilization
Utilized : 1 - Bagger Mixer
Rental = 172.00 /hr. (incl. fuel & operator)
9.00 bags /m3 x 10.00 min./bag
Time of Mixer/day = = 1.50 hrs./m3
60.00 min./hr.

Cost = 172.00 /hr. x 1.50 hrs./m3 = 258.00 /m3

SUMMARY
5%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 6,672.30 - 6,672.30 /m3
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 2,200.00 110.00 2,310.00 /m3
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = 258.00 12.90 270.90 /m3
TOTAL DIRECT COST = 9,130.30 122.90 9,253.20 /m3
Plus: 20% OCM & Profit = 1,826.10 91.30 1,917.40 /m3
UNIT COST = 10,956.40 214.20 11,170.60 /m3
say 11,170.60 /m3

B. REINFORCING STEEL BARS


1. Furnishing & Stockpiling
Furnishing Cost = 58.60 /kg. (VAT inclusive)
Plus: 20% OCM & Profit = 11.70 /kg.
5% VAT (OCM & Profit) = 0.60 /kg.
UNIT COST = 70.90 /kg.
say 70.90 /kg.

2. Cut, Bend & Placing of RSB


Capability = 80.00 kgs./day
1 -Steelman @ 550.00 /day = 550.00 /day
1 -Laborer @ 400.00 /day = 400.00 /day
950.00 /day

950.00 /day
Cost = = 11.90 /kg.
80.00 kgs./day kgs./day
Plus: 20% OCM & Profit = 2.40 /kg.
5% VAT (Labor) = 0.60 /kg.
5% VAT (OCM & Profit) = 0.10 /kg.
UNIT COST = 15.00 /kg.
say 15.00 /kg.

D. GRAVEL BLANKET
1. Materials
Gravel = 0.80 cu.m./cu.m. x 1,162.10 /cu.m. = 929.68 /m3
Sand = 0.45 cu.m./cu.m. x 1,162.10 /cu.m. = 522.95 /m3

Page 31
Material Cost . . . . . = 1,452.63 /m3

2. Labor
Capability = 5.00 cu. m./day
1 -Laborers @ 400.00 /day = 400.00 /day
400.00 /day

400.00 / day
Cost = = 80.00 /m3
5.00 m3/day

SUMMARY
5%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 1,452.60 - 1,452.60 /m3
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 80.00 4.00 84.00 /m3
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = - - - /m3
TOTAL DIRECT COST = 1,532.60 4.00 1,536.60 /m3
Plus: 20% OCM & Profit = 306.50 15.30 321.80 /m3
UNIT COST = 1,839.10 19.30 1,858.40 /m3
say 1,858.40 /m3

E. 4" THK CHB Lining


a. Materials (Laying & Plastering of One Side)
Cement = 0.76 bags /m2 x 253.10 / bag = 191.09 /m2
Sand = 0.063 m3 /m2 x 1,126.40 /m3 = 70.96 /m2
RSB = 3.080 kg. /m2 x 58.60 /kg. = 180.49 /m2
Tie Wire = 0.030 kg. /m2 x 100.60 /kg. = 3.02 /m2
4" CHB = 12.50 pcs. /m2 x 17.60 /m3 = 220.00 /m2
Material Cost . . . . . = 665.56 /m2

b. Labor
b.1 Laying
Capability = 14.00 sq. m./day
1 -Mason @ 550.00 /day = 550.00 /day
2 -Laborers @ 400.00 /day = 800.00 /day
1,350.00 /day

1,350.00 / day 96.43 /m2


Cost = =
14.00 m3/day
b.2 Plastering
Capability = 12.00 sq. m./day
1 -Mason @ 550.00 /day = 550.00 /day
1 -Laborers @ 400.00 /day = 400.00 /day
950.00 /day

950.00 / day 79.17 /m2


Cost = =
12.00 m3/day

Page 32
SUMMARY
5%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 665.60 - 665.60 /m2
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 175.60 8.78 184.38 /m2
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = - - - /m2
TOTAL DIRECT COST = 841.20 8.80 850.00 /m2
Plus: 20% OCM & Profit = 168.20 8.40 176.60 /m2
UNIT COST = 1,009.40 17.20 1,026.60 /m2
say 1,026.60 /m2

Prepared by: Checked & Submitted by:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer

Page 33
DERIVATION OF UNIT COST
(ABC/EPC/UCD)
PROPOSED FENCE FOR BARANGAY CALLANGIGAN
I. DAILY RATES TO BE USED

DESIGNATION DAILY RATE


1. Foreman 700.00 /day
2. Carpenter 550.00 /day
3. Mason 550.00 /day
4. Steelman 550.00 /day
6. Heavy Equipment Operator 650.00 /day
7. Light Equipment Operator 500.00 /day
8. Driver 500.00 /day
9. Safety Officer 850.00 /day
10 . First Aider 550.00 /day
11 . Laborer 400.00 /day

II. LIST OF EQUIPMENT TO BE UTILIZED


Note: Rental Rates used are based on Operated Hour of the ACEL Rates (includes cost of operation).
OPERATED RENTAL
EQUIPMENT RENTAL MODEL/MAKE BARE MONTH RENTAL
RATE
1 165 HP DOZER 2,257.00 KOMATSU D65P-11 3,233.00 /hr. 293,436.00 /month
2 BACKHOE 1.0 m3 2,886.00 KOMATSU PC-220-6 3,494.00 /hr. 375,232.00 /month
3 LOADER 1.0 m3 1,746.00 CAT 908 1,746.00 /hr. 226,980.00 /month
4 GRADER, 100-125 HP 1,658.00 KOMATSU GD510-R 1,658.00 /hr. 215,501.00 /month
5 VIB. COMPACTOR, 8 TONS 1,616.00 DYNAPAC CA152D 1,616.00 /hr. 210,067.00 /month
6 CRANE, 25 TONS 1,384.00 ALL MODELS 1,384.00 /hr. 179,894.00 /month
7 PILE HAMMER (SINGLE ACTING) 1,608.00 DELMAG D46-13 (W/O CRANE) 1,608.00 /hr. 209,040.00 /month
7 PILE DRIVING HYDRAULIC 1,800.00 AKP300 HYDRAULIC TYPE 1,800.00 /hr. 233,948.00 /month
4 DUMP TRUCK, 6 m3 877.00 ALL MODELS 1,087.00 /hr. 114,036.00 /month
10 WATER TRUCK, 5000 LIT CAP. 1,672.00 3000 - 5000 LIT. ALL MODELS 1,672.00 /hr. 217,360.00 /month
5 6X6 CARGO TRUCK 920.00 6-8 TONS CAP. ALL MODEL 920.00 /hr. 119,652.00 /month
6 LOW BED TRUCK 1,620.00 ALL MODELS 1,620.00 /hr. 210,636.00 /month
12 TRANSIT MIXER, 4.0 cu.m. 1,151.00 3.5 - 4.5 CU.M. ALL MODELS 1,151.00 /hr. 149,604.00 /month
13 601 cfm COMPRESSOR 1,367.00 ALL MODELS 1,367.00 /hr. 177,749.00 /month
14 ROCK DRILL MACHINE 243.00 ALL MODELS 243.00 /hr. 31,603.00 /month
7 4" Ø CENTRIFUGAL PUMP 466.00 ALL MODELS 466.00 /hr. 44,730.00 /month
8 1 BAGGER MIXER 172.00 ALL MODELS 172.00 /hr. 22,308.00 /month
INDIRECT COST (%) 20%

III. ITEM OF WORK


A. TEMPORARY WORKS, MOB. AND DEMOB., CAMP FACILITIES & CONST. PLANT
1. Mobilization and Demobilization
a. Equipments to be Mobilized
2 -Backhoe
1- Loader
1- Dozer
1- Vibratory Roller
1- Grader

Page 34
Utilized: Truck - Tractor with Trailer/Lowbed
Rental 1,620.00 /hr. (incl. fuel, oil and operator)
AHD 13.00 kms. (Samonte, Quezon, Isabela To Project Site)
No. of Trips : Heavy Equipment : 6 trips
Cycle Time:
13 kms. 13 kms
Travel Time = + = 0.81 hrs./trip
25 kph 45 kph
Loading & Unloading = 1.50 hrs./trip
Delay, etc = 0.50 hrs./trip
Total Time = 2.81 hrs./trip
Rental = 1,620.00 /hr. x 2.81 hrs/trip = 4,550.40
*for one (1) trip only.
Total Mob. & Demob Cost = 4,550.40 /trip x 6 trips = 27,302.40

3. Project Billboard

WORK TO BE DONE
ACTIVITY
unit Quantity Unit Cost Estimated Cost
1. EARTHWORKS
a. Common Structure Excavation (Manual) cu.m 1.00 200.00 200.00
2. CARPENTRY WORKS
a. Wood Frame (2"x2") bd.ft 25.00 75.00 1,875.00
b. CWN kg. 2.00 100.60 201.20
Sub-total 2,076.20
3. TARPAULIN
a. Tarpaulin l.s. 1.00 2,500.00 2,500.00
3. LABOR
a. Laborer (Half-day) unit 2.00 200.00 400.00
Sub-total 400.00
TOTAL AMOUNT 5,176.20
=
TOTAL DIRECT COST 5,176.20

Plus: 20% OCM & Profit = 1,035.20


5% VAT (OCM & Profit) = 51.80
TOTAL = 6,263.20 lump.sum

B. Safety and Health Program

A. PERSONAL PROTECTIVE
EQUIPMENT (PPPE) UNIT QUANTITY UNIT COST TOTAL COST

Safety Helmet pcs. 20.00 64.60 1,292.00


Safety Vest pcs. 20.00 125.00 2,500.00
Face Mask pcs. 2,536.00 3.00 7,608.00
Sub-total A 11,400.00

Page 35
QUANTITY
B. MEDICAL TEAM/ SAFETY DAILY RATE TOTAL COST
OFFICER
No. of PersonnelNo. of Days (Prop.
Proj. Duration)

