Download as pdf or txt
Download as pdf or txt
You are on page 1of 79

PROJECT:

‐ CEDAR LAXURIA.


 
TECHNICAL SPECIFICATIONS PLUMBING WORKS 
1.  BASIS OF DESIGN 
The  Plumbing,  Sanitary,  Drainage  System  for  the  project  is  designed  keeping  in  view  the 
following: 
   
1.1  Requirement of adequate and equal pressure availability of hot and cold water lines in Public 
Toilets, Kitchen and other identified areas. 
   
1.2  Adequate storage of water in underground raw + overhead treated domestic water tanks. 
   
1.3  Levels of roads / pavements and other services in the area. 
 
1.4  Landscape layout. 
   
  The  execution  of  works  and  materials  used  shall  be  as  per  the  latest  relevant  I.S. 
specifications. 
 
  Wherever reference has been made to Indian Standard or any other specifications, the same 
shall  mean  to  refer  to  the  latest  specification  irrespective  of  any  particular  edition  of  such 
specification being mentioned in the specifications below or Schedule of Quantities. 
 
   
2.   CONCEPT OF THE SYSTEM  
 
 The following services are envisaged for the complex: 
 
2.1  Water Treatment System for meeting the domestic water quality requirement with chemical 
parameters in acceptable limits as per SP: 35(S & T) 1987 which is considered safe for human 
consumption. 
 
2.2  Domestic water supply through pumping system. 
 
2.3  Sewage and Sullage collection system based on IS: 1742 and applicable standards for domestic 
drainage and connected to outfall into municipal system after treatment in a sewage treatment 
plant. 
 
2.4  Storm / Rain water drainage system from various levels of the building and disposal to Rain 
Water harvesting and over flow to into municipal system. 
 
 

 
Behera and Associates Page - 1
PROJECT: ‐ CEDAR LAXURIA.


3.  WATER STORAGE & DISTRIBUTION SYSTEM 
 3.1  Water Requirement 
 
The water requirement for this project is proposed to be as per the provisions in    IS : 1172/NBC 
and prevalent practices. 
 
3.2  Source of Water 
 
 It  is  expected  that  part  of  the  daily  domestic  water  requirement  for  the  Complex  shall  be 
through Bore well only. 
 
3.4  Appurtenant 
 
  Following components shall be included in the water supply system for efficient functioning: 
 
i.  Automatic air vent  
ii.  Pressure Gauge. 
iii.  Water Hammer arrestors. 
 
4.  SEWAGE, SULLAGE AND STORM WATER 
 
  The soil and waste shall be carried down through one pipe/ 2 pipe drainage system.  Venting of 
system shall be carried out by using separate anti syphonage pipe.   
 
5.  WORKMANSHIP 
 
  The workmanship shall be best of its kind and shall confirm to the specifications, as below or Indian 
Standard Specifications in every respect or latest trade practices and shall be subject to approval of 
the  Owner’s  Site  Representative.  All  materials  and/or  Workmanship  which  in  the  opinion  of  the 
Owner’s  Site  Representative  /  Architect  /  Consultant  is  defective  or  unsuitable  shall  be  removed 
immediately  from  the  site  and  shall  be  substituted  with  proper  materials  and/or  workmanship 
forthwith. 
 
6.     MATERIALS 
 
   All materials shall be best of their kind and shall confirm to the latest Indian Standards. 
  All materials shall be of approved quality as per samples and origins approved by the Owner’s Site 
Representative / Architect / Consultants.  
 
  As  and  when  required  by  the  Owner’s  Site  Representative  /  Consultant,  the  contractor  shall 
arrange to test the materials and/or portions of works at his own cost to prove their soundness and 

 
Behera and Associates Page - 2
PROJECT: ‐ CEDAR LAXURIA.


efficiency. If after tests any materials, work or portions or work are found defective or unsound by 
the Owner’s Site Representative / Consultant, the contractor shall remove the defective material 
from  the  site,  pull  down  and  re‐execute  the  works  at  his  own  cost  to  the  satisfaction  of  the 
Owner’s  Site  Representative  /  Consultant.  To  prove  that  the  materials  used  are  as  specified  the 
contractor shall furnish the Owner’s Site Representative with original vouchers on demand. 
 
SECTION I: GENERAL INSTRUCTIONS 
 

1.0 GENERAL REQUIREMENTS  
 
1.1  Scope of Work 
 
1.1.1  The form of Contract shall be according to the “Conditions of Contract”. The following clauses 
shall be considered as an extension and not in limitation of the obligation of the Contractor.  
1.1.2  Work  under  this  contract  shall  consist  of  furnishing  all  labour,  materials,  equipment  and 
appliances  necessary  and  required.  The  Contractor  is  required  to  completely  furnish  all  the 
Plumbing  and  other  specialized  services  as  described  hereinafter  and  as  specified  in  the 
Schedule of Quantities and/or shown on the Plumbing Drawings. 
1.1.3  Without restricting to the generally of the foregoing, the sanitary installations shall include the 
following:‐ 
  A.  Plumbing Works 
 
i)   Sanitary Fixtures (Only Fixing) 
ii)  Soil, Waste & Vent and Rain Water Pipes and fittings. 
iii)  Water Supply System (Cold & Hot). 
iv)         Sewerage & Storm water drainage system  
v)   Pumping system & water Treatment Plant 
 
1.1.4  Services rendered under this section shall be done without any extra charge. 
 
1.2  Specifications 
 
1.2.1   Work under this contract shall be carried out strictly in accordance with Specifications attached 
with the tender. 
 
1.2.2     Items  not  covered  under  these  Specifications  due  to  any  ambiguity  or  misprints,  or  additional 
works,  the  work  shall  be  carried  out  as  per  Specifications  of  the  latest  Central  Public  Works 
Department  with  upto  date  amendments  as  applicable  in  the  contract  and  or  as  per  the 
requirement of the client or its representative. 
 

 
Behera and Associates Page - 3
PROJECT: ‐ CEDAR LAXURIA.


1.2.3  Works  not  covered  above  in  para  1.2.1  and  1.2.2  shall  be  carried  out  as  per  relevant  Indian 
Standards and in case of its absence as per British Standard Code of Practice.  
  
1.3.  Execution of Work 
 
1.3.1  The Contractor should visit and examine the site of work and satisfy himself as to the nature of 
the existing roads and other means of communication and other details pertaining to the work 
and local conditions and facilities for obtaining his own information on all matters affecting the 
execution  of  work.  No  extra  charge  made  in  consequence  of  any  misunderstanding,  incorrect 
information on any of these points or on ground of insufficient description will be allowed.     
 
1.3.2  The  work  shall  be  carried  out  in  conformity  with  the  Plumbing  drawings  and  within  the 
requirements  of  Architectural,  HVAC,  Electrical,  Structural  and  Other  specialized  services 
drawings. 
 
1.3.3  The Contractor shall cooperate with all trades and agencies working on the site.  He shall make 
provision  for  hangers,  sleeves,  structural  openings  and  other  requirements  well  in  advance  to 
prevent hold up of progress of the construction schedule. 
 
1.3.4  On award of the work, Contractor shall submit a schedule of construction in the form of a PERT 
Chart or BAR Chart for approval of the Project Manager/Architect/Consultant. All dates and time 
schedule  agreed  upon  should  be  strictly  adhered  to,  within  the  stipulated  time  of 
completion/commissioning along with the specified phasing, if any. 
 
1.4  Drawings 
 
1.4.1  Plumbing  drawings  are  diagrammatic  but  shall  be  followed  as  closely  as  actual  construction 
permits.  Any deviations made shall be in conformity with the Architectural and other services 
drawings. 
 
1.4.2    Architectural drawings shall take precedence over Plumbing or other services drawings as to all 
dimensions. 
 
1.4.3  Contractor shall verify all dimensions at site and bring to the notice of the Project Manager all 
discrepancies or deviations noticed.  Decision of the Project Manager shall be final. 
 
1.4.4  Large  size  details  and  manufacturers  dimensions  for  materials  to  be  incorporated  shall  take 
precedence over small scale drawings. 
 

 
Behera and Associates Page - 4
PROJECT: ‐ CEDAR LAXURIA.


1.4.5   All  drawings  issued  by  the  Architects/Consultant  for  the  work  are  the  property  of  the 
Architects/Consultant  and  shall  not  be  lent,  reproduced  or  used  on  any  works  other  than 
intended without the written permission of the Architects/Consultant. 
 
1.5  Inspection and Testing of Materials 
 
1.5.1  Contractor  shall  be  required,  if  requested,  to  produce  manufacturers  Test  Certificate  for  the 
particular batch of materials supplied to him.  The tests carried out shall be as per the relevant 
Indian Standards. 
 
1.5.2  For  examination  and  testing  of  materials  and  works  at  the  site  Contractor  shall  provide  all 
Testing and Gauging Equipment necessary but not limited to the followings:‐ 
 
a) Theodolite, Steel tapes 
b) Dumpy level 
c) Weighing machine 
d) Plumb bobs, Spirit levels, Hammers 
e) Micrometers, Tachometers  
f) Thermometers, Stoves 
g) Hydraulic test machine 
h) Smoke test machine 
 
1.5.3  All such equipment shall be tested for calibration at any approved laboratory, if required by the 
Project Manager. 
 
1.5.4  All Testing Equipment shall be preferably located in a special room meant for the purpose. 
 
1.5.5  Samples of all materials shall be got approved before placing order and the approved samples 
shall  be  deposited  with  the  Architects  or  kept  at  site  in  a  sample  room  as  prepared  by  the 
owners.  Any  materials  declared  defective  by  Project  Manager/Architect/Consultant  shall  be 
removed from the site within 48 hours.     
 
1.6  Metric Conversion 
 
1.6.1  All  dimensions  and  sizes  of  materials  and  equipment  given  in  the  tender  document  are 
commercial metric sizes. 
 
1.6.2  Any weights, or sizes given in the tender having changed due to metric conversion, the nearest 
equivalent sizes accepted by Indian Standards shall be acceptable without any additional cost. 
 
 

 
Behera and Associates Page - 5
PROJECT: ‐ CEDAR LAXURIA.


1.7  Reference Points 
 
1.7.1  Contractor shall provide permanent Bench Marks, Flag Tops and other reference points for the 
proper execution of work and these shall be preserved till the end of the work. 
 
1.7.2  All such reference points shall be in relation to the levels and locations given in the Architectural 
and Plumbing drawings. 
 
1.8  Reference Drawings 
 
1.8.1  The Contractor shall maintain one set of all drawings issued to him as reference drawings. These 
shall not be used on site. All important drawings shall be mounted on boards and placed in racks 
indexed. No drawings shall be rolled.  
 
1.8.2  All  corrections,  deviations  and  changes  made  on  the  site  shall  be  shown  on  these  reference 
drawings for final incorporation in the completion drawings. All   changes to be made shall be 
initialed by the Project Manager or Architects. 
 
1.9  Shop Drawings 
 
1.9.1  The Contractor shall submit to the Project Manager three copies of the shop drawings.  
 
1.9.2  Shop drawings shall be submitted under following conditions:‐  
  
(a) Showing any changes in layout in the plumbing drawings. 
 
(b) Equipment layout, piping and wiring diagram.  
 
(c) Manufacturer’s  or  Contractor’s  fabrication  drawings  for  any  materials  or  equipment 
supplied by him.  
 
1.9.3  The  Contractor  shall  submit  two  copies  of  catalogues,  manufacturer’s  drawings,  equipment 
characteristics data or performance charts as required by the Project Manager.  
 
1.10  Completion Drawings 
 
1.10.1  On completion of work, Contractor shall submit one complete  set of original tracings and two 
prints  of  “as  built”  drawings  to  the  Project  Manager.  These  drawings  shall  have  the  following 
information.    
 
a) Run of all piping, diameters on all floors, vertical stacks and location of external services.    

 
Behera and Associates Page - 6
PROJECT: ‐ CEDAR LAXURIA.


 
b) Ground  and  invert  levels  of  all  drainage  pipes  together  with  location  of  all  manholes  and 
connections upto outfall. 
 
c) Run of all water supply lines with diameters, locations of control valves, access panels.   
 
d) Location of all mechanical equipment with layout and piping connections. 
 
No completion certificate shall be issued unless the above drawings are submitted.  
 
1.10.2  Contractor  shall  provide  two  sets  of  catalogues,  service  manuals  manufacturer’s  drawings, 
performance  data  and  list  of  spare  parts  together  with  the  name  and  address  of  the 
manufacturer for all electrical and mechanical equipment provided by him.     
 
1.10.3  All “Warranty Cards” given by the manufacturers shall be handed over to the Project Manager.  
 
1.11.  Contractors Rates 
 
1.11.1  Rates quoted in this tender shall be inclusive of cost of materials, labour, supervision, erection, 
tools, plant, scaffolding, service connections, transport to site, taxes, octroi and levies, breakage, 
wastage and all such expenses as may be necessary and required to completely do all the items 
of work and put them in a working condition. 
 
1.11.2  Rates quoted are for all heights and depths and in all positions as may be required for this work. 
 
1.11.3  All rates quoted must be for complete items inclusive of all such accessories, Fixtures and fixing 
arrangements,  nuts,  bolts,  hangers  as  are  a  standard  part  of  the  particular  item  except  where 
specially mentioned otherwise. 
 
1.11.4  All rates quoted are inclusive of cutting holes and chases in walls and floors and making  good 
the  same  with  cement  mortar/concrete/water  proofing  of  appropriate  mix  and  strength  as 
directed  by  Project  Manager.  Contractor  shall  provide  holes,  sleeves  and  recesses  in  the 
concrete and masonry work as the work proceeds. 
 
1.11.5  The  Contractor  shall  furnish  the  Architects  with  vouchers  and  test  certificates,  on  request,  to 
prove that the materials as specified and to indicate that the  rates at which  the  materials are 
purchased in order to work out the rate analysis of non tendered items which he may be called 
upon to be carried out. 
 
 
 

 
Behera and Associates Page - 7
PROJECT: ‐ CEDAR LAXURIA.


1.12  Testing 
 
1.12.1  Piping  and  drainage  works  shall  be  tested  as  specified  under  the  relevant  clause(s)  of  the 
specifications. 
 
1.12.2  Tests shall be performed in the presence of the Project Manager/ Consultant. 
 
1.12.3  All materials and equipment found defective shall be replaced and whole work tested to meet 
the requirements of the specifications. 
 
1.12.4  Contractor shall perform all such tests as may be necessary and required by the local authorities 
to meet Municipal or other bye‐laws in force. 
 
1.12.5  Contractor shall provide all labour, equipment and materials for the performance of the tests. 
 
1.13  Site Clearance and Cleanup 
 
1.13.1  The Contractor shall, from time to time clear away all debris and excess materials accumulated 
at the site. 
 
1.13.2  After the Fixtures, equipment and appliances have been installed and commissioned, Contractor 
shall clean‐up the same and remove all plaster, paints stains, stickers and other foreign matter 
of discoloration leaving the same in a ready to use condition. 
 
1.13.3  On  completion  of  all  works,  Contractor  shall  demolish  all  stores,  remove  all  surplus  materials 
and  leave  the  site  in  a  broom  clean  condition,  failing  which  the  same  shall  be  done  at 
Contractors risk and cost. 
 
1.14  License Permits and Authorities  
 
1.14.1  Contractor  must  keep  constant  liaison  with  the  Municipal/statutory  authority  and  obtain  all 
approval of all drainage, water supply and other works carried out by him. 
 
1.14.2  Contractor  shall  obtain,  from  the  Municipal  and  other  authority’s  necessary  completion 
certificate(s) with respect to his work as required for occupation of the building. Contractor shall 
obtain permanent water supply and drainage connections from authorities concerned. Employer 
shall pay all fees/deposits as required to be paid to the authorities towards connection charges. 
  
 
 
 

 
Behera and Associates Page - 8
PROJECT: ‐ CEDAR LAXURIA.


1.15  Recovery of Cost for Materials issued to Contractors Free of Cost  
 
1.15.1  If any materials issued to the Contractor free of cost, are damaged or pilfered, the cost of the 
same  shall  be  recovered  from  the  Contractor  on  the  basis  of  actual  cost  to  owner  which  shall 
include all freight and transportation, excise duty, sales tax, octroi, import duty etc. plus 100%. 
The  decision  on  the  actual  cost  given  by  the  Employer  shall  be  final  and  binding  on  the 
Contractor.        
 
1.16  Cutting of Water Proofing Membrane  
 
  No  walls,  terraces  shall  be  cut  for  making  and  opening  after  water  proofing  has  been  done 
without  written  approval  of  Project  Manager/Architects.  Cutting  of  water  proofing  membrane 
shall  be  done  very  carefully  to  ensure  that  other  portion(s)  of  water  proofing  is  (are)  not 
damaged.  On  completion  of  work  at  such  place  the  water  proofing  membrane  shall  be  made 
good and ensured that the opening/cutting is made fully water proof as per specifications and 
details of water proofing approved by Architects.       
 
1.17      Cutting of Structural Members  
 
No  structural  member  shall  be  chased  or  cut  without  the  written  permission  of  the  Project 
Manager. 
 
1.18.  Materials Supplied by Owner 
1.18.1  The  Contractor  shall  verify  that  all  materials  supplied  by  the  Employer  confirm  to  the 
specifications of the relevant item in the tender.  Any discrepancy found shall be brought to the 
notice of the Project Manager. 
 
1.19  Materials 
 
1.19.1 Unless  otherwise  specified  and  expressly  approved  in  writing  by  the  Project  Manager,  only 
materials  of  makes  and  specifications  mentioned  in  the  list  of  approved  makes  attached  with 
the specifications shall be used.  
 
1.19.2 If required, the Contractor shall submit samples of materials proposed to be used in the works. 
Approved  samples  shall  be  kept  in  the  office  of  the  Project  Manager  and  returned  to  the 
Contractor at the appropriate time.   
 
 
                     
                                        END OF SECTION I 
 

 
Behera and Associates Page - 9
PROJECT: ‐ CEDAR LAXURIA.


 
SECTION II: SANITARY FIXTURES 
 
2.  SANITARY FIXTURES  
 
2.1  Scope of Work 
 
2.1.1  Work  under  this  section  shall  consist  of  furnishing  all  materials  and  labour  as  necessary  and 
required to completely install all Sanitary Fixtures, chromium plated fittings and accessories as 
required by the drawings and specified hereinafter or given in the Schedule of Quantities. 
 
2.1.2  Without  restricting  to  the  generally  of  the  foregoing  the  sanitary  fixtures  shall  include  the 
following:‐ 
 
a) Sanitary fixtures  
b) Chromium plated fittings 
c) Porcelain or stainless steel sinks 
d) Accessories e.g. towel rods, toilet paper holders, soap dish, towel rack, coat hooks etc. 
e) Mirrors 
f) Connections  to  all  kitchen  equipments  pump  headers  and  other  equipment  requiring 
water and drainage connections.    
 
2.1.3  Whether specifically mentioned or not all fixtures and appliances shall be provided with all fixing 
devices, nuts, bolts, screws, hangers as required. 
 
2.1.4  All  exposed  pipes  within  toilets  and  near  fixtures  shall  be  chromium  plated  brass  or  copper 
unless otherwise specified. 
 
2.2  General Requirements 
 
2.2.1  Sanitary fixtures shall be of best quality approved by the Project Manager. Wherever particular 
makes are mentioned, the choice of selection shall remain with the Project Manager. 
 
2.2.2  All fixtures and fittings shall be provided with all such accessories as are required to complete 
the  item  in  working  condition  whether  specifically  mentioned  or  not  in  the  Schedule  of 
Quantities,  specifications,  drawings  accessories  shall  include  proper  fixing  arrangement, 
brackets, nuts, bolts, screws and required connection pieces.       
 
2.2.3  Fixing screws shall be half round head Chromium Plated brass screws with C.P. washers where 
necessary. 
 

 
Behera and Associates Page - 10
PROJECT: ‐ CEDAR LAXURIA.


2.2.4  Contractor shall furnish without cost of all such accessories and fixing devices that are necessary 
and  required  but  not  supplied  along  with  the  Plumbing  Fixtures  and  C.P  fittings  by  the 
manufactures as a part of the original standard supply.  
 
2.2.5  All Fittings and Fixtures shall be fixed in a neat workmanlike manner true to levels and heights 
shown on the drawings and in accordance with the manufacturer’s recommendations. Care shall 
be taken to fix all Inlet and Outlet pipes at correct positions. Faulty locations shall be made good 
and any damage to the finished floor, tiling or terrace shall be made good at Contractors cost. 
 
2.2.6  Contractor  seal  fixtures  fixed  near  wall,  marble  and  edges.  With  an  approved  type  of  poly‐
sulphide sealant appropriate for its application.   
 
2.3  Supply of Fixtures & Fittings by Owners 
 
2.3.1  All Porcelain fittings, C.P fittings and accessories shall be supplied by the owners free of cost at 
site, unless specified otherwise. 
 
2.3.2 Contractor  shall  take  the  delivery  of  the  materials  directly  from  the  suppliers  and  will  be 
responsible for its safe storage and custody in the godown as provided by the owner. 
 
2.3.3  Only materials, accessories and fixing devices supplied as standard supplies by the manufacturer 
shall be given to the Contractor free of cost at site.     
 
2.3.4  All balance materials e.g. nuts, bolts, CP nuts and bolts; other fixing devices shall be supplied by 
the Contractor within the quoted rates.  
 
2.3.5  Description and method of fixing is given below for the contractor to understand the scope and 
extent of the work for which main materials will be supplied by the Owners.  
 
