Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

Accelerat ing t he world's research.

Identifying Construction Resource


Factors Affecting Construction Cost:
Case of johor
Aftab Hameed Memon

Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET


2011)

Cite this paper Downloaded from Academia.edu 

Get the citation in MLA, APA, or Chicago styles

Related papers Download a PDF Pack of t he best relat ed papers 

Relat ionship bet ween Fact ors of Const ruct ion Resources Affect ing Project Cost
Nader Green

Invest igat ing Causes of Const ruct ion Delay in Et hiopian Const ruct ion Indust ries
Werku K O S H E Hareru

Const ruct ion Delays Causing Risks on T ime and Cost -a Crit ical Review
Mohamed Rafeek
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

Identifying Construction Resource Factors


Affecting Construction Cost: Case of Johor
Aftab Hameed Memon*, Ismail Abdul Rahman, Ade Asmi Abdul Aziz, Kumarason V. Ravish, and
Noor Ikmalah Mohammad Hanas
Faculty of Civil and Environmental Engineering,
Universiti Tun Hussein Onn Malaysia, 86400 Parit Raja, Batu Pahat, Johor, Malaysia

*Corresponding e-mail: aftabm78@hotmail.com

Abstract
The success of any construction project highly depends on proper and effective management of construction
resources flow. Studies show various resources factors that affect the cost management resulting in significant
amount of cost overrun. This study focuses on the significant resource factors causing construction cost overrun
in the state of Johor. Data collection was carried out through a structured questionnaire survey consisting of 16
factors identified through a comprehensive literature review. Data was analyzed with statistical software package
SPSS. It was found that average cost overrun for this study is in the range of 10% to 15% of the project cost. The
Cronbach's alpha of the data was 0.910 which means that the data collected was highly reliable. The factors were
ranked through mean rank calculation and it was found that fluctuation of prices of materials, cash flow and
financial difficulties faced by contractors and shortages of materials were the significant factors affecting
construction cost overrun. Insufficient numbers of equipment, relationship between management and labour, and
labour absenteeism were found as factors of least significance causing cost overrun. The result of Spearman test
indicates that cash flow and financial difficulties faced by contractors, and financial difficulties of owner
correlates with each other at a significant value of 0.752. Furthermore, equipment availability and failure, and
insufficient numbers of equipment are correlated with the value of correlation 0.703. Similarly, shortage of site
workers, financial difficulties of owner, and cash flow and financial difficulties faced by contractors are inter-
correlated significantly between them.

Keywords: Construction management, construction resource factor, cost overrun, Johor

budget to perform its vital function. The necessity of


1. INTRODUCTION proper budgeting for a project, an explanation of
Money is always of special importance to those resource management, and the economic benefits that
involved in construction project. Hence, completion of would accrue to the project are addressed. In order to
any project within the estimated cost of project is the control cost, equipment and labour should be utilized
basic criteria for success of any project. The success of in the most efficient way possible.
any project highly depends on adequate availability Managing resources in the framework of civil
and efficient management of various resources. Hence, engineering construction sector is usually an extremely
prior and adequate arrangement for provision of complex task. Factors contribute to this complexity
resource involved in construction such as type and include the variety and great number of existing
quantity of material, manpower, machines and finance resources of both human and material, the diversity of
are required at each stage of construction. There are tasks that each working unit is able to execute, the
various factors that cause failing resources performance of each working unit, the involved costs,
management. More common, the importance of and the spatial distribution of all resources over the
resource management is not considered properly in the different places, leading to the need for displacement
conceptual and planning phases of a construction from one site to another. All these important factors
project which results in construction cost overrun. imply a high number of variables, resulting in a
Therefore, this leads to the project having inadequate somewhat difficult optimization process. The basic
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

