Professional Documents
Culture Documents
LMM Lec - 4 - Capacity Management
LMM Lec - 4 - Capacity Management
A s s i s . P ro f. M o h a m m e d A b d e l g ha ny
A s s i s t a n t P ro fe s s o r, I n d u s t r i a l E n g i n e e r i n g ,
Mechanical Engineering Department
E - m a i l / M A b d e l g h a ny @ n u . e d u . e g
Te l . / + 2 0 1 1 4 4 8 7 6 7 0 2
Previous Lecture Review
• Material Requirements Planning.
• Standard time:
• The work required to make a product is expressed as the time required to make the
product.
• Time study techniques is used to determine the standard time (standard hours) for
a job.
The firm planned to make 500 tables, 300 The amount of wood needed is:
chairs, and 1500 stools in a particular
period.
Resource bill
• The difference is that now we are working with a product and not a family of
products.
Medium 40 25 40 15 120
Fine 20 10 30 20 80
Week 1 2 3 4 Totals
Medium
Fine
Total hours
Week 1 2 3 4 Totals
Medium 20 12.5 20 7.5 60
Fine 24 12 36 24 96
Total hours 44 24.5 56 31.5 156
• Available capacity can be adjusted with overtime, extra workers, routing through other
work centers, or subcontracting.
• CRP is the most detailed, complete, and accurate of the capacity planning
techniques.
• A record of all the active shop orders is maintained manually or as a computer file.
• Wait time is the time a job is at a work center after completion and before being moved,
• Queue time is the time a job waits at a work center before being processed.
• Lead time is the sum of queue, setup, run, wait, and move times.
• The Gregorian calendar has some serious drawbacks for manufacturing planning:
• months do not have the same number of days,
• Suppose that the lead time for an item is 35 working days and on December 13 an
order is placed for delivery by January 22.
• Example: A work center has 3 machines and is operated for 8 hours a day, 5
days a week. What is the available time?
• Answer: Available time = 3 × 8 × 5 = 120 hours per week
• Example: A work center is available 120 hours but actually produces goods for only
100 hours. What is the utilization of the work center?
100
• Answer: 𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑡𝑖𝑜𝑛 = × 100% = 83.3%
120
• Example: A work center produces 120 standard hours of work in 100 hours. What is the
efficiency?
120
• Answer: 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 = × 100% = 120%
100
• Theoretical capacity:
• The maximum capacity available, with no regard for downtime, utilization, or
efficiency.
• Answer:
• Theoretical capacity = 4 × 8 × 5 = 160 hours per week → (Available time)
• It is based on the actual load input to the work center, not necessarily reflective of
what the work center is capable of producing.
• Example: Over the previous 4 weeks, a work center produced 120, 130, 150, and 140
standard hours of work. What is the demonstrated capacity of the work center?
120+130+150+140
• Answer: 𝐷𝑒𝑚𝑜𝑛𝑠𝑡𝑟𝑎𝑡𝑒𝑑 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 = = 135 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠
4
• Answer:
• A two-step process:
1) Determine the standard hours needed for each order at each work center.
2) Add all the standard hours together for each work center in each period
• Run time is equal to the run time per piece multiplied by the number of pieces
in the order.
• Example: A work center is to process 150 units of gear shaft SG 123 on work
order 222. The setup time is 1.5 hours, and the run time is 0.2 hours per piece.
What is the standard time needed to run the order?
• Answer: Total standard time = setup time + run time = 1.5 + (150×0.2) = 31.5 hrs
• It is necessary to calculate when orders must be started and completed on each work
center so the final due date can be met [Scheduling].
• Backward Scheduling: starting with the due date and using the lead times to work
back to find the start date for each operation.
• The following must be known for each order: ✓ Setup and run times for each operation,
95 103
105 113
115 121
123 133
135
• Load calculations