2.4  European W.C 
 
2.4.1   European W.C. shall be wash down or syphonic type floor or wall mounted set flushed by means 
of porcelain flushing cistern, exposed or concealed type flush valve or by imported type plastic 
flushing  systems  which  will  be  an  integral  part  of  the  wall  system.  Framework,  walling  and 
finishing will not form a part of the Contractor’s work. Where ever applicable flush pipe/bend 
shall be connected to the W.C. by means of a suitable rubber adapter.  Wall hung W.C. shall be 
supported by a floor mounted chair. 
 
2.4.2  Each W.C. set shall be provided with a plastic seat shall be with rubber buffers and chromium 
plated hinges. 
 

 
Behera and Associates Page - 11
PROJECT: ‐ CEDAR LAXURIA.


2.4.3  Plastic  seat  shall  be  so  fixed  that  it  remains  absolutely  stationery  in  vertical  position  without 
falling down on the W.C.  
 
2.4.4  Flushing cistern (exposed/coupled/concealed/others) when  provided shall be provided with all 
internal  flushing  mechanism,  15mm  dia  ball  cock  with  unbreakable  polyethylene  float  and 
overflow pipe. Any frame work required for fixing cistern has to be provided by the Contractor. 
Each W.C shall be suitable for flushing in low volume of water 5‐6 liters.  
   
 
2.4.5  Indian W.C. pan shall be Orissa pattern of size as specified in the Schedule of Quantities.  Each 
W.C. shall be provided with a 100 mm dia P or S trap with or without vent horn. The W.C. shall 
be  flushed  by  means  of  an  exposed  (or  concealed)  type  flush  vale.  Flush  pipe/bend  shall  be 
connected to the W.C by means of suitable rubber adaptor.  
 
2.4.6  The Indian W.C. shall be fixed in level in a neat workmanlike manner.  The W.C. and trap shall be 
set in cement concrete 1:2:4 mix (1 cement: 2 coarse sand: 4 stone aggregate 20 mm nominal 
size).  
 
2.5  Urinals 
 
2.5.1  Urinals shall be white glazed Vitreous China of size, shape and type specified in the Schedule of 
Quantities. 
 
 
2.5.2  Half  stall  Urinals  shall  be  provided  with  15  mm  dia  C.P.  spreader,  32  mm  dia  stainless  steel 
domical waste and C.P. cast brass bottle trap with pipe and wall  
 
            flange, and shall be fixed to wall by one C.I. bracket and two C.I. wall clips as recommended by 
manufacturers complete as directed by Project Manager. 
 
2.5.3  Half  stall  urinals  shall  be  fixed  with  C.P.  Brass  screws  and  shall  be  provided  with  32  mm  dia 
domical waste leading to urinal’s trap. 
 
2.5.4  Flush  pipe  shall  be  G.I  pipes  concealed  in  wall  chase  but  with  chromium  plated  bends  at  inlet 
and outlet or as given in Schedule of Quantities.  
 
2.5.5     Urinals  shall  be  flushed  by  means  of  fully  automatically  no‐touch  flush  valve  with  solenoid 
valves. 
 

 
Behera and Associates Page - 12
PROJECT: ‐ CEDAR LAXURIA.


2.5.6  Waste pipes  for urinals shall be G.I  pipes (Medium Class) to IS: 1239/uPVC 6 kg/cm2 as per IS 
4985.  Waste  pipes  may  be  exposed  on  wall  or  concealed  in  chase  as  directed  by  the 
Specifications for waste pipes shall be same as given in Section 3. 
 
2.6  Lavatory Basin 
 
2.6.1   Lavatory  basins  shall  be  white  glazed  vitreous  china  of  size,  shape  and  type  specified  in  the 
Schedule of Quantities. 
 
2.6.2     Each Basin shall be provided with brackets and clips of approved and securely fixed.  Placing of 
Basins over the brackets without secure fixing shall not be accepted. 
 
2.6.3  Each  Basin  shall  be  provided  with  a  32mm  dia  waste  with  overflow,    pop‐up  waste  or  rubber 
plug and chain as specified in the Schedule of Quantities, 32mm dia PP bottle trap with built‐in 
AAV & pipe to wall and flange. 
 
2.6.4   Each basin shall be provided with mixing fitting as specified in the Schedule of Quantities. 
 
2.6.5  Basins shall be fixed at proper heights as shown on drawings.  If height is not specified, the rim 
level shall be 79 cms or as directed by Project Manager. 
 
2.7      Sinks 
 
2.7.1     Sinks shall be white glazed fireclay or vitreous china or stainless steel or any other material as 
specified in the Schedule of Quantities. 
 
2.7.2  Each  sink  shall  be  provided  with  brackets  of  approved  and  securely  fixed.    Counter  top  sinks 
shall be fixed with suitable brackets or clips as recommended by the manufacturer.  Each sink 
shall  be  provided  with  40  mm  dia  C.P.  waste  with  chain  and  plug  as  given  in  the  Schedule  of 
Quantities. Fixing shall be done as directed by Project Manager. 
 
2.7.3  Supply  fittings  for  sinks  shall  be  mixing  fittings  or  C.P.  taps  as  specified  in  the  Schedule  of 
Quantities. 
 
2.9  Hand Drier 
 
2.9.1  The  hand  drier  shall  be  no  touch  operating  type  with  solid  waste  time  delay  to  allow  user  to 
keep hand in any position. 
 
2.9.2  The hand drier shall be fully hygienic, rated for continuous repeat use.   
 

 
Behera and Associates Page - 13
PROJECT: ‐ CEDAR LAXURIA.


 
2.9.3  The  rating  of  hand  drier  shall  be  such  that  time  required  to  dry  a  pair  of  hands  upto  wrists  is 
approximately 30 seconds.   
 
2.9.4  The hand drier shall be wall mounting type suitable for 230 volts, single phase, 50 Hz, A.C power 
supply.  
 
2.10    Accessories 
 
2.10.1  Contractor shall install all Chromium Plated and porcelain accessories as shown on the drawings 
or directed by Project Manager. 
 
2.10.2  All C.P. Accessories shall be fixed with C.P. brass half round head screws and cup washers in wall 
with  rawl  plugs  or  nylon  sleeves  and  shall  include  cutting  and  making  good  as  required  or 
directed by Project Manager. 
 
2.10.3  Recessed porcelain accessories shall be fixed in walls and set in cement mortar 1:2 (1 cement: 2 
coarse sand) and fixed in relation to the tiling work as per Interior Designer’s drawings. 
 
2.11  Urinal Partitions 
 
2.11.1  Urinal  partitions  shall  be  white  glazed  vitreous  china,  marble,  granite  or  any  other  material 
selected  by  the  same  shall  be  fixed  by  contractor  executing  the  finishing  work.  The  exact 
location shall however be co‐oriented by the Plumbing Contractor.     
 
2.11.2   Urinal partitions shall be fixed at proper heights with C.P. brass bolts, anchor fasteners and M.S. 
clips as recommended by the manufacturer and directed by Project Manager. 
 
2.12    Pan connector 
 
The WC pan connector shall be of Macfit type, soft and shall be made of single body 
construction with integral fins, made from EVA (Ethyl Vinyl Acetate). The pan connector must 
confirm to BS 5627:1984.The pan connector must be supplied with one seal made of TPE 
(Thermoplastic Elastomeric). The pan connector must be supplied with factory fitted spring 
loaded seal guard fixed on the seal.  
 
The connector shall not be allowed to come in contact with mineral oil, grease, putty or any 
compound containing mineral oil or grease. 
 
The pan connectors must be stored away from direct sun light and flames. 
 

 
Behera and Associates Page - 14
PROJECT: ‐ CEDAR LAXURIA.


Fixing: The soil pipe must be reasonably clean and smooth on the inner surface; in case the soil 
piping is in C.I. then supplier supplied bush/adaptor shall be used. The connector socket is 
pushed fully home onto the pan spigot; thereafter the WC is placed in position gently pushing 
the fitment to ensure that the connector end fits into the spigot of the pipe. The pan connector 
must be pushed in such a way as to ensure that the seals and fins turn inward to ensure proper 
sealing. 
 
2.16     Measurement 
 
2.16.1   Sanitary fixtures and accessories shall be measured by numbers in the unit given in the Schedule 
of Quantities. 
 
2.16.2  Rates for all items shall be inclusive of cutting holes and chases and making good the same, C.P 
brass  screws,  nuts,  bolts  and  any  fixing  arrangements  required  and  recommended  by 
manufacturers, testing and commissioning. 
 
 
 
 
 
 
                                       END OF SECTION II 

 
Behera and Associates Page - 15
PROJECT: ‐ CEDAR LAXURIA.


          
SECTION III                                       Soils, Waste, Vent, Rainwater Pipes & Fittings  
 
1         Scope of work  
 
1.1   Work under this section shall consist of furnishing all labour, materials, equipments and 
appliances necessary and required to completely install all soil, waste, vent and rain water pipes and 
fittings as required by the drawings and as given in the Schedule of Quantities. 
 
1.2    Without restricting to the generality of the foregoing, the work shall include the following:‐ 
 
a) Vertical and horizontal soil, waste, vent and rain water pipes, and fittings, joints, clamps 
and connections to fixtures. 
b) Soil & rainwater pipes to external sewers/drains. 
c) Connection  of  all  pipes  to  sewer  lines  as  shown  on  the  drawings  at  basement  ceiling 
level. 
d) Floor and urinal traps, cleanout plugs, inlet fittings and rainwater heads/Khurras. 
e)       Testing of all pipe lines.  
 
2  General requirements  
 
2.1   All materials shall be new and best quality conforming to Latest IS Code and specifications and 
subject to the approval of the Project Manager /Architect. 
 
2.2    Pipes  and  fittings  shall  be  fixed  truly  vertical,  horizontal  or  in  slopes  as  required  in  a  neat 
workmanlike manner. 
 
2.3  Pipes shall be fixed in a manner as to provide easy accessibility for repair and maintenance and 
shall not cause obstruction in shafts, passages etc. 
 
2.4  Pipes shall be securely fixed to walls and ceilings by suitable clamps an interval specified. 
 
2.5  Access  doors  for  fittings  and  cleanouts  shall  be  so  located  that  they  are  easily  accessible  for 
repair and maintenance. 
 
3        Piping System  
3.1      Soil, Waste & Vent Pipes   
 
a) The  Soil    &  Waste  pipe  system  above  ground  has  been  planned  as  a    "two  pipe  system"  as 
defined  in  IS:  5329,  having  separate  pipes  for  waste  from  kitchen  sinks,  bath  tubs,  showers, 

 
Behera and Associates Page - 16
PROJECT: ‐ CEDAR LAXURIA.


washbasins, AHU's condensate drains and floor drains and is approved by  the local authority. 
Waste stacks have been provided with a “P” trap at basement ceiling. 
 
b) Vertical soil & waste stacks shall be connected to a common horizontal drain pipe at basement 
floor ceiling as shown on the drawings. 
 
c) All Floors of toilets, kitchens and other service areas located on structural slab are SUNK by 300 
mm to accommodate all soil & waste pipes. 
 
d) All soil and waste from areas below general ground level will be collected in sumps and pumped 
into sewer lines. 
e) Anti‐siphonage  pipe  (ASP)  shall  be  provided  for  soil  fittings  on  vertical  stacks.  It  may  also  be 
provided for waste lines where shown on the drawings. 
 
3.2       Rainwater Pipes  
a) All terraces shall be drained by providing down‐takes rainwater pipes.  
 
b) A separate piped drainage system for slopping roof with leaders shall be provided. 
 
c) Rainwater pipes are separate and independent connected to the external storm water drainage 
system as shown on the drawings.  
 
3.3        Balcony/Planter drainage  
          Open balconies, terraces, planters and formal landscape areas will be drained by a separate pipe 
connected to external storm water drainage system. 
  
3.4   uPVC pipes for SWR system (for soil & waste) 
 
3.4.1   Pipes  
3.4.2  All  pipes  shall  be  straight  and  smooth  and  inside  free  from  cracks  and  other  manufacturing 
defects.  Pipes shall be conforming to IS: 13952 type B for soil & waste and of type A for rain 
water. 
 
3.4.3  Pipes shall be joined by approved type of socket and ‘O’ rubber ring (confirms to IS: 5382) joints 
with rubber lubricant. 
 
3.5.       Fittings  
3.5.1     Fittings  shall  conform  to  the  Indian  Standard  recommended  for  the  pipes.    Pipes  and  fittings 
must be of matching IS specification. Interchange of pipes of one standard with fittings on the 
other standard will not be permitted. 
 

 
Behera and Associates Page - 17
PROJECT: ‐ CEDAR LAXURIA.


3.5.2     Fittings shall be of the required degree of curvature with or without access door. 
 
3.5.3   Connection  from  a  vertical  stack  or  position  to  a  horizontal  line  shall  be  made  only  by  a  “Y” 
junction. 
 
3.6        Fixing  
3.6.1  All vertical pipes shall be fixed truly vertical to walls with approved type of uPVC saddle clamp. 
Branch pipes shall be connected to the stack at the same angle as that of the fittings. No collars 
shall  be  used  on  vertical  stacks.  Each  stack  shall  be  terminated  at  top  with  a  cowl  (terminal 
guard).  However  shaft  where  more  vertical  pipes  run,  the  pipes  may  be  fixed  to  the  slotted 
angle/channel supports fixed to walls at intervals specified here under:‐ 
 
3.6.2  Horizontal pipes running along ceiling shall be fixed on galvanized structural adjustable clamps 
(Clevis clamps) of special design shown on the drawings or as directed. Horizontal pipes shall be 
laid to uniform slope and the clamps adjusted to the proper levels so that the pipes fully rest on 
them. 
3.6.3    Contractor shall provide all sleeves, openings, hangers, inserts during the construction. He shall 
provide  all  necessary  information  to  the  Project  Manager/Building  Contractor  for  making  such 
provisions in the structure as necessary. All damages shall be made good to restore the surfaces 
at no extra cost. 
 
 
4.0        Clamps  
4.1     Holder bat clamps shall be of standard design and fabricated from galvanized MS standard flats 
40x3 mm thick and 12 mm dia MS rod and 6 mm nuts and bolts. Holder bat clamps shall be fixed 
in cement concrete 1 : 2 : 4 mix blocks 10x10x10 cms deep. 
 
4.2  Where holder bat clamps  are to be fixed in  RCC column or slotted angles, walls or beam  they 
shall  be  fixed  with  galvanized  40x3  mm  flat  iron  "U"  type  clamps  with  anchor  fasteners  of 
approved design or 6 mm nuts and bolts. 
 
4.3  For  SWR  pipes  conforming  to  IS:  13592  shall  be  clamped  to  wall  with  approved  type  of  uPVC 
saddle clamp/U‐clamp or as given in the Bill of quantities. 
 
4.4  Structural clamps shall be fabricated by electro‐welding from MS structural members e.g. rods, 
angles, channels flats as per detailed drawing. Contractor shall provide all nuts & bolts, welding 
material. All fabricated clamps, nuts, bolts and washers shall be not dipped galvanized. 
 
4.5    Galvanized  slotted  angle/channel  supports  on  walls  shall  be  provided  wherever  shown  on 
drawings.  Angles/channels  shall  be  of  sizes  shown  on  drawings  or  specified  in  schedule  of 
quantities.  Angles/channels  shall  be  fixed  to  brick  walls  with  bolts  embedded  in  cement 

 
Behera and Associates Page - 18
PROJECT: ‐ CEDAR LAXURIA.


concrete  blocks  and  to  RCC  walls  with  suitable  anchor  fasteners.  The  spacing  of  support  bolts 
horizontally shall not exceed 1 m. 
 
4.6    Wherever MS clamps are required to be anchored directly  to brick walls, concrete slabs, beams 
or  columns,  nothing  extra  shall  be  payable  for  clamping  arrangement  and  making  good  with 
cement concrete 1 : 2 : 4 mix (1 cement : 2 coarse sand : 4 mm stone aggregate 20 mm nominal 
size) as directed by the Project Manager. 
 
4.7  For sleeves, anchor fasteners and clamp spacing chart shall be as follows: 
 
CLAMP AND PIPE SUPPORT SPACING  
 
<-------- Commercial Pipe Dia.( Spacing in m ) ------------->
S.No. Type of Pipes & Position 15/20 20/25 32/40 50 75/80 100/110 150/160
1 Vertical Pipes
1.1 GI /MS Pipes 2.4 2.4 3 3.6 4.5 5.4
1.2 uPVC Pipes
SWR Pipes x x <----------- 1 m ------------------------>
IS 13592
1.3 uPVC /cPVC Pipes
IS 4985 for Water Supply x x x <----------1 m------------->

IS 13585 for SWR x x 0.5 0.7 0.9 0.9


2 Horizontal Pipes
2.1 GI /MS Pipes <------2.0 m ------> 2.4 m 3 3.6 4 4.5
2.2 uPVC pipes
SWR Pipes <------------------- 1.0 m ---------------->
IS
Water Supply Pipes uPVC <----------1 m------------>
IS 4985
2.3 Fittings All traps and tees and fittings runing below ceiling shall be
supported on both sides
 
5.0    Traps  
5.1   Floor traps  
Floor traps shall be siphon type full bore P or S type cast iron having a minimum 50 mm deep 
seal.. The trap and waste pipes in sunken area (where required) shall be set in cement concrete 
blocks firmly supported on the structural floor. The blocks shall be in 1 : 2 : 4 mix (1 cement : 2 
coarse sand : 4  stone aggregate 20  mm nominal size)  and extended to 40 mm below finished 
floor level. Contractor shall provide all necessary shuttering and centering for the blocks. Size of 
the block shall be 30x30 cms of the required depth. 
          
5.2  Floor trap inlet  
          Bath room traps and connections shall ensure free and silent flow of discharging water. Where 
specified, Contractor shall provide a special type inlet fitting fabricated from uPVC pipe without, 
with  one,  two  or  three  inlet  sockets  fixed  on  side  to  connect  the  waste  pipe.  Joint  between 
waste and hopper inlet socket of the trap shall be joined with solvent cement recommended by 

 
Behera and Associates Page - 19
PROJECT: ‐ CEDAR LAXURIA.


the manufacturer. Inlet shall be connected to an uPVC. P or S trap. Floor trap inlet hoppers and 
the traps if set in cement concrete blocks as specified in para above without extra charge. UPVC 
multi‐inlet trap can be used where ever possible to be decided by the project Engineer. 
 
Trap & Seals 
  All  traps  shall  be  self  cleaning  design  and  the  seal  depth  shall  be  as specified  below  wherever 
the traps are not integral with the appliances: 
   
Appliance or ware  Material  Trap Type  Seal 
depth(mm) 
Lavatory /wash basin   C.P. cast brass  32 mm dia Bottle  75 mm 
Sink  C.P. cast brass  40 mm dia Bottle  75 mm 
Kitchen  floor  drain  of  fabricated  uPVC/C.I.  75/100 mm dia ‘P’ or  ‘S’  50 mm 
drain boxes 
Urinals  uPVC/C.I.  100 mm dia ‘P’ or ‘S’  50 mm 
AHU’s  uPVC/C.I.  75 mm dia ‘P’ or ‘S’  50 mm 
 
 
5.3  Floor Gratings      
 
          Floor  and  urinal  traps  shall  be  provided  with  100‐150mm  square  or  round  CP/stainless  steel 
grating,  with  rim  of  approved  design  and  shape.  Minimum  thickness  shall  be  4  mm  or  as 
specified in the Schedule of Quantities 
5.4  Jointing  
 
  Pipe to pipe and pipe to fitting (SWR) joint shall be with ‘O’ rubber ring as recommended by the 
manufacturer. Jointing with solvent cement shall be applied to uPVC waste pipes (confirming to 
I.S. 4985) and fittings or as recommended by the manufacturer’s. 
 
6  Cleanout Plugs (on soil pipes)  
6.1  uPVC Clean out pipe for Soil, Waste or Rainwater pipes laid under floors shall be provided near 
pipe  junctions  bends,  tees,  “Ys”  and  on  straight  runs  at  such  intervals  as  required  as  per  site 
conditions. Cleanout pipe shall terminate flush with the floor levels.  
6.2      Cleanout on Drainage Pipes 
a) Cleanout  pipe  shall  be  provided  on  starting  point  of  each  drain  and  in  between  at  locations 
indicated on plans or directed by the Project Manager. Cleanout pipe shall be of size matching 
the full bore of the pipe but not exceeding 160 mm OD.  
 
b)  Cleanouts at ceiling level pipe shall be provided with a bend terminating at floor level above. 
The cap of the cleanout pipe shall have a cap flush with floor. 
 

 
Behera and Associates Page - 20
PROJECT: ‐ CEDAR LAXURIA.


7.0  Waste pipe from appliances  
 
7.1  General  
 
a)  Waste pipe from appliances e.g. wash basins, sinks and urinals shall be of uPVC pipes 40, 50 or 
63 mm OD conforming to IS: 4985 class III (6 kg/cm2 or as given in the Schedule of Quantities or 
shown on the drawings. 
 
b)  All pipes shall be fixed in gradient towards the outfalls of drains. Pipes inside a toilet room shall 
be  in  chase  unless  otherwise  shown on  drawings.  Where  required  pipes  may  be  run  at  ceiling 
level in suitable gradient and supported on galvanized structural clamps. Spacing for clamps for 
such pipes shall be as per the pipe spacing chart given in section 1.  
 
8.0  Encasing pipe in Cement Concrete  
 
   uPVC soil and waste pipes and drainage under floor in sunken slabs  and  in wall chases (when 
cut specially for the pipe) shall be encased in cement concrete 1 : 2 : 4 mix (1 cement : 2 coarse 
sand : 4 stone aggregate 12 mm size) 75 mm in bed and all‐round. When pipes are running well 
above the structural slab, the encased pipes shall be supported with suitable cement concrete 
pillars  of  required  height  at  intervals  of  one  meter.  Rate  for  concreted  round  pipes  shall  be 
inclusive of pillars, supports, shuttering and centering. 
 