objective of resource management is to supply and 1. Machines or Equipment Resources: This type of
support the project so that established time objectives resource has an advantage over manpower resource
can be met and costs can be kept within the project as it can work under adverse circumstances
budget [1]. continuously, requires less manpower and other
In Malaysia, many projects are facing cost overrun. facilities. The selection and utilization of equipment
One of the main causes of cost overrun is ineffective in a project must be an integral part of the total
resource managements. There are various resource plan. The type and number of the equipments
related factors which lead to failure of resource required in any project depends on the nature of the
management resulting in construction cost overrun. project. It affects significantly on construction cost.
Hence, this study is aimed at investigating construction
resources-related factors that cause construction cost 2. Manpower Resource: For any project, manpower
overrun in Malaysian construction industry. However, resource or human labour are as significant as
the scope of this paper is limited to investigations in financial resources and that efficient use of
Johor state only. manpower is critical for success. Good results
certainly cannot be achieved without the adequate
2. RELATED WORKS availability of skilled and unskilled manpower,
Completion of any project within the estimated cost most suitable allocation and management of human
is the basic criteria for the success of any construction or manpower resource. Expected construction
project. Primary target of practitioners involved in progress can be achieved only through the
construction projects is to complete the project within attainment of effective man-hour effort and the
budgeted cost regardless of size and complexity of meeting of scheduled mile stone dates. Effective
project. However, completion of any project highly manpower management can reduce labour costs
depends on the construction resources. Project and thereby increase profits for company.
resources provide the means for accomplishing the
work objectives [2]. Construction resources 3. Material Resource: Materials are the essence in
management is the most important factor contributing the construction industry. Material resource
to cost success [3]. represents a substantial proportion of the total value
Construction resources management has a high and of the project. A material management system
significant relationship with cost performance for includes the major functions needed in construction
successful projects [3]. As cited by [4] in a project, i.e. identifying, acquiring, storing,
multiannual research conducted in Croatia from 1996 distributing and disposing of materials. Material
till 1998 as part of the scientific project Construction planning may vary, depending on the project size,
Project Risk and Resource Management, the location, cash flow requirements, and procedure for
occurrence of price overrun was observed in no less purchasing and inspection. Regular supply of the
than 81% of the projects. Previous studies reveal that material in proper quantity must be ensured. It is
there are various construction resource related factors extremely important because late or irregular
which significantly influence construction cost. Ref [5] delivery or wrong type of material delivered during
found that increment of construction materials prices construction are major factors that contribute to the
due to continuous border closures, delay in delay of a project. Also the effective utilization of
construction and supply of raw materials and manpower can be greatly enhanced by ensuring
equipment by contractors, fluctuations in the cost of proper and sufficient availability of material.
building materials, and resources constraint of funds
and the associated auxiliaries not ready, were among 4. Money: Financial management is the use of
the top ten factors affecting construction cost. financial or accounting information at all levels to
Financial difficulties of owner and contractor were assist in planning, making decisions and controlling
ranked as the first problems affecting construction cost the activities of an enterprise [7]. Money has great
in Vietnam [6]. If the contractor can minimize importance in the construction industry. It is the
problems such as inefficient use and lack of first and foremost resource or item required for any
construction equipment and shortage of quality construction work. The design and specifications of
material, the construction budget can be reduced [3]. a project depend upon it, and without sufficient
In any project, various types of resources are fund, any project cannot be completed. Cash flow
essentially required be managed for the success of the affects the progress of construction. A project
project. The most important resources for any cannot be completed in the absence of fund and it
construction project are: will be entirely wastage of time and energy in
designing the project. Therefore, it is absolutely
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

