Sump Pump Method of Statement
Sump Pump Method of Statement
Sump Pump Method of Statement
Method Statement for Sump Pump defines the specified materials are installed
and the agreed procedure is implemented as per quality, project specifications, and
health, safety & environment requirements.
Scope
This method statement covers the installation procedures for the following type
of GRUNDFOS Storm Water Submersible Pumps: SLV Model
Here GRUNDFOS Submersible Pump brand will be used otherwise feel free to
substitute it with whatever brand that meets the project specifications for
approval.
References
Local Authority Regulations
Grundfos Installation & Operating Instructions for the respective pumps and
controls.
IFC drawings
Approved material submittal for the submersible sump pump
Abbreviations
QC – Quality Control
HSE – Health, Safety, and Environment
ITP – Inspection & Test Plan
MS – Method Statement
PPE – Personal Protective Equipment
MSDS – Material Safety Data Sheet
RA – Risk Assessment
QCP – Quality Control Procedure
INR – Inspection Request
QA/QC – Quality Assurance/ Quality Control
Responsibilities
Project Manager
Responsible to manage, execute, complete, and handover the construction activities
within approved budgets and resources in compliance with requirements as specified
in project specifications.
He will be overall in charge of implementing the Method Statement in accordance with
QA/QC and HSE requirements.
Construction Manager
Responsible for overall construction activities ensuring that all quality and safety
procedures are implemented.
Ensure that the required approved permits are obtained.
Managing construction activities and leading the site supervision, subcontractors, and
vendors to assist them in working to the project schedule by conforming QA/QC and
HSE requirements at the site.
HSE Manager
Generally plans, coordinates, and implements issues and directives within the
organization.
Ensures safe environmental working conditions for all employees.
HSE Supervisor
Monitors the site engineer’s strict implementation of the Method Statement for Sump
Pump Installation and Risk Assessment.
Implements the use of proper tools and equipment to maintain safety, certifications of
equipment and adherence to safety regulations.
Reports any unsafe work or stopping work that does not comply with HSE procedures.
QA/QC Manager
QA/QC Engineer
Site Engineer
Supervises the operations in accordance with the approved Method Statement for
Sump Pump Installation, shop drawings, specifications, material submittals, and
schedules to achieve the acceptance of the project deliverables.
Site Supervisor
Supervise closely, the activities designated to them and ensure that all instructions and
safety procedures are followed.
Site Foreman
Liaises with the Site Engineer and Supervisor for the work execution.
Electricians
Responsible for assisting their superiors during all construction work-related activities.
Work in line with the HSE and QA/QC requirements.
Store In-charge
Receives and inspects all incoming materials and reconciles all related documents.
Processes and distributes documents and tracks damage and discrepancies.
Resources
Testing instrument Required
• Clamp-on Ammeter
• Megger, 500V DC
• Digital Multimeter
Manpower
Construction Manager
Site Engineer
QA/ QC Engineer
HSE Officer
Supervisor
Electricians
Helpers
The pump shall be kept on a flat secluded surface with a well-ventilated storage area.
The unit selection, locations, and levels shall be in full compliance with the approved
materials, IFC drawings, approved shop drawings, BOQ, and project specifications
including but not limited to all supporting systems, anchoring, and spacing
requirement.
Shift the pumps and their accessories to the working area in a safe manner as per site
conditions by the use of either a hand trolley, forklift, or crane.
Prior to the commencement of any construction works, the area and access will
be inspected to confirm that they are in a suitable condition for construction
work to commence. Prepare a working permit (if any) and submit it to any
designated safety officer.
All relevant documentation (approved shop drawing, coordination drawing,
approved method statement, approved material submittal, approved ITP, the
checklist) and material applicable to a particular section of work will be
checked before the commencement of work.
The sequence of work activity shall be coordinated at the site with other
disciplines and secure other trades (Civil/Structure & Architectural) to ensure
smooth coordination and to avoid re-work.
The mechanical site engineer will instruct the supervisor in charge who in return
will relay to the tradesmen regarding the execution of the work and will
distribute all necessary approved construction shop drawings and
coordinated layout plans.