9.0  Cutting and making good  
 
9.1  Contractor’s rate shall include for providing all necessary holes, sleeves, cut outs and chases in 
structural  members  as  building  work  proceeds.  Wherever  holes  are  cut  or  left  originally,  they 
shall be made good with cement concrete 1 : 2 : 4 (1 cement : 2 coarse sand : 4 stone aggregate 
20 mm nominal size) or cement mortar 1 : 2 (1 cement : 2 coarse sand) and the surface restored 
as in original condition.  
 
10.0     Testing  
 
10.1    Testing procedure specified below apply to all soil, waste and vent pipes above ground including 
pipes laid along basement ceiling. 
        
10.2  Entire  drainage  system  shall  be  tested  for  water  tightness  during  and  after  completion  of  the 
installation.  No  portion  of  the  system  shall  remain  untested.  Contractor  must  have  adequate 
number  of  expandable  rubber/bellow  plugs,  manometers,  smoke  testing  machines,  pipe  and 
fitting work test benches and any other equipment necessary and required to conduct the tests. 
All testing equipment/motors etc. shall be certified for its calibration by an approved laboratory.  

 
Behera and Associates Page - 21
PROJECT: ‐ CEDAR LAXURIA.


10.3  All materials obtained and used on site must have manufacturer's hydraulic test certificate for 
each batch of materials used on the site. 
10.4  Testing soil, waste and rainwater pipes  
 
a) Apart  from  factory  test  all  pipes  and  fittings  shall  be  hydraulically  tested  for  a  head  of  3  m 
preferably  on  a  specially  set  up  work  bench.  After  applying  pressure,  strike  the  pipe  with  a 
wooden  pallet  and  inspect  for  blow  holes  and  cracks.  Pressure  may  be  applied  for  about  2 
minutes. Reject and remove all defective pipes. 
 
b) After  installation  all  connections  from  fixtures,  vertical  stacks  and  horizontal  drains  including 
pipes along ceiling shall be tested to a hydraulic pressure not exceeding 3 m. Such tests shall be 
conducted for each floor separately by suitable plugs. 
 
c)   After the installation is fully complete, it should be tested by flushing the toilets, running at least 
20%  of  all  taps  simultaneously  and  ensuring  that  the  entire  system  is  self  draining,  has  no 
leakages, blockages etc. Rectify and replace where required. 
 
10.5  Contractor shall maintain a test register identifying date and time of each area. All tests shall be 
conducted in presence of Project Manager and signed by both. 
            
11       Measurements  
 
11.1  General  
 
a)  Rates for all items quoted shall be inclusive of all work and items given in the specifications and 
Schedule of Quantities.   
 
b)  Rates are applicable for the work in basements, under floors, in shafts at ceiling level area for all 
heights and depths. 
 
c)  Rates are inclusive of cutting holes and chase in RCC and masonry work and making  good the 
same. 
 
d)  Rates  are  inclusive  of  pre  testing,  on  site  testing,  of  the  installations,  materials  and 
commissioning of the    works. 
 
e)  Pipes (unit of measurement. Linear meter to the nearest centimeter) 
 
11.2  Pipes  shall  measured  per  running  meter  correct  to  a  centimeter  for  the  finished  work  which 
shall include fittings e.g. bends, tees, crosses, etc. The length shall be taken along centre line of 
the  pipes  and  fittings.  All  pipes  and  fittings  shall  be  classified  according  to  their  diameter, 

 
Behera and Associates Page - 22
PROJECT: ‐ CEDAR LAXURIA.


method  of  jointing  and  fixing  substance,  quality,  and  finish.  The  diameters  shall  be  nominal 
outer diameter. 
 
11.3  Cement  concrete  around  pipes  shall  be  measured  along  the  center  of  the  pipe  line  measured 
per linear meter and include any masonry supports, shuttering and centering cutting complete 
as described in the relevant specifications. 
 
11.4  Slotted angles/channels shall be measured per linear meter of finished length and shall include 
support  bolts,  nuts  and  clamps  embedded  in  masonry  walls  with  cement  concrete  blocks  and 
nothing extra will be paid for making good the same. 
 
11.5    Fittings 
          Unit  of  measurement  shall  be  the  number  of  pieces.  Pipe  fittings  are  included  in  the  rate  for 
pipes.  Urinal  traps,  trap  gratings,  hoppers,  cleanout  plugs  shall  be  measured  by  number  per 
piece  and  shall  include  all  items  described  in  the  relevant  specifications  and  Schedule  of 
Quantities. 
 
11.6  Excavation for soil pipes  
 
          No  payment  shall  be  admissible  with  respect  to  excavation,  refilling  and  disposal  of  surplus 
earth for soil and waste pipes laid below ground, in sunken slabs or over basement rafts. 
 
11.7  Project  Manager’s  decision  with  respect  to  the  correct  interpretation  regarding  mode  of 
measurement shall be final and binding on the contractor.  
 
 
 
 
 
 
 
 
End of Section III 
Soil, Waste, Vent & Rainwater Pipes & Fittings 
 
 
 
 
 
 
 

 
Behera and Associates Page - 23
PROJECT: ‐ CEDAR LAXURIA.


 
SECTION IV: WATER SUPPLY SYSTEM 
 
4.  WATER SUPPLY SYSTEM 
 
4.1  Scope of Work 
 
4.1.1  Work  under  this  section  consists  of  furnishing  all  labour,  materials  equipment  and  appliances 
necessary  and  required  to  completely  install  the  water  supply  system  as  required  by  the 
drawings, specified hereinafter and given in the Schedule of Quantities. 
 
4.1.2  Without restricting to the generality of the foregoing, the water supply system shall include the 
following:‐ 
 
a) Distribution system from main supply headers to all fixtures and appliances for   cold/hot water.   
b) Cold  water  supply  lines  from  tube‐wells  and  city  water  connections  to  fire  and  underground 
water tanks. 
c) Municipal water and Bore‐well connections to U.G. water tanks. 
d) Garden irrigation system if any 
e) Excavation and refilling of pipes trenches.   
f) Insulation to hot water pipes if required. 
g) Pipe protection and painting. 
h) Control valves, masonry chambers and other appurtenances. 
i) Connections to all plumbing fixtures, tanks, appliances and Municipal mains  
 
4.2  General Requirements 
 
4.2.1  All materials shall be new of the best quality conforming to specifications.  All works executed 
shall be to the satisfaction of the Project Manager. 
 
4.2.2  Pipes  and  Fittings  shall  be  fixed  truly  vertical,  horizontal  or  in  slopes  as  required  in  a  neat 
workmanlike manner. 
 
4.2.3  Short or Long bends shall be used on all main pipe lines as far as possible. Use of Elbows shall be 
restricted for short connections. 
 
4.2.4  Pipes shall be fixed in a manner so as to provide easy accessibility for repair and maintenance 
and shall not cause obstruction in shafts, passages etc. 
 
4.2.5  Pipes shall be securely fixed to walls and ceilings by suitable clamps at intervals specified. 
 

 
Behera and Associates Page - 24
PROJECT: ‐ CEDAR LAXURIA.


4.2.6  Clamps, hangers and supports on RCC walls, columns and slabs shall be fixed only by means of 
approved made of expandable metal fasteners inserted by use of power drills.   
 
4.2.7  All  pipe  clamps,  supports,  nuts,  bolts,  washers  shall  be  galvanized  MS  steel  throughout  the 
building. Painted MS clamps & MS nuts, bolts and washers shall not be accepted.   
 
4.2.8  Valves  and  other  appurtenances  shall  be  so  located  as  to  provide  easy  accessibility  for 
operations, maintenance and repairs. 
 
4.3  Water Supply System 
 
4.3.1  Contractor should study the site plan and water supply system diagram for an overview of the 
system. 
 
4.3.2  Source 
 
  Water supply will be acquired from Municipal Corporation water mains to a service connection 
and captive tube‐wells within the site and collected in water storage tanks located in basement.   
 
4.4  G.I. Pipes, Fittings & Valves  
 
4.4.1     All pipes inside the buildings and where specified, outside the building shall be galvanized steel 
tubes conforming to I.S. 1239 of medium/ heavy class as specified in the BOQ. 
 
4.4.2    Fittings  shall  be  malleable  iron  with  a  reinforcing  ring  over  the  threaded  ends  upto  50mm  dia 
and  without  reinforcing  rings  for  sizes  65mm  dia  and  above.  Each  fitting  shall  have 
manufacturer’s trade mark stamped on it.  Fittings for G.I. pipes shall include Couplings, Bends, 
Tees, Reducers, Nipples, Unions, and Bushes.  Fittings shall conform to I.S:1879 (Part I to X). 
 
4.4.3 Pipes and fittings shall be jointed with screwed joints. Care shall be taken to remove burr from 
the end of the pipe after reaming with a proper time.   
 
4.4.3.1  Pipe threaded joints will be made by applying suitable grade of TEFLON tape used for drinking 
water supply.  
 
4.4.3.2  All pipes shall be fixed in accordance with layout and alignment shown on the drawings.  Care 
shall  be  taken  to  avoid  air  pockets.    G.I.  pipes  inside  toilets  shall  be  fixed  in  wall  chases  well 
above the floor.  No pipes shall be run inside a sunken floor as far as possible.  Pipes may be run 
under the ceiling or floors and other as shown on drawings. 
 
 

 
Behera and Associates Page - 25
PROJECT: ‐ CEDAR LAXURIA.


4.4.4  Pipe Supports 
 
4.4.4.1  All pipes clamps, supports, hangers, rods, pipe supports, nuts and washers shall be factory made 
galvanized MS steel or alternatively galvanized after fabrication to suit site requirements.      
 
4.4.4.2  G.I  pipes  in  shafts  and  other  locations  shall  be  supported  by  galvanized  M.S  clamps  of  design 
approved by pipes in wall chases shall be anchored by G.I hooks, pipes at ceiling level shall be 
supported on structural clamps fabricated from M.S structural steel. Pipes in typical shafts shall 
be supported on Galvanised slotted angles/channels as specified elsewhere.       
 
4.4.4.3 Clamps  
 
G.I. pipes in shafts and other locations shall be supported by M.S. clamps of design approved by 
Project Manager. Pipes in wall chases shall be anchored by iron hooks, Pipes at ceiling level shall 
be  supported  on  structural  clamps  fabricated  from  M.S.  structural  steel  as  described  above. 
Pipes in typical shafts shall be supported on slotted angles/channels as specified. 
 
4.5 Anchor Fasteners  
 
4.5.1 All  pipe  supports,  hangers  and  clamps  to  be  fixed  on  RCC  walls,  beams,  columns,  slabs  and 
masonry walls 230mm thick and above by means of galvanised expandable anchor fasteners in 
drilled holes of correct size and model to carry the weight of pipes. Drilling shall be made only by 
approved  type  of  power  drill  as  recommend  and  approved  by  manufacturer  of  the  anchor 
fasteners. Failure of any fastening devices shall be the entire responsibility and contractor shall 
redo or provide additional supports at his own cost. He shall also compensate the owner for any 
damage that may be caused by such failures. 
 
4.6      Unions  
 
Contractor  shall  provide  adequate  number  of  unions  on  all  pipes  to  enable  easy  dismantling 
later  when  required.  Unions  shall  be  provided  near  each  gunmetal  valve,  stop  cock,  or  check 
valve and on straight runs as necessary at appropriate locations as required and/or directed by 
Project Manager.  
 
4.7  Flanges  
 
Flanged connections shall be provided on pipes as required or where shown on the drawings, all 
equipment connections as necessary and required or as directed by connections shall be made 
by the correct number and size of GI nuts, bolts & washers with 3 mm thick gasket. Where hot 
water  or  steam  connections  are  made  insertion  gasket  shall  be  of  suitable  high  temperature 

 
Behera and Associates Page - 26
PROJECT: ‐ CEDAR LAXURIA.


grade and quality approved by Bolt hole dia for flanges shall conform to match the specification 
for C.I. sluice valve to I.S.780. and C.I. butterfly valve to IS: 3095.  
 
4.8     CPVC pipes, fittings & valves 
 
4.8.1  All pipes inside the buildings and where specified, outside the building shall be CPVC pipes tubes 
conforming to IS 15778:1996 .Specific Gravity ASTM D 792 at 23oC should be 1.55 as specified. 
With Tensile Strength as per ASTM D 638 at 23oC should be 55N/mm2. 
 
4.8.1  JOINING PIPE & FITTINGS 
 
a. Cutting 
Pipes  shall  be  cut  either  with  a  wheel  type  plastic  pipe  cutting  or  hacksaw  blade  and  care 
shall be taken to make a square cut which provides optimal bonding area within a joint. 
 
b. Deburing/ Beveling 
Burrs and fittings should be removed from the outside and inside of pipe with a pocket knife 
or  file  otherwise  burrs  and  fittings  may  prevent  proper  contact  between  pipe  and  fitting 
during assembly. 
 
c. Fitting Preparation 
A  clean  dry  rag/cloth  should  be  used  to  wipe  dirt  and  moisture  on  the  fitting  sockets  and 
tubing end.The tubing should make contact with the socket wall 1/3 or 2/3 of the way into 
the fitting socket. 
 
d. Solvent Cement Application  
Only  CPVC  solvent  cement  confirming  to  ASTM‐F493  should  be  used  for  joining  pipe  with 
fittings.  CPVC  schedule  40  &  80  heavy  bodied  CPVC  solvent  cement  only  should  be  used 
confirming to ASTM‐F493. 
 
e. Assembly 
After  applying  the  solvent  cement  on  both  pipe  and  fitting  socket,  pipes  should  be  insert 
into the fitting socket within 30 seconds, and rotating the pipe ¼ to ½ turn while inserting so 
as  to  ensure  even  distribution  of  solvent  cement  with  the  joint.  The  assembled  system 
should be held for 10 seconds (approx) in order to allow the joint to set up. 
 
An  even  bead  of  cement  should  be  evident  around  the  joint  and  if  this  bead  is  not 
continuous, remake the joint to avoid potential leaks. 
Set & Cure times: 
 

 
Behera and Associates Page - 27
PROJECT: ‐ CEDAR LAXURIA.


Solvent  cement  set  &  cure  times  shall  be  strictly  adhered  to  as  per  the  below  mentioned 
table: 
Minimum Core prior to pressure testing at 150 psi 
 
S.no  Ambient  Temperature  during  Pipe Size 
Core period  ½” to 1”  1.1/4” to 2” 
1  Above 15 deg C  1 Hr  2 Hrs 
2  4 – 15 deg C  2 Hrs  4 Hrs 
3  Below 4 deg C  4 Hrs  8 Hrs 
 
f. Once an installation is completed and cored as per above mentioned recommendations, the 
system  should  be  hydrostatically  pressure  tested  at  150  psi  (10  Bar)  for  minimum 
24hrs.During pressure testing the system should be filled with water and if a leak is found, 
the joint should be cut out and replacing the same with new one by using coupler. 
 
4.8.2       Transition  of CPVC to Metals 
  When  making  a  transition  connection  to  metal  threads,  special  brass/plastic  transition 
fitting (Male & Female adopters) should be used. Plastic threaded connection should not be 
over torque Hard tight pluts one half turn should be adequate.  
 
4.8.3       Threaded Sealants 
        Teflon tapes shall be used to make threaded connection leak proof. 
 
4.8.4        Hangers & Supports 
 
  For horizontal runs, support should be given at 3 ft ( 90 cms) intervals for diameter of 1” and 
below and at 4 ft (1.20 mtr) intervals for larger size. 
      Hangers should not have throw or sharp edges which come in contact with the tubing and 
shall be of GI. 
 
  Support should be as per the below mentioned table: 
 
  S.No  Size of Pipe  210C  490C  710C  820 C 
  Inch  Ft  Ft   Ft  Ft 
1  ½”  5.5  4.5  3.0  2.5 
2  ¾”  5.5  5.0  3.0  2.5 
3  1”  6.0  5.5  3.5  3.0 
1/4
4  1 ”  6.5  6.0  3.5  3.5 
1/2
5  1 ”  7.0  6.0  3.5  3.5 
6  2”  7.0  6.5  4.0  3.5 
  

 
Behera and Associates Page - 28
PROJECT: ‐ CEDAR LAXURIA.


4.8.5    All  special  fittings  and  accessories  like  internally  or  externally  threaded  brass  adaptors,  ball 
valves,  globe  valves,  unions,  diaphragm  valves,  butterfly  valves,  etc  shall  be  made  of  CPVC  by 
licensee.  
 
4.8.6  The CPVC solvent cement used for installing CPVC piping systems shall conform to ASTM F493. 
Pipes  from  ½”  up  to  2”  pipes  and  fittings,  single  step  medium  bodied  CPVC  solvent  cement 
should be used. For CPVC pipes and fittings upwards of 2”, a primer shall be used followed by 
heavy  bodied  solvent  cement  conforming  to  ASTM  F493.  PVC  solvent  cement  should  not  be 
used. 
 
4.8.7  Concealed Plumbing: 
All  internal  concealed  plumbing  for  water  supply  shall  be  done  with  CPVC  pipes.  The  pipes  & 
fittings  shall  conform  to  CTS  (Copper  Tube  Size)  SDR‐11  as  per  ASTM  D2846.  All  pipes  and 
fittings  from  ½”  up  to  2”  shall  come  under  this  category.  Medium  body  CPVC  solvent  cement 
conforming to ASTM F493 should be used for joining pipes to fittings. 
 
4.09  Trenches  
All water supply pipes below ground shall be laid in trenches with a minimum cover of 60 cms. 
The width and depth of the trenches shall be as follows 
 
  Dia of pipe    Width of Trench     Depth of Trench 
  15mm to 50mm   30 cms        75cms 
  65mm to 100mm  45 cms        100 cms 
 
4.10     Sand filling  
 
Pipes  in  trenches  shall  be  protected  with  fine  sand  15  cms  all  round  before  filling  in  the 
trenches.  
             Painting  
 
4.10.1 All  pipes  above  ground  shall  be  painted  with  one  coat  of  red  lead  and  two  coats  of  synthetic 
enamel paint of approved shade and quality. Pipes shall be painted to standard color code given 
in this document or specified by Project Manager.  
 
4.11 Pipe protection  
 
4.11.1 All GI pipes in wall chase and below floor in toilets (where so fixed) shall be protected against 
corrosion by the application of two coats of bitumen paint covered with polythene tape and a 
final coat of bitumen paint. 
 

 
Behera and Associates Page - 29
PROJECT: ‐ CEDAR LAXURIA.


4.11.2 G.I. water supply pipes, if buried in ground or sunken slab, shall be protected with multi layer 
bitumen membrane tape 3mm thick with a final coat of hot or cold applied bitumen. "Pypkote" 
or equivalent.  
 
4.12 Valves  
 
4.12.1 Ball Valves  
 
Valves upto 50 mm dia. shall be screwed type Ball Valves with stainless steel balls spindle teflon 
seating  and  gland  packing  tested  to  a  hydraulic  pressure  of  20  kg  ,  sq.cm.,  and  accompanying 
couplings and steel handles.( to BS 5351 )  
 
4.13 Butterfly Valves – Slim Seal Type 
 
4.13.1 Valves 65 mm dia and above shall be cast iron butterfly valve to be used for isolation. The valves 
shall  be  bubble  tight,  resilient  seated  suitable  for  flow  in  either  direction  and  seal  in  both 
direction with accompanying flanges and steel handle.  
 
4.13.2 Butterfly valve shall be of best quality conforming to IS: 13095. 
 
4.14. Non Return Valve  (Dual Slim Type) 
  
Where  specified,  non  return  valve  shall  be  provided  through  which  flow  shall  occur  in  one 
direction only.  
 
  Each Butterfly and Slim Type Swing Check (NRV) Valve shall be provided with a pair  
     of flanges screwed or welded to the main line and having the required number of    
     nuts, bolts and washers of correct length.  
 
4.15.   Storage tanks Underground & Overhead Tank. ( Accessories & Connections)  
 
4.15.1   Storage  tanks  for  water  supply  shall  be  in  reinforced  cement  concrete  built  by  the  building 
contractor. 
 
4.15.2 Each tank shall be provided with a 560mm Dia Heavy Duty Cast Iron / SFRC  manhole frame and 
cover. 
 
 
 
 
 

 
Behera and Associates Page - 30
PROJECT: ‐ CEDAR LAXURIA.


4.16.   Storage Tanks  
 
4.16.1 Underground 
 
Underground  storage  tanks  for  water  supply  shall  be  reinforced  cement  concrete  built  by  the 
building contractor.  
 
Each tank shall be provided with a 560mm Dia Heavy Duty Cast Iron manhole frame and cover 
or as approved by local municipal authority.  
 
4.17    Outlets and overflow  
 
All  nozzles  for  puddle  flanges  in  RCC  tank  for  inlet,  outlet,  overflow  and  scour  etc.  shall  be 
provided by civil contractor or as given in the Schedule of Quantities, further connections and 
accessories shall be provided under this contract.  
 
4.18.   Testing  
 
     All pipes, fittings and valves, after fixing at site, shall be tested by hydrostatic   
            pressure of 1.5 times the working pressure or 7 kg / sq.cm whichever is more.  
Pressure  shall  be  maintained  for  a  period  of  at  least  thirty  minutes  without  any  drop.  A  test 
register  shall  be  maintained  and  all  entries  shall  be  signed  and  dated  by  Contractor  (s)  and 
Project Manager.  
 