Safety Officer 1.00 150.00 850.00 127,500.00


First Aider 1.00 150.00 550.00 82,500.00
Sub-total B 210,000.00

C. SAFETY SIGNAGES UNIT QUANTITY UNIT COST TOTAL COST

PPE Signage (4'x8') set 2.00 800.00 1,600.00


Safety First (4'x4') set 4.00 400.00 1,600.00
Safety First (2'x3') set 4.00 150.00 600.00
Warning Signs (2'x3') set 12.00 150.00 1,800.00
Caution Tape, 1000ft roll 1.00 800.00 800.00
Wood Frame and Studs (2"x2") bd.ft. 190.00 75.00 14,250.00

Sub-total C 20,650.00

=
TOTAL DIRECT COST 242,050.00

Plus: 20% OCM & Profit = 48,410.00


5% VAT (OCM & Profit) = 2,420.50
TOTAL = 292,880.50 lump.sum
C. CLEARING & GRUBBING
a. Using Dozer
Utilized : 160 HP Dozer
Production : 210 sq. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)

3,233.00 /hr.
Cost = = 15.40 /m2
210 m2/hr
Plus: 20% OCM & Profit = 3.10 /m2
5% VAT (Equipment) = 0.80 /m2
5% VAT (OCM & Profit) = 0.20 /m2
UNIT COST = 19.50 /m2
say 19.50 /m2

C. STRUCTURE EXCAVATION
1. Common Materials
a. Using Dozer
Utilized : 160 HP Dozer
Production : 25 cu. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)

3,233.00 /hr.
Cost = = 129.30 /m3
25 m3/hr
Plus: 20% OCM & Profit = 25.90 /m3
12% VAT (Equipment) = 15.50 /m3
12% VAT (OCM & Profit) = 3.10 /m3

Page 36
UNIT COST = 173.80 /m3
say 173.80 /m3
a. Using Backhoe
Utilized : 1.0 cu.m. Backhoe
Production : 30 cu. m./hr.
Rental : 3,494.00 /hr. (incl. Fuel & operator)

3,494.00 /hr.
Cost = = 116.50 /m3
30 m3/hr
Plus: 20% OCM & Profit = 23.30 /m3
5% VAT (Equipment) = 5.80 /m3
5% VAT (OCM & Profit) = 1.20 /m3
UNIT COST = 146.80 /m3
say 146.80 /m3

c. Manual
Utilized : 1 - Laborer
Production : 2.00 cu. m./day
Daily Rate : 400.00 /day

400.00 /day
Cost = = 200.00 /m3
2 m3/day
Plus: 20% OCM & Profit = 40.00 /m3
5% VAT (Labor) = 10.00 /m4
5% VAT (OCM & Profit) = 2.00 /m3
UNIT COST = 252.00 /m3
say 252.00 /m3

D. CANAL EXCAVATION
1. Common Materials
a. Using Backhoe
Utilized : 1.0 cu.m. Backhoe
Production : 40 cu. m./hr.
Rental : 3,494.00 /hr. (incl. Fuel & operator)

3,494.00 /hr.
Cost = = 87.40 /m3
40 m3/hr
Plus: 20% OCM & Profit = 17.50 /m3
5% VAT (Equipment) = 4.40 /m3
5% VAT (OCM & Profit) = 0.90 /m3
UNIT COST = 110.20 /m3
say 110.20 /m3

I. EMBANKMENT CONSTRUCTION AND COMPACTION


a. Haul Borrow
1 Quarrying
Utilized : 160 HP Dozer
Production : 60 cu. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)

3,233.00 /hr
Cost = = 53.88 /cu. m
60 /cu. m./hr.

2 Loading
Utilized : 1.0 cu.m. Loader
Production : 50 cu. m./hr.
Rental : 1,746.00 /hr. (incl. Fuel & operator)

Page 37
1,746.00 /hr
Cost = = 34.92 /cu. m
50 /cu. m./hr.

3 Hauling
use : 4.0 cu. m. Dump Truck
rental = 1,087.00 /hr.
AHD = 6 kms.
Shrinkage Factor = 15%
Type of Road : Poorly Maintained Road
speed of dump truck with load = 20 km./hr.
without load = 25 km./hr.
Cycle Time
travel time
with load = 6 kms. / 20 km./hr. = 0.30 hrs./trip
without load = 6 kms. / 25 km./hr. = 0.24 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 0.66 hrs./trip
1,087.00 /hr. x 0.66 hrs./trip
Cost = = 209.94 /cu. m
4 cu.m./trip x 85% s.f.

4 Spreading
Utilized : 160 HP Dozer
Production : 110 cu. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)

3,233.00 /hr
Cost = = 29.39 /cu. m
110 /cu. m./hr.

5 Watering
Utilized : 5000 lit. Water Truck
Production : 70 cu. m./hr.
Rental : 1,672.00 /hr. (incl. Fuel & operator)

1,672.00 /hr
Cost = = 23.89 /cu. m
70 /cu. m./hr.

6 Compaction
Utilized : 8 Tons Vibratory Roller
Production : 40 cu. m./hr.
Rental : 1,616.00 /hr. (incl. Fuel & operator)

1,616.00 /hr
Cost = = 40.40 /cu. m
40 /cu. m./hr.
SUMMARY
Direct Cost 5%VAT TOTAL
1 Quarry Pit Fee = 70.00 - 70.00 /m3
2 Quarrying = 53.88 2.69 56.58 /m3
3 Loading = 34.92 1.75 36.67 /m3
4 Hauling = 209.94 10.50 220.44 /m3
5 Spreading = 29.39 1.47 30.86 /m3
6 Watering = 23.89 1.19 25.08 /m3
7 Compaction = 40.40 2.02 42.42 /m3
TOTAL DIRECT COST = 462.40 19.60 482.00 /m3
2% Excise Tax = 9.20 - 9.20 /m3
Plus: 20% OCM & Profit = 92.50 4.60 97.10 /m3
UNIT COST = 564.10 24.20 588.30 /m3
say 588.30 /m3

Page 38
E. STRUCTURE BACKFILL W/ COMPACTION (Side Borrow)

1. Manual
a. Backfilling
Utilized : 1 - Laborer
Production : 3.00 cu. m./day
Daily Rate : 400.00 /day

400.00 /day
Cost = = 133.33 /m3
3 m3/day
b. Compaction
Utilized : 1 - Laborer
Production : 5.00 cu. m./day
Daily Rate : 400.00 /day

400.00 /day
Cost = = 80.00 /m3
5 m3/day

SUMMARY
a. Backfilling = 133.33 /m3
b. Compaction = 80.00 /m3
TOTAL DIRECT COST 213.30 /m3
Plus: 20% OCM & Profit = 42.70 /m3
5% VAT (Labor) = 10.70 /m4
5% VAT (OCM & Profit) = 2.10 /m3
UNIT COST = 268.80 /m3
say 268.80 /m3

K. DISPOSAL OF EXCESS EXCAVATED MATERIALS (OVERHAUL)


1 Loading
Utilized : 1.0 cu.m. Loader
Production : 50 cu. m./hr.
Rental : 1,746.00 /hr. (incl. Fuel & operator)

1,746.00 /hr
Cost = = 34.92 /cu. m
50 /cu. m./hr.

2 Hauling
use : 4.0 cu. m. Dump Truck
rental = 1,087.00 /hr.
AHD = 4 kms.
Type of Road : Poorly Maintained Road
speed of dump truck with load = 20 km./hr.
without load = 25 km./hr.
Cycle Time
travel time
with load = 4 kms. / 20 km./hr. = 0.20 hrs./trip
without load = 4 kms. / 25 km./hr. = 0.16 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 0.48 hrs./trip
1,087.00 /hr. x 0.48 hrs./trip
Cost = = 129.53 /cu. m
4 cu.m./trip

4 Spreading
Utilized : 160 HP Dozer
Production : 110 cu. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)

3,233.00 /hr
Cost = = 29.39 /cu. m

Page 39
Cost = = 29.39 /cu. m
110 /cu. m./hr.

SUMMARY
Direct Cost 5%VAT TOTAL
1 Loading = 34.92 1.75 36.67 /m3
2 Hauling = 129.53 6.48 136.01 /m3
3 Spreading = 29.39 1.47 30.86 /m3
TOTAL DIRECT COST = 193.80 9.70 203.50 /m3
Plus: 20% OCM & Profit = 38.80 1.90 40.70 /m3
UNIT COST = 232.60 11.60 244.20 /m3
say 244.20 /m3

M. Road Metalling
1 Quarrying
Utilized : 160 HP Dozer
Production : 65 cu. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)
Equipment
3,233.00 /hr
Cost = = 49.74 /cu. m
65 /cu. m./hr.

2 Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 1,746.00 /hr. (incl. Fuel & operator)
Equipment
1,746.00 /hr
Cost = = 31.75 /cu. m
55 /cu. m./hr.

3 Hauling
use : 4.0 cu. m. Dump Truck
rental = 1,087.00 /hr.
AHD = 25 kms.
Shrinkage Factor = 5%
Type of Road : Poorly Maintained Road
speed of dump truck with load = 20 km./hr.
without load = 25 km./hr.
Cycle Time
travel time
with load = 25 kms. / 20 km./hr. = 1.25 hrs./trip
without load = 25 kms. / 25 km./hr. = 1.00 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 2.37 hrs./trip
1,087.00 /hr. x 2.37 hrs./trip
Cost = = 676.99 /cu. m
4 cu.m./trip x 95% s.f.

4 Spreading
Utilized : 110 HP Grader
Production : 70 cu. m./hr.
Rental : 1,658.00 /hr. (incl. Fuel & operator)

1,658.00 /hr
Cost = = 23.69 /cu. m
70 /cu. m./hr.

5 Compaction
Utilized : 8 Tons Vibratory Roller
Production : 60 cu. m./hr.
Rental : 1,616.00 /hr. (incl. Fuel & operator)

1,616.00 /hr
Cost = = 26.93 /cu. m
60 /cu. m./hr.

