Approved MS&TRA For Platform Works

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

Global Ascent Business Center

PO Box 93820, Abu Dhabi / Musafah


United Arab Emirates
Phone: +971-2-5550013
Telefax: +971-2-5550017

ETIHAD RAIL STAGE 2 PROJECT-PACKAGE 2B

REVIEW OF CONTRACTOR’S DOCUMENT TRANSMITTAL FORM No. DTS-004.Rev.A

Project Title: ETIHAD RAIL STAGE 2 PROJECT-PACKAGE 2B


Contract No: C0304

To : KEC International Ltd Fax No: +97102 6394887


Attn : Project Manager

Document Approval : DTS.No-004. Rev.A Comment : UAE/2341870/IKH/


Submission Sheet Sheet Ref. DTS-101

Submission Date : 14 Jun 2020 Date : 18 Jun 2020.

Receipt Date : 14 Jun 2020 Page(s) : 01

S.No Titles / Details DOC. No. Rev. Status Comments


Method Statement for Construction of Tower
S02-EUE-
1. Stabilization Layers and Construction A AP Nil
PM-00002
Access Road.
AEN Approved except as
Status AP= Approved NA = Not Approved
= noted

Not Subject to
RET=
Approval

Comments:

S.No Comments

Nil

Signed Received
GOPA-intec KEC

Note: The above comments and/or approval do not relieve the OHL Contractor from the obligation in the Contract to ensure
conformance to the Specifications. Any Specification deviations found subsequent to approval are to be corrected by the OHL
Contractor to the satisfaction of the TRANSCO/JV/Engineer.
CS DTS-004.Rev.A Page 1 of 1 20 Jun. 20
REGIONAL OFFICE :
P.O.BOX 27830, ABU DHABI, UAE.
TEL. 02 6394886 FAX 02 6394887

DOCUMENT TRANSMITTAL SHEET


To, GOPA - International Energy Consultants GmbH
P.O Box 93830
Abu Dhabi
United Arab Emirates
Tel: 00 971 25550013 Fax: 00 971 25550017

Contract No. C0304 - CRCC/GTGC/JV/PD/0029 Our Reference : TM-013-04A Date: 14-Jun-20

ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE 2B Design & Build Contract (Tarif-Seih DTS.
04A
Shuaib) NO.

The following Documents are enclosed : SHEET - 1 OF 1

For Information only √ For Comments and Approval Approved Documents

DOCUMENT CSD NO. STATUS DATE


S/N TITLE AND DETAILS Rev
C0304 - NA RE AP dd.mm.yy

METHOD STATEMENT FOR CONSTRUCTION OF TOWER


1 S02 - EUT - PM - 0 0 0 0 2 01
STABILIZATION LAYERS AND CONSTRUCTION ACCESS ROADS

Note:

Please return with approval Please confirm receipt One copy of each document returned

CONTRACTOR
KEC INTERNATIONAL LTD. GOPA Intec CRCC-GTGC JV

Project Manager
KEC International Ltd.

DOCUMENT DISTRIBUTION:-

1 x GOPA Intec - Abu Dhabi Office + 1 Soft copy 1 x KEC - Abu Dhabi Office

1 x CRCC-GTGC JV - Abu Dhabi Office - Soft Copy Only


1 Revised as per Comments on DTS 004. SHUBHAM ALN 14-Jun-20
REV DESCRIPTION PREPARED CHECKED DATE

CLIENT

ENGINEER PMC

SUB CONSULTANT OHTL CONSULTANT

P.O.Box.
7497
CONTRACTOR'S JOINT VENTURE

SUB CONTRACTOR
P.O Box 27830, Abu Dhabi
United Arab Emirates
Tel: +971 2 6394886
Fax: +971 2 6394887

PROJECT

CONTRACT NO. C0304 - CRCC/GTGC/JV/PD/0029


ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE 2B DESIGN & BUILD CONTRACT (TARIF-SEIH
SHUAIB)

NAME DATE TITLE

PREPARED ABRAR 3-Mar-20

DRAWN
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
CHECKED SHUBHAM 4-Mar-20 STABILIZATION LAYERS AND CONSTRUCTION ACCESS
ROADS
APPROVED ALN 4-Mar-20

SHEET SIZE

SUPERSEDED DRG. No. CSD No. C0304 - S02 - EUT - PM - 0 0 0 0 2 01

SCALE KEC DRAWING No.

