Kegiatan : Perbaikan Jalan Desa Kali Berau

Tanggal : 27/08/2022 ; 08.00-17.30


28/08/2022 ; 09.00-17.00
Lokasi : Jalan Desa Kali Berau ( Pos B81-POS 14- Simpang Kapuk; 1 Km)

Date Company Item Unit Frequency


BSE Motorgrader HM 19
BSE Manpower (Basic) Rupiah 1
BSE Manpower (Overtime) Rupiah 19
TPE Dump Truck Ritase 11
TPE Dump Truck Ritase 5
27/08/2022- TPE Compactor HM 3
28/08/2022 TPE Compactor HM 14
TPE Excavator HM 1.5
TPE Excavator HM 2.5
TPE Manpower ( OT) Rupiah 16
TBU Fuel Liter 275
MAL Material Kubik 50
Grand Total
Price/Unit Total Remark
Rp 925,000 Rp 17,575,000 MG 705
Rp 3,252,282 Rp 3,252,282
Rp 18,584 Rp 353,096
Rp 185,000 Rp 2,035,000 Hauling Batu Split
Rp 185,000 Rp 925,000 Hauling FABA
Rp 180,000 Rp 540,000
Rp 180,000 Rp 2,520,000
Rp 285,000 Rp 427,500 Loading Batu Split
Rp 285,000 Rp 712,500 Drainase
Rp 16,000 Rp 256,000
Rp 16,931 Rp 4,656,025
Rp 400,000 Rp 20,000,000
Rp 53,252,403