necessary to manage the fund of a project. Without accepted reliability is when Cronbach  is greater than
proper management of the money or finance, the 0.3. If  is greater than 0.7, the collected data is
management of other resource becomes useless. considered as highly reliable [18], [19].
Resources are organizational assets. Resource
3.2 Ranking Study
planning should take into consideration not only
what is best for an individual project, but also what A five point Likert-scale of 1 to 5 was adopted to
is best for the organization as whole. Effective assess the likelihood of each of the identified factor in
resource planning is also important when causing construction cost overrun, where scales of 1 =
considering the impact of changes on the project extremely significant, 2 = most significant, 3 =
schedule [1]. Unanticipated overtime, schedule moderately significant, 4 = significant, and 5 = not
delays, and the resulting cost overruns can all be significant. The studied factors were ranked based on
symptomatic of ineffective resource management. the mean rank score. Lower mean rank score
represents the higher the ranking is. The equation used
Based on previous studies, the most frequent and to compute for the mean rank is
important factors related to construction resource which
affect construction cost were identified. A total of 16 nR
MR (1)
factors were identified [5], [6], and [8]-[17]. The M max
factors were grouped in four categories, i.e. material,
manpower, machinery and money as shown in Table 1.
where, MR is mean rank, R is individual mean rank of
Table 1: Factors causing construction cost overrun cause, Rmax is the maximum individual mean rank of
Category Resources-related factor cause, and n is the number of causes. The
Fluctuation of prices of materials determination of the significance of the causes is based
Shortages of materials on the mean rank score.
Material
Changes in material specification and type 3.3 Correlation
Delay in delivery of materials The strength of associations of pairs of variables
High cost of labour understudy was determined by correlation
Relationship between management and relationships. The 3 commonly used methods for
labour ascertaining the strength of association between 2
Manpower Labour productivity variables is the Pearson correlation method, the
Spearman rank correlation method and the Chi square
Labour absenteeism
test of independence method.
Shortage of site workers As data collected in this study is non-parametric and
Financial difficulties of owner ordinal variables, the powerful method of examining
Cash flow and financial difficulties faced the relationship between pairs of variables is by using
Money by contractors Spearman’s rank order correlation [20]. Spearman’s
Mode of financing, bonds and payments formula is given as
Poor financial control on site
6¦ d 2
Equipment availability and failure U 1 (2)
Insufficient number of equipments n n 2  1
Machinery
Increase cost of machinery and its
maintenance where, d is the difference between ranks and n is the
highest weight.
3. METHODS The correlation coefficient  ranges from 1.0 to
Data was collected through a structured +1.0. The closer  is to +1 or 1, the more closely the
questionnaire survey carried out among the personnel two variables are related. The value of  close to 1
involved in construction industry. The survey was implies there is strong positive linear relationship
conducted in Johor state of Malaysia. It was carried out between the two variables while the value of  close to
physically with the respondents. A total of 53 1 shows a strong negative linear relationship between
responses were collected. the two variables [21]. Ideally, the correlation
coefficient value of ± 1 is said to be a perfect
3.1 Reliability Test correlation. If the correlation coefficient value lies
A reliability test was performed on the collected data between ± 0.5 and ± 1, it is said to have a high degree
to determine its degree of consistency. The Cronbach  of correlation. For correlation coefficient value
coefficient is computed for data consistency. The between ± 0.3 and ± 0.5, the degree of correlation is
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

moderate. Low degree of correlation occurs when the 4.2 Extent of Cost Overrun
correlation coefficient lies between ± 0.1 and ± 0.3. Respondents were asked about the extent of cost
Meanwhile, zero coefficient value represents no overrun compared to the contracted cost of the various
correlation at all [22]. projects they have handled. The results are presented
in Fig. 1.
4. RESULTS AND DISCUSSION
The respondents involved in the survey have had
several years of experience in handling various types
of projects. The demographic of the respondents
participated in survey are summarized in Table 2.
Table 2 indicates that majority of the respondents,
i.e. 43 out of 53, or 81.1% of the respondents had
experienced handling large construction projects, i.e.
project with contract exceeding RM 5 million [23].
52.8% of the respondents experienced in handling
building projects, 26.4% respondents experienced in
handling infrastructure project, and 20.8% respondents
were involved in both building and infrastructure
projects.

