PVsyst - Simulation report


Grid-Connected System

Project: 810.7 KWp Rooftop Solar Power Plant for Multazim Group at ASF Fiber Mill
Variant: N/S
No 3D scene defined, no shadings
System power: 810 kWp
Bharadoba, Bhaluka, Mymensingh - Bangladesh

Client Chint Solar Bangladesh Company


Multazim Group
Voradoba, Bhaluka, Mymensingh
Bangladesh
Project: 810.7 KWp Rooftop Solar Power Plant for Multazim
Group at ASF Fiber Mill
PVsyst V7.2.3
Variant: N/S
VC0, Simulation date:
12/11/22 10:43
with v7.2.3

Project summary
Geographical Site Situation Project settings
Bharadoba, Bhaluka, Mymensingh Latitude 24.45 °N Albedo 0.20
Bangladesh Longitude 90.39 °E
Altitude 17 m
Time zone UTC+6

Meteo data
Bharadoba, Bhaluka, Mymensingh
Meteonorm 8.0 (1996-2015), Sat=100% - Synthetic

System summary
Grid-Connected System No 3D scene defined, no shadings
Simulation for year no 1

PV Field Orientation Near Shadings User's needs


Fixed planes 2 orientations No Shadings Unlimited load (grid)
Tilts/azimuths 4/0°
4 / 180 °

System information
PV Array Inverters
Nb. of modules 1472 units Nb. of units 7 units
Pnom total 810 kWp Pnom total 700 kWac
Pnom ratio 1.157

Results summary
Produced Energy 1047 MWh/year Specific production 1293 kWh/kWp/year Perf. Ratio PR 84.93 %

Table of contents
Project and results summary 2
General parameters, PV Array Characteristics, System losses 3
Main results 5
Loss diagram 6
Special graphs 7
Aging Tool 8

12/11/22 PVsyst Licensed to Page 2/9


Project: 810.7 KWp Rooftop Solar Power Plant for Multazim
Group at ASF Fiber Mill
PVsyst V7.2.3
Variant: N/S
VC0, Simulation date:
12/11/22 10:43
with v7.2.3

General parameters
Grid-Connected System No 3D scene defined, no shadings

PV Field Orientation
Orientation Sheds configuration Models used
Fixed planes 2 orientations No 3D scene defined Transposition Perez
Tilts/azimuths 4/0° Diffuse Perez, Meteonorm
4 / 180 ° Circumsolar separate

Horizon Near Shadings User's needs


Free Horizon No Shadings Unlimited load (grid)

PV Array Characteristics
PV module Inverter
Manufacturer Astronergy Manufacturer ChintPower
Model CHSM72M-HC-550 Model CPS SCA110KTL-DO/EU
(Custom parameters definition) (Custom parameters definition)
Unit Nom. Power 550 Wp Unit Nom. Power 100 kWac
Number of PV modules 1472 units Number of inverters 7 unit
Nominal (STC) 810 kWp Total power 700 kWac
Modules 92 Strings x 16 In series Operating voltage 200-1000 V
At operating cond. (50°C) Max. power (=>45°C) 110 kWac
Pmpp 739 kWp Pnom ratio (DC:AC) 1.16
U mpp 605 V
I mpp 1223 A

Total PV power Total inverter power


Nominal (STC) 810 kWp Total power 700 kWac
Total 1472 modules Nb. of inverters 7 units
Module area 3803 m² Pnom ratio 1.16
Cell area 3500 m²

Array losses
Array Soiling Losses Thermal Loss factor DC wiring losses
Loss Fraction 2.0 % Module temperature according to irradiance Global array res. 11 mΩ
Uc (const) 29.0 W/m²K Loss Fraction 2.0 % at STC
Uv (wind) 0.0 W/m²K/m/s

Serie Diode Loss LID - Light Induced Degradation Module Quality Loss
Voltage drop 0.7 V Loss Fraction 2.0 % Loss Fraction -0.8 %
Loss Fraction 0.1 % at STC

