Detailed Construction Program and Timetable
Detailed Construction Program and Timetable
Cumulative Accomplishment ##### 5.56% 15.41% 20.26% 25.11% 33.79% 42.47% 51.15% 59.83% 66.73% 73.63% 77.19% 80.75% 96.31% 98.88% 99.44% 100.00%
Note:
Expect low productivity in Weeks 3 to S‐curve
5 due to Holidays
120.00%
Prepared by:
100.00%
80.00%
Raj Deep Singh
Project Manager
60.00%
40.00%
Approved by
20.00%