FILE : REV. 01
CLARIFICATION SHEET

Contract No.: C0304


Project Title: ETIHAD RAIL STAGE 2 PROJECT-PACKAGE 2B

Reply to Comments on DTS No. 004 dated 12-Mar-20

DTS TITLE:

METHOD STATEMENT FOR CONSTRUCTION OF TOWER STABILIZATION LAYERS AND CONSTRUCTION ACCESS ROADS

STATUS: “AEN”

S/N Comment Contractor’s reply to the Comment

CONSULTANT’S COMMENTS VIDE COMMENT SHEET REF. 2341870/DA/0011/Z/011


The approved Gatch shall be deposited in layers not exceeding 25cm compacted
1. thickness and shall be compacted in layers up to required thickness level for the Noted & revised accordingly.
platforms. That shall be corrected.
Compaction test shall be done by approved laboratory as per specification and the
2. Confirmed & the same is included in the Method Statement.
test reports shall be submitted for approval. To be Confirmed.

Page 1 / 1
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD

METHOD STATEMENT FOR CONSTRUCTION OF TOWER


STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD

CONTRACT NO. C0304 - CRCC/GTGC/JV/PD/0029

ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE 2B


Design & Build Contract (Tarif-Seih Shuaib)

CLIENT : CRCC-GTGC JV

OHTL CONSULTANT : GOPA - Intec

OHTL CONTRACTOR : KEC INTERNATIONAL LTD.

Page 1 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD

1.0 Specific work Activity and Scope:

Under the subject Contract, the Contractor needs to construct the Tower Stabilization
Platform of thickness as per the approved profile but a minimum of 0.5m for each New
Tower & Gantry as per the TRANSCO specification S-TR-CIVIL-OHL (Rev.0-2009).

The purpose of this Method Statement is to describe the methodology involved for
construction of Tower Stabilization Platform and refurbishment of existing Construction
Access Road.
Construction Access Road does not require any Specification & should be constructed
as per the Site requirement.

2.0 Starting and Completion Date:

Refurbishment of Construction Access Road is planned to start from the end of May’20
& construction of Tower Stabilization Platforms is scheduled to start from Jun’20. Both of
these activities are scheduled to finish within 1st week of Aug’20. This depends on the
route approvals & work front availability.

3.0 Terminology:

2.1 Competent Person


A person who has sufficient technical knowledge and experience to recognize
and avoid danger and been appointed in writing by an appropriate officer of
TRANSCO to carry out defined duties. These may include the operation of
equipment and the receipt and clearance of specified Permit to Work, in
accordance with a Competency Certificate.

2.2 Danger
A risk for Human Health, Property & Environmental Damage.

2.3 Danger Notice


A notice of an approved type, convey a warning of the probability of Danger of
approach to either electrical or general hazards. These notices are also
displayed at the limits of safe working areas calling attention to the adjacent
Dangers.

2.4 General Safety


The provision and maintenance of safe access to and from the place of work, a
safe place of work, a safe working environment, safe methods of work and the
correct use of effective personal protective equipment.

2.5 Permit to Work


A safety document being a form of declaration which specifies the equipment, the
works which may be carried out and specifies the necessary safety precautions.

2.6 Supervision
The control and direction exercised by a Competent Person who is present at the
point of work at all times during the progress of the work.

Page 2 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD

2.7 Working Party


Individuals who will be working under the direct supervision of a Competent
Person.

Site Engineer: KEC’s site-in-charge for this particular activity –


Mr. Suresh: 050-6137402

4.0 Roles and Responsibility:

• Project Manager:
Overall control and Project Management of all activities at Project level. Distribution
of resources & finance. Review and implement procedure for meeting statutory and
quality requirements. Co-ordination with project co-ordinators and customer/
consultant/ sub-contractors/ sub-vendors/ local statuary bodies at the Project level
and shall have the final responsibility on HSE.