Module mismatch losses Strings Mismatch loss Module average degradation


Loss Fraction 2.0 % at MPP Loss Fraction 0.1 % Year no 1
Loss factor 0.55 %/year
Mismatch due to degradation
Imp RMS dispersion 0.4 %/year
Vmp RMS dispersion 0.4 %/year

IAM loss factor


Incidence effect (IAM): User defined profile

0° 40° 50° 60° 70° 75° 80° 85° 90°


1.000 1.000 1.000 1.000 1.000 0.984 0.949 0.830 0.000

12/11/22 PVsyst Licensed to Page 3/9


Project: 810.7 KWp Rooftop Solar Power Plant for Multazim
Group at ASF Fiber Mill
PVsyst V7.2.3
Variant: N/S
VC0, Simulation date:
12/11/22 10:43
with v7.2.3

System losses
Auxiliaries loss
Proportionnal to Power 5.0 W/kW
0.0 kW from Power thresh.

AC wiring losses
Inv. output line up to injection point
Inverter voltage 400 Vac tri
Loss Fraction 1.00 % at STC
Inverter: CPS SCA110KTL-DO/EU
Wire section (7 Inv.) Copper 7 x 3 x 70 mm²
Average wires length 53 m

12/11/22 PVsyst Licensed to Page 4/9


Project: 810.7 KWp Rooftop Solar Power Plant for Multazim
Group at ASF Fiber Mill
PVsyst V7.2.3
Variant: N/S
VC0, Simulation date:
12/11/22 10:43
with v7.2.3

Main results
System Production
Produced Energy 1047 MWh/year Specific production 1293 kWh/kWp/year
Performance Ratio PR 84.93 %

Normalized productions (per installed kWp) Performance Ratio PR

Balances and main results

GlobHor DiffHor T_Amb GlobInc GlobEff EArray E_Grid PR


kWh/m² kWh/m² °C kWh/m² kWh/m² MWh MWh ratio
January 102.6 61.2 17.07 102.5 100.0 74.9 73.1 0.882
February 111.2 62.1 20.97 111.1 108.5 79.6 77.6 0.863
March 154.4 79.8 25.76 154.4 151.0 108.1 105.2 0.841
April 153.2 89.1 27.63 153.2 149.7 106.7 103.8 0.837
May 159.1 104.6 28.30 158.8 155.2 110.7 107.8 0.839
June 123.5 88.7 28.14 123.2 120.3 86.4 84.1 0.844
July 119.0 78.5 28.52 118.7 116.0 82.9 80.7 0.840
August 145.6 94.4 28.68 145.4 142.0 101.8 99.2 0.842
September 126.8 73.9 28.00 126.7 123.8 88.6 86.3 0.841
October 118.9 75.9 27.14 118.7 115.9 83.7 81.6 0.849
November 111.9 55.5 23.01 111.9 109.3 79.9 77.9 0.860
December 98.6 56.0 18.89 98.5 96.1 71.6 69.9 0.876
Year 1524.7 919.7 25.19 1523.0 1487.9 1075.1 1047.2 0.849

Legends
GlobHor Global horizontal irradiation EArray Effective energy at the output of the array
DiffHor Horizontal diffuse irradiation E_Grid Energy injected into grid
T_Amb Ambient Temperature PR Performance Ratio
GlobInc Global incident in coll. plane
GlobEff Effective Global, corr. for IAM and shadings

12/11/22 PVsyst Licensed to Page 5/9


Project: 810.7 KWp Rooftop Solar Power Plant for Multazim
Group at ASF Fiber Mill
PVsyst V7.2.3
Variant: N/S
VC0, Simulation date:
12/11/22 10:43
with v7.2.3