Page 40
SUMMARY
Direct Cost 5%VAT TOTAL
1 Quarrying = 49.74 2.49 52.23 /m3
2 Loading = 31.75 1.59 33.33 /m3
3 Hauling = 676.99 33.85 710.84 /m3
4 Spreading = 23.69 1.18 24.87 /m3
5 Compaction = 26.93 1.35 28.28 /m3
TOTAL DIRECT COST = 809.10 40.50 849.60 /m3
Plus: 20% OCM & Profit = 161.80 8.10 169.90 /m3
UNIT COST = 970.90 48.60 1,019.50 /m3
say 1,019.50 /m3

Prepared by: Checked & Submitted by:

ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Muicipal Engineer

Page 41
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.5 Project Billboard / Signboard


Quantity : 2
Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor
Construction Foreman 1 1.00 101.96 101.96
A.1 Unskilled Laborer 2 1.00 56.74 113.48

Sub - Total for A.1 - As Submitted 215.44


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment
B.1
Sub - Total for B.1 - As Submitted -
Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 215.44
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 215.44
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

Marine Plywood (12mm thk. x 4' x 8') pc 1.00 660.00 660.00


8' X 8' Tarpaulin sqft 32.000 25.00 800.00
F.1
Good Lumber bdft 50.00 55.00 2,750.00
Assorted Common Wire Nails kg 1.00 75.00 75.00

Sub - Total for F.1 - As Submitted 4,285.00


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 4,500.44
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 12% of G.1 540.05
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 12% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 360.04
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 270.03
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 5,670.55
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer Acting Municipal Engineer


Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.7 (2) Occupational Safety and Health Program


Quantity : All
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

Safety Practitioner/ Officer (Part Time) 1 600.00 62.50 37,500.00


A.1
Health Personnel (Full Time) 1 1200.00 35.00 42,000.00

Sub - Total for A.1 - As Submitted 79,500.00


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment
B.1
Sub - Total for B.1 - As Submitted -
Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 79,500.00
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 79,500.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

. man-day 436.35 #N/A #N/A


Safety Shoes man-day 238.540 2.77 660.76
Safety Gloves man-day 436.35 7.67 3,346.80
F.1
Vest man-day 436.35 2.22 968.70
Rubber Boots man-day 197.81 1.39 274.96
Rain coats man-day 130.91 0.34 44.51

Sub - Total for F.1 - As Submitted #N/A


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted #N/A
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 0% of G.1 #N/A
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 0% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 #N/A
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) #N/A
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 #N/A
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.8 (2) Traffic Management


Quantity : All
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

A.1 Traffic Controllers 2 1200.00 56.74 136,176.00

Sub - Total for A.1 - As Submitted 136,176.00


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

Two Way Radio 2 1200.00 2.60 6,240.00


B.1
Barricade Flasher 29 1200.00 0.65 22,620.00

Sub - Total for B.1 - As Submitted 28,860.00


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 165,036.00
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 165,036.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

Speed Restrictions (R4-1) each 636 4.73 3,008.28


Roadwork Ahead (T1-1) each 636 10.95 6,964.20
End Roadwork (T2-16) each 636 10.95 6,964.20
End Speed Restriction(R4-2) each 636 4.73 3,008.28
Workmen Ahead (T1-5) each 636 5.64 3,587.04
Prepare to Stop (T1-18) each 318 5.64 1,793.52
F.1 Temporary Hazard Marker (Chevron, T5-5) each 159 5.76 915.84
Temporary Bollards(@ 5 meters apart) each 2,544 1.64 4,172.16
Plastic Safety Barriers each 25,440 2.74 69,705.60
Safety Vest each 318 2.22 705.96
Hard Hat each 318 0.25 79.50
Safety Shoes each 318 2.70 858.60

Sub - Total for F.1 - As Submitted 101,763.18


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 266,799.18
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 0% of G.1 -
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 0% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 21,343.93
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 14,407.16
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Value Added Tax - As Submitted G.1 + H.1 + I.1 + J.1 302,550.27
K.2 Value Added Tax - As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

MENCHIE C. MAGNO CRISPIN B. GARCIA JR.


Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.9 Mobilization/Demobilization


Quantity : All
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

A.1

Sub - Total for A.1 - As Submitted -


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

1% of Direct Cost CW 74,171.70

B.1

Sub - Total for B.1 - As Submitted 74,171.70


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 74,171.70
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 74,171.70
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

F.1

Sub - Total for F.1 - As Submitted -


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 74,171.70
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 0% of G.1 -
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 0% of G.2 -
I.1 Contractor's Profit - As Submitted 0% of G.1 -
I.2 Contractor's Profit - As Evaluated 0% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 3,708.58
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 77,880.28
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II

Farm to Market Road Barucoc - San Juan


Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : Embankment from Borrow


Quantity : 1200
Unit of Measurement : cu.m
Output per hour - As Submitted : 50.00
Output per hour - As Evaluated :
Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)
Labor

Construction Foreman 1 1 101.96 101.96


Unskilled Laborer 2 1.00 56.74 113.48
A.1

Sub - Total for A.1 - As Submitted 215.44


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

Motorized Road Grader 1 1.00 2,173.00 2,173.00


B.1
Vibratory Roller 1 1.00 1,846.00 1,846.00
Water Truck/Pump 1 0.25 2,450.00 612.50

Sub - Total for B.1 - As Submitted 4,631.50


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 4,846.94
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 50.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 96.94
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
Materials (w/ 25% Shrinkage Factor) cu.m. 1.25 504.27 630.34
F.1

Sub - Total for F.1 - As Submitted 632.34


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 729.28
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 12% of G.1 87.51
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 12% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 58.34
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 43.76
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 918.89
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : Embankment from Borrow (Granular Coarse Material)


Quantity : 1700
Unit of Measurement : cu.m
Output per hour - As Submitted : 50.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

Construction Foreman 1 1 101.96 101.96


Unskilled Laborer 2 1.00 56.74 113.48
A.1

Sub - Total for A.1 - As Submitted 215.44


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

Motorized Road Grader 1 1.00 2,173.00 2,173.00


B.1
Vibratory Roller 1 1.00 1,846.00 1,846.00
Water Truck/Pump 1 0.25 2,450.00 612.50

Sub - Total for B.1 - As Submitted 4,631.50


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 4,846.94
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 50.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 96.94
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
Granular Materials (w/ 25% Shrinkage Factor) cu.m. 1.25 504.27 630.34
F.1

Sub - Total for F.1 - As Submitted 632.34


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 729.28
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 12% of G.1 87.51
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 12% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 58.34
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 43.76
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 918.89
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200 (1) Aggregate Subbase Course


Quantity : 1400
Unit of Measurement : cu.m
Output per hour - As Submitted : 50.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

Construction Foreman 1 1 101.96 101.96


A.1
Unskilled Laborer 2 1 56.74 113.48

Sub - Total for A.1 - As Submitted 215.44


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

Motorized Road Grader 1 1.00 2,173.00 2,173.00


B.1 Vibratory Roller 1 1.00 1,846.00 1,846.00
Water Truck/Pump 1 0.25 2,450.00 612.50

Sub - Total for B.1 - As Submitted 4,631.50


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 4,846.94
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 50.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 96.94
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

F.1 Aggregate Subbase Course cu.m 1.15 578.81 665.63

Sub - Total for F.1 - As Submitted 665.63


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 762.57
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 12% of G.1 91.51
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 12% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 61.01
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 45.75
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 960.84
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : Portland Cement Concrete Pavement (Unreinforced - 0.20m Thk)


Quantity : 3500
Unit of Measurement : sqm
Output per hour - As Submitted : 80.50
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

Construction Foreman 1 1 101.96 101.96


A.1 Skilled Laborer 4 1 73.66 294.64
Unskilled Laborer 12 1 56.74 680.88

Sub - Total for A.1 - As Submitted 1,077.48


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

Transit Mixer 4 1.00 1,318.00 5,272.00


Concrete Vibrator 2 1.00 91.25 182.50
Concrete Batch Plant 1 1.00 1,759.50 1,759.50
Payloader 1 1.00 1,733.00 1,733.00
Concrete Screeder 1 1.00 545.00 545.00
B.1
Water Truck/Pump 1 1.00 2,450.00 2,450.00
Concrete Saw 1 1.00 32.63 32.63
Bar Cutter 1 0.10 219.75 21.98
Mechanized Joint Sealer Equipment/Machine 1 1.00 56.38 56.38
Minor Tools (5% of LC) 53.87

Sub - Total for B.1 - As Submitted 12,106.86


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 13,184.34
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 80.50
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 163.78
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

Reinforcing Steel Bars


kg 0.39 42.00 16.38
Deformed Grade 40
Curing Compound L 0.29 52.00 15.08
Asphalt Sealant L 0.12 55.55 6.67
Steel Forms 20cm Width lnm 0.46 95.00 43.70
Sand cum 0.110 628.50 69.14
F.1 Gravel cum 0.20 653.34 130.67
Portland Cement bags 1.90 260.00 494.00
Concrete Saw Blade pc 0.00015 8,000.00 1.20
Pipe Sleeve lnm 0.0086 126.67 1.09
Grease/Tar L 0.0056 220.00 1.23

Sub - Total for F.1 - As Submitted 779.16


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 942.94
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 12% of G.1 113.15
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 12% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 75.44
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 56.58
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 1,188.11
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : Reinforcing Steel (Box Culvert)


Quantity : 3756.8
Unit of Measurement : kg
Output per hour - As Submitted : 180.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

Construction Foreman 1 1 101.96 101.96


A.1 Skilled Laborer 2 1 73.66 147.32
Unskilled Laborer 8 1 56.74 453.92

Sub - Total for A.1 - As Submitted 703.20


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

Bar Cutter 1 0.50 219.75 109.88


Bar Bender 1 0.50 351.50 175.75
B.1
Cargo / Service Truck 1 0.15 1,212.00 181.80

Sub - Total for B.1 - As Submitted 467.43


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,170.63
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 180.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 6.50
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

GI Tie Wire #16 kg 0.021 75.00 1.58


F.1
Reinforcing Steel Bars Deformed Grade 40 kg 1.05 45.00 47.25

Sub - Total for F.1 - As Submitted 48.83


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 55.33
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 12% of G.1 6.64
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 12% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 4.43
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 3.32
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 69.72
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : Structural Concrete Class A (Box Culvert)


Quantity : 47.24
Unit of Measurement : cu.m
Output per hour - As Submitted : 1.40
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

Construction Foreman 1 1 101.96 101.96


Skilled Laborer 4 1 73.66 294.64
Unskilled Laborer 8 1 56.74 453.92
A.1
Installaion/Removal of Formworks
Skilled Laborer 4 1 73.66 294.64
Unskilled Laborer 8 1 56.74 453.92