The site mechanical engineer/supervisor should also check the tools and
equipment available which should be compliant with the contract requirement
and are in good and safe working condition.
Ensure that only approved materials are required to carry out the work shall be
available.
Pump selection is based on the certified performance curve and rated capacity
of the selected model mentioned as per approved material submittal, project
specification & design equipment schedule.
Electrical component devices and accessories shall be defied in the latest TEC
Standard acceptable.
The drainage water pump must be as per the approved material submittal and
project specification.
When two or more units of equipment of the same type and class shall be the
product of one manufacturer.
Pumps identifications: Manufacturers nameplate, trademark, model, serial
number, GPM, TDM, 994, HD Impeller, discharge, and suction shall be fixed at
each piece of equipment.
The in-charge Mechanical Engineer, supervisor, and foreman should verify that
the personnel or assigned person must have sufficient knowledge of the
procedure for the installation, operating Instruction, and necessary
fundamental Information Review training and qualification record for those
individuals who will do the task to determine whether they are skilled enough
to follow the procedure before the work is carried out.
Mockup for submersible pumps (mechanical and electrical) installation complete
with all hook-up details (including all accessories and supporting
arrangement) shall be carried out at the site prior to proceeding.
The installer will receive a set of installation drawing from the factory with a tag
number and hosting shall be executed as per the manufacturer’s
recommendation.
Pump installation shall be carried out in accordance with the approved shop
drawing, plan, section, and details and as per the manufacturer’s
recommendation, and project specification.
All safety regulations must be observed at the installation site.
Equipment Supports
The pump assembly will be mounted inside the concrete sump pit with the
required supports as per
manufacturer’s recommendation and approved drawings and materials.
All required accessories shall be fixed as per approved detail drawings.
Inspection
After completing the pump installation, The Site Engineer / Supervisor shall
systematically check and Inspect the work as per approved shop drawings.
Any rectification modification shall be immediately done prior to raising an
INR.
After satisfactory inspection by the Site Engineer/ Supervisor on the fixed pump,
the INR has to be raised by them with complete attachment & Information
regarding the scope of the inspection, including highlighted drawings to show
the scope of Inspection. The inspection shall be performed according to the
typical checklist and approved Inspection and Test Plans ( ITP ).
The needed attachment will be forwarded by the Site Engineer/Supervisor to the
QA/QC Department who shall check and process the INR documents of
completed works for Supervision Consultant installation inspection and
approval.
After ensuring that safety precautions are in place, check that all pump valve
packages shall be fully open to avoid damage to the disk and seat ring.
Correct alignment, and flat and smooth settling of the pump shall be inspected
by the Site Engineer/Supervisor.
The pump’s freewheel and direction of impeller rotation as well as the fluid flow
direction shall be observed; and made sure that supplied electrical power is in
– line with the equipment nameplate rating.
Check nameplates and cross-check with the specifications/approved shop
drawings/approved materials to ensure the correct pump.
Check the impeller to ensure free and smooth rotation.
After Site Engineer satisfactorily completed the inspection, INR shall be
submitted to QA/QC Department who shall check and process the documents
to have completed work inspected by Supervision Consultant for final
approval.
All workers involved shall be equipped with adequate PPE as stated below:
• Safety helmet with company logo
• Safety boots
• High visibility vest, safety goggles, hand gloves, coveralls
• Twin-tail harness, Max 1.20 m long (when working at height). All special PPE (harness)
is considered
as a last resort when we cannot engineer, administratively eliminate, or guard against
hazards.
Information to Personnel
a. Safety Induction
b. Job training
C. Superintendents Notices/Memos
d. Toolbox talks
e. STARRT Card
Emergency Procedures
The contractor shall provide first aid kits on site for handling light injuries.
In the event of an emergency, all workers will be asked to evacuate and assemble at
the ASSEMBLY POINT and wait for further instruction from supervisors.
Permit Required
Records
Checklist (CL)
Inspection Request (INR)
Inspection and Test Record (ITR)