Blasting and Painting Procedure
Blasting and Painting Procedure
JOB DESCRIPTION:
SAND BLASTING AND PAINTING
RESIDUAL
INTIAL RISK COMPLETION
N0 TASK HAZARD RISK CONTROL MEASURIES RISK ACTION PARTY TARGET DATE FOLLOW UP
S P R S P R DATE
1 Operate Compressor - Compressor air hose breaks Se Po U - All hose shall suitable for intended work Se Vu A CTR
couping disconnect (shall be to prevent shock from statistic electricity) Safety Officer
- Air hose joined with standart manufacture couping
(metal), secure the hose couping with steel clamp
band and steel safety clip on both coupling
connection for safety.
- Blast hose shall be joined with standart manufacture
coupling (metal or plastic).
- Safety valve should working properly.
2 Wet Blasting High pressurized hoses -Use anti-whip checks on connection SPV
(Unsecured hoses, substandard hoses) -Hoses to be standard pressure hoses Se Vu A SPV
-Human consecuences Se Po U -Dead new valve to be blowid and never issue passed Se Vu A
Personal Injury (hurt)
-Environment consecuences Se Po U -Cover blasting area Se Vu A
Polluted atmosphere
Uncontrolled dust particles -Operator to wear appropiaterespiratory and pro- OPR, SPV
-Human consecuences Se Po U tective equipment Se Vu A SPV
Health exposure (air contamination) -Full protection for blasting operator to be provided SPV
-Environment consecuences Mo Po T and wom No Vu A SPV
Polluted atmosphere -Blasting activity to be done in a enclosed area
and far from personnel
3 Painting works Fire (hot work nearby) -No hot work at painting area ALL
-Human consecuences Mo Po T -No hot work after painting activity ALL
Personnal injury (bum, fatality) -MSDS to be on site (Material Safety Data Sheet) Se Vu A HSE
-Material consecuences Mo Po T
Fire Se Vu A
JOB RISK ASSESSMENT - FRONT SHEET
A. SCOPE OF WORK
1 Operate Compressor 3. Painting
2 Blasting 4. Storing of Painting & Blasting Material
B. MAIN EQUIPMENT.
1 Air Compressor 175 CFM
2 Elcometer, Hygrometer, Thermometer
3 Paint pot, Manifold, Nozzle
4 Spray Gun, Sand Pot
5 Consumables (wirw brush, paint brush, etc)
6 Hand Tools
D. TEAM WORK
1 PGM : Supervisor (1), Foreman (1), Blaster & Painter (3), Operator Compressor (1), Safety man (1)
Helper (4)
2 CST/OPS : 1 person
E. NOTE
1 List of assessed tasks as per attached sheets.
This JRA shall reflect safety actions to be implemented for each specific job and equipment.
2 Toolbox talk / pre job briefing to be held with personnel who will take part in work activities.
This shall be conducted by crew supervisor and safety supervisor prior to work commencing.
3 All activities mentioned on JRA should be covered by Permit to Work
4 Before starting the job, identification on site muster area, emergency access way
5 Sufficient PPE is required (Gloves, Safety shoes, Helmet, Masker)
ASSESSMENT REVIEWED AND ACCEPTED BY (COMPANY):
POSITION PRINT NAME SIGNATURE DATE
JOB DESCRIPTION:
SAND BLASTING AND PAINTING
RESIDUAL
INTIAL RISK COMPLETION
N0 TASK HAZARD RISK CONTROL MEASURIES RISK ACTION PARTY TARGET DATE FOLLOW UP
S P R S P R DATE
Air contamination - Painters to be use appropiate respiratory OPR
-Human consecuences Mo Po T & Protective equpiment at all times Mi Vu A ALL
Personal injury (health effect, fatallity) - Other PPE (goggles to be worn)
(1) If one answer "tolerable" then filled by Entity Management but if one answer "unacceptable" then a new JRA must be organized regarding a new proposal for the execution of the job
Note : The "OK" to start work will be given after completion of the last follow up column and use of the Work Permit
SPV = Supervisor, WRK=Worker, ALL=All Participant, HSE=Safety, RIG=Rigger, SCF=Scaffolder