PLANT MANPOWER PROJECT

Hari : Kamis
Tanggal : 27 Oktober 2022

MASONRY
NO. NAME BN / ID PLAN ACTUAL LOCATION REMARKS
1 Bunga Petrus Malino Z 83953 1 Pt.Dire Pratama
2 Joni David Z 93485 1 Grouting PLTU
3 Rasa Alang Z 93481 1 Pt.Dire Pratama
4 Taufik Hidayat Z 94753 1 Grouting PLTU
5 Heriansyah Z 118438 Standby
6 Abd Haq Z 98369 Standby
TOTAL MANPOWER

HELPER
NO. NAME BN / ID PLAN ACTUAL LOCATION REMARKS
1 Abdul Haris Z 116383 Standby
2 Abd Haq Z 98369 Standby
3 Aris Maryono Z 116641 1 PT. Dire Pratama
4 Liwandry Wesli Z 111220 1 PT. Dire Pratama
5 M. Wahyudin Z 117113 Standby
6 Risik Herianto Z 117109 Standby
7 Mursalin Z 118409 Standby
8 Mansur Z 118437 Standby
TOTAL MANPOWER

WELDER
NO. NAME BN / ID PLAN ACTUAL LOCATION REMARKS
1 Yulius Bunga Z 117327 1 Workshop
2 Abd Haq Z 98369
TOTAL MANPOWER

FITTER
NO. NAME BN / ID PLAN ACTUAL LOCATION REMARKS
1 Yulius Bunga Z 117327
2 Abd Haq Z 98369 1 Workshop
TOTAL MANPOWER

SCAFFOLDER
NO. NAME BN / ID PLAN ACTUAL LOCATION REMARKS
1 Junaedi Z 116905 1 PT. Dire
TOTAL MANPOWER

NOTE

Masonry :
Helper :
Welder :
Fitter :
Scaffolder :