Sub - Total for A.1 - As Submitted 1,599.08


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

One Bagger Mixer 1 1.00 172.00 172.00


Concrete Vibrator 1 1.00 91.25 91.25
B.1
Water Truck/Pump 1 0.10 2,450.00 245.00
Minor Tools (5% of LC) 79.95

Sub - Total for B.1 - As Submitted 588.20


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 2,187.28
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.40
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,562.34
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

Good Lumber bdft 45.000 55.00 2,475.00


Marine Plywood (12mm thk. x 4' x 8') pc 1.60 660.00 1,056.00
Assorted Common Wire Nails kg 0.7000 75.00 52.50
F.1
Portland Cement bags 9.50 260.00 2,470.00
Sand cu.m 0.50 628.50 314.25
Gravel cu.m 1.00 653.34 653.34

Sub - Total for F.1 - As Submitted 7,021.09


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 8,583.43
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 12% of G.1 1,030.01
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 12% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 686.67
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 515.01
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 10,815.13
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : Stone Masonry


Quantity : 181.44
Unit of Measurement : cu.m
Output per hour - As Submitted : 1.60
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

Construction Foreman 1 1 101.96 101.96


A.1 Skilled Laborer 2 1 73.66 147.32
Unskilled Laborer 8 1 56.74 453.92

Sub - Total for A.1 - As Submitted 703.20


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

Backhoe, Wheel Mounted 1 0.10 922.00 92.20


Water Truck/Pump 1 0.05 2,450.00 122.50
B.1
One Bagger Mixer 1 1.00 172.00 172.00
Minor Tools (10% of LC) 70.32

Sub - Total for B.1 - As Submitted 457.02


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,160.22
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.60
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 725.14
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

Portland Cement bags 5.500 260.00 1,430.00


Sand cu.m 0.300 628.50 188.55
Filter Cloth sq.n 0.0150 160.00 2.40
PVC Pipes (101mm D) m 0.300 100.00 30.00
F.1
Boulders cu.m 1.050 1,235.07 1,296.83
Gravel Fill cu.m 0.020 653.34 13.07
Miscellaneous (1% of MC) 29.61

Sub - Total for F.1 - As Submitted 2,990.46


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 3,715.60
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 12% of G.1 445.87
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 12% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 297.25
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 222.94
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 4,681.65
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : Structural Backfill


Quantity : 30
Unit of Measurement : cu.m
Output per hour - As Submitted : 1.25
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

Construction Foreman 1 1 101.96 101.96


A.1
Unskilled Laborer 4 1 56.74 226.96

Sub - Total for A.1 - As Submitted 328.92


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

Plate Compactor 1 1.00 123.00 123.00


B.1 Water Truck/Pump 1 0.01 2,450.00 24.50
Minor Tools (5% of LC) 16.45

Sub - Total for B.1 - As Submitted 163.95


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 492.87
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.25
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 394.30
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

-
-
F.1 -
-

Sub - Total for F.1 - As Submitted -


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 394.30
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 12% of G.1 47.32
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 12% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 31.54
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 23.66
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 496.81
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : Structure Excavation


Quantity : 90.72
Unit of Measurement : cu.m
Output per hour - As Submitted : 20.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hours Hourly Rate Amount (PhP)


Labor

Construction Foreman 1 1 101.96 101.96


A.1
Unskilled Laborer 4 1 56.74 226.96

Sub - Total for A.1 - As Submitted 328.92


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment

Backhoe 1 1.00 1,537.00 1,537.00


B.1 Dumptruck 2 1.00 1,420.00 2,840.00
Minor Tools (5% of LC) 16.45

Sub - Total for B.1 - As Submitted 4,393.45


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 4,722.37
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 20.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 236.12
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
-
-
F.1 -

Sub - Total for F.1 - As Submitted -


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 236.12
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies and Miscellaneous - As Submitted 12% of G.1 28.33
H.2 Overhead, Contingencies and Miscellaneous - As Evaluated 12% of G.2 -
I.1 Contractor's Profit - As Submitted 8% of G.1 18.89
I.2 Contractor's Profit - As Evaluated 8% of G.2 -
J.1 Value Added Tax - As Submitted 5% of (G.1 + H.1 + I.1) 14.17
J.2 Value Added Tax - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Unit Cost - As Submitted G.1 + H.1 + I.1 + J.1 297.51
K.2 Unit Cost- As Evaluated G.2 + H.2 + I.2 + J.2 -

Prepared by: Checked/Reviewed by:

Engineer II Engineer II
Reinforcing Steel Bar (Grade 60)
Reinforcing Steel Bar (Grade 40)
Tie wire
Curing Compound
Asphalt Sealant
Forms (Rental)-200mm
Ready Mix Concrete
Polyethylene sheet
RMX
Fine aggregates
Fine aggregates (sand bedding)
Coarse aggregates
Gravel fill
Selected borrow matls
Agg. Subbase course matls
Garden soil
Portland cement
Concrete Saw (Diamond Blade -14"Ø)
Pipe sleeve
Protection Matls (double lane) or boulders
Grease tar
Concrete Admix
Good lumber
Good lumber (coco)
Plywood (1/2' x 4' x 8')
Project Sign (Tarpaulin)
Plywood 4.5mm
Assorted CWN
RC Pipe 24 Ø
RC Pipe 30 Ø
RC Pipe 36 Ø
Weephole PVC
Filter cloth
Boulders
Rope, 1"Ø
Readymix concrete class A w/ pumpcrete 7 days
Readymix concrete class A w/ pumpcrete 14 days
Readymix concrete class A w/ pumpcrete 28 days
Readymix concrete class A 7 days
Readymix concrete class A 14 days
Readymix concrete class A 28 days
Soil poisoning
50mmØ PVC Pipe Series 600
50mmØ PVC Pipe Series 1000
150mmØ PVC Pipe Series 600
150mmØ PVC Pipe Series 1000
Gypsum board
Metal furring
Carrying channel
Hanger bars/rod
Channel clip
Wall angle
Rivets
Metal screw
Hollow core flush door
Wooden panel door
Corrugated roofing sheet
Tekscrew w/ j bolt with washers
Ridge roll 0.60mm
Hip roll 0.60mm
Valley roll 0.60mm
Counter flashing 0.60mm
Blind rivets
Gutter 0.60mm
12" x 1" Plain GI strap
Prepainted metal sheets (Corr.)
Cement based waterproofing
Primer coat
Liquid waterproofing
Asphalt primer
Preformed membrane
50mm -100mmØ Roof drain, canopy drain/ gutter drain
with strainer
Glazed tiles
Tile grout
Tile adhesive (25kg)
Unglazed tiles/granite/synthetic granite tiles
1/2" TO 2" x 3M PVC PIPE BLUE
PVC ORANGE S1000 2"-4" Ø
PVC ORANGE S1000 4"-8" Ø
Fixtures
STAINLESS WATERTANK(8000 LIT) WITH STEEL
FRAMING
2 HOLES PANEL BOARD WITH BREAKER
6 HOLES PANEL BOARD WITH BREAKER
12 HOLES PANEL BOARD WITH BREAKER
1.6mm² - 5.5mm WIRES THW/THHN/THWN
8.0mm² - 22mm WIRES THW/THHN/THWN
PVC ORANGE 15mmØ-32mmØ
UTILITY & JUNCTION BOX(PVC)
SWITCH PLATES WITH ELEMENTS
CONV. OUTLET PLATES W/ ELEMENT
LIGHTING -18WATTS LED BULBS INCLUDING
RECEPTACLES
LAMP POST WITH LED BULB
STREETLIGHTS WITH LED BULBS
ELECTRICAL TRASNFORMER 37.5KVA
Double-Throw Switch
KHW METER
Mega-Spotlight (4-branches)
1.0mm THK. X 0.465m Steel Deck
0.8mm THK. X 0.465m Steel Deck
Concrete neutralizer
Concrete sealer/primer
Patching compound
Semi gloss latex
Glazing putty
Flat wall enamel
Enamel quick dry
Paint thinner
Tinting color
Red oxide primer
Enamel paint
Panel Door Set
Ployethylene sheets 6 mils
Reflective insulation
Stainless door and frames
PVC door and frames
100mm CHB
Structural steel roof framing matls
Acetylene
Oxygen
Welding rod
Structural steel purlins
Anchor bolt
Sagrods with nuts and bolts
Turnbuckle
Cross bracing
Steel plates
15mm - 32mmØ PVC (electl pipe)
Conduit fittings
Junction/utility/pull square box
1.6mm² - 5.5mm² Electric Wire (TW/THHN/TWHN)
8mm² - 22mm² Electric Wire (TW/THHN/TWHN)
30mm² - 38mm² Electric Wire (TW/THHN/TWHN)
50mm² - 60mm² Electric Wire (TW/THHN/TWHN)
Switches
Single convenience outlet
Duplex convenience outlet
Rope, 1" 0- 5 uses
Developing
Safety Helmet
Safety Shoes
Safety Vest
Working Gloves
Rain Coats (30% of the Duration)
Rubber Boots
Eye Goggles
Face Mask (Surgical/Cloth)
Pop up convenience outlet

EQUIPMENT RENTAL
simplicity RATES
in computation, the operated rental rates are preferred over the bare rental rates as the former includes ope
maintenance.

E.1 List of Equipment adopted in the


standard DUPA with make, model and
capacity.