 
In addition to the sectional testing carried out during the construction, Contractor shall test the 
entire  installation  after  connections  to  the  overhead  tanks  or  pumping  system  or  mains.    He 
shall rectify all leakages and shall replace all defective materials in the system. Any damage done 
due  to  carelessness,  open  or  burst  pipes’  or  failure  of  fittings,  to  the  building,  furniture  and 
fixtures  shall  be  made  good  by  the  Contractor  during  the  defects  liability  period  without  any 
cost.  
 
After commissioning of the water supply system, Contractor shall test each valve by closing and 
opening  it  a  number  of  times  to  observe  if  it  is  working  efficiently.  Valves,  which  do  not 
effectively operate, shall be replaced by new ones at no extra cost and the same shall be tested 
as above. 
 
Hot  water  pipes  chased    into  the  walls  shall  be  provided  with  a    6mm    thick  insulation  with 
elastic  flexible  material  having  hermetic  closed  cell  structure    of  expanded  synthetic  material 
rated for 60ºC hot water supply. 
 

 
Behera and Associates Page - 31
PROJECT: ‐ CEDAR LAXURIA.


 
4.19      Measurement  
 
a) Pipes  above  ground  shall  be  measured  per  linear  meter  (to  the  nearest  cm)  and  shall  be 
inclusive  of  all  fittings  e.g.  coupling,  tees,  bends,  elbows,  unions,  flanges  and  U  clamps  with 
nuts, bolts & washers fixed to wall or other standard supports.  
 
b) Jointing  with  teflon  tape,  white  lead,  solvent,  crimping  and  insertion  gasket  of  appropriate 
temperature grade. 
 
c) Cutting holes, and chases in walls, floors, any pipe support required for pipes below ground & 
making good the same.  
 
d) Excavation,  backfilling,  disposal  of  surplus  earth  and  restoring  the  ground  &  floor  in  original 
condition.  
 
4.20       Pipe Supports 
 
Fabricated and / or galvanised supports shall be measured by weight. Weight for each type of 
clamp  shall  be  calculated  on  basis  of  the  quantity  of  structurals  and  MS  used  from  the 
theoretical weight calculated on basis of the components theoretical weight of the sections. 
 
4.20.1 Rate  quoted  for  supports  &  hangers  shall  be  inclusive  of  : 
 
a) Expandable anchor fastens.  
b) Galvanising of all supports & hangers.  
c) Cutting holes in walls, ceilings on floors and making good where permitted. 
d) Nuts, bolts and washers for fixing and assembling.  
e) Wooden / PVC pipe saddles for vertical or horizontal runs.  
 
4.20.2 Valves 
 
Gunmetal,  cast  iron,  butterfly  and  non  return  valves  and  puddle  flanges  shall  measured  by 
numbers and shall include wheels I caps, GI nuts, bolts, washers, insertion gasket.  
 
4.20.3 Painting/pipe protection/insulation 
 
Painting/pipe protection /insulation for pipes shall be measured per linear meter over finished 
surface and shall include all valves and fittings for which no deduction shall be made. No extra 
payment shall be made for fittings, valves or flanges.  
END OF SECTION IV

 
Behera and Associates Page - 32
PROJECT: ‐ CEDAR LAXURIA.


 
SECTION V: DRAINAGE 
 
5.  DRAINAGE (Sewers & Storm Water Drains) 
 
5.1 Scope of work  
 
5.1.1 Work  under  this  section  shall  consist  of  furnishing  all  labour,  materials,  equipment  and 
appliances necessary and required to completely install all the drainage system as required by 
the drawings and specified hereinafter or given in the Schedule of Quantities. 
 
5.1.2 Without restricting to the generality of the foregoing, the drainage system shall include:‐  
 
a) Sewer  lines  including  excavations,  pipelines,  manholes,  drop  connections  and  connections  to 
the existing sewer.  
 
b) Storm  water  drainage,  excavation,  pipelines,  manholes,  catch  basins,  drain  channels  and 
connections to the existing storm water drain.  
 
5.2 General requirements  
 
5.2.1 All  materials  shall  be  new  of  the  best  quality  conforming  to  specifications  and  subject  to  the 
approval of the Project Manager.  
 
5.2.2 Drainage lines and open drains shall be laid to the required gradients and profiles. 
 
5.2.3  All drainage work shall be done in accordance with the local municipal bye‐laws.  
 
5.2.4 Contractor  shall  obtain  necessary  approval  and  permission  for  the  drainage  system  from  the 
municipal or any other competent authority.  
 
5.2.5 Location  of  all  manholes,  etc.  shall  be  got  confirmed  by  the  Contractor  from  the  Architect  / 
Landscape Architect. As far as possible, no drains or sewers shall be laid in the middle of road 
unless otherwise specifically shown on the drawings or directed by the Project Manager. 
 
5.3 Excavation 
 
5.3.1 Alignment and grade  
 
The sewer pipes shall be laid to alignment and gradient shown on the drawings but subject to 
such  modifications  as  shall  be  ordered  by  the  Project  Manager.  No  deviations  from  the  lines, 

 
Behera and Associates Page - 33
PROJECT: ‐ CEDAR LAXURIA.


depths  of  cutting  or  gradients  of  sewers  shown  on  the  plans  and  sections  shall  be  permitted 
except by the express direction in writing of the Project Manager. 
 
5.3.2 Excavation in tunnels  
 
The excavation for sewer works shall be open cutting only, unless the permission of the Project 
Manager  is  obtained  for  laying  pipes  in  tunnel  where  sewers  have  to  be  constructed  along 
narrow passages or difficult ground.  
 
5.3.3 Opening out trenches 
 
In excavating the trenches, etc. the solid road metalling, pavement, kerbing, etc. and turf is to 
be placed on one side and preserved for reinstatement when the  
 
trenches  or  other  excavation  shall  be  filled  up.  Before  any  road  metal  is  replaced,  it  shall  be 
carefully  sifted.  The  surface  of  all  trenches  and  holes  shall  be  restored  and  maintained  to  the 
satisfaction of the Project Manager.  
 
The Contractor shall grub up and clear the surface over the trenches and other excavations of all 
trees,  stumps  roots  and  all  other  encumbrances  affecting  execution  of  the  work  and  shall 
remove them from the site to the approval of the Project Manager.  
 
5.3.4 Obstruction of roads  
 
The Contractor shall not occupy or obstruct by his operation more than one half of the width of 
any road or street and sufficient space shall then be left for public and private transit, he shall 
remove the materials excavated and bring them back again when the trench is required to be 
refilled. The Contractor shall obtain the consent of the Project Manager.  
 
5.3.5 Removal of filth 
 
All  night  soil,  filth  or  any  other  offensive  matter  met  with  during  the  execution  of  the  works, 
immediately after it is taken out of any trench, sewer or cess pool, shall not be deposited on to 
the surface of any street or where it is likely to be a nuisance or passed into any sewer or drain 
but  shall  be  at  once  put  into  the  carts  and  remove  to  a  suitable  place  to  be  provided  by  the 
Contractor.  
 
 
 
 
 

 
Behera and Associates Page - 34
PROJECT: ‐ CEDAR LAXURIA.


5.3.6 Excavation to be taken to proper depths  
 
The  trenches  shall  be  excavated  to  such  a  depth  that  the  sewer  shall  rest  on  concrete  as 
described  in  the  several  clauses  relating  thereto  and  so  that  the  inverts  may  be  at  the  levels 
given in the sections.  
 
5.3.7 Refilling 
 
After the sewer or other work has been laid and proved to be water tight, the trench or other 
excavations shall be refilled. Utmost care shall be taken in doing this, so that no damage shall be 
caused  to  the  sewer  and  other  permanent  work.  The  filling  in  the  haunches  and  upto  75cms 
above  the  crown  of  the  sewer  shall  consist  of  the  finest  selected  materials  placed  carefully  in 
15cms  layers  and  flooded  and  consolidated.  After  this  has  been  laid,  the  trench  and  other 
excavation shall be refilled carefully in 15cms layers with materials taken from the excavation, 
each layer is being watered to assist in the consolidation unless the Project Manager.       
 
5.3.8  Contractor to restore settlement and damages  
 
The contractor shall, at his own costs and charges make good promptly during the whole period 
the  works  are  in  hand,  any  settlement  that  may  occur  in  the  surfaces  of  roads,  berms, 
footpaths, gardens, open spaces etc. Whether public or private caused by his trenches or by his 
other excavations and he shall be reliable for any accidents caused thereby. He shall also at his 
own cost and expenses and charges, repair any make of any damage done to the buildings and 
other property.  
     
5.3.9  Disposal of Surplus Earth 
 
The  Contractor  shall  at  his  own  costs  and  charges  provide  places  for  disposal  of  all  surplus 
materials not required to be used on the works. As each trench is refilled the surplus soil shall be 
immediately removed, the surface properly restored and roadways and sides left clear.  
 
5.3.10  Timbering of sewer and trenches  
 
a) The  contractor  shall  at  all  times  support  efficiently  and  effectively  the  sides  of  the  sewer 
trenches and other excavations by suitable timbering, pilling and sheeting and they shall be 
closed, timbered in loose of sandy strata and below the surface of the sub soil water level. 
 
b) All  timbering,  sheeting  and  piling  with  their  walling  and  supports  shall  be  of  adequate 
dimensions  and  strength  and  fully  braced  and  strutted  so  that  no  risk  of  collapse  of 
subsidence of the walls of the trench shall be take place.         
 

 
Behera and Associates Page - 35
PROJECT: ‐ CEDAR LAXURIA.


c) The  contractor  shall  be  held  responsible  and  will  be  accountable  for  the  sufficiency  of  all 
timbering, bracings, sheeting and piling used as also for, all damage to persons and property 
resulting from improper quality, strength, placing, maintaining or removing of the same. 
 
5.3.11  Shoring of Buildings        
 
The Contractor shall shore up all buildings, walls and other structures, the stability of which is 
liable  to  be  endangered  by  the  execution  of  the  work  and  shall  be  fully  responsible  for  all 
damages to persons or property resulting from any accident.   
 
5.3.12 Removal of water from sewer, trench etc  
 
a) The Contractor shall at all times during the progress of the work keep the trenches and 
excavations  free  from  water  which  shall  be  disposed  of  by  him  in  a  manner  as  will 
neither cause injury to the public health nor to the public or private property nor to the 
work completed or in progress nor to the surface of any roads or streets, nor cause any 
interference with the use of the same by the public.  
 
b) If  any  excavation  is  carried  out  at  any  point  or  points  to  a  greater  width  than  the 
specified cross section of the sewer with its envelope, the full width of the trench shall 
be filled with concrete by the Contractor at his own expenses. 
 
5.3.13 Width of trench  
 
5.3.14 Recommended width of trenches at the bottom shall be as follows:‐  
 
100 mm dia pipe     55 cms 
150 mm dia pipe     55 cms 
225‐250 mm dia pipe     60 cms 
300 mm dia pipe     75 cms 
 
Maximum width of the bed concrete shall also be as above. No additional payment is admissible 
for widths greater than specified.  
 
5.4      SALT GLAZED STONEWARE PIPES 
 
5.4.1  Stoneware pipes shall be of first class quality salt glazed and free from rough texture inside or 
outside and straight.  All pipes shall have the manufacturers name marked on it and shall comply 
to IS: 651‐1971 and shall be of approved makes. 
 
5.4.2  The maximum permissible slope to the various diameters of pipes shall be as follows: 

 
Behera and Associates Page - 36
PROJECT: ‐ CEDAR LAXURIA.


  100mm pipe  ……  1 in 40 to 1:50 
  150mm pipe  ……  1 in 60 to 1:100 
  200mm pipe  ……  1 in 80   1: 120 to 1: 200 
  250mm pipe  ……  1 in 90   1: 120 to 1: 250  
 
5.4.3  Where necessary, pipe shall be laid on a bed of plain cement concrete 1:3:6 and minimum 150 
mm thick, and shall be projected by providing hunching up to half the diameter of the pipes. The 
width of the concrete bed for various diameters shall be as follows:   
 
  100mm dia pipe  ……  380mm wide 
  150mm dia pipe  ……  450mm wide 
  200mm dia pipe  ……  600mm wide 
  250mm dia pipe   ……  700mm wide 
Where the pipes are laid on a soft soil, with the maximum water table level, laying at the invert 
level of the pipe, the pipe shall be bedded  in concrete. 
 
5.4.5  Laying and Jointing of Stoneware Salt Glazed Pipes 
 
a) Pipes  are  liable  to  be  damaged  in  transit  and  notwithstanding  tests  that  may  have  been 
made  before  dispatch  each  pipe  shall  be  examined  carefully  on  arrival  at  site.    Each  pipe 
shall  be  rung  with  a  wooden  hammer  or  mallet  and  those  that  do  not  ring  true  and  clear 
shall be rejected.  Sound pipes shall be carefully stacked to prevent damage.  All defective 
pipes  should  be  segregated,  marked  in  a  conspicuous  manner  and  their  use  in  the  works 
prevented. 
 
b) The  pipes  shall  be  laid  with  sockets  leading  uphill  and  should  rest  on  solid  and  even 
foundations for the full length of the barrel.  Socket holes shall be formed in the foundation 
sufficiently deep to allow the pipe jointer room to work right round the pipe and as short as 
practicable to admit the socket and allow the joint to be made. 
 
c) Where pipes are not bedded on concrete the  trench bottom shall  be left slightly high and 
carefully bottomed up as pipe laying proceeds so that the pipe barrels rest on firm ground.  
If excavation has been carried too low it shall be made up with cement concrete 1:5:10 mix 
at the Contractor’s cost and charges. 
 
d) If  the  bottom  of  the  trench  consists  of  rock  or  very  hard  ground  that  cannot  be  easily 
excavated to a smooth surface, the pipes shall be laid on cement concrete bed of 1:5:10 mix 
to ensure even bearing. 
 
 
 

 
Behera and Associates Page - 37
PROJECT: ‐ CEDAR LAXURIA.


 
5.4.6  Jointing of Pipes 
 
a) Tarred gaskin shall first be wrapped round the spigot of each pipe  and the spigot shall then 
be  placed  into  the  socket  of  the  pipe  previously  laid,  the  pipe  shall  then  be  adjusted  and 
fixed in its correct position and the gaskin caulked tightly home so as to fill not more than 
one quarter of the total length of the socket. 
 
b) The remainder of the socket shall be filled with stiff mix of cement mortar (1 cement: 1 clear 
sharp washed sand).  When the socket is filled, a fillet should be formed round the joint with 
a  trowel  forming  an  angle  of  45  degrees  with  the  barrel  of  the  pipe.    The  mortar  shall  be 
beaten up and used after it has begun to set. 
 
c) After the joint has been made any extraneous materials shall be removed from inside of the 
joint with a suitable scraper or “Badger”.  The newly made joints shall be protected until set 
from  the  sun,  drying  winds,  rain  or  dust.    Sacking  or  other  materials,  which  can  be  kept 
damp,  shall  be  used.    The  joints  shall  be  exposed  and  space  left  all  rounds  the  pipes  for 
inspection by the Project Manager.  The inside of the sewer must be left absolutely clear in 
bore and free from cement mortar or other obstructions throughout its entire length, and 
shall efficiently drain and discharge. 
 
5.6      Testing 
 
 All  lengths  of  the  sewer  and  drain  shall  be  fully  tested  for  water  tightness  by  means  of  water 
pressure maintained for not less than 30 minutes. Testing shall be carried out from manhole to 
manhole. All pipes shall be subjected to a test pressure of at least 1.5 meter head of water. The 
test pressure shall, however, not exceed 6 meter head at any point. The pipes shall be plugged 
preferably  with  standard  design  plugs  with  rubber  plugs  on  both  ends.  The  upper  end  shall, 
however, be connected to a pipe for filling with water and getting the required head.  
 
 Sewer lines shall be tested for straightness by: (i) inserting a smooth ball 12 mm less than the 
internal diameter of the pipe. In the absence of obstructions such as yarn or mortar projecting 
at the joints the ball should roll down the invert of the pipe and emerge at the lower end. (ii) 
means of a mirror at one and a lamp at the other end. If the pipeline is straight the full circle of 
light will be seen otherwise obstruction of deviation will be apparent.  
 
 The Contractor shall give a smoke test to the drains and sewer at his own expense and charges, 
if directed by the Project Manager.  
 
A test register shall be maintained which shall be signed and dated by Contractor. 
 

 
Behera and Associates Page - 38
PROJECT: ‐ CEDAR LAXURIA.


5.7      Gully traps  
 
Gully traps shall be of the same quality as described for stoneware pipes in clause 5.4.1 above 
and used where shown on drawings.  
 
Gully  traps  shall  be  fixed  in  cement  concrete  1:5:10  mix  (1  cement:  5  coarse  sand:  10  stone 
aggregate 40 mm nominal size) and a brick masonry chamber 30x30 cms inside plastered with 
cement  mortar  I:5  with  15x  15  cms  grating  inside  and  30x30  cms  C.I.  sealed  cover  and  frame 
weighing  not  less  than  7.3  kg  to  be  constructed  as  per  standard  drawing.  Where    necessary, 
sealed cover shall be replaced with C.I. grating of the same size.  
 
5.8 Reinforced cement concrete pipes  
 
 All underground storm water drainage pipes and sewer lines where specified (other than those 
specified cast iron) shall be centrifugally spun S & S RCC pipes of specified class. Pipes shall be 
true and straight with uniform bore, throughout. Cracked, warped pipes shall not be used on the 
work.  All  pipes  shall  be  tested  by  the  manufacturer  and  the  Contractor  shall  produce,  when 
directed a certificate to that effect from the manufacturer.  
 
 Laying 
R.C.C. spun pipes shall be laid on cement concrete bed or cradles as specified and shown on the 
detailed  drawings.  The  cradles  may  be  precast  and  sufficiently  cured  to  prevent  cracks  and 
breakage in handling. The invert of the cradles shall be left 12 mm below the invert level of the 
pipe properly placed on the soil to prevent any disturbance. The pipe shall then be placed on the 
bed  concrete  or  cradles  and  set  for  the  line  and  gradient  by  means  of  sight  rails  and  bonding 
rods etc. Cradles or concrete bed may be omitted, if directed by the Project Manager. 
 
 Jointing 
After setting out the pipes the socket shall be centered over the spigot and filled in with tarred 
gaskin, so that sufficient space is left on either side of the collar to receive the mortar. The space 
shall  then  be  filled  with  cement  mortar  1:2  (1  Cement:  2  fine  sand)  and  caulked  by  means  of 
proper tools. All joints shall be  
 
finished at an angle of 45 degrees to the longitudinal axis of the pipe on both sides of the collar 
neatly.  
 
 Testing  
All pipes shall be tested to a hydraulic test of 1.5 m head for at least 30 minutes at the highest 
point in the section under test. Test shall also be carried out similar to those for stoneware pipes 
given  above.  The  smoke  test  shall  be  carried  out  by  the  contractor,  if  directed  by  the  Project 

 
Behera and Associates Page - 39
PROJECT: ‐ CEDAR LAXURIA.


Manager  and  a  test  register  shall  be  maintained  which  shall  be  signed  and  dated  by  the 
Contractor/Project Manager.   
 
5.9  Cement Concrete and masonry works (For Manholes and Chambers)  
 
5.9.1  Materials 
 
a) Water 
Water  used  for  all  the  construction  purposes  shall  be  clear  and  free  from  Oil,  Acid,  Alkali, 
Organic and other harmful matters, which shall deteriorate the strength and/or durability of 
the structure.  In general, the water suitable for drinking purposes shall be considered good 
enough for construction purpose. 
 
b) Aggregate for Concrete 
The aggregate for concrete shall be in accordance with I.S. 383 and I.S. 515 in general, these 
shall  be  free  from  all  impurities  that  may  cause  corrosion  of  the  reinforcement.    Before 
actual  use  these  shall  be  washed  in  water,  if  required  as  per  the  direction  of  Project 
Manager.  The size of the coarse aggregate shall be done as per I.S.383. 
 
c) Sand 
Sand  for  various  constructional  purposes  shall  comply  in  all  respects  with  I.S  650  and  I.S. 
2116.  It  shall  be  clean,  coarse  hard  and  strong,  sharp,  durable,  uncoated,  free  from  any 
mixture  of  clay,  dust,  vegetable  matters,  mica,  iron  impurities  soft  or  flaky  and  elongated 
particles, alkali, organic  matters, salt, loam and other impurities which may be considered 
by the Project Manager. 
  
d) Cement 
The  cement  used  for  all  the  constructional  purposes  shall  be  ordinary  Portland  cement  or 
rapid hardening Portland cement conforming to I.S. 269. 
 
e) Mild Steel Reinforcement 
The mild steel for the reinforcement bars shall be in the form of round bars conforming to 
all requirements of I.S. 432 (Grade I). 
 
f) Bricks 
Bricks  shall  have  uniform  color,  thoroughly  burnt  but  not  over  burnt,  shall  have  plan 
rectangular faces with parallel sides and sharp right angled edges.  They should give ringing 
sound when struck.  Brick shall not absorb more than 20% to 22% of water, when immersed 
in water for 24 hours.  Bricks to be used shall be approved by the Project Manager. 
 
 

 
Behera and Associates Page - 40
PROJECT: ‐ CEDAR LAXURIA.


g) Other Materials 
Other materials not fully specified in these specifications and which may be required in the 
work  shall  conform  to  the  latest  I.S.    All  such  materials  shall  be  approved  by  the  Project 
Manager before use. 
 