Table 2: Demographic of respondents Fig. 1 Extent of cost overrun


Cumulative
Aspects Frequency Percent Figure 1 shows that majority of the respondents
Percent
Type of agreed that cost overrun in construction projects is a
Organization common issue. Only 15.09% respondents mentioned
Client 8 15.1 15.1 that the projects were executed within the estimated
Consultant 11 20.8 35.9 cost. A significant number of respondents (37.74%)
Contractor 34 64.1 100 mentioned that cost overrun ranges from 1% to 5% of
Type of Project contracted cost followed by 5-10% cost overrun
Building 28 26.4 26.4 responded by 28.30%. However, 11.32% respondents
Infrastructure 11 52.8 79.2 mentioned that cost overrun was above 15% of
Build-Infra 14 20.8 100 contracted cost and only 7.55% responses show that
cost overrun ranging from 10% to 15%.
Size of Project
(RM) 4.3 Ranking of Resource Related Factors
< 5 Million 10 18.9 18.9 In ranking analysis, the SPSS 17 software was used
5 – 10 Million 10 18.9 37.8
to compute the mean rank of the resource related
10 – 50 Million 22 41.5 79.3
11 factors causing construction cost overrun. The results
> 50 Million 20.7 100
of the analysis are given in Table 4.
Table 4 shows that fluctuation of prices of materials
4.1 Reliability Test
is an extremely significant factor affecting
Data from each category of questionnaire were construction cost. Fluctuation of material cost can be
analyzed for its Cronbach D value. This was to ensure caused by various factors. Monopoly of suppliers
that the data collected are valid and reliable for further could be one of main reasons of fluctuation of prices.
analysis. Table 3 shows high values of Cronbach D in Unavailability of construction materials locally can
each category of the questionnaire data. The alpha also affects the cost of material. However, [5] ranked
values are in the range of 0.736 to 0.883. This range is fluctuation of material prices as the fourth most
considered high. Thus, the reliability of the important factors affecting construction cost in Gaza.
questionnaire is assured. Certainly, this indicates that Second most significant factor is cash flow and
the questionnaire data are valid and reliable. financial difficulties faced by contractors. This factor
has been found to be the most significant in large
Table 3: Reliability test results
MARA construction projects [9]. Financial difficulties
Category of data Cronbach D
Material 0.736
faced by contractor were ranked as the fourth major
Manpower 0.745 factor causing cost overrun in Vietnam construction
Money 0.883 industry [6]. In a study of Ghana, this factor was rated
Machinery 0.760 as 5th major factor causing cost overrun [15].
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

Table 4: Rank analysis results Table 4 is the shortages of materials. However,


Mean previous studies have shown that this factor is
Attribute Rank Category
rank
Fluctuation of prices of
moderately important factor affecting construction cost.
5.05 1 Material Ref [14] in the study of cost escalation in Nigeria
materials
Cash flow and financial found that shortage of material was ranked as sixth
difficulties faced by 6.71 2 Money significant factor. While, in Vietnamese construction
contractors projects, practitioners have ranked this factor as the 9th
Shortages of materials 7.08 3 Material most significant [6]. In Ghana, this factor was the 15th
Shortage of site workers 7.51 4 Manpower significant cause affecting construction cost [15].
Financial difficulties of owner 7.88 5 Money 4.4 Relationship Between Factors
Mode of financing, bonds and
payments
7.89 6 Money Relation between pairs of variables was examined
Changes in Material by using Spearman’s rank order correlation [20]. The
8.24 7 Material
Specification and type correlation analysis of the factors is shown in Table 5.
Poor financial control on site 8.33 8 Money Based on Table 5, cash flow and financial
labour productivity 8.46 9 Manpower difficulties faced by contractors, and financial
difficulties of owner correlate to each other at a
Late delivery of materials 8.46 10 Material
significant value of 0.752. Also, equipment availability
High cost of labour 9.31 11 Manpower and failure, and insufficient numbers of equipment are
High cost of machinery and correlated at the value of correlation 0.703. Similarly,
9.37 12 Machinery
its maintenance
Equipment availability and
shortage of site workers, financial difficulties of owner,
10.08 13 Machinery and cash flow and financial difficulties faced by
failure
Labour Absenteeism 10.18 14 Manpower contractors are inter-correlated significantly between
Relationship between them as shown in Fig. 2. Also, there is significant
10.73 15 Manpower
management and labour correlation between poor financial control on site,
Insufficient Numbers of
10.74 16 Machinery financial difficulties of owner, cash flow and financial
equipment difficulties of owner, and mode of financing.
Summary of correlation of effect of delay is shown in
The third most significant factor as indicated in Table 6.