DESCRIPTION MODEL
Bulldozer D6H SERIESS II PSDS/DD
Bulldozer w/ Ripper D6H SERIESS II PSDS/DD
Payloader LX80-2C
Motorized Road Grader G710A
Motorized Road Grader w/ Scarifier G710A
Compaction Equipment
Pneumatic Tire Roller 9-SWHL, 9.00X20,4PR
Vibratory Roller SD100DC
Tandem Steel Roller CC421
Plate Compactor 400-500 Gasoline Engine
Lifting Equipment
Crawler Crane All models
Truck Mounted Crane (31-35mt) All models
Truck Mounted Crane (41-45mt) All models
Low bed trailer
Excavating Equipment
Backhoe SE 130 LC-2
Backhoe w/ Breaker SE 130 LC-3
Backhoe w/ Chipping Hammer added by HTD
Backhoe, Wheel Mounted PW60N-1
Foundation Equipment
Vibro Hammer DPD600T Hydraulic Pile Driver
Asphalting Equipment
Asphalt Distributor ROSCO/5 ton
Asphalt Paver NF220BIIVDM
Concreting Equipment
Concrete Screeder Wacker Truss Screed
Concrete Paver COMMANDER III, FOUR TRACK
One Bagger Mixer
Transit Mixer All models
Hauling Equipment
Dump Truck All models
Cargo/Service Truck (160HP) All models
Boom Truck All models
Cargo/Service Truck (270HP) All models
Water Truck/Pump All models
Water Truck/Pump (2) All models
Air Equipment
Air Compressor (356-450cfm) All models
Air Compressor (161-185cfm) All models
Air Compressor (15-35 cfm) All models
Diamond Drill CP-8
Jackhammer
Pneumatic Drilling Machine
Pumping Equipment
Water Pump 100mmØ suction 2667 liters/min
Shop Equipment
Welding Machine (Electric Driven)
Welding Machine (Gas/Diesel Driven)
Special Support Equipment
Chainsaw

Truck mounted, Scissors Lift


Miscellaneous Equipment
Concrete Vibrator Flexible Shaft Type 2" Head Ø with 5Amperes Gasoline Driven Unit
Concrete Saw (7.5hp -14"Blade Ø)
Bar Cutter, Single Phase
Bar Bender 25mmØ Maximum Rebar, Three Phase
Asphalt Concrete Plant
Concrete Batch Plant
Pumpcrete
Others
Power Broom, Towed type
Hydroseeding Machine
Kneading Machine
Drop Hammer
Cutting Outfit
Steel Wheel with Nylon Rope
Improvised Bamboo with Bucket
Portable Mist-Based Sanitation Tent
Thermal Scanner (w/ rechargeable
battery)

Power Sprayer w/ complete accessories


Asphalt Kettle/Drum

labor factor cost


Construction Foreman 1.80
Skilled laborer 1.30
Unskilled laborer 1.00
unskilled 1.00
Govt suggested
unitcost Current Unit Cost
Kg 46.00 1.00 46.00 50.60
kgs 45.00 1.00 45.00 49.50
kgs 75.00 1.00 75.00 82.50
L 52.00 1.00 52.00
L 56.55 1.00 56.55
m 55.00 1.00 55.00
cu. m 4,585.00 1.00 4,585.00
sq. m 15.00 1.00 15.00
1.00 -
cu. M 800.00 1.00 800.00
cu. M 500.00 1.00 500.00
cu. M 800.00 1.00 800.00
cu. M 800.00 1.00 800.00
cu. M 300.00 1.00 300.00
cu. M 500.00 1.00 500.00
1.00 -
bag 270.00 1.00 270.00 297.00
pc 8,000.00 1.00 8,000.00
m 126.67 1.00 126.67
cu. m 1.00 -
L 220.00 1.00 220.00
L 55.00 1.00 55.00
bd. Ft 50.00 1.00 50.00
25.00 1.00 25.00
pcs 300.00 1.00 300.00
sq.ft. 40.00 1.00 40.00
pcs 300.00 1.00 300.00
kgs 75.00 1.00 75.00
pc 2,400.00 1.00 2,400.00
pc 3,000.00 1.00 3,000.00
pc 3,600.00 1.00 3,600.00
lm 150.00 1.00 150.00
sq. m 275.00 1.00 275.00
cu. m 1,100.00 1.00 1,100.00
m 75.00 1.00 75.00
cu. m 9,000.00 1.00 9,000.00
cu. m 8,000.00 1.00 8,000.00
cu. m 7,000.00 1.00 7,000.00
cu. m 5,500.00 1.00 5,500.00
cu. m 5,000.00 1.00 5,000.00
cu. m 4,600.00 1.00 4,600.00
L 1,000.00 1.00 1,000.00
pc 250.00 1.00 250.00
pc 275.00 1.00 275.00
1.00 -
1.00 -
pc 300.00 1.00 300.00
pc 150.00 1.00 150.00
pc 250.00 1.00 250.00
pc 30.00 1.00 30.00
pc 35.00 1.00 35.00
pc 25.00 1.00 25.00
pc 10.00 1.00 10.00
pc 2.00 1.00 2.00
sq. m 900.00 1.00 900.00
sq. m 1,500.00 1.00 1,500.00
sq. m 250.00 1.00 250.00
pc 5.00 1.00 5.00
m 255.00 1.00 255.00
m 250.00 1.00 250.00
m 245.00 1.00 245.00
m 230.00 1.00 230.00
pc 2.00 1.00 2.00
m 265.00 1.00 265.00
pc 15.00 1.00 15.00
sq. m 450.00 1.00 450.00
sq. m 400.00 1.00 400.00
gal 500.00 1.00 500.00
gal 575.00 1.00 575.00
pails 2,600.00 1.00 2,600.00
sq. m 300.00 1.00 300.00

set 250.00 1.00 250.00


sq. m 250.00 1.00 250.00
bags 55.00 1.00 55.00
bags 250.00 1.00 250.00
sq. m 166.67 1.00 166.67
pc 118.15 1.00 118.15
pc 852.00 1.00 852.00
pc 1,237.50 1.00 1,237.50
pc 1,290.00 1.00 1,290.00

SET 200,000.00 1.00 200,000.00


SET 1,107.00 1.00 1,107.00
SET 3,000.00 1.00 3,000.00
SET 6,000.00 1.00 6,000.00
ln.m. 18.51 1.00 18.51
ln.m. 37.25 1.00 37.25
ln.m. 16.03 1.00 16.03
PC 30.00 1.00 30.00
PC 150.00 1.00 150.00
PC 150.00 1.00 150.00

PC 350.00 1.00 350.00


UNIT 2,000.00 1.00 2,000.00
UNIT 15,000.00 1.00 15,000.00
SET 80,000.00 1.00 80,000.01
set 5,000.00 1.00 5,000.00
set 2,500.00 1.00 2,500.00
set 150,000.00 1.00 150,081.26
ln.m. 360.00 1.00 360.00
ln.m. 315.00 1.00 315.17
gal 350.00 1.00 350.00
gal 485.00 1.00 485.26
gal 275.00 1.00 275.00
gal 565.00 1.00 565.31
gal 515.00 1.00 515.00
gal 518.00 1.00 518.28
gal 575.00 1.00 575.00
L 60.00 1.00 60.03
pint 157.00 1.00 157.00
gal 450.00 1.00 450.24
gal 465.00 1.00 465.00
set 8,250.00 1.00 8,254.47
sq.m 15.00 1.00 15.00
sq.m 75.00 1.00 75.04
sq.m 4,000.00 1.00 4,000.00
sq.m 1,500.00 1.00 1,500.81
pc 11.00 1.00 11.00
kgs 55.00 1.00 55.03
kgs 50.00 1.00 50.00
kgs 25.00 1.00 25.01
kgs 75.00 1.00 75.00
kgs 900.00 1.00 900.49
pc 125.00 1.00 125.00
pc 50.00 1.00 50.03
pc 135.00 1.00 135.00
kgs 55.00 1.00 55.03
kgs 50.00 1.00 50.00
m 55.00 1.00 55.03
pc 10.00 1.00 10.00
pc 35.00 1.00 35.02
m 25.00 1.00 25.00
m 35.00 1.00 35.02
m 45.00 1.00 45.00
m 60.00 1.00 60.03
pc 25.00 1.00 25.00
set 125.00 1.00 125.07
set 175.00 1.00 175.00
lin.m. 40.00 1.00 40.00
each 15.00 1.00 15.00
m-day 0.34 1.00 0.34
m-day 4.11 1.00 4.11
m-day 2.22 1.00 2.22
m-day 7.67 1.00 7.67
m-day 0.34 1.00 0.34
m-day 1.39 1.00 1.39
m-day 5.00 1.00 5.00
m-day 5.00 1.00 5.00
set 200.00 1.00 200.11

ental rates as the former includes operator's wages, fringe benefits, fuel, oil, lubricants and equipment
maintenance.

FLYWHEEL ADJUSTED
CAPACITY HORSEPOWER 2014 Rental Rate RENTAL RATE Rental Rate per day
165 3,379.00 3,492.53 27,940.24
165 3,885.85 31,086.80
1.5 cu.m/1.95 cu. Yd 110 1,733.00 1,810.96 14,487.68
140 2,173.00 2,260.48 18,083.84
140 2,824.00 22,592.00
-
10 mt 107 561.00 4,488.00
10 mt 125 1,846.00 1,916.40 15,331.20
10.10 mt 123.4 1,652.00 13,216.00
5 123.00 123.00 984.00
-
36-40mt 190 1,522.00 1,902.00 15,216.00
31-35 mt 238 1,861.00 1,861.00 14,888.00
41-45 mt 246 2,151.00 2,606.00 20,848.00
3,750.00 30,000.00
-
0.80 cu.m/1.04 cu yd 99 1,537.00 1,537.00 12,296.00
0.80 cu.m/1.04 cu yd 99 2,074.95 1,998.00 15,984.00
99 1,998.00 15,984.00
0.28 cu m/0.37 cu yd 50 922.00 922.00 7,376.00
-
60 ton 201 2,123.00 16,984.00
-
3000 USG 100 936.00 7,488.00
80 1,833.00 14,664.00
-
5.5 545.00 545.00 4,360.00
6,765.00 6,765.00 54,120.00
4-6 cu ft/min 172.00 172.00 1,376.00
5-6 cu yd 1,318.00 1,386.99 11,095.92
-
12 cu yd 290 1,420.00 1,420.00 11,360.00
2-5 mt 160 783.00 783.00 6,264.00
2-5 mt 160 1,017.90 1,017.00 8,136.00
9-10 mt 270 1,212.00 1,212.00 9,696.00
16000 L 360 2,450.00 2,543.42 20,347.36
1000L 360 1,420.00 2,543.42
-
356-450 cfm 130 965.00 965.00 7,720.00
161-185 cfm 69 502.00 502.00 4,016.00
15-35 cfm 20 205.00 205.00 1,640.00
201.25 201.00 1,608.00
150.00 150.00 1,200.00
170.00 170.00 1,360.00
-
50 16 266.25 266.25 2,130.00
-
500Ampere 391.00 391.00 3,128.00
300Ampere 371.00 371.00 2,968.00
-
75.36 75.36 602.88
-
1,386.00 1,386.00 11,088.00
-
with 5Amperes Gasoline Driven Unit 91.25 91.25 730.00
32.63 32.63 261.04
219.75 219.75 1,758.00
um Rebar, Three Phase 351.50 351.50 2,812.00
4,286.63 4,286.63 34,293.04
1,759.50 1,759.50 14,076.00
6,900.00
130.54 130.54 1,044.32
952.00 952.00 7,616.00
93.75 93.75 750.00
187.50 187.50 1,500.00
200.00 200.00 1,600.00
45.45 45.45 363.60
300.00 300.00 2,400.00
200.00 200.00 1,600.00
ls 9.79 1.00 9.79

ls 1.03 1.00 1.03

ls 3.47 1.00 3.47


10.00 10.00 80.00

basic daily basic monthly leaves 13th month sss


666.00 17,369.28 666.00 1,447.44 1,517.50
481.00 12,544.48 481.00 1,045.37 1,072.50
370.00 9,649.60 370.00 804.13 817.50
596.77 15,563.76 596.77 1,296.98 817.50
0.1
45.50