5.9.2 Cement concrete (plain or reinforced)  
 
a) Cement  concrete  pipes  bedding,  cradles,  foundations  and  R.C.C.  slabs  for  all  works  shall  be 
mixed by a mechanical mixer where quantities of the concrete poured at one time permit. Hand 
mixing  on  properly  constructed  platforms  may  be  allowed  for  small  quantities  by  the  rate  for 
cement concrete shall be inclusive of all shuttering and centering at all depth and heights.  
 
b) Concrete work shall be of such thickness and mix as given in the Schedule of Quantities. 
 
c) All concrete work shall be cured for a period or at least 7 days. Such work shall be kept moist by 
means of gunny bags at all times. All pipes trenches and foundations shall be kept dry during the 
curing period. 
 
5.9.3 Masonry  
 
Masonry work for manholes, chambers, septic tanks, and such other works as required shall be 
constructed  from  1st  class  bricks  or  2nd  class  as  specified  in  the  Schedule  of  quantities  in 
cement mortar 1:5 mix (1 cement: 5 coarse sand). All joints shall be properly raked to receive 
plaster. 
 
5.9.4 Cement concrete for pipe support 
 
Wherever  specified  or  shown  on  the  drawing,  all  pipes  shall  be  supported  in  bed  all  round  or 
haunches.  The  thickness  and  mix  of  the  concrete  shall  be  given  in  the  Schedule  of  Quantities. 
Width of the bedding shall be as per para 5.3.1.4. 
 
Unless  otherwise  directed  by  the  Project  Engineer,  cement  concrete  for  bed,  all‐round  or  in 
haunches shall be laid as follows: ‐ 
 
upto 1.5 m    upto 3 m    beyond 3 m 
depth      depth      depth 
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 
Stoneware  pipes  All round              Haunches   All round 
In open ground   (1:4:8)      (1:4:8)      (1:4:8) 
(no sub soil water)     
 

 
Behera and Associates Page - 41
PROJECT: ‐ CEDAR LAXURIA.


R.C.C              All round              Haunches          Haunches 
(In sub soil water)  (1:3:6)      (13:6)      (1:3:6) 
 
PP Pipes    All round    Haunches    Haunches 
(In all conditions)  (1:3:6)      (13:6)      (1:3:6) 
 
R.C.C Pipes    All round    All round    All round 
Or PP Pipes    (1:3:6)      (13:6)      (1:3:6) 
Under or building 
(Ratio refer to cement: coarse sand: stone aggregate 40 mm nominal size) 
 
R.C.C pipes or PP pipes may be supported on brick masonry or precast R.C.C or in situ cradles. 
Cradles shall be shown on the drawings. Pipes in loose soil or above ground shall be supported 
on brick or stone masonry pillars as shown on the drawings. 
 
5.10 Manholes and chambers  
 
5.10.1 All manholes, chambers and other such works as specified shall be constructed on brick masonry 
in cement mortar 1:5(1 cement: 5 coarse sand) as specified in the Schedule of Quantities. 
  
5.10.2 All  manholes  and  chambers,  etc.  shall  be  supported  on  base  of  cement  concrete  of  such 
thickness and mix as given in the Schedule or Quantities or shown in the drawings. 
 
Where not specified, manholes shall be constructed as follows:‐ (all dimensions internal clear in 
cms) 
 
Size of manhole   90x80    120x90    91 dia     122 dia 
 type       Rect.     Rect.     Conical  Conical 
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 
Maximum depth   120     240     167     168  
 
Average thickness 
Of R.C.C slab     15    15    ‐    ‐   
 
Size of cover and  
frame cms    60x45    50 dia     50 dia    50 dia 
 
Weight of Cover  38 kg    116 or     116 or    116 or 
and frame    ‐‐‐‐‐‐    208 kg    208 kg    208 kg 
 
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 

 
Behera and Associates Page - 42
PROJECT: ‐ CEDAR LAXURIA.


 
5.10.3 All manholes shall be provided with cement concrete benching in 1:2:4 mix. The benching shall 
have a slope of 10 cms towards the channel. The depth of the channel shall be full diameter of 
the  pipe.  Benching  shall  be  finished  with  a  floating  coat  of  neat  cement.  (1  cement:  2  coarse 
sand: 4 stone aggregate 20 mm nom. Size) as per standard details. 
 
5.10.4 All manholes shall be plastered with 12mm thick cement mortar 1: 3 (1 cement: 3 coarse sand) 
and finished with a floating coat of neat cement inside. Manhole shall be plastered outside as 
above but with rough plaster mixed with water proofing compound.  
 
5.10.5 All  manholes  with  depths  greater  than  1  m.  shall  be  provided  with  20  mm  square  or  25  mm 
round rods plastic coated catch rings set in cement concrete blocks 25x10x10 cms in 1:2:4 mix 
30 cms vertically and staggered. Foot rests shall be coated with coal tar before embedding. 
 
5.10.6 All  manholes  shall  be  provided  with  cast  iron/steel  fiber  reinforced  plastic  (SFRC)  covers  and 
frames and embedded in reinforced cement concrete slab. Weight of cover, frame and thickness 
of slab shall be as specified in the Schedule of Quantities or given above. 
 
5.10.7 Road gullies, ramp drains, gratings in basement shall be cast iron with M.S. frame or Steel Fiber 
Reinforced Concrete (SFRC) with frame as specified in the Schedule of Quantities. 
 
5.11 Making connections  
 
5.11.1 Contractor shall connect the sewer line of the building to the main manhole by providing making 
holes and channels etc.  
 
5.12      Measurement 
 
5.12.1 Excavation 
 
Measurement  for  excavation  of  pipe  trenches  shall  be  made  per  linear  meter  under  the 
respective category of soil classification encountered at site and specified in the tender. 
 
 A)   Ordinary soil 
 B)  Hard soil (hard moorum & soft rock) 
 C)  Hard rock requiring chiseling 
 D)  Hard rock requiring blasting 
 
Trenches shall be measured between outside walls of manholes at top and the depth shall be 
the  average  depth  between  the  two  ends  to  the  nearest  cm.  The  rate  quoted  shall  be  for  a 
depth up to 1.5 m or as given in the Schedule of Quantities.  

 
Behera and Associates Page - 43
PROJECT: ‐ CEDAR LAXURIA.


 
Payment for trenches more than 1.5 m in depth shall be made for extra depth as given in the 
schedule of quantities and above the rate for depth up to 1.5 m.  
 
Timbering and Shoring Timbering and  shoring as described above  shall be  measured per  sq m 
and paid for as per the type of timbering of shoring done at site and as per the relevant item in 
the Schedule of Quantities. Rate for timbering and shoring shall be for all depths and types of 
soil classifications including saturated soil.  
 
Saturated Soil  
 
No  extra  payment  for  pumping  and  bailing  out  water  shall  be  made  for  excavation  with  an 
average depth of 1.5 m in saturated soil, surface water from rain falls or broken pipes lines, or 
sieves and other similar sources. An extra rate as quoted in the schedule of quantities shall be 
paid  for  excavation  in  saturated  soil  for  pipe  trenches  above  average  depth  of  1.5  m.  No 
payment is admissible for water collected from surface sources and broken pipelines or sewers. 
 
Refilling, Consolidation and Disposal of Surplus Earth  
 
Rate quoted for excavation of trenches shall be inclusive of refilling, consolidation and disposal 
of surplus earth within a lead of 200 m.  
 
 
5.12.2   SW Pipes / RCC pipes 
                        SW /R.C.C. pipes shall be measured for the finished length of the Pipe line per                            
                         linear meter i.e.     
 
(a)   Lengths  between  manholes  shall  be  recorded  from  inside  of  one  manhole  to  inside  of 
other manhole 
(b)   Length between gully trap and manhole shall be recorded between socket of pipe near 
gully  trap  and  inside  of  manhole.  Rate  shall  include  all  items  given  in  the  schedule  of 
quantities and specifications.  
 
5.12.3 Gully Traps  
 
Gully traps shall be measured by the number and rate shall include all excavation, foundation, 
concrete  brick  masonry,  cement  plaster  inside  and  outside,  C.I.  grating  and  sealed  cover  and 
frame.  
 
 
 

 
Behera and Associates Page - 44
PROJECT: ‐ CEDAR LAXURIA.


5.12.4 Cement Concrete for Pipes  
 
Cement concrete in bed and all round or in haunches shall be paid per running meter between 
the outside walls of manholes at bottom of the trench. No additional payment is admissible in 
respect  of  concreting  done  for  widths  greater  than  specified,  for  shuttering  or  centering  and 
concreting in sub soil water conditions.  
 
5.12.5 Manholes, Catch basins & Ramp drains  
 
a)   All manholes and catch basins shall be measured by numbers and shall include all items 
specified above and necessary excavation, refilling & disposal of surplus earth.  
 
b)  Manholes  with  depths  greater  than  specified  under  the  main  item  shall  be  paid  for 
under  "extra  depth"  and  shall  include  all  items  as  given  for  manholes.  Measurement 
shall be done to the nearest cm. Depth of the manholes shall be measured from top of 
the manhole cover to bottom of chancel.  
 
a) Ramp drains shall be measured per meter length.  
 
5.12.6 Making Connections 
 
Item for making connection to municipal sewer shall be paid for by number and shall include all 
items given in the Schedule of Quantities and specifications. 
 
 
 
 
END OF SECTION V 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
Behera and Associates Page - 45
PROJECT: ‐ CEDAR LAXURIA.


SECTION VI 

WATER SUPPLY PUMPS & EQUIPMENTS AND WATER TREATMENT UNITS ETC. 

1.0        Pumps and Water Treatment Equipment 

1.1    Work under this sub‐head consists of furnishing all labour, materials, equipment and accessories 
necessary and required to completely install pumping system for various water supply services 
and water treatment as per drawings, specified hereinafter and given in the Bill of Quantities. 

1.2     Without restricting to the generality of the foregoing, the work of pumps and water treatment 
equipment shall include the followings: 

a) Filter feed pumps. 
b) Domestic water transfer pump (Hydroprnumatic System) 
c) Sump pumps for drainage. 
d) Water treatment unit consisting of MGF  and chlorination etc. 
e) Motor control panels, power and control cabling and allied electrical works. 
f) Pipes, valves, accessories, hangers, supports, delivery and suction feeders and connection to 
proposed pipe work. 
 

1.3  Source of Water Supply: 

  All the water supply requirement o shall be meeting from tube well / borewell water supply. 

1.4        QUALITY OF RAW WATER 

Parameters  Values 

   

Colour Hazen Units  < 5 

Odour  objectionable 

Taste  unagreeable 

Turbidity, NTU  3.90 

Ph  7‐7.5 

Total Dissolved solids mg/l  700 

Chloride  (as Cl)  mg/l  36 

 
Behera and Associates Page - 46
PROJECT: ‐ CEDAR LAXURIA.


  Total hardness  (as CaCo3)  mg/l  250 

  Iron  (as Fe)  mg/l  Nil 

  Coliform Organism / 100 ml.  Nil 

  E coli/100ml  absent 

2.0        PUMP SET 

2.1        Water Supply Pumps 

  (These  specifications  are  applicable  for  all  clear  water  pumps  and  as  specified  in  Bill  of 
Quantities) 

2.1.1   Water  supply  pumps  shall  be  suitable  for  clean  water.    Pumps  shall  be  single  or  multistage, 
monoblock  horizontal,  vertical,  centrifugal  pumps  with  cast  iron/stainless  steel  body  and 
stainless  steel/bronze  impeller,  stainless  steel  shaft  and  coupled  to  a  TEFC  electric  motor  by 
means  of  a  flexible  coupling  or  as  specified  in  bill  of  quantities.  Each  pump  should  operate  a 
curve 10m below specified head. 

2.1.2     Pump and motor shall be mounted on a common M.S. structural or C.I. base plate or as required 
as per site conditions. 

2.1.3 Each pump shall be provided with a totally enclosed fan cooled induction motor of required H.P. 
and RPM specified in the bill of quantities and as per requirement. 
2.1.4    Each pumping set shall be provided with a 150mm dia or of suitable size gunmetal “Bourden” 
type pressure gauge with gunmetal isolation cock and connecting piping. 

2.1.5   Provide vibration‐eliminating pads appropriate for each pump.  

2.1.6    Provide  rate  of  flow  measuring  meter  with  bypass  arrangement  with  every  set  of  pumps  as 
shown on the drawings and given in the bill of quantities (to be paid separately). 

2.1.7   All water supply pumps shall be provided with mechanical seals, of required specifications. 

3.0       SUMP PUMP 

3.1   Sump pumps shall be submersible type for lifting domestic sewage or muddy water/drainage as 
specified  in  Bill  of  Quantities.  Pump  with  impeller  of  approved  material  shall  be  mounted  on 
waterproof motor. The impeller shall be suitable for handling solids upto 46‐100mm dia. or as 
specified in Bill of Quantities. 

 
Behera and Associates Page - 47
PROJECT: ‐ CEDAR LAXURIA.


3.2       The pump shall automatically operate with high water level and stop at low water level in the 
sump by means of “Electronic Level Controller”, of the approved make. 

3.3    The  sump  pumps  shall  be  complete  in  all  respect  and  shall  be  installed  as  per  manufacturer’s 
requirement  as  shown  in  the  drawing.  All  accessories  shall  be  In‐Built  as  per  manufacturer’s 
specification. 

5.0     CABLES          

5.1      Contractor  shall  provide  all  power  control  cables  from  the  motor  control  center  to  various 
motors, level controllers and other control devices. 

5.2        Cables shall conform to I.S: 1554 and carry ISI mark. 

5.3        Wiring cables shall conform to I.S 694. 

5.4       All  power  and  wiring  cables  shall  be  aluminum  conductor  PVC  insulated  armored  and  PVC 
sheathed of 1100 volts grade. 

5.5    All control cables shall be copper conductor PVC insulated armored and PVC sheathed 1100 Volt 
grade. 

5.6     All  cables  shall  have  stranded  conductors.  The  cables  shall  be  in  drums  as  far  as  possible  and 
bear manufacturer’s name. 

5.7        All cable joints shall be made in approved manner as per standard practice. 

6.0        CABLE TRAYS 

6.1      Contractor  shall  provide  M.S  slotted  cable  trays  at locations  as shown  on  the  drawings  and  of 
sizes as given in the bill of quantities. 

6.2       Cable trays shall be supported from the bottom of the slab at intervals of 60cms at both ends by 
anchor fasteners.  Cost of MS angle, rods and anchor fasteners etc.  shall be included in the rate 
of the tray and no separate payment shall be made on this account. 

6.3       Cost of clips, bolts, nuts, support rods and any other materials required to fix the trays in proper 
manner shall be included in the rate for trays. 

8.0      CONTROL PANELS / STARTERS 

8.1        Switch board cubicles of approved type shall be fabricated from 16‐gauge M.S. sheet with dust 
and vermin proof construction.  It shall be painted with powder‐coated finish of approved make 
and  shade.    It  shall  be  fitted  with  suitable  etched  plastic  identification  plates  for  each  motor.  
The cubicle shall comprise of the followings:‐ (Switch gear as given in the bill of quantities). 

 
Behera and Associates Page - 48
PROJECT: ‐ CEDAR LAXURIA.


a)
Incoming main isolation MCCB of required capacity. 
b)
Fully Aluminum taped Bus Bar of required capacity.  
c)
Isolation MCCB one for each motor. 
d)
Fully  automatic  as  specified  D.O.L/Star  Delta  starters  suitable  for  motor  H.P.  with  push 
buttons  one for each motor and on/off indicating neon lamps. (DOL upto 7.5 HP and Star 
Delta from more than 7.5 H.P)   
e) Single phase preventor of appropriate rating for each motor. 
f) Panel type ampere meters one for each motor with selector switch. 
g) Panel type voltmeter on incoming main with rotary selector switch to read voltage between 
phase to neutral and phase‐to‐phase. 
h) Neon phase indicating lamps for incoming main and on/off indicating lamps for each motor. 
i) Rotary switch for manual or auto operation for each pump (manual/auto off). 
j) Fully taped separate aluminum bus bars of required capacity and with required outlets. 
k) Space for liquid level controllers as specified + 1 extra space.      
l) The  panel  shall  be  pre‐wired  with  colour‐coded  wiring.  All  interconnecting  wiring  from 
incoming main to switch gear, meters and accessories within the switchboard panel. 
m) Provision of main incoming cables from the top of the panel. 
8.2       All  switch  gears  and  accessories  shall be  of  approved  make  such  as  “Siemens,  English  Electric, 
Larsen & Toubro” or equivalent, or as specified. 

8.3    Switchboard cubicles shall be floor or wall mounted type as recommended by manufacturers. All 
floor‐mounted  switchboard  shall  rest  on  minimum  225mm  high  platform.  The  contractor  shall 
provide the shop drawings for base and panels. 

9.0        VIBRATION ELIMINATORS 

  Provide  on  all  suction  and  delivery  lines  double  flanged  reinforced  neoprene  flexible  pipe 
connectors. Connectors should be suitable for a working pressure of each pump.  Length of the 
connector shall be as per manufacturer’s details.   

11.0      WATER FILTER 

11.1      Water filter shall be of dual filter media pressure filter downward or upward flow type suitable 
for a rate of filtration given in bill of quantities. 

11.2  Filter shall be vertical type of required diameter. The shell shall be fabricated from M.S. plate 
suitable to withstand a working pressure given in bill of quantities. The minimum thickness of 
shell will be 8mm and dished ends shall be 10mm. The filter shall have at least one pressure 
tight manhole cover or as specified in Bill of Quantities.  
  Filter  shall  be  provided  with  screwed  or  flanged  connections  for  inlet,  outlet,  individual  drain 
connections and all other connections necessary and required. Filter shall be painted inside with 
two or more coats of non‐toxic corrosion resistant paint, one coat of red oxide primer outside 
with two or more coats of synthetic enamel paint of approved shade. 

 
Behera and Associates Page - 49
PROJECT: ‐ CEDAR LAXURIA.

11.3      Under Drain System 

  Filter shall be provided with an efficient under  drain system  comprising    of   collecting  pipes, 


gunmetal/polypropylene  nozzles of  manufacturer’s  design. The  entire  under  drain system be 
provided on  M.S.  plate or cement concrete supports. 

11.4      Face Piping 

Complete uPVC frontal face piping (10 kg/cm2 rating conforming to IS:4985) and valves battery 
with CI Butterfly valves, pressure gauges and sampling points at inlet and outlet. etc. covering all 
functions of service, backwash, rinse, air release etc. 

11.5      Accessories 

  Each filter shall be provided with following accessories:‐ 

a) Air release valve with connecting piping. 
b) 100mm dia dial bourden type gunmetal pressure gauges with gunmetal isolation cock and 
connecting piping on inlet and outlet. 
c) Sampling cocks on raw water inlet and filtered water outlet. 
d) Individual drain connection with gunmetal fullway valve. 
e) Connection with valve for air scouring. 
13.0      PIPING 

13.1      Pipes for suction and delivery shall be galvanised/M.S tube (heavy duty) confirming to I.S:1239 
upto  150mm  dia  and  as  per  I.S:3589  for  dia  200mm  and  above  or  as  specified  in  bill  of 
quantities. The M.S  flanges shall confirm to I.S:6392‐1971. 

13.2     Gate valve and check valve above 65mm dia shall be C.I. double flanged conforming to I.S:780  
manufactured  by the reputed manufacturers or C.I. double flanged butterfly valves as specified 
in bill of quantities or elsewhere or as per approval of Engineer‐in‐charge. 

13.3  Full way and check valves 65mm dia and below shall be gunmetal  tested  to  20Kg/cm2 pressure 
certified and conforming to I.S:778. 

13.4      Suction strainer or foot valves shall be C.I., confirming to I.S:4038 ‐ 1979, as specified in bill of 
quantities. 

13.5      Joints 

  All pipes and fittings shall be provided with flanged joints, with flanges either screwed or welded 
complete and jointed with 1.5mm thick gasket complete with nuts, bolts and washers etc. 

 
Behera and Associates Page - 50
PROJECT: ‐ CEDAR LAXURIA.


13.6      Testing 

  All G.I/M.S pipes (except fire pipe) shall be tested hydrostically for a period of 30 minutes to a 
pressure  of  7  Kg/cm2  without  drop  in  pressure  and  all  G.I/M.S  pipes  for  fire  shall  be  tested 
hydrostically for a period of 30 minutes to a pressure of 12.5 Kg/cm2 without drop in pressure. 

14.0      MEASUREMENTS 

14.1      Raw water, garden pump and fire pumps shall be measured by numbers and hydro pumps and 
sump  pumps  shall  be  measured  by  sets  and  shall  include  all  items  as  given  in  the  bill  of 
quantities. 

14.2      Motor  control panel and level controllers shall be measured by numbers. 

14.3      Pipes for suction and delivery header and mains shall be measured per linear metre along the 
centre line of the pipe and shall be inclusive of all fittings. 

14.4      Cable trays and cables shall be measured per linear meter. 

14.5      Structural clamps including hangers shall be measured by weight calculated from sections used.  
No separate payment shall be admissible for bolts, anchor bolts, rawl plugs etc. 

14.6      No separate payment shall be made for making connections of the existing service lines to the 
pumps.  Vibration eliminator pads  are included in the scope of this work. 

15.0      GUARANTEE 

15.1  The contractor shall submit a warranty for all equipment, materials and accessories supplied by 
him against manufacturing defects, malfunctioning or under capacity functioning. 

15.2      The form of warranty shall be as approved by the Engineer‐in‐charge. 

15.3    The warranty shall be valid for a period of one year from the date of commissioning and handing 
over. 

15.4  The warranty shall expressly include replacement of all defective or under capacity equipment, 
Engineer‐in‐charge  may  allow  repair  of  certain  equipment  if  the  same  is  found  to  meet  the 
requirement for efficient functioning of the system. 