Table 5: Correlation between construction resources related factors causing cost overrun
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

Cash flow & financial


difficulties faced by contractors

Shortage of site
workers

Financial difficulties of owner

(a)
Cash flow & Financial difficulties
financial difficulties of owner
Equipment availability &
faced by contractors
failure

(c)

Insufficient Numbers of
equipment

(b)
Fig. 2 Relationship between factors causing cost overrun

Table 6: Summary of correlation between resource factors


Variable High degree of correlation Moderate degree of correlation
Shortages of materials 9 Fluctuation of prices of materials 9 Shortage of site workers
9 Cash flow and financial difficulties 9 Shortage of site workers
faced by contractors 9 Mode of financing, bonds and payments
Financial difficulties of owner
9 Labour productivity
9 Poor financial control on site
9 Shortage of site workers 9 Cash flow and financial difficulties faced
Labour productivity 9 Financial difficulties of owner by contractors
9 Mode of financing, bonds and payments

5. CONCLUSION Financial problems of contractors also influence


The findings of the study carried out to identify the procurements of material and arrangement of
the problems of cost overrun and effect of resource adequate number of material and equipment. This
related factors on cost overrun in the state of Johor, affects labour productivity. Resolving this issue
Malaysia are summarized as follows: plays an important role in achieving successful
a) About 85% of the respondents agreed that most projects.
construction projects face cost overrun problem.
b) About 11.32% projects face cost overrun above ACKNOWLEDGMENT
15%, where the normal range of cost overrun is The authors would like to thank Universiti Tun
between 0 and 15%. Hussein Onn Malaysia for supporting this study.
c) Fluctuation of prices of materials, cash flow and Also, we are thankful to construction practitioners
financial difficulties faced by contractors and for providing comprehensive and important
shortages of materials were found as most information, and a lot of cooperation which made
significant factors causing cost overrun. data collection easier.
d) Cash flow and financial difficulties faced by
contractor has strong correlation with the REFERENCES
financial difficulties of owner. [1] Just, R. Michael, Murphy, P. James, “The effect
e) Shortage of site workers, financial difficulties of of resource constraints on project schedules,”
owner, and cash flow and financial difficulties Transaction of AACE International,
faced by contractors are significantly inter- Morgantown, 1994.
correlated between each other. [2] M. E. Padilla and I. R. Carr, “Resource
The financial problem faced by the owner and strategies for dynamic project management,”
contractor was the most critical issue in construction Journal of Construction Engineering and
projects. This often leads to construction delay, and Management, Vol. 117 (2), 1991: pp. 279-293.
subsequently cost overrun.
Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011)