4583.3333333

G40 10 0.616 6
G60 12 0.888
G60 16 1.578 6
G60 20 2.466 7.5
G60 20 2.466 9
G60 25 3.853 9
list all diameter of this series specify length
list all diameter of this series specify length
philhealth pag-ibig wage monthly wage daily wage hourly
260.57 100.00 21,360.79 819.05 102.38
188.19 100.00 15,431.54 591.70 73.96
144.76 100.00 11,885.99 455.75 56.97
144.76 100.00 18,519.77 710.11 88.76
3.696 176.5 47.754329004

9.468 458.4 48.415716096


18.495 904.1 48.883482022
22.194 1084.8 48.878075155
34.677 1684.92 48.588978285
194.76625156
48.69156289
96.445891894
48.222945947
CEMENT 87.00 BAGS
10mm RSB X6m 160 PCS
CHB 1280 CHB
SAND 6.5 CU.M.
GRAVEL 15.5 CU.M.
1 1/4" ∅ GI Pipe x 6M 22 PCS
4"x4" Interinks (1.2M) 77 sq.m.
forms 167.84 sq.m.
DETAILED UNIT COST ANALYSIS

Item No./Description: B.5 Project Billboard / Signboard


Quantity 1.00
Unit of Measurement: each
Labor output per hour: 1.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 0 1.00 102.38 - 1.00


b. Skilled laborer 0 1.00 73.96 - 1.00
c. Unskilled laborer 0 1.00 56.97 - 1.00

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Dump Truck 0 1.00 1,420.00 - 1.00
Payloader 0 1.00 1,810.96 - 1.00
Bulldozer 0 1.00 3,492.53 - 1.00

Subtotal B -

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
Plywood (1/2' x 4' x 8') pc 1.00 300.00 300.00
Good lumber bd.ft. 41.00 50.00 2,050.00
Project Sign (Tarpaulin) sq.ft. 32.00 40.00 1,280.00
Assorted CWN kgs. 1.00 75.00 75.00
Consumables (5% of matls cost) 15.00
Subtotal C 3,720.00
SUMMARY
A. Labor -
B. Equipment -
C. Materials 3,720.00
D. Total Estimated Direct Cost 3,720.00
E. Direct Unit Cost 3,720.00
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0 -
L. Unit Cost 3,720.00
DETAILED UNIT COST ANALYSIS

Item No./Description: Mobilization and Demobilization


Quantity 1.00
Unit of Measurement: l.s.
Labor output per hour: 1.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 0 1.00 102.38 - 1.00


b. Skilled laborer 0 1.00 73.96 - 1.00
c. Unskilled laborer 0 1.00 56.97 - 1.00
Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Backhoe 1
Dumptruck 1
Payloader 1
Bulldozer 1
Road Grader 1
Vibratory Roller 1
Water truck Err:509
Subtotal B Err:509

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
0.43
0.29
0.12
0.46
0.13
0.23
2.19
0.00
0.01
Subtotal C -
SUMMARY
A. Labor -
B. Equipment Err:509
C. Materials -
D. Total Estimated Direct Cost Err:509
E. Direct Unit Cost Err:509
F. OCM 0.12 Err:509
G. Profit 0.08 Err:509
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 Err:509
L. Unit Cost Err:509
DETAILED UNIT COST ANALYSIS

Item No./Description: B.9 Mobilization / Demobilization


Quantity 1.00
Unit of Measurement: ls
Labor output per hour: 1.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 0 1.00 102.38 - 1.00


b. Skilled laborer 0 1.00 73.96 - 1.00
c. Unskilled laborer 0 1.00 56.97 - 1.00

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Low bed trailer 2 1.00 3,750.00 7,500.00 1.00
Payloader 1 1.00 1,810.96 1,810.96 1.00
Bulldozer 1 1.00 3,492.53 3,492.53 1.00
Backhoe 1 1.00 1,537.00 1,537.00 1.00
Dump truck 2 1.00 1,420.00 2,840.00 1.00
Motorized Road Grader 1 1.00 2,260.48 2,260.48 1.00
Vibratory Roller 1 1.00 1,916.40 1,916.40 1.00
Water Truck/Pump 1 1.00 2,543.42 2,543.42 1.00
Plate Compactor 1 1.00 123.00 123.00 1.00
Dump truck 1 1.00 1,420.00 1,420.00 1.00

Subtotal B 25,443.79

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
A. Labor -
B. Equipment 25,443.79
C. Materials -
D. Total Estimated Direct Cost 25,443.79
E. Direct Unit Cost 25,443.79
F. OCM 0.12 3,053.25
G. Profit 0.08 2,035.50
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 1,526.63
L. Unit Cost 32,059.18
DETAILED UNIT COST ANALYSIS

Item No./Description: 800(1) Clearing and Grubbing


Quantity 500.00
Unit of Measurement: sq.m.
Labor output per hour: 500.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 1 1.00 102.38 102.38 1.00


b. Skilled laborer 0 1.00 73.96 - 1.00
c. Unskilled laborer 2 1.00 56.97 113.94 1.00

Subtotal A 216.32
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Dump Truck 2 1.00 1,420.00 2,840.00 1.00
Payloader 1 1.00 1,810.96 1,810.96 1.00
Bulldozer 1 1.00 3,492.53 3,492.53 1.00

Subtotal B 8,143.49

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials

Consumables (5% of matls cost) -


Subtotal C -
SUMMARY
A. Labor 216.32
B. Equipment 8,143.49
C. Materials -
D. Total Estimated Direct Cost 8,359.81
E. Direct Unit Cost 16.72
F. OCM 0.12 1,003.18
G. Profit 0.08 668.78
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 501.59
L. Unit Cost 21.07
DETAILED UNIT COST ANALYSIS

Item No./Description: 102(2) Roadway Excavation (Surplus Common) including disposal


Quantity 60.00
Unit of Measurement: pcs
Labor output per hour: 60.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 1 1.00 102.38 102.38 1.00


b. Unskilled Laborer 2 1.00 56.97 113.94 1.00

Subtotal A 216.32
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Backhoe 2 1.00 1,537.00 3,074.00 1.00
Payloader 1 1.00 1,810.96 1,810.96 1.00
Payloader 1 0.25 1,810.96 452.74 1.00
Dump truck 2 1.00 1,420.00 2,840.00 1.00
Minor Tools (10% of Labor Cost) 21.63

Subtotal B 8,199.33

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials

Consumables (5% of matls cost) -

Subtotal C -
SUMMARY
A. Labor 216.32
B. Equipment 8,199.33
C. Materials -
D. Total Estimated Direct Cost 8,415.65
E. Direct Unit Cost 140.26
F. OCM 0.12 1,009.88
G. Profit 0.08 673.25
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 504.94
L. Unit Cost 176.73
DETAILED UNIT COST ANALYSIS

Item No./Description: 803(1)b Structure Excavation (Common Soil)


Quantity 14.00
Unit of Measurement: sq.m.
Labor output per hour: 14.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 0 1.00 102.38 - 1.00


b. Skilled laborer 0 1.00 73.96 - 1.00
c. Unskilled laborer 0 1.00 56.97 - 1.00

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Dump Truck 2 1.00 1,420.00 2,840.00 1.00
Backhoe 1 1.00 1,537.00 1,537.00 1.00
Minor Tools (10% of Labor Cost) -

Subtotal B 4,377.00

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials

Consumables (5% of matls cost) -

Subtotal C -
SUMMARY
A. Labor -
B. Equipment 4,377.00
C. Materials -
D. Total Estimated Direct Cost 4,377.00
E. Direct Unit Cost 312.64
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0 -
L. Unit Cost 312.64
DETAILED UNIT COST ANALYSIS

Item No./Description: 104(1)a Embankment from Roadway Excavation (Common Soil)


Quantity 50.00
Unit of Measurement: cu.m.
Labor output per hour: 50.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 1 0.83 102.38 84.98 1.00


b. Unskilled Laborer 2 0.83 56.97 94.57 1.00
c. Construction Foreman 1 1.00 102.38 102.38 1.00
c. Unskilled Laborer 2 1.00 56.97 113.94 1.00

Subtotal A 395.86
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Backhoe 2 1.00 1,537.00 3,074.00 1.00
Dump Truck 1 1.00 1,420.00 1,420.00 1.00
PayLoader 1 1.00 1,810.96 1,810.96 1.00
Motorized Road Grader 2 1.00 2,260.48 4,520.96 1.00
Vibratory Roller 1 1.00 1,916.40 1,916.40 1.00
Water Truck/Pump 1 1.00 2,543.42 2,543.42 1.00
Minor Tools (10% of Labor Cost) -

Subtotal B 15,285.74

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials

Consumables (5% of matls cost) -


Subtotal C -
SUMMARY
A. Labor 395.86
B. Equipment 15,285.74
C. Materials -
D. Total Estimated Direct Cost 15,681.60
E. Direct Unit Cost 313.63
F. OCM 0.12 1,881.79
G. Profit 0.08 1,254.53
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 940.90
L. Unit Cost 395.18
DETAILED UNIT COST ANALYSIS