15.5  The warranty shall include replacement of any equipment found to have capacity lesser than the 
rated capacity as accepted in the contract. The replacement equipment shall be approved by the 
Engineer‐in‐charge. 

 
Behera and Associates Page - 51
PROJECT: ‐ CEDAR LAXURIA.

TECHNICAL INFORMATIONS FOR WATER SUPPLY  PUMPS & EQUIPMENTS AND WATER TREATMENT 
UNIT ETC.  

(TO BE FILLED BY THE TENDERER) 

(I).  FILTER FEED PUMPS 

  1.  Discharge         : 

  2.  Head         : 

  3.  Type           : 
  4.  H.P of Motor       : 

  5.  Other Details         : 

        : 

(II).   WATER TRASFER PUMP  

A.   PUMP: 

1. Discharge.        : 

2. Total head at full  

          discharge.        : 

3. Make and Model No.        : 

4. Type.       : 

5. Frame size.        : 

6. BHP absorbed  

       (a) at rated head and  

                    discharge. 

7. Casing material.      : 

8. Impeller material.      : 

9. Shaft material.      :   

 
Behera and Associates Page - 52
PROJECT: ‐ CEDAR LAXURIA.


10. No. of stages.      : 

11. Type of drive.      : 

12. Type of seal.      : 

B. MOTOR: 

1. Make.        : 

2. Frame size.        : 

3. Type.       : 

4. Protection type.      : 

5. Insulation class.      : 

6. Electrical particulars 

         (Voltage/No. of phase/ 

         frequency).        : 

7. I.S. conforming to       :       

8. H.P.          : 

9. Speed.        : 

(III).  FILTER BOTH FOR ACF & MGF 
 
  1.  Make        :   
   
  2. Model        : 
 
  3. Dia Meter        : 
 
  4. Height        : 
 
  5. Type of Flow      :   
 
  6. Material of Construction    : 
   
  7. Shell/Dished end thickness  :   
 
  8. Max. working pressure    : 

 
Behera and Associates Page - 53
PROJECT: ‐ CEDAR LAXURIA.


 
  9. Hydro test pressure      : 
 
  10. Max. Flow rate      : 
 
  11. Min. flow rate      : 
 
  12. Filtration Rate      : 
 
  13. Inlet/outlet pipe Size    :   
 
  14. Type of Media      : 
 
  15. Media Quantity      : 
 
  16. Type of Valve      : 
 
  17. Back Wash Frequency    : 
 
  18. Pressure drop across bed    : 
 
(IV).  SUMP PUMPS (FOR DRAINAGE) 

  1.  Discharge         : 

  2.  Head         : 

  3.  Type         : 
  4.  Solid Handling Capacity     : 

  5.  H.P of Motor     : 

  6.  Other Details       : 

(V).   ELECTRIC CONTROL PANEL 

1.  Make          : 

2.  Make of switch fuse unit/breaker used.  : 

3.  Thickness of sheet metal used.    : 

4.  Make of contractors.     : 

 
Behera and Associates Page - 54
PROJECT: ‐ CEDAR LAXURIA.


5.  Make of cables and size of  

           cables for different motors.         : 

6.  Any other informations.      : 

Note:‐ 

The  tenderer  must  give  as  maximum  as  possible  information.  They  may  add  any  other  relevant 
information’s also, if required. 

END OF SECTION – I 

 
Behera and Associates Page - 55
PROJECT: ‐ CEDAR LAXURIA.


LIST OF APPROVED MAKES 

 
5.1  All materials and equipment used in execution of work shall be of approved makes listed below. 
Any make offered by Tendered other than the approved makes will be subject to the approval of 
Owner/ Architect/ Consultant/ Interior Designer. If other makes are offered, the same shall be 
clearly indicated in tender. 
 
5.2  Contractor  shall  list  out  the  makes  of  equipment  and  materials  offered  during  tender  stage 
itself.    Decision  about  the  final  selection  of  the  make  from  the  makes  included  in  Agreement 
shall rest with the Owner/ Architect/ Consultant as applicable. 
 
Sl No  Item / Material  Make 

1  GI Pipes as per IS:1239  Surya Prakash/ Jindal 

2  GI Fittings (Malleable Cast Iron) as per IS:1879   Zoloto / C Brand /Crescent /`R’


Brand / VS Brand / B&M 

3  Butterfly Valve / Check Valve  Audco / CIM / LP / Econosta 

4  Ball Valves  Zolato / CIM /Audco / LP 

5  Cables  KEI / Sky tone / HAVELL’S 

6  Water Meter  Kranti / Kent 

7  PVC Copper Wire  Sky tone / Finolex /KEI 

8  uPVC Pipes & Fittings  Supreme / Finolex 

9  CPVC Pipes & Fittings  Astral / Ashirvad/ Ajay 

10  RCC Pipes  Jai Spun Pipe/ Indian Hume Pipes 

11  Stainless Steel Grating  Camry / Chilly 

12  Air Release Valve  Sant / Kartar 

13  Stoneware Pipe  Anand 

14  SW Gully Trap  Anand 

16  Pumps  WILO / Ground foss / ITT 

17  Filter & Softener   MSEP  

 
Behera and Associates Page - 56
PROJECT: ‐ CEDAR LAXURIA.


18  Chemical Dosing Pumps/Tanks  Toshcon/ ASIA LMI/Edose  

19  Level Controller / Lvel Censor   AIP /Danfoss / Flow line 

20  Vibration Eliminator  Resistoflox, Noida/ Dwren ‐ 


Calcutta 

21  ELECTRICAL WORK   

  a)  Starter  Legrand /  Schneider 

  b)  SFUs  Legrand /  Schneider 

  c)  Cables  Finolex/ KEI 

  d)  Liquid Level Controller  Femack/Minilec 

  e)  MCCB  Legrand / Schneider

  f)  MCB  Legrand / Schneider

  g)  Panel  Tricolite Industries/ Installation 


control panel /Rajeev Associates/ 
Engineers & Engineers  
 

 
Behera and Associates Page - 57
SHAFT -01
SHAFT -02

SHAFT -03

SHAFT -08

SHAFT -11

KEY PLAN

ARCHITECT :
Jaipur - Bangalore - Hyderabad
maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664
email - studio@maarchitects.in,
web - www.maarchitects.in
STRUCTURAL CONSULTANTS
SG STRUCTURES
Sg A-36,1ST FLOOR, SUNDER SINGH BANDARI NAGAR,
SWEJ FARM, NEW SANGANER ROAD, JAIPUR-302019
E-mail: sg.structures@gmail.com
Tel: 09772202219,0141-2297076

PROJECT :

scale : A1@ NTS drawn by : SONU.SINGH

date : 04-12-2015 checked by: BHIM .SINGH


SHAFT-01 SHAFT-02 SHAFT-03 SHAFT-04 SHAFT-05 SHAFT-06 SHAFT-07 SHAFT-08 SHAFT-09 SHAFT-10 SHAFT-11 SHAFT-12 SHAFT-13 SHAFT-14 SHAFT-15
project no : approved by: SOMNATH
drawing no : PL-BA--CEDAR-101 DIRECTION

REVISION : R-0 R-1 R-2 R-3


D-C56 D-C57

TOILET
1570 x 2555
D-C53
UTILITY
D-C50 BEDROOM
3425 x 1755
BALCONY 3350 x 4005 BALCONY
BEDROOM 1600 x 1525 1820 x 2400
4185 x 3090 11 10
DINING 12 9
3505 x 3315 13 8
14 7
KITCHEN
15 6 D-C48
3430x 2390 TERRACE
16 5
2500 x 4615 TOILET
17 4
18 3 2585 x 1605
D-C42 D-C43 D-C44 D-C45 19 2
20 1
DN
UP

BEDROOM TOILET
3195 x 3975 2505 x 1515
BALCONY
2125 x 3200 LIVING D-C40 D-C41
7060 x 3205

KITCHEN BEDROOM
4155 x 3315
D-C38 D-C39 2685 x 3230

LIVING
BALCONY 7060 x 3200
2125 x 3200 DRAWING / D-C35 D-C36
DINING
D-C34
4440 x 5830

D-C30 D-C32 LIFT TERRACE


D-C31 D-C33
2500 X 1950 4330 x 2365
(13 PESS.
MAKE OTIS)
KITCHEN
D-C28 D-C29
3430 x 2390
DINING
3505 x 3315
LIFT
BEDROOM 1900 X 2000 TERRACE
4230 x 3085 (13 PESS. 4330 x 2500
MAKE OTIS)
D-C26 D-C27
D-C23 DRAWING /
TOILET
BEDROOM 2390 x 1500 D-C22 DINING D-C24 D-C25
4085 x 3190 4440 x 5830

M.V.
TOILET
2390 x 1540

F.H.C. BEDROOM
4155 x 3180
D-C20 D-C21

D-C18 D-C19
STUDY
KITCHEN TOILET
TERRACE 2695 x 1940
2730 x 3255 2505 x 1515
2745 x 2630

BEDROOM
D-C16 3195 x 3950
D-C15 DRAWING/DINING
4430 x 6080
306.978 BEDROOM TOILET
DN 3350 x 3825 2590 x 1605
UP
20 D-C14
19
1 18
2 17 TERRACE
3 16 2500 x 3940 BALCONY BALCONY
BEDROOM KITCHEN 4 15 1600 x 1655 1525 x 2300
4185 x 3225 2590 x 3230 5 14
6 13
D-C7 D-C8 D-C9 D-C10
7 12
TOILET BEDROOM 8 11 TOILET
2470 x 1515 3155 x 4165 1570 x 2485
9
10
1013.397 1013.397
UTILITY 170.132
2510 x 1375

TOILET BEDROOM
2470 x 1615 3360 x 4215
D-C4

BALCONY BALCONY
1525x 2600 1660 x 1525

D-C1 TOILET
1470 x 2585

ARCHITECT :
Jaipur - Bangalore - Hyderabad
maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664
email - studio@maarchitects.in,
web - www.maarchitects.in
STRUCTURAL CONSULTANTS
SG STRUCTURES
Sg A-36,1ST FLOOR, SUNDER SINGH BANDARI NAGAR,
SWEJ FARM, NEW SANGANER ROAD, JAIPUR-302019
E-mail: sg.structures@gmail.com
Tel: 09772202219,0141-2297076

BALCONY

PROJECT :

SHAFT-01 SHAFT-02 SHAFT-03 SHAFT-04 SHAFT-05 SHAFT-06 SHAFT-07 SHAFT-08 SHAFT-09 SHAFT-10 SHAFT-11 SHAFT-12 SHAFT-13 SHAFT-14 SHAFT-15 SHAFT-16 SHAFT-17 SHAFT-18 SHAFT-19 SHAFT-20

scale : A1@ NTS drawn by : BHIM .SINGH

date : 03-12-2015 checked by: BHIM .SINGH

project no : approved by: SOMNATH


drawing no : PL-BA--CEDAR-102 DIRECTION

REVISION : R-0 R-1 R-2 R-3


SHAFT -12

SHAFT -03
3114.645

SHAFT -11

SHAFT -10

ARCHITECT :
Jaipur - Bangalore - Hyderabad
maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664
email - studio@maarchitects.in,
web - www.maarchitects.in
STRUCTURAL CONSULTANTS
SG STRUCTURES
Sg A-36,1ST FLOOR, SUNDER SINGH BANDARI NAGAR,
SWEJ FARM, NEW SANGANER ROAD, JAIPUR-302019
E-mail: sg.structures@gmail.com
Tel: 09772202219,0141-2297076

PROJECT :

scale : A1@ NTS drawn by : BHIM .SINGH

SHAFT-01 SHAFT-02 SHAFT-03 SHAFT-04 SHAFT-05 SHAFT-06 SHAFT-07 SHAFT-08 SHAFT-09 SHAFT-10 SHAFT-11 SHAFT-12 SHAFT-13 SHAFT-14 date : 03-12-15 checked by: BHIM .SINGH

project no : approved by: SOMNATH


drawing no : PL-BA--CEDAR-103 DIRECTION

REVISION : R-0 R-1 R-2 R-3


TOILET
1470 x 2585
D-C1

BALCONY BALCONY
1525x 2600 1660 x 1525

D-C4

TOILET BEDROOM
2470 x 1615 3360 x 4215

UTILITY
2510 x 1375 334.575
56.17334.575
10
TOILET BEDROOM 9 TOILET
2470 x 1515 3155 x 4165 8 11 1570 x 2485
D-C7 D-C8 7 12 D-C9 D-C10
6 13
KITCHEN 5 14
BEDROOM
4 15 BALCONY BALCONY
4185 x 3225 2590 x 3230
3 16 BALCONY 1600 x 1655 1525 x 2300
2 17 2500 x 3940
1 18
19
20 D-C14

DRAWING/DINING
UP
DN
101.349 BEDROOM
3350 x 3825
TOILET
2590 x 1605

D-C15 D-C16 4430 x 6080 BEDROOM


3195 x 3950

BALCONY
2745 x 2630 KITCHEN TOILET
STUDY
2730 x 3255 2505 x 1515
2695 x 1940 D-C18 D-C19

D-C20 D-C21
BEDROOM
4155 x 3180
F.H.C.

TOILET
2390 x 1540
M.V.
BEDROOM
DRAWING /
4085 x 3190 TOILET D-C22 D-C24 D-C25
DINING
2390 x 1500 D-C23 4440 x 5830
D-C26 D-C27
LIFT
BEDROOM 1900 X 2000 BALCONY
(13 PESS. 4330 x 2500
4230 x 3085
MAKE OTIS)
DINING
3505 x 3315
KITCHEN D-C28 D-C29
3430 x 2390
LIFT
2500 X 1950
(13 PESS. BALCONY
D-C30 D-C31 D-C32 D-C33 MAKE OTIS) 4330 x 2365

D-C34 DRAWING /
DINING
D-C35 D-C36
4440 x 5830
BALCONY
2125 x 3200 LIVING
7060 x 3200

D-C38 D-C39
KITCHEN BEDROOM
2685 x 3230 4155 x 3315

LIVING
BALCONY 7060 x 3205 D-C40 D-C41
2125 x 3200 BEDROOM TOILET
3195 x 3975 2505 x 1515

UP
DN
20 1
D-C42 D-C43 D-C44 D-C45 19 2
18 3 TOILET
17 4 2585 x 1605
16 5
BALCONY
KITCHEN 15 6 2500 x 4615 D-C48
3430x 2390 14 7
DINING 13 8
3505 x 3315 12 9
BEDROOM 11 10
BALCONY BALCONY
4185 x 3090 1600 x 1525 1820 x 2400
BEDROOM
UTILITY 3350 x 4005
D-C50
3425 x 1755
D-C53
TOILET
1570 x 2555

D-C56 D-C57

ARCHITECT :
Jaipur - Bangalore - Hyderabad
maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664
email - studio@maarchitects.in,
web - www.maarchitects.in
STRUCTURAL CONSULTANTS
SG STRUCTURES
Sg A-36,1ST FLOOR, SUNDER SINGH BANDARI NAGAR,
SWEJ FARM, NEW SANGANER ROAD, JAIPUR-302019
E-mail: sg.structures@gmail.com
Tel: 09772202219,0141-2297076

BALCONY

PROJECT :

SHAFT-01 SHAFT-02 SHAFT-03 SHAFT-04 SHAFT-05 SHAFT-06 SHAFT-07 SHAFT-08 SHAFT-09 SHAFT-10 SHAFT-11 SHAFT-12 SHAFT-13 SHAFT-14 SHAFT-15 SHAFT-16 SHAFT-17 SHAFT-18 SHAFT-19 SHAFT-20

scale : A1@NTS drawn by : BHIM .SINGH

date : 03-12-2015 checked by: BHIM .SINGH

project no : approved by: SOMNATH


drawing no : PL-BA--CEDAR-104 DIRECTION

REVISION : R-0 R-1 R-2 R-3


D 50 D 50 D 50 D
300
TOILET
1470 x 2585

BALCONY
1.52M x 2.6M
BALCONY
1660 x 1525

TOILET
BEDROOM
2470 x 1615
3360 x 4215
RISER = 145
UTILITY TREAD = 300
2510 x 1525 WIDTH = 1370
3155 x 4165
BEDROOM

1370 1370

TOILET TOILET
2470 x 1515 1570 x 2485
STANDING BALCONY

BEDROOM KITCHEN
2590 x 3230 BALCONY BALCONY
4185 x 3225
3135 x 600

1600 x 1655 1525 x 2300

DN BEDROOM TOILET
STAIRS UPTO 3350 x 3825 2590 x 1605
DRAWING/DINING 14TH FLOOR UTILITY
4430 x 6080 2505 x 1605

FFL +41750
BEDROOM
3195 x 3950
BALCONY
1605 x 2630 KITCHEN TOILET
2730 x 3255 2505 x 1515
FFL +41740

STANDING BALCONY
BEDROOM

150
4155 x 3180

3135 x 600
F.H.C.

FFL +41750
M.V.

DRAWING /
DINING
4440 x 5830
FFL +41700
LIFT TERRACE
1900 X 2000 1875 x 2500
(13 PESS.
MAKE OTIS)
PASSAGE 2970 MM WIDE

D BLOCK LIFT
2500 X 1950
(13 PESS.
MAKE OTIS)

FFL +41700

D-C38

D BLOCK
FFL +41700

FFL +41700

PROJECT:

CEDAR LUXURIA
PATRAKAR COLONY, JAIPUR
FFL +41700
L.V. BALCONY
T.O.C. LVL
+47850 F.H.C. 1675 x 1900
BEDROOM
3165 x 4610
TOILET
1515 x 2395
M.V.
BEDROOM
4275 x 3525

C BLOCK
TOILET
2515 x 1520 CLIENT :
B 230 x 450

PUJA/STORE DRESS
LIFT 1390 x 1515 2240 x 1410
1900 X 2000
(13 PESS. 2275

CEDAR
PASSAGE 2970 MM WIDE

MAKE OTIS)

DRAWING BALCONY
5460

AREA LIVING AREA 1935 x 3810

C BLOCK
4920 x 3710 4925 x 3710
JAIPUR
LIFT
2500 X 1950 FFL +41750
(13 PESS. MAKE OTIS)
230 460

FFL +41740
600

KITCHEN
DRESS
230

2440 x 3870 PWD. RM.


2230 x 1510
1400 x 1615
600
230

230 600 230 600 230 600 240 SERVANT TOILET


ROOM 2550 x 1625
DN 2225 x 2210
BEDROOM
FFL +41700
4310 x 3580
ARCHITECT :

TOILET UTILITY
BALCONY
1525 x 1900 pvt. ltd.
1335 x 1630 3205 x 1755
Jaipur - Bangalore - Hyderabad
maithel & associates architects pvt. ltd.
RISER = 145
TREAD = 300
WIDTH = 1370
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664
email - studio@maarchitects.in,
web - www.maarchitects.in

MEP CONSULTANTS
T.O.C. -370
FROM T.O.C.
FFL +41700

B-C17

TOC +1700
FROM T.O.C.

T.O.C. LVL
B BLOCK
+47850

FFL +41700

FFL +41740
PASSAGE 2970 MM WIDE

FFL +41700

LIFT
1900 X 2000
(13 PESS.
MAKE OTIS)

F.H.C.

TOC +2830
M.V. FROM T.O.C.