Loss diagram
1525 kWh/m² Global horizontal irradiation

-0.11% Global incident in coll. plane


-0.31% IAM factor on global
-2.00% Soiling loss factor

1488 kWh/m² * 3803 m² coll. Effective irradiation on collectors

efficiency at STC = 21.32% PV conversion

1206 MWh Array nominal energy (at STC effic.)


-0.29% Module Degradation Loss ( for year #1)
-0.60% PV loss due to irradiance level

-5.85% PV loss due to temperature

+0.75% Module quality loss

-2.00% LID - Light induced degradation

-2.06% Mismatch loss, modules and strings

-1.21% Ohmic wiring loss


-0.01% Mixed orientation mismatch loss
1075 MWh Array virtual energy at MPP
-1.64% Inverter Loss during operation (efficiency)
0.00% Inverter Loss over nominal inv. power
0.00% Inverter Loss due to max. input current
0.00% Inverter Loss over nominal inv. voltage
0.00% Inverter Loss due to power threshold
0.00% Inverter Loss due to voltage threshold
-0.02% Night consumption
1057 MWh Available Energy at Inverter Output

-0.50% Auxiliaries (fans, other)


-0.45% AC ohmic loss
1047 MWh Energy injected into grid

12/11/22 PVsyst Licensed to Page 6/9


Project: 810.7 KWp Rooftop Solar Power Plant for Multazim
Group at ASF Fiber Mill
PVsyst V7.2.3
Variant: N/S
VC0, Simulation date:
12/11/22 10:43
with v7.2.3

Special graphs
Daily Input/Output diagram

System Output Power Distribution

12/11/22 PVsyst Licensed to Page 7/9


Project: 810.7 KWp Rooftop Solar Power Plant for Multazim
Group at ASF Fiber Mill
PVsyst V7.2.3
Variant: N/S
VC0, Simulation date:
12/11/22 10:43
with v7.2.3

Aging Tool
Aging Parameters
Time span of simulation 25 years
Module average degradation Mismatch due to degradation
Loss factor 0.55 %/year Imp RMS dispersion 0.4 %/year
Vmp RMS dispersion 0.4 %/year
Meteo used in the simulation
#1 Bharadoba Bhaluka Mymensingh MN80 SYN
Years 1990 (reference year)
Years simulated 1-25

Energy injected into grid

Performance Ratio

12/11/22 PVsyst Licensed to Page 8/9


Project: 810.7 KWp Rooftop Solar Power Plant for Multazim
Group at ASF Fiber Mill
PVsyst V7.2.3
Variant: N/S
VC0, Simulation date:
12/11/22 10:43
with v7.2.3

Aging Tool
Aging Parameters
Time span of simulation 25 years
Module average degradation Mismatch due to degradation
Loss factor 0.55 %/year Imp RMS dispersion 0.4 %/year
Vmp RMS dispersion 0.4 %/year
Meteo used in the simulation
#1 Bharadoba Bhaluka Mymensingh MN80 SYN
Years 1990 (reference year)
Years simulated 1-25

Bharadoba Bhaluka Mymensingh MN80 SYN

Year E Grid PR PR loss


MWh %
1 1047 0.849 0%
2 1042 0.845 -0.5%
3 1035 0.84 -1.1%
4 1029 0.834 -1.8%
5 1021 0.828 -2.5%
6 1013 0.822 -3.3%
7 1004 0.814 -4.1%
8 994.5 0.807 -5%
9 985.2 0.799 -5.9%
10 976.1 0.792 -6.8%
11 968.1 0.785 -7.5%
12 961.2 0.78 -8.2%
13 954.5 0.774 -8.8%
14 948.1 0.769 -9.5%
15 941.7 0.764 -10.1%
16 935.4 0.759 -10.7%
17 929.0 0.753 -11.3%
18 922.3 0.748 -11.9%
19 915.2 0.742 -12.6%
20 907.6 0.736 -13.3%
21 898.8 0.729 -14.2%
22 888.7 0.721 -15.1%
23 878.3 0.712 -16.1%
24 867.5 0.704 -17.2%
25 856.6 0.695 -18.2%