Item No./Description: 804(1)b Embankment from Common Borrow by Equipment


Quantity 9.84
Unit of Measurement: sq.m.
Labor output per hour: 9.840
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 1 1.00 102.38 102.38 1.00


b. Skilled laborer 0 1.00 73.96 - 1.00
c. Unskilled laborer 3 1.00 56.97 170.91 1.00

Subtotal A 273.29
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Backhoe 2 1.00 2,689.75 5,379.50 1.00
Plate Compactor 1 1.00 215.25 215.25 1.00
Minor Tools (10% of Labor Cost) 27.33 1.00

Subtotal B 5,622.08

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials

Consumables (5% of matls cost) -

Subtotal C -
SUMMARY
A. Labor 273.29
B. Equipment 5,622.08
C. Materials -
D. Total Estimated Direct Cost 5,895.37
E. Direct Unit Cost 599.12
F. OCM 0.12 707.44
G. Profit 0.08 471.63
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 353.72
L. Unit Cost 754.89
DETAILED UNIT COST ANALYSIS

Item No./Description: 105(1)a Subgrade Preparation (Common Material)


Quantity 300.00
Unit of Measurement: sq.m.
Labor output per hour: 300.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 1 1.00 102.38 102.38 1.00


b. Skilled laborer 0 1.00 73.96 - 1.00
c. Unskilled laborer 2 1.00 56.97 113.94 1.00

Subtotal A 216.32
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Motorized Road Grader 1 1.00 2,260.48 2,260.48 1.00
Vibratory Roller 1 1.00 1,916.40 1,916.40 1.00
Water Truck/Pump 1 1.00 2,543.42 2,543.42 1.00

Subtotal B 6,720.30

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials

Consumables (5% of matls cost) -

Subtotal C -
SUMMARY
A. Labor 216.32
B. Equipment 6,720.30
C. Materials -
D. Total Estimated Direct Cost 6,936.62
E. Direct Unit Cost 23.12
F. OCM 0.12 832.39
G. Profit 0.08 554.93
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 416.20
L. Unit Cost 29.13
DETAILED UNIT COST ANALYSIS

Item No./Description: 200(1) Aggregate Subbase Course


Quantity 50.00
Unit of Measurement: cu.m.
Labor output per hour: 50.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 1 1.00 102.38 102.38 1.00


b. Skilled laborer 0 1.00 73.96 - 1.00
c. Unskilled laborer 2 1.00 56.97 113.94 1.00

Subtotal A 216.32
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Motorized Road Grader 1 1.00 2,260.48 2,260.48 1.00
Vibratory Roller 1 1.00 1,916.40 1,916.40 1.00
Water Truck/Pump 1 1.00 2,543.42 2,543.42 1.00

Subtotal B 6,720.30

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
Agg. Subbase course matls cu.m. 25.00 500.00 12,500.00
Consumables (5% of matls cost) 625.00

Subtotal C 13,125.00
SUMMARY
A. Labor 216.32
B. Equipment 6,720.30
C. Materials 13,125.00
D. Total Estimated Direct Cost 20,061.62
E. Direct Unit Cost 401.23
F. OCM 0.12 2,407.39
G. Profit 0.08 1,604.93
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 1,203.70
L. Unit Cost 505.55
DETAILED UNIT COST ANALYSIS

Portland Cement Concrete Pavement (Unreinforced) - 0.23


Item No./Description: 311(1)c1 m thick, 14 days
Quantity 70.00
Unit of Measurement: sq.m.
Labor output per hour: 70.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 1 1.00 102.38 102.38 1.00


b. Skilled laborer 4 1.00 73.96 295.85 1.00
c. Unskilled laborer 12 1.00 56.97 683.63 1.00
Subtotal A 1,081.86
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Concrete Vibrator 2 1.00 91.25 182.50 1.00
Concrete Screeder 1 1.00 545.00 545.00 1.00
Concrete Saw (7.5hp -14"Blade Ø) 1 1.00 32.63 32.63 1.00
Bar Cutter, Single Phase 1 1.00 219.75 219.75 1.00
Minor Tools (5% of Labor Cost) 54.09
Subtotal B 1,033.97

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
Reinforcing Steel Bar (Grade 40) 30.10 45.00 1,354.50 0.43
Curing Compound 20.30 52.00 1,055.60 0.29
Asphalt Sealant 8.40 56.55 475.02 0.12
Forms (Rental)-200mm 32.20 55.00 1,771.00 0.46
Fine aggregates 8.86 800.00 7,084.00 0.13
Coarse aggregates 16.10 800.00 12,880.00 0.23
Portland cement 153.30 270.00 41,391.00 2.19
Concrete Saw (Diamond Blade -14"Ø) 0.01 8,000.00 84.00 0.00
Grease tar 0.55 220.00 120.74 0.01
Subtotal C 66,215.86
SUMMARY
A. Labor 1,081.86
B. Equipment 1,033.97
C. Materials 66,215.86
D. Total Estimated Direct Cost 68,331.69
E. Direct Unit Cost 976.17
F. OCM 0.12 8,199.80
G. Profit 0.08 5,466.53
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 4,099.90
L. Unit Cost 1,229.97
DETAILED UNIT COST ANALYSIS
Item No./Description: 804(1)a Embankment from structure excavation
Quantity 9.84
Unit of Measurement: cu. M
Labor output per hour: 9.84
Duration 1 hour
Description No. of men No. of hours Hourly rate Amount
A. Labor
Excavation work
a. Construction Foreman 0 1.00 83.25 -
b. Unskilled laborer 0 1.00 46.25 -

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Excavation work
a. Plate compactor 1 0.75 123.00 92.25
b. Backhoe 1 0.75 1,537.00 1,152.75
Minor tools (10% labor cost) -

Subtotal B 1,245.00

Name and specifications Unit Quantity Unit Cost Amount


C. Materials

Subtotal C -
SUMMARY
A. Labor -
B. Equipment 1,245.00
C. Materials -
D. Total Estimated Direct Cost 1,245.00
E. Direct Unit Cost 126.52
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0 -
L. Unit Cost 126.52
LGU 189.37
Variance 62.85
DETAILED UNIT COST ANALYSIS

Item No./Description: 804(4) Gravel bedding (see derivation using 26km AHD)
Quantity 1.20
Unit of Measurement: cu. M
Labor output per hour: 1.20
Duration 1 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor
a. Construction Foreman 0 1.00 83.25 - 1.00
b. Unskilled laborer 0 1.00 46.25 - 1.00

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
a. Plate Compactor 0 0.50 123.00 - 0.50

Minor tools (10% of labor) -


Subtotal B -

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
Gravel fill cu. M 1.26 600.00 756.00 1.05

Subtotal C 756.00
SUMMARY
A. Labor -
B. Equipment -
C. Materials 756.00
D. Total Estimated Direct Cost 756.00
E. Direct Unit Cost 630.00
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0 -
L. Unit Cost 630.00
LGU 1,066.88
Variance 436.88

password: henry
DETAILED UNIT COST ANALYSIS

Item No./Description: 900(1) Structural Concrete(Class A, 28 days)


Quantity 0.27
Unit of Measurement: sq.m.
Labor output per hour: 0.270
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 0 1.00 102.38 - 1.00


b. Skilled laborer 0 1.00 73.96 - 1.00
c. Unskilled laborer 0 1.00 56.97 - 1.00

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
One Bagger Mixer 0 1.00 172.00 - 1.00
Minor Tools (10% of labor Cost) - 1.00

Subtotal B -

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
Coarse aggregates cu.m. 1.00 600.00 600.00
Fine aggregates cu.m. 0.50 600.00 300.00
Portland cement bags 9.50 245.00 2,327.50
Consumables (5% of matls cost) 161.38

Subtotal C 3,388.88
SUMMARY
A. Labor -
B. Equipment -
C. Materials 3,388.88
D. Total Estimated Direct Cost 3,388.88
E. Direct Unit Cost 12,551.39
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0 -
L. Unit Cost 12,551.39
DETAILED UNIT COST ANALYSIS

Item No./Description: 902( 1) Reinforcing Steel of Reinforced Concrete Structures


Quantity 143.44
Unit of Measurement: sq.m.
Labor output per hour: 143.438
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 0 1.00 102.38 - 1.00


b. Skilled laborer 0 1.00 73.96 - 1.00
c. Unskilled laborer 0 1.00 56.97 - 1.00

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Bar Cutter, Single Phase 0 1.00 219.75 - 1.00
Bar Bender 0 1.00 351.50 - 1.00
Minor Tools (10% of Labor Cost) -

Subtotal B -

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
Reinforcing Steel Bar (Grade 40) kg 1.00 51.00 51.00
Tie wire kg 0.02 75.00 1.13
Consumables (5% of matls cost) 2.61

Subtotal C 54.73
SUMMARY
A. Labor -
B. Equipment -
C. Materials 54.73
D. Total Estimated Direct Cost 54.73
E. Direct Unit Cost 0.38
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0 -
L. Unit Cost 0.38
DETAILED UNIT COST ANALYSIS

Structural concrete for tie beam, column, suspended


Item No./Description: 900(4) slab, beam (Class A 28 days)
Quantity 2,796.89
Unit of Measurement: sq. m
Labor output per hour: 0.357
Duration 7,834.43 hour
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor
a. Construction Foreman 1 7,834.43 83.25 652,215.95 1.00
b. Skilled laborer 1 7,834.43 60.13 471,044.85 1.00
c. Unskilled laborer 4 7,834.43 46.25 1,449,368.77 1.00

Subtotal A 2,572,629.56
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment

a. One bagger mixer 1 7,834.43 172.00 1,347,521.23 1.00

Minor Tools (10% of Labor Cost) 257,262.96 10%

Subtotal B 1,604,784.19

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
Portland cement bag 25,172.01 220.00 5,537,842.20 9.00
Fine aggregates cu. M 1,398.45 800.00 1,118,756.00 0.5000
Coarse aggregates cu. M 2,796.89 800.00 2,237,512.00 1.000

Subtotal C 8,894,110.20
SUMMARY
A. Labor 2,572,629.56
B. Equipment 1,604,784.19
C. Materials 8,894,110.20
D. Total Estimated Direct Cost 13,071,523.95
E. Direct Unit Cost 4,673.59
F. OCM - -
G. Profit - -
H. Mineral Tax 40.00 per cu. M
I. Excise Tax see table
J. Contractor's Tax - -
K. VAT - -
L. Unit Cost 4,673.59
LGU 3,384.06 No pumpcrete
password: henry LGU 3,516.98 w/ pumpcrete
variance 1 (1,289.53)
variance 2 (1,156.61)
DETAILED UNIT COST ANALYSIS