B BLOCK LIFT
2500 X 1950
L.V. (13 PESS.
MAKE OTIS)

FFL +41750

PASSAGE
1450
FFL +41750
BALCONY DRAWING/DINING
1605 x 2630 4060 x 7455
DRAWING/DINING LIVING
4430 x 5985 2765 x 3565
STAIRS UPTO
14TH FLOOR
No. ISSUED FOR : DATE : CKD:
STANDING BALCONY
STANDING BALCONY

DN
3135 x 600

KITCHEN
3135 x 600

2685 x 3675

BEDROOM BEDROOM DRAWING TITLE :


4185 x 3130 KITCHEN
2590 x 3230
4310 x 3205
PLUMBING DRAWING
TOILET
2480 x 1515 BEDROOM BEDROOM
3360 x 4270
TOILET
2470 x 1515
BLOCK - A,B,C & D
3155 x 4225

UTILITY
2020 x 2545
14th FLOOR PLAN
UTILITY
2510 x 1550
TOILET
LOWER TERRACE WATER SUPPLY & FLOOR PLAN
TOILET
2620 x 1710
2470 x 1710

BEDROOM NORTH:
3365 x 4310
DRAWN BY :
BALCONY
BALCONY
1685 x 1640
BHIM
1525 x 2600 BALCONY
1675 x 1525 BEDROOM BALCONY
3380 x 4335 1605 x 2600
TOILET
1640 x 2590
CHECKED BY :
SOMNATH

DATE : 03-12-15 SCALE :


1:175

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA - 501(A)
D 50 D 50 D 50 D
300
TERRACE

DN

TERRACE

LIFT
1900 X 2000
(13 PESS.
MAKE OTIS)

D BLOCK
5095

LIFT
2500 X 1950
(13 PESS.
MAKE OTIS)
TERRACE BELOW

TERRACE BELOW
D BLOCK

STAIRS UPTO
13th FLOOR LVL
RISER = 145
TREAD = 300
WIDTH = 1370

PROJECT:

CEDAR LUXURIA
TERRACE BELOW TERRACE PATRAKAR COLONY, JAIPUR

C BLOCK CLIENT :
18
CA

LIFT
1900 X 2000
(13 PESS.
MAKE OTIS) ST
AI
RC CA
19
CEDAR
TE
17

AS
RR
CA

E
AC

UP
5460

TO

C BLOCK JAIPUR
LIFT
2500 X 1950
(13 PESS. MAKE OTIS)

TERRACE CA 20 CA 21

DN

ARCHITECT :
TERRACE BELOW
SWA 1
pvt. ltd.
LIFT PIT TERRACE
BELOW Jaipur - Bangalore - Hyderabad
2450

1900
maithel & associates architects pvt. ltd.
RISER = 145
TREAD = 300
WIDTH = 1370
A BLOCK SWA 2 Plot No. -1, Lal Kothi Scheme, Jaipur-302001
LIFT PIT Tel : 91 141 4299999
1950

BELOW
Fax : 91 141 2741664
2500
SWA 3
email - studio@maarchitects.in,
web - www.maarchitects.in

RISER = 145
TREAD = 300
WIDTH = 1370
MEP CONSULTANTS

TERRACE BELOW
CA

DN
39

CA
41
6630

TERRACE

TERRACE BELOW

LIFT PIT
1900 x 2000
TERRACE BELOW

B BLOCK
LIFT PIT
2500 x 1950

TERRACE
No. ISSUED FOR : DATE : CKD:

DRAWING TITLE :
PLUMBING DRAWING
BLOCK - A,B,C & D
TERRACE FLOOR PLAN
WATER SUPPLY LAYOUT
NORTH:
DRAWN BY :
TERRACE BHIM

CHECKED BY :
SOMNATH

DATE : 03-12-15 SCALE :


NTS

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA - 601 (A)
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PROJECT:

CEDAR LUXURIA
PATRAKAR COLONY, JAIPUR

CLIENT :

CEDAR
JAIPUR

ARCHITECT :

Jaipur - Bangalore - Hyderabad


maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664
email - studio@maarchitects.in,
web - www.maarchitects.in

STRUCTURAL CONSULTANTS

MEP CONSULTANTS

No. ISSUED FOR : DATE : CKD:

DRAWING TITLE :
PLUMBING DRAWING
BLOCK - A
TYP. FLOOR PLAN
NORTH:
DRAWN BY :
SONU

CHECKED BY :
SOMNATH

DATE : 03-01-15 SCALE :


NTS

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA -TA- 301

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

B-C1 B-C2

TOILET
2400 x 1560

230

BEDROOM

B-C4
B-C3
3995 x 3190 TOILET
2400 x 1480

B-C5 B-C6
UTILITY
3245 x 1755
BEDROOM
4185 x 3090 TOILET
1640 x 2585
B-C9

B-C8
B-C7
STANDING BALCONY
3135 x 600
KITCHEN
3430 x 2365
DINING BALCONY
3505 x 3315
BALCONY 1525 x 2665
1685 x 1640

B-C13 BEDROOM

B-C14
B-C10 B-C11 B-C12

B-C15
3360 x 4375
BALCONY
2125 x 3200 B-C16
TOILET
DN UP 2615 x 1710

UTILITY
LIVING 2020 x 2440
7060 x 3200

B-C17 B-C18

B-C19
BEDROOM TOILET
3325 x 4320 2470 x 1510
B-C20 B-C21
BALCONY
2125 x 3200
KITCHEN
BEDROOM
2685 x 4240

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


LIVING 4310 x 3250
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

STANDING BALCONY
7060 x 3205

3135 x 600
CLIENT :
B-C22 B-C23 B-C24 B-C25
CEDAR LUXURIA
450

KITCHEN
3430 x 2385 B-C26 B-C27 PATRAKAR COLONY, JAIPUR
PASSAGE
STANDING BALCONY

1870 PROJECT:
3135 x 600

BEDROOM DINING DRAWING/DINING


4060 x 7460 TERRACE
4185 x 3095 3505 x 3315

PASSAGE 2970 MM WIDE


B-C28
B-C30
4710 x 3985
CEDAR
B-C31 1900
TOILET B-C29
JAIPUR
2390 x 1515 LIFT

2000
CUTOUT
BEDROOM 2575 x 3965 F.H.C. 1900 X 2000
4015 x 3195 (13 PESS.
MAKE OTIS) ARCHITECT :
TOILET M.V.
B-C32 B-C33
2390 x 1530
LIFT
2500 X 1950 Jaipur - Bangalore - Hyderabad

1950
L.V. (13 PESS. maithel & associates architects pvt. ltd.
MAKE OTIS) Plot No. -1, Lal Kothi Scheme, Jaipur-302001
B-C34 B-C35
2500 Tel : 91 141 4299999
TERRACE Fax : 91 141 2741664
B-C36
4710 x 4100
PASSAGE email - studio@maarchitects.in,
STUDY 1665 web - www.maarchitects.in
BALCONY 2695 x 1940 DRAWING/DINING
2125 x 2630 4060 x 7455

DRAWING/DINING
4430 x 5985
MEP CONSULTANTS
300 x 600 B-C37 B-C38 B-C39 B-C40

STANDING BALCONY
UP
STANDING BALCONY

DN

3135 x 600
3135 x 600

KITCHEN
B-C41

2590 2685 x 3700

BEDROOM BEDROOM
3230

4185 x 3130 KITCHEN 4310 x 3205


2590 x 3230
B-C44

B-C42 B-C45 B-C46


TOILET
TOILET
BEDROOM BEDROOM 2470 x 1515
2480 x 1515
3155 x 4225 3360 x 4270

UTILITY
2020 x 2545
UTILITY
B-C47

B-C48

2510 x 1550
TOILET
TOILET 2620 x 1710
2470 x 1710
B-C52

B-C50 B-C49
B-C51
1525 x 2600

DRAWING TITLE :
BALCONY

BALCONY
B-C53

BALCONY 2665 x 2600


BALCONY 1685 x 1640 PLUMBING DRAWING
BEDROOM 1675 x 1525
BEDROOM
BLOCK - B
B-C54

3365 x 4310 3380 x 4335


TOILET B-C55
TYP FLOOR PLAN
1640 x 2590
NORTH:
DRAWN BY : SONU

CHECKED BY : SOMNATH

DATE : 30-12-2014 SCALE : 1 : 125

DRAWING NO. :
PROJECT NO. : GH-2030
PL - BA - 201
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

BALCONY
1525 x 2590
TOILET
2400 x 1705

TOILET BEDROOM
3365 x 4265 UTILITY
2760 x 1530
2730 x 1525

PROJECT:

BEDROOM
TOILET 3160 x 4090 KITCHEN CEDAR LUXURIA
2515 x 1660 2685 x 3345
PATRAKAR COLONY, JAIPUR

L.V. BALCONY
F.H.C. 1675 x 1900
STANDING BALCONY

BEDROOM CLIENT :
M.V.
3135 x 600

3165 x 4610
BEDROOM

1515 x 2395
4235 x 3230

TOILET
BEDROOM
CEDAR
4275 x 3525 JAIPUR
DRAWING / TOILET
DINING 2515 x 1520
4440 x 5960

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PUJA/STORE DRESS
BALCONY LIFT 1390 x 1515 2240 x 1410
2125 x 2500 1900 X 2000
(13 PESS. 2240 ARCHITECT :

PASSAGE 2970 MM WIDE


MAKE OTIS)

Jaipur - Bangalore - Hyderabad


DRAWING BALCONY maithel & associates architects pvt. ltd.
AREA LIVING AREA 1935 x 3810 Plot No. -1, Lal Kothi Scheme, Jaipur-302001
4920 x 3710 4925 x 3710 Tel : 91 141 4299999
Fax : 91 141 2741664
BALCONY email - studio@maarchitects.in,
LIFT
2125 x 2730
2500 X 1950 web - www.maarchitects.in
(13 PESS. MAKE OTIS)

DRAWING / MEP CONSULTANTS


DINING
4445 x 6095
DRESS
KITCHEN

1400 x 1615
2230 x 1510

PWD. RM.
2440 x 3870
STANDING BALCONY
3135 x 600

SERVANT
ROOM TOILET
BEDROOM 2215 x 2210
2550 x 1625
DN UP BEDROOM
4185 x 3140
20 1 4310 x 3580
19 2
BEDROOM KITCHEN
18 3
TOILET 2580 x 3555
17 4
2465 x 1515
3160 x 3990
16 5
TOILET
15 6 1335 x 1630 BALCONY
1525 x 1900
14 7 UTILITY
UTILITY 13 8 3205 x 1755
2500 x 1650 12 9
2760 x 1530
TOILET

11 10

BEDROOM
3365 x 4120

TOILET
No. ISSUED FOR : DATE : CKD:
BALCONY
1525 x 2590 2400 x 1670
DRAWING TITLE :
PLUMBING DRAWING
BLOCK - C
TYP. FLOOR PLAN
NORTH:
DRAWN BY :
SONU

CHECKED BY :
SOMNATH

DATE : 02-01-2015 SCALE :


NTS

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA - 201
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

TOILET
1470 x 2585
D-C1

BALCONY

D-C2
BALCONY
1525x 2600 1660 x 1525

D-C3
D-C4
TOILET BEDROOM
2470 x 1615 3360 x 4215

D-C5

D-C6
UTILITY

1525
2510 x 1375

1825
230
10 1370 1370

BEDROOM 9 TOILET
TOILET
2470 x 1515 3155 x 4165 8 11 1570 x 2485
D-C7 D-C8 7 12 D-C9 D-C10
6 13
KITCHEN 5 14
BEDROOM
4 15 BALCONY BALCONY
4185 x 3225 2590 x 3230
TERRACE
STANDING BALCONY

3 16 1600 x 1655 1525 x 2300


2500 x 3940
3135 x 600

2 17

D-C13
1 18

D-C12
19
20 D-C14
UP
DN BEDROOM TOILET
3350 x 3825 2590 x 1605
DRAWING/DINING
PROJECT:
D-C15 D-C16 4430 x 6080

CEDAR LUXURIA

2695 x 1940
TERRACE
PATRAKAR COLONY, JAIPUR

STUDY
2745 x 2630 BEDROOM
KITCHEN TOILET
3195 x 3950

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


2730 x 3255 2505 x 1515
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

D-C18 D-C19

D-C17

STANDING BALCONY
D-C20 D-C21 CLIENT :
BEDROOM

3135 x 600
4155 x 3180
F.H.C.
TOILET CEDAR
2390 x 1540
M.V. JAIPUR
BEDROOM
DRAWING /
4085 x 3190 TOILET D-C22 D-C24 D-C25
DINING
2390 x 1500 D-C23 4440 x 5830
D-C26 D-C27
LIFT
STANDING BALCONY

BEDROOM 1900 X 2000 TERRACE


ARCHITECT :
3135 x 600

(13 PESS. 4330 x 2500


4230 x 3085
MAKE OTIS)
DINING
3505 x 3315 Jaipur - Bangalore - Hyderabad
KITCHEN PASSAGE 2970 MM WIDE D-C28 D-C29
3430 x 2390 maithel & associates architects pvt. ltd.
LIFT Plot No. -1, Lal Kothi Scheme, Jaipur-302001
2500 X 1950 Tel : 91 141 4299999
(13 PESS. TERRACE Fax : 91 141 2741664
D-C30 D-C31 D-C32 D-C33 MAKE OTIS) 4330 x 2365
email - studio@maarchitects.in,
web - www.maarchitects.in
D-C34 DRAWING /
DINING
D-C35 D-C36
BALCONY 4440 x 5830
2125 x 3200 LIVING
7060 x 3200

STANDING BALCONY
D-C37

3135 x 600
D-C38 D-C39
KITCHEN BEDROOM
2685 x 3230 4155 x 3315

LIVING
BALCONY 7060 x 3205 D-C40 D-C41
2125 x 3200 BEDROOM TOILET
3195 x 3975 2505 x 1515

UP
D-C46

DN
20 1
D-C42 D-C43 D-C44 D-C45 19 2
18 3 TOILET
17 4 2585 x 1605
16 5
TERRACE
KITCHEN 2500 x 4615
STANDING BALCONY

15 6 D-C48
D-C47

3430x 2390 14 7
3135 x 600

DINING 13 8
3505 x 3315 12 9
BEDROOM 11 10 BALCONY
BALCONY
D-C49

4185 x 3090 1600 x 1525


1820 x 2400
BEDROOM
UTILITY
D-C52
D-C51

D-C50 3350 x 4005


3425 x 1755
D-C53
D-C55
D-C54

TOILET
1570 x 2555 No. ISSUED FOR : DATE : CKD:

DRAWING TITLE :
PLUMBING DRAWING
BLOCK - D
D-C56 TYP. FLOOR PLAN
NORTH:
DRAWN BY :
SONU

CHECKED BY :
SOMNATH

DATE : 28-12-2014 SCALE :


NTS

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA - 201
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

CA 2
CA 2

CA 1
CA 1

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PROJECT:

CEDAR LUXURIA
PATRAKAR COLONY, JAIPUR

CLIENT :

CEDAR
JAIPUR

ARCHITECT :

Jaipur - Bangalore - Hyderabad


maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999

ILET
TO
ON
Y
Fax : 91 141 2741664

30
LC

x 18
BA

40
25

24
17
3

CA
CA
email - studio@maarchitects.in,

75
x 16
web - www.maarchitects.in

9
CA
2
CA

x 3 NY
0
30 O
70
18 ALC
1
CA

B
x3 G
0
80 IN
81

12
42 LIV

CA
x 1 NY
0
00 O
79
32 ALC
B

OM

8
0

CA
31

13
DR
x3

CA
4

BE
CA 15
44

x3 G
30 WIN

0
81
35 RA
D

11

45 .
x 21 T RM
7

CA
CA

24 RVAN
SE
30

18
16

CA
NY

CA
O

0
81
LC

x3
BA

30
18

x 3 OM
0
15 O
34
44 EDR
B
10
19

CA
CA

17
CA
15
CA
LV / MV

CA 20 CA 21 CA 24

CA 23
CA 22
14
CA
BEDROOM
4310 x 3525
CA 25

BEDROOM
3130 x 4565

PUJA/STORE
1390 x 1515
SWA 1

CA 27 CA 28 CA 29
LIFT PIT
LTA 01 DRAWING
AREA LIVING AREA
PASSAGE 4885 x 3710 4990 x 3710
2170 MM WIDE

SWA 2

LIFT PIT
LTA 02
CA 30 CA 31

SWA 3

FHS KITCHEN
2370 x 3860

CA 32
SERVANT
ROOM
2215 x 2375

CA 34
BEDROOM
4345 x 3535

No. ISSUED FOR : DATE : CKD:

CA
UTILITY

42

CA 37
3205 x 1720

CA 36
CA 38
CA 35
UPTO HT. OF
900 MM
LV / MV

DRAWING TITLE :

TO x 14
24

ILET 05
05
CA
43

PLUMBING DRAWING

CA
CA

40

CA
46 BE

39
DR

44
OO

15
M

x3
35
0
BA
LC
BLOCK - A

18
ON

30
Y

CA
x3

SE

41
81
24

RV
0
30

CA
AN
x2

TYP. TOILET DETAIL

44
T
14

RM
D CA

CA
35 RA 5

.
47

49
30 W IN
x 38 G
10

CA NORTH:

KIT 0 x
39
53

BE
44

CH 258
DRAWN BY :

8
15

DR

CA
EN 0
x3

OO

45
UPTO HT. OF

CA

B
31

M
SONU

A
50
0

SL
900 MM

LIV x 3
42

G
IN
80
IN 81
BA 00 x

LD
G 0
32

FO
LC 17
ON 90
Y
CA
48

PU TOR 505
JA E
S x1
11
18

BA
/
95
55

30

LC
CA

x3
CHECKED BY :

ON
81

Y
DR 0
ES

21
SOMNATH
S

90
56

x1
CA

50
5

CA
51
DATE : 03-01-2015 SCALE :
A3 1:50
CA

CA
57

54
Upto Ht. Of
1150 MM from
floor finish

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA - 201
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

B-C2 B-C2

TOILET
2400 x 1480

TOILET
2400 x 1560 TOILET
2400 x 1560
B-C6 TOILET
2400 x 1480

B-C6

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


B-C16
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

B-C16
TOILET
2615 x 1710
TOILET
2615 x 1710
PROJECT:

CEDAR LUXURIA
PATRAKAR COLONY, JAIPUR
CLIENT :
CEDAR
JAIPUR

ARCHITECT :

Jaipur - Bangalore - Hyderabad


TOILET maithel & associates architects pvt. ltd.
TOILET 2470 x 1510 Plot No. -1, Lal Kothi Scheme, Jaipur-302001
2470 x 1510 Tel : 91 141 4299999
Fax : 91 141 2741664

B-C21 email - studio@maarchitects.in,


B-C21 web - www.maarchitects.in

TOILET
2390 x 1530 TOILET
2390 x 1530

DRAWING TITLE :
PLUMBING DRAWING
BLOCK - B
TYP.TOILET DETAIL
300 x 600

NORTH:
DRAWN BY : SONU

CHECKED BY : SOMNATH

DATE : 30-12-2014 SCALE : 1 : 125

DRAWING NO. :
PROJECT NO. : GH-2030
PL - BA - 201

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

TOILET
1640 x 2585

TOILET
2390 x 1515 TOILET

B-C7
B-C7

B-C8
B-C8
2390 x 1515

TOILET
1640 x 2585

B-C3

B-C3

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

KITCHEN
KITCHEN 3430 x 2365
3430 x 2365
PROJECT:

CEDAR LUXURIA
B-C12 B-C13 PATRAKAR COLONY, JAIPUR
B-C12 B-C13

CLIENT :
CEDAR
JAIPUR

ARCHITECT :

Jaipur - Bangalore - Hyderabad


B-C19

450

maithel & associates architects pvt. ltd.


Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
B-C19

Fax : 91 141 2741664


email - studio@maarchitects.in,
web - www.maarchitects.in
B-C20

B-C20
KITCHEN
2685 x 4240
KITCHEN
2685 x 4240

300 x 600

DRAWING TITLE :
PLUMBING DRAWING
BLOCK - B
TYP. TOILET DETAIL
NORTH:
DRAWN BY : SONU

CHECKED BY : SOMNATH

DATE : SCALE : 1 : 125


30-12-2014
DRAWING NO. :
PROJECT NO. : GH-2030
PL - BA - 201
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

UTILITY
2730 x 1525

TOILET TOILET UTILITY


2730 x 1525
2760 x 1530
2760 x 1530
TOILET
2400 x 1705

KITCHEN
2685 x 3345

TOILET KITCHEN
2685 x 3345
2515 x 1660
TOILET
2515 x 1660

TOILET
2400 x 1705

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PROJECT:
TOILET
1370 x 1525
TOILET
1370 x 1525 CEDAR LUXURIA
PATRAKAR COLONY, JAIPUR
DRESS
PWD. RM. 2230 x 1510 PWD. RM.
1400 x 1615
1400 x 1615

DRESS
CLIENT :
2230 x 1510

CEDAR
JAIPUR
TOILET
2550 x 1625 ARCHITECT :
TOILET
2550 x 1625

Jaipur - Bangalore - Hyderabad


maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664
email - studio@maarchitects.in,
web - www.maarchitects.in

MEP CONSULTANTS

KITCHEN KITCHEN
2580 x 3555 2580 x 3555

581.429

No. ISSUED FOR : DATE : CKD:

DRAWING TITLE :
PLUMBING DRAWING
BLOCK - C
UTILITY
2500 x 1650 TYP. TOILET DETAIL
UTILITY
2500 x 1650 NORTH:
DRAWN BY :
SONU

CHECKED BY :
SOMNATH

DATE : 28-10-2014 SCALE :


1 : 125

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA - 201
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
D-C4

D-C5
TOILET
2470 x 1615 D-C4
UTILITY
2510 x 1375

TOILET
2470 x 1615
TOILET TOILET
1470 x 2585 1470 x 2585

D-C8
TOILET

D-C2
D-C2

2470 x 1515

D-C7 KITCHEN
2590 x 3230

TOILET
2470 x 1515

D-C7

D-C5
UTILITY
2510 x 1375
PROJECT:

CEDAR LUXURIA

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PATRAKAR COLONY, JAIPUR


TOILET
2390 x 1540
TOILET CLIENT :
2390 x 1540
CEDAR
D-C8
JAIPUR

ARCHITECT :
KITCHEN
2590 x 3230
Jaipur - Bangalore - Hyderabad
maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
TOILET
D-C1 1470 x 2585 Fax : 91 141 2741664
email - studio@maarchitects.in,
BALCONY BALCONY
1525x 2600 1660 x 1525 web - www.maarchitects.in

D-C4
TOILET BEDROOM
2470 x 1615 3360 x 4215
UTILITY
2510 x 1375 424.336
71.239
424.336
10
TOILET BEDROOM 9 TOILET
2470 x 1515 3155 x 4165 8 11 1570 x 2485
D-C7 D-C8 7 12 D-C9 D-C10
6 13
KITCHEN 5 14
BEDROOM
4 15 BALCONY BALCONY
4185 x 3225 2590 x 3230 TERRACE
3 16 1600 x 1655 1525 x 2300
KITCHEN 2
1
17
18
2500 x 3940

19
3430 x 2390 UP
20 D-C14

KITCHEN DRAWING/DINING
DN
128.54 BEDROOM
3350 x 3825
TOILET
2590 x 1605

D-C15 D-C16 4430 x 6080 BEDROOM


3430 x 2390 3195 x 3950

TERRACE
2745 x 2630 KITCHEN TOILET
STUDY
2730 x 3255 2505 x 1515
2695 x 1940 D-C18 D-C19

D-C20 D-C21
BEDROOM

D-C32 D-C33 F.H.C.