[3] S. Meepol and S. O. Ogunlana, “Factors Nigeria,” Proceedings 6th Int. Postgraduate
affecting cost and time performance on highway Research Conference, Delft University of
construction projects: Evidence from Thailand,” Technology and TNO, the Netherlands, 3rd-7th
Journal of Financial Management of Property April 2006,
and Construction, Vol. 11 (1), 2006: pp. 3-20. [15]Y. Frimpong, J. Oluwoye, and L. Crawford,
[4] V. Žujo, D. C. Puši and A. B. Vejzovi, “Causes of delay and cost overruns in
“Contracte price overrun as contracted construction of groundwater projects in a
construction time overrun function,” Technical developing country: Ghana as a case study,”
Gazette Vol. 17 (1), 2010: pp. 23-29. International Journal of Project Management,
[5] A. Enshassi, J. Al-Najjar, and M. Vol. 21(5), 2003, pp.321–326
Kumaraswamy, “Delays and cost overruns in [16]A. S. T. Chang, “Reasons for cost and schedule
the construction projects in the Gaza Strip,” increase for engineering design projects,”
Journal of Financial Management of Property Journal of Management in Engineering, ASCE,
and Construction, Vol. 14 (2), 2009: pp. 126- Vol. 18 (1), 2002: pp. 29-36.
151 [17]S. Jackson, “Project cost overrun and risk
[6] L. Le-Hoai, Y. D. Lee, and J. Y. Lee J. Y, management,” Proceedings of Association of
“Delay and cost overruns in Vietnam large Researchers in Construction Management 18th
construction projects: A comparison with other Annual ARCOM Conference, Newcastle,
selected countries,” KSCE Journal of Civil Northumber University, UK, 2-4 September
Engineering, Vol. 12 (6), 2008: pp. 367-377. 2002.
[7] D. Lock, Handbook of Engineering [18]Y. B. Yang and S. F. Ou, “Using structural
Management, 2nd edn., Oxford: Butterworth- equation modeling to analyze relationships
Heinemann, 1993. among key causes of delay in construction,”
[8] O. J. Ameh, A. A. Soyingbe, and K. T. Canadian Journal of Civil Engineering, Vol. 35,
Odusami, “Significant factors causing cost 2008: pp. 321-332.
overruns in telecommunication projects in [19]P. S. P. Wong and S. O. Cheung, “Structural
Nigeria,” Journal of Construction in Developing equation model of trust and partnering success,”
Countries, Vol. 15, 2010. Journal of Management in Engineering, Vol. 21
[9] A. H. Memon, I. Abdul Rahman, M. R. (2), 2005: pp.70-80.
Abdullah, and A. A. Abdul Aziz, ‘Factors [20]A. Bryman and D. Cramer, Quantative Data
affecting construction cost in MARA large Analysis with SPSS Release 10 for Windows,
construction project: Perspective of project 2nd ed., Taylor and Francis Inc., 2002.
management consultant,” International Journal [21]Z. M. Daud, M. H. Ahmad, and F. Yusof,
of Sustainable Construction Engineering & Elementary Statistics, Preatice Hall, Pearson
Technology, Vol. 1 (2), 2010. (M) Sdn. Bhd, 2009.
[10]C. Kaliba, M. Muya, and L. Mumba, “Cost [22]J. Cohen, Statistical Power Analysis for the
escalation and schedule delays in road Behavioral Sciences, 2nd ed., 1988.
construction projects in Zambia,” International [23]M. R. Abdullah, A. A. Abdul Aziz, and I. Abdul
Journal of Project Management, Vol. 27, 2009: Rahman, “Causes of delay and its effects in
pp. 522- 531. large MARA construction project,”
[11]N. Azhar, R. U. Farooqui, and S. M. Ahmed, International Journal of Integrated Engineering
“Cost overrun factors in construction industry in (Issue on Mechanical, Materials and
Pakistan,” Proceedings 1st Int. Conf. on Manufacturing Engineering), 2009.
Construction in Developing Countries
(ICCIDE-1), Karachi, Pakistan, 4-5 August
2008: pp. 499-508.
[12]I. R. Endut, A. Akintoye, and J. John Kelly,
Cost and Time Overrun Projects in Malaysia,
2009, available at http://www.irbnet.de/daten/
iconda/CIB10633.pdf
[13]V. Žujo and D. C. Puši, “Application of time-
cost model in construction project,”
Proceedings 8th Int. Conf. on Organization,
Technology and Management in Construction,
Umag, Croatian Association for Organization in
Construction, Zagreb, 2008: pp. 1-7.
[14]A. Omoregie and D. Radford, “Infrastructure
delays and cost escalation: Causes and effects in

You might also like