Item No./Description: 903 Shoring (2-5 storey bldg)


Quantity 1.00
Unit of Measurement: sq .m
Labor output per hour: 3.24
Duration 0.31 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor
Installation
a. Construction Foreman 0 0.31 83.25 - 1.00
b. Skilled laborer 0 0.31 60.13 - 1.00
c. Unskilled laborer 0 0.31 46.25 - 1.00
Stripping 0
a. Construction Foreman 0 0.13 83.25 - 0.41
b. Unskilled laborer 0 0.13 46.25 - 0.41

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment

Minor tools (10% of labor cost) -

Subtotal B -

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
Plywood (1/2' x 4' x 8') pcs 0.35 330.00 38.17 0.3470000
Good lumber bd. Ft 7.19 50.00 119.83 7.190
Assorted CWN kgs 0.21 75.00 15.75 0.21
Consumables (5% of matls cost) 8.69

Subtotal C 182.44
SUMMARY
A. Labor -
B. Equipment - -
C. Materials 182.44
D. Total Estimated Direct Cost 182.44
E. Direct Unit Cost 182.44
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0 -
K. VAT 0 -
L. Unit Cost 182.44 1,025.84
DETAILED UNIT COST ANALYSIS

Item No./Description: 1046 100 mm CHB (Non load bearing)


Quantity 1.00
Unit of Measurement: sq. m
Labor output per hour: 7.650
Duration 0.13 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 0 0.13 83.25 - 1.00


b. Skilled laborer 0 0.13 60.13 - 1.00
c. Unskilled laborer 0 0.13 46.25 - 1.00

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
One bagger mixer 0 0.13 172.00 - 1.00
Minor tools (10% of labor cost) -

Subtotal B -

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
100mm CHB pc 12.50 11.00 137.50 12.500
Portland cement bag 0.39 245.00 96.29 0.393
Fine aggregates cu. M 0.05 600.00 27.00 0.045
Reinforcing Steel Bar (Grade 40) kgs 3.24 51.00 165.24 3.240
Tie wire kgs 0.05 75.00 3.75 0.050
Qty derived from 10mmØ bars spaced at 0.4m
vertically and every 3 layers

Subtotal C 429.78
SUMMARY
A. Labor -
B. Equipment -
C. Materials 429.78
D. Total Estimated Direct Cost 429.78
E. Direct Unit Cost 429.78
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax 40.00
I. Excise Tax 23.16
J. Contractor's Tax 0
K. VAT 0 -
L. Unit Cost 429.78
DETAILED UNIT COST ANALYSIS

Item No./Description: 1027(1) Cement plaster finish


Quantity 21.38
Unit of Measurement: sq. m
Labor output per hour: 21.375
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 0 1.00 83.25 - 1.00


b. Skilled laborer 0 1.00 60.13 - 1.00
c. Unskilled laborer 0 1.00 46.25 - 1.00

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment

Minor tools (10% of labor cost) -

Subtotal B -

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
Portland cement bag 7.05 245.00 1,728.17 0.330
Fine aggregates cu. M 0.58 600.00 346.28 0.027

Subtotal C 2,074.44
SUMMARY
A. Labor -
B. Equipment -
C. Materials 2,074.44
D. Total Estimated Direct Cost 2,074.44
E. Direct Unit Cost 97.05
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax 40.00
I. Excise Tax 23.16
J. Contractor's Tax 0 -
K. VAT 0 -
L. Unit Cost 97.05
DETAILED UNIT COST ANALYSIS

Item No./Description: Interlinks


Quantity 1.00
Unit of Measurement: sq.m.
Labor output per hour: 1.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 0 0.04 83.25 - 0.04


b. Skilled laborer 0 0.04 60.13 - 0.04
c. Unskilled laborer 0 0.04 46.25 - 0.04

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment

Minor tools (10% of labor cost) -

Subtotal B -

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
4"x4" INTERLINKS sq.m. 1.00 210.00 210.00 1.000
Consumables (0.5% of matls cost) 1.05

Subtotal C 211.05
SUMMARY
A. Labor -
B. Equipment -
C. Materials 211.05
D. Total Estimated Direct Cost 211.05
E. Direct Unit Cost 211.05
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax 40.00
I. Excise Tax 23.16
J. Contractor's Tax 0
K. VAT 0 -
L. Unit Cost 211.05
DETAILED UNIT COST ANALYSIS

Item No./Description: 1 1/4" ∅ GI Pipe


Quantity 1.00
Unit of Measurement: sq.m.
Labor output per hour: 1.000
Duration 1.00 hours
Description No. of men No. of hours Hourly rate Amount Factor
A. Labor

a. Construction Foreman 0 0.04 83.25 - 0.04


b. Skilled laborer 0 0.04 60.13 - 0.04
c. Unskilled laborer 0 0.04 46.25 - 0.04

Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment

Minor tools (10% of labor cost) -

Subtotal B -

Name and specifications Unit Quantity Unit Cost Amount Factor


C. Materials
1 1/4" ∅ GI Pipe ln.m. 1.00 145.00 145.00 1.000
Consumables (0.5% of matls cost) 0.73

Subtotal C 145.73
SUMMARY
A. Labor -
B. Equipment -
C. Materials 145.73
D. Total Estimated Direct Cost 145.73
E. Direct Unit Cost 145.73
F. OCM 0 -
G. Profit 0 -
H. Mineral Tax 40.00
I. Excise Tax 23.16
J. Contractor's Tax 0
K. VAT 0 -
L. Unit Cost 145.73
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED FENCE FOR BARANGAY CALLANGIGAN

MINIMUM EQUIPMENT REQUIREMENT


Equipment Description Capacity No. of Equipments
1. Backhoe (SE 130 LC-2) 1.00 m³ 2.00

2. Bulldozer (D6H SERIES II PSDS/DD) 160 HP 1.00

3. Motorized Road Grader (G710A) 100-125 HP 1.00

4. Vibratory Roller (SD100DC) 8 tons 1.00

5. Transit Mixer (All Models) 4.00 m³ 1.00

6. Cargo/Service Truck(All Models) 9-10mt 1.00

7. Payloader (LX9-2C) 1.00 m³ 1.00

Prepared by: Recommending Approval:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer

Approved by:

Hon. JIMMY S. GAMAZON JR.


Municipal Mayor
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED FENCE FOR BARANGAY CALLANGIGAN

DETAILED UNIT PRICE ANALYSIS


Provision of Progress Photographs
Name and Capacity No. of units No. of Hours Hourly Rate Amount
A. LABOR

A.1. Laborer

A.1.1 Earthworks 1.00 0.50 400.00 200.00

A.1.2 Wood Frame & Tarpaulin 2.00 0.50 400.00 400.00

A.2. Materials No. of units Unit Unit cost Amount

A.1.1 Wood Frame (2"x2") 25.00 bd.ft 75.00 1,875.00

A.1.1 CWN 2.00 kg. 100.60 201.20

A.1.1 Tarpaulin 1.00 l.s. 2,500.00 2,500.00

Total Unit Cost 5,176.20

Prepared by: Recommending Approval:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer

Approved by:

Hon. JIMMY S. GAMAZON JR.


Municipal Mayor
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED FENCE FOR BARANGAY CALLANGIGAN

DETAILED UNIT PRICE ANALYSIS


Structure Excavation
Name and Capacity No. of units No. of Hours Hourly Rate Amount
A. EQUIPMENT

A.1. Bulldozer (D6H SERIES II PSDS/DD) 1.00 Err:509 1,303.34 Err:509

A.1.1 Fuel Consumption 1.00 Err:509 697.00 Err:509

Total Unit Cost Err:509

Prepared by: Recommending Approval:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer

Approved by:

Hon. JIMMY S. GAMAZON JR.


Municipal Mayor
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED FENCE FOR BARANGAY CALLANGIGAN

DETAILED UNIT PRICE ANALYSIS


Class "A" Concrete
Name and Capacity No. of units No. of Hours Hourly Rate Amount
A. EQUIPMENT

A.1. Transit Mixer (All Models) 1.00 118.43 99.14 11,741.48

A.1.1 Fuel Consumption 1.00 118.43 51.66 6,118.27

A.2. Bulldozer (D6H SERIES II PSDS/DD) 1.00 1.55 1,303.34 2,024.79

A.2.1 Fuel Consumption 1.00 1.55 697.00 1,082.82

A.3. Payloader (LX9-2C) 1.00 1.84 734.09 1,347.79

A.3.1 Fuel Consumption 1.00 1.84 369.00 677.48

A.4. Cargo/Service Truck(All Models) 1.00 2,996.37 304.23 911,585.17

A.4.1 Fuel Consumption 1.00 2,996.37 615.00 1,842,766.60

B. MATERIALS

A.1. Cement 16.42 276.00 4,530.82

A.2. Sand 0.78 120.00 93.31

A.3. Gravel 1.56 120.00 186.62

Total Unit Cost 2,782,155.15

Prepared by: Recommending Approval:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer

Approved by:

Hon. JIMMY S. GAMAZON JR.


Municipal Mayor
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED FENCE FOR BARANGAY CALLANGIGAN


STA. 0+000 - STA. 2+000
SUMMARY OF QUANTITES

DESCRIPTION QTY UNIT UNIT COST ESTIMATED DIRECT COST OCM & PROFIT VAT TOTAL INDIRECT COST TOTAL COST
A. EARTHWORKS

A.1. Clearing and Grubbing Err:509 sq.m. 9.53 Err:509 Err:509

A.2. Common Excavation Err:509 cu.m. 80.01 Err:509 Err:509

TOTAL OF PART A Err:509 Err:509

B. ROAD CONSTRUCTION

B.1. Class "A" Concrete 1.73 cu.m. 4065.34 7,024.91 7,024.91

TOTAL OF PART B 7,024.91 7,024.91

TOTAL Err:509 Err:509

Prepared by: Recommending Approval:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer

Approved by:

Hon. JIMMY S. GAMAZON JR.


Municipal Mayor