4155 x 3180

TOILET
2390 x 1540
M.V.
D-C32 D-C33 BEDROOM
4085 x 3190 D-C22
DRAWING /
D-C24 D-C25
TOILET DINING
2390 x 1500 D-C23 4440 x 5830
D-C26 D-C27
LIFT
BEDROOM 1900 X 2000 TERRACE
(13 PESS. 4330 x 2500
4230 x 3085
MAKE OTIS)
DINING
3505 x 3315
KITCHEN D-C28 D-C29
3430 x 2390
LIFT
2500 X 1950
(13 PESS. TERRACE
D-C30 D-C31 D-C32 D-C33 MAKE OTIS) 4330 x 2365

D-C34 DRAWING /
DINING
D-C35 D-C36
4440 x 5830
BALCONY
2125 x 3200 LIVING
7060 x 3200

D-C38 D-C39
KITCHEN BEDROOM
2685 x 3230 4155 x 3315

LIVING
No. ISSUED FOR : DATE : CKD:
BALCONY 7060 x 3205 D-C40 D-C41
2125 x 3200 BEDROOM TOILET
3195 x 3975 2505 x 1515

DRAWING TITLE :
UP
DN
D-C42 D-C43 D-C44
20
D-C45 19
1
2 PLUMBING DRAWING
18 3 TOILET
TOILET 17 4
TERRACE
2585 x 1605
BLOCK - D
16 5
2390 x 1500 KITCHEN 15 6 2500 x 4615 D-C48

DINING
3430x 2390 14
13
7
8
TYPICAL TOILET DETAIL
3505 x 3315 12 9
BEDROOM 11 10
D-C27 4185 x 3090

D-C50
UTILITY
BALCONY
1600 x 1525 BEDROOM
3350 x 4005
BALCONY
1820 x 2400
DRAWN BY : SONU
NORTH:
3425 x 1755
D-C53

D-C27 TOILET
1570 x 2555

CHECKED BY : SOMNATH

D-C56 D-C57
DATE : SCALE : 1 : 125
29-12-2014
DRAWING NO. :
PROJECT NO. : GH-2030
PL - BA - 201
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
CEDAR LUXURIA
PATRAKAR COLONY, JAIPUR

CEDAR
JAIPUR

maithel & associates architects pvt. ltd.


Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


ROLLING
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

SHUTTER

PLUMBING CONSULTANT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT


PROJECT:

CEDAR LUXURIA
PATRAKAR COLONY, JAIPUR

CLIENT :

CEDAR
JAIPUR

ARCHITECT :
m a a r c h i t e c t s
Jaipur - Bangalore - Hyderabad
maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664
email - studio@maarchitects.in,
web - www.maarchitects.in

STRUCTURAL CONSULTANTS

CUT OUT AT RETAINING WALL


SIZE = 300X300mm
B.O.C = -1200

SERVICE CONSULTANTS

CUT OUT AT RETAINING WALL


SIZE = 850X300mm
B.O.C = -2350

CUT OUT AT RETAINING WALL


SIZE = 1000X300mm
B.O.C = -2030

CUT OUT AT RETAINING WALL


SIZE = 1000X300mm
B.O.C = -1800

CUT OUT AT RETAINING WALL


SIZE = 1100X300mm
B.O.C = -2720

PLUMBING CONSULTANT
BEHERA & ASSOCIATES
F - 623a, LADO SARAI, BEHIND CNG
STATION NEW DELHI - 110030 Ph:
011-40583839, 09811911853 Email:
CUT OUT AT RETAINING WALL behera.associates@gmail.com
SIZE = 800X300mm
B.O.C = -1350

No. ISSUED FOR : DATE : CKD:

DRAWING TITLE :

CUT OUT AT RETAINING WALL


PLUMBING DRAWING
SIZE = 1000X300mm
B.O.C = -2300
O&G TWT
EXTERNAL SITE PLAN LAYOUT
DPS
MBBR1 MBBR2
SST1
O&G EQT CCT CCT
SST2
MBBR3 MBBR4 TWT
BSC
NORTH:
DRAWN BY :
BHIM

CHECKED BY :
SOMNATH

DATE : 08-12-15 SCALE :


1 : 150

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA - 101
PROJECT:

CEDAR LUXURIA
PATRAKAR COLONY, JAIPUR

CLIENT :

CEDAR
JAIPUR

PATTA LINE

S7 S9
S10
ARCHITECT :
S12

Jaipur - Bangalore - Hyderabad


S17
maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664
email - studio@maarchitects.in,
web - www.maarchitects.in
CUT OUT AT RETAINING WALL
S4 SIZE = 300X300mm
B.O.C = -1200
S3
S5
S6
STRUCTURAL CONSULTANTS

S2

S18

-5.10
WATER TANK
LVL -5100
WATER TANK

S1
LVL -5100

Dependable Car S19


D59 D60

Dependable Car
D39 D40

S20
PIPE COMING FROM UGT

Dependable Car
D57 D58

S21

D55 D56
Dependable Car

Dependable Car S22


D53 D54

Dependable Dependable Dependable Dependable


Car Car Car Car
Dependable Car D95 D97 D99 D101
D51 D52 S87

D96 D98 D100 D102

S23
Dependable Car
D23 D24
S24

Dependable Car
D21 D22

Dependable Car
CUT OUT AT RETAINING WALL
D19 D20 Dependable Dependable Dependable
SIZE = 700X300mm
Dependable Car Car Car Car
B.O.C = -1300
D49 D50 D93 D91 D89

Dependable Car Dependable Car


D94 D92 D90
D17 D18 D87 D88 S27
Dependable Car CUT OUT AT RETAINING WALL
Dependable Car SIZE = 1000X300mm
D47 D48
Dependable Car D103 D104 B.O.C = -2030
D15 D16

Dependable Car Dependable Car


Dependable Car
D45 D46 D85 D86
Dependable Car D105 D106
S29
D13 D7 D14

S60
S33
Dependable Car Dependable Car
Dependable Car
Dependable Car Dependable Dependable D83 D84 D107 D108
D43 D44 Car Car
D11 D12
D79 D81 S30
S34
Dependable Car
Dependable Car Dependable Car D100 D110 S61
D80 D82
D9 D10 D41 D42

Dependable Car
Dependable Car D111 D112 S62
D7 D8

S32
Dependable Car Dependable Car

D5 D6 D39 D40 S66


S37
Dependable Dependable Dependable
Car Car Car Dependable Car
Dependable Car S47
D77 D75 D73 D113 D114 S63
D3 D4 Dependable Car
D37 D38
D78 D76 D74
S38 CUT OUT AT RETAINING WALL
Dependable Car
D115 D116 S64 SIZE = 1000X300mm
D1 D2 Dependable Car B.O.C = -1800
S65
Dependable Car D36
D35 Dependable Car S48
D117 D118
D72 S40
Dependable Car
D71
CUT OUT AT RETAINING WALL Dependable Car
SIZE = 1100X300mm D119 S70 D120
D33 D34 S41
B.O.C = -1300
Dependable Car
Dependable Car
D69 D70
Dependable Car
Dependable Car D121 D122
S49 S43
D31 D32

Dependable Car
D67 D68 S59
PLUMBING CONSULTANT
Dependable Car
D29 D30
S50

S45
BEHERA & ASSOCIATES
Dependable Car
S58
F - 623a, LADO SARAI, BEHIND CNG
D65 D66
Dependable Car S46
STATION NEW DELHI - 110030 Ph:
CUT OUT AT RETAINING WALL
D27 D28 S51
D1
De
pe
nd
SIZE = 800X300mm 011-40583839, 09811911853 Email:
3 ab B.O.C = -1350
9 le
Ca behera.associates@gmail.com
De D1 r
pe 40
Dependable Car D1 nd
-5.10 Dependable Car 3 7 ab
le
D25 D26 Ca
D63 D64 S56 S53
De D1 r
pe 38
D1 nda
35 ble
Ca
D1 r
36
-4.275 Dependable Car De
pe
D61 D62 S55 D1 nd
3 a
-5.10 3 ble
Ca
S70
De D1 r
S69 pe 34
S68 D1 nd
S67 31 ab
S54 le
Ca
De D1 r
pe 32
D1 nd
29 ab
le
C ar
De
D1
30
No. ISSUED FOR : DATE : CKD:
pe
D1 nd
2 7 ab
le
Ca
De D1 r
D1
pe
n 28 DRAWING TITLE :
-4.275 25
da
ble
-5.10 Ca
CUT OUT AT RETAINING WALL
PIPE COMING FROM S.T.P D1
De
pe
nd
D1
26
r
PLUMBING DRAWING
SIZE = 450X300mm 23 ab
B.O.C = -1250
D1
le
Ca
r
BASEMENT CEILING PLAN
24

NORTH:
DRAWN BY :
BHIM

CHECKED BY :
SOMNATH

DATE : 13-04-16 SCALE :


1 : 150

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA - 01
TOILET
1470 x 2585

BALCONY
1.52M x 2.6M
BALCONY
1660 x 1525

TOILET
BEDROOM
2470 x 1615
3360 x 4215
RISER = 145
UTILITY TREAD = 300
2510 x 1525 WIDTH = 1370
3155 x 4165
BEDROOM

1370 1370

TOILET TOILET
2470 x 1515 1570 x 2485
STANDING BALCONY

BEDROOM KITCHEN
2590 x 3230 BALCONY BALCONY
4185 x 3225
3135 x 600

1600 x 1655 1525 x 2300

DN BEDROOM TOILET
STAIRS UPTO 3350 x 3825 2590 x 1605
DRAWING/DINING 14TH FLOOR UTILITY
4430 x 6080 2505 x 1605

FFL +41750
BEDROOM
3195 x 3950
BALCONY
1605 x 2630 KITCHEN TOILET
2730 x 3255 2505 x 1515
FFL +41740
STANDING BALCONY

BEDROOM
4155 x 3180
3135 x 600

F.H.C.

FFL +41750

M.V.

DRAWING /
DINING
FFL +41700 4440 x 5830
LIFT TERRACE
1900 X 2000 1875 x 2500
(13 PESS.
MAKE OTIS)
PASSAGE 2970 MM WIDE

ROOF @ +44355

D BLOCK
5095

LIFT
2500 X 1950
(13 PESS.
MAKE OTIS)

FFL +41700
MS VERTICAL
ROOF @ +44355 MEMBERS
D-C38 150 x 100 x 2600
THICKNESS 3MM
T.O.C. LVL
+47850

FFL +41700

HT. OF WALL
+2450 FROM
T.O.C.

FFL +41700
D BLOCK

TOC +2680
FROM FFL Upto Ht. Of
1150 MM from
floor finish
x 1 NY
0
25 O
83
17 ALC
B

x1 T
5
4 0 ILE
67
24 TO

OM
RO
95
34

D
BE
60
x
25

S
39

ES
5
50

DR
x2 T

x1
0
05 ILE
59

90
16 TO

21

Y
ON
00

/ LC
37

JA BA
x
x1 E

PU
30
5
95 OR
50

18

Upto Ht. Of
11 ST

1150 MM from
floor finish
x3 G
0
80 IN
81

PROJECT:
42 LIV
25
x 1 NY
0
00 O
79
32 ALC
B

x 3 OM

x 2 EN
0
15 O
31

CEDAR LUXURIA
95 H
44 EDR

58
39 ITC

FFL +41700
B

L.V. BALCONY
MS VERTICAL T.O.C. LVL
MEMBERS +47850 F.H.C. 1675 x 1900
150 x 100 x 2600 BEDROOM TY
ILI
0
30

3165 x 4610
UT
PATRAKAR COLONY, JAIPUR
x2

THICKNESS 3MM
10

TOILET
x 3 NG

18
0
30 WI

1515 x 2395
81

M.V.
35 RA
D

BEDROOM
14 M.

4275 x 3525
x2 R

TOILET
C BLOCK
30 NT

5
24 RVA

2515 x 1520 Y
ON
SE
10

LC
38

B 230 x 450 BA
x
30

T
ILE
30
18

PUJA/STORE DRESS
16

TO
x

LIFT
90

1390 x 1515 2240 x 1410


14

M
1900 X 2000 OO 40
(13 PESS. 2275 DR 33
BE 15 x CLIENT :
PASSAGE 2970 MM WIDE

MAKE OTIS) 44 .
RM
15

D
14

PW
x
15

DRAWING BALCONY
15
5460

AREA LIVING AREA 1935 x 3810


4920 x 3710 4925 x 3710 5
T

41
C BLOCK
ILE

x1
TO

05
LIFT
2500 X 1950
(13 PESS. MAKE OTIS)
FFL +41750
24
LV / MV
CEDAR
BALCONY
JAIPUR
230 460

FFL +41740
1635 x 1900
DRESS
600

KITCHEN 2230 x 1510


230

2440 x 3870 PWD. RM. BEDROOM


TOILET 4310 x 3525
1400 x 1615
600

1505 x 2545
230

230 600 230 600 230 600 240 SERVANT TOILET TOILET
ROOM 2550 x 1625 BEDROOM 2505 x 1550

DN 2225 x 2210 3130 x 4565


BEDROOM
4310 x 3580

FHS PUJA/STORE DRESS


FFL +41700 1390 x 1515 2315 x 1515
BALCONY
1525 x 1900
TOILET UTILITY
1335 x 1630 3205 x 1755
LIFT PIT
LTA 01
ARCHITECT :
BALCONY
LIVING AREA 1935 x 3710

RISER = 145
TREAD = 300 A BLOCK
PASSAGE
2170 MM WIDE
DRAWING
AREA
4885 x 3710
4990 x 3710
pvt. ltd.
WIDTH = 1370
Jaipur - Bangalore - Hyderabad
LIFT PIT
LTA 02 maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
FHS KITCHEN PWD. RM.
1400 x 1615
Tel : 91 141 4299999
2370 x 3860

SERVANT
DRESS
2330 x 1590
Fax : 91 141 2741664
2480 x 1525
TOILET

ROOM
2215 x 2375 email - studio@maarchitects.in,
BEDROOM
web - www.maarchitects.in
4345 x 3535

TOILET BALCONY
1335 x 1595 1525 x 1900
UTILITY
3205 x 1720

ROOF @ +44355
T.O.C. -370
FROM T.O.C.
T.O.C. -370
FROM T.O.C. LV / MV
UPTO HT. OF
900 MM Upto Ht. Of
1150 MM from
MEP CONSULTANTS
TO 5 x 1

floor finish
24

FFL +41700
ILE 40
0

T 5

ROOF @ +44355
PW 5 x
15

D 140
2

RM 5
.
BE 15
DR x 3
44

OO 350
M

TO x 1
14
BA 30 x

ILE 53
90
18
LC 38

T 0
ON 10
Y

SE 2430
RV x
AN 21
T 45
RM

B-C17
.
DR 30 x
35
AW 38
IN 10
G

TOC +1700
UT 0 x
19

ILI 251

FROM T.O.C.
6

TY 5
KI 0 x

TOC +2830
BE
39
TC 25

DR
8
HE 80

T.O.C. LVL
44

FROM T.O.C. OO
N
15

+47850 ROOF @ +44355 M UPTO HT. OF


x3

B BLOCK
31

900 MM
LIV x 3
0

42

FFL +41700
80
IN 810
BA 00 x

G
32
LC 17
ON 90
Y

FFL +41740 FFL +41700


PU TOR 505
JA E
S x1
11

BA 30 x
95

18
LC 38
ON 10
PASSAGE 2970 MM WIDE

Y
TO 0 x 2
15

ILE 62
3

DR 0 x 1
21
T 0

ES 50
9

BE
S 5

DR
LIFT TOC +2830
39

OO
25

F.H.C. 1900 X 2000 FROM T.O.C. M


x3

(13 PESS.
46

CUTOUT
0

2575 x 3965 MAKE OTIS) TOC +2830


M.V. FROM T.O.C.

LIFT
2500 X 1950
B BLOCK
L.V. (13 PESS. BA
MAKE OTIS) LC
17

ON
25

Y
x1

Upto Ht. Of
79

FFL +41750
0

1150 MM from
PASSAGE floor finish
1450
FFL +41750
BALCONY DRAWING/DINING
1605 x 2630 4060 x 7455
DRAWING/DINING LIVING
4430 x 5985 2765 x 3565
STAIRS UPTO
14TH FLOOR
STANDING BALCONY

DN
STANDING BALCONY

3135 x 600

KITCHEN
3135 x 600

2685 x 3675

BEDROOM BEDROOM No. ISSUED FOR : DATE : CKD:


KITCHEN 4310 x 3205
4185 x 3130
2590 x 3230

TOILET TOILET
2480 x 1515 BEDROOM BEDROOM
2470 x 1515
3155 x 4225 3360 x 4270
DRAWING TITLE :
UTILITY
UTILITY
2020 x 2545 PLUMBING DRAWING
2510 x 1550
TOILET
2620 x 1710
BLOCK - A,B,C & D
TOILET
2470 x 1710

BEDROOM
14th FLOOR PLAN
BALCONY
3365 x 4310

BALCONY
LOWER TERRACE KHURRA & FLOOR PLAN
1525 x 2600 BALCONY 1685 x 1640
1675 x 1525 BEDROOM
3380 x 4335
BALCONY
1605 x 2600 NORTH:
TOILET DRAWN BY :
1640 x 2590
BHIM

CHECKED BY :
SOMNATH

14TH FLOOR PLAN DATE : 03-12-15 SCALE :


1:175

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA - 501
TERRACE

DN

DOMESTIC
WATER TANK
2.97 x 3.40 x 1.70

FIRE WATER
TANK
2.97 x 2.08 x 1.70

LIFT
PASSAGE 2970 MM WIDE BELOW

1900 X 2000
(13 PESS.
MAKE OTIS)
TERRACE

D BLOCK
5095

LIFT
2500 X 1950
(13 PESS.
MAKE OTIS)
TERRACE BELOW

FLUSHING
WATER TANK
2.97 x 2.00 x 1.80

TERRACE BELOW
D BLOCK

STAIRS UPTO
13th FLOOR LVL
RISER = 145
TREAD = 300
WIDTH = 1370

TERRACE BELOW TERRACE PROJECT:

FIRE WATER TANK


2.97 x 2.00 x 1.80
CEDAR LUXURIA
DOMESTIC WATER PATRAKAR COLONY, JAIPUR
C BLOCK
18
TANK

CA
2.97 x 2.00 x 1.80

LIFT
1900 X 2000
(13 PESS.
PASSAGE 2970 MM WIDE

MAKE OTIS)
ST ERR

19
AI AC
T

CA
17

RC E
CA

CLIENT :
AS
BELOW
5460

E
UP
TO

C BLOCK
4170

LIFT
2500 X 1950
(13 PESS. MAKE OTIS)

FLUSHING
WATER TANK
CA 20 CA 21
CEDAR
2.97 x 1.15 x 1.80

TERRACE JAIPUR
FLUSHING
DN WATER TANK
2.50 x 2.69 x 1.0

TERRACE BELOW
SWA 1
TERRACE
LIFT PIT
BELOW
2450

1900
PASSAGE
BELOW
ARCHITECT :
RISER = 145
TREAD = 300 A BLOCK SWA 2
WIDTH = 1370

LIFT PIT
pvt. ltd.
1950

BELOW
Jaipur - Bangalore - Hyderabad
2500
SWA 3 maithel & associates architects pvt. ltd.
DOMESTIC
WATER TANK Plot No. -1, Lal Kothi Scheme, Jaipur-302001
2330

2.69 x 2.33 x 1.80


Tel : 91 141 4299999
2690 Fax : 91 141 2741664
2690
RISER = 145
email - studio@maarchitects.in,
TREAD = 300 FIRE WATER
2325

WIDTH = 1370 TANK


2.69 x 2.33 x 1.80
web - www.maarchitects.in

TERRACE BELOW
MEP CONSULTANTS
CA

DN
39
CA
41
6630

TERRACE BELOW TERRACE

FLUSHING WATER TANK


2970 x 1800 x 1800
PASSAGE 2970 MM WIDE

LIFT PIT
1900 x 2000
TERRACE BELOW
BELOW

B BLOCK
LIFT PIT
2500 x 1950
TERRACE
DOMESTIC
WATER TANK
2.97 x 3.65 x 1.80

FIRE WATER
TANK
2.97 x 2.25 x 1.80
No. ISSUED FOR : DATE : CKD:

DRAWING TITLE :
PLUMBING DRAWING
BLOCK - A,B,C & D
TERRACE TERRACE FLOOR PLAN
RAIN WATER KHURRA LAYOUT
NORTH:
DRAWN BY :
BHIM

CHECKED BY :
SOMNATH

DATE : 03-12-15 SCALE :


1:175

15TH FLOOR PLAN PROJECT NO. :


GH-2030
DRAWING NO. :
PL - BA - 601
PROJECT:

CEDAR LUXURIA
PATRAKAR COLONY, JAIPUR

CLIENT :

CEDAR
JAIPUR

ARCHITECT :

Jaipur - Bangalore - Hyderabad


maithel & associates architects pvt. ltd.
Plot No. -1, Lal Kothi Scheme, Jaipur-302001
Tel : 91 141 4299999
Fax : 91 141 2741664
email - studio@maarchitects.in,
web - www.maarchitects.in

STRUCTURAL CONSULTANTS

SERVICE CONSULTANTS

PLUMBING CONSULTANT
BEHERA & ASSOCIATES
F - 623a, LADO SARAI, BEHIND CNG
STATION NEW DELHI - 110030 Ph:
011-40583839, 09811911853 Email:
behera.associates@gmail.com

No. ISSUED FOR : DATE : CKD:

DRAWING TITLE :
PLUMBING DRAWING
RAIN WATER HARVESTING PIT DETAIL

NORTH:
DRAWN BY :
BHIM

CHECKED BY :
SOMNATH

DATE : 11-08-16 SCALE :


NTS

PROJECT NO. : DRAWING NO. :


GH-2030 PL - BA - DET

You might also like