• Construction Manager:
For ensuring all the activities are undertaken and constructed as per the drawings,
coordinate for necessary work permits, all approved QC requirements are met by the
construction team and ensure that all necessary resources are available to meet the
schedule targets.

• Safety Officer:
For ensuring all the activities are undertaken and constructed in a safe manner as
per the approved Method Statement, Risk Assessment & HSE Manual.

• Site Coordinator
For liaising with related authorities for obtaining permission for smooth functioning of
project and facilitate site team.

• Site Engineer:
For ensuring that all the works are executed meeting HSE & QC requirements,
allotment and supervision works to individual groups, conduct Tool Box Talks, Guide
and Monitor the work force for progress, report to the Construction Manager on
regular basis.

Further reference is made to Annexure 1 - Site Responsibility Chart.

5.0 References to any other interface processes:

The following NOC & Work Permits, if required:

1. Existing 400/ 220 kV OHL crossings with consent of TRANSCO.


2. Oil/ gas pipeline crossings with consent of ADNOC.
3. Common NOC approved from all the concerned utilities.

6.0 Required Safety Documents, Project Documents & Drawings:

The required documents to be kept at work site are as under.

1. Route Alignment Drawing

Page 3 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD

2. Approved Profile Drawing


3. Approved Line Schedule
4. TRANSCO safety document, if required.
5. Project Quality Plan
6. Approved Method Statement & site specific HSE Plan
7. TRANSCO Specification S-TR-CIVIL-OHL (Rev. 0-2009)
8. Standard drawing DWG TR CIV 11 04
9. Project specific cross section drawings of access road & tower platforms

7.0 Resources:

Equipment & Sign Boards Man Power (2 Teams)


➢ Dozer ➢ Foreman
➢ Vibratory roller ➢ Operators and Drivers
➢ Grader ➢ Technicians
➢ Excavator ➢ Surveyor and Aids
➢ Tipper trailers
➢ 6-wheeler trucks
➢ Mobile water tankers
➢ Shovel
➢ 4-wheel pick-up & mini-bus
➢ Warning Sign boards

8.0 Sequence of work for Construction Access Road:

➢ Construction Access roads shall be constructed as per the Site requirement. And for
sharing of the existing access roads shall be coordinated with all the concerned
stakeholders.

9.0 Sequence of work for Tower stabilization layer platform:

➢ Gatch from approved source should be taken & the following tests are to be carried out
as per the requirements of TRANSCO specifications:
1. Particle Size Distribution/ Sieve Analysis
2. Atterberg Limits (Liquid limit, Plastic limit and Plasticity index)
3. Optimum Moisture content and Dry Density (Proctor Test),
4. California Bearing Ratio (CBR)
5. Acid Soluble Chloride Content,
6. Acid Soluble Sulphate Content

➢ The gatch to be piled-up and stocked ready to be shifted by Shovels at the Tower
locations under the existing Overhead lines.

➢ Material to be used for stabilising layers platforms shall be well graded granular material
& It shall be free from contamination.

➢ The surveyor shall set out the centre of the platforms and transfer the reduced level (RL)
of the centre peg to a suitable distance outside the size of platform and working area of
the machines for future reference. The required platform dimensions are then marked.

➢ The height of stabilization in each section shall be decided by Client /Consultant based
on actual site conditions and approved profile.

Page 4 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD

➢ The existing ground at the platforms shall then be prepared for receiving further fill by
levelling the ground by means of a shovel/ dozer and compacted using vibrating roller in
suitable layers not exceeding 25cm compacted thickness and shall be compacted in
layers up to required thickness level for the platforms.

➢ Suitable work platform shall be made for feasibility of positioning the stringing equipment
and erection of tower according to the type of tower. Platform shall be at least extending
5.0m beyond the foundation edges.

➢ The final thickness of platform should be as per the approved drawing and specification.
However, the thickness can be increased after written approval from Client/ Consultant
and as per approved profile.

➢ Compaction test shall be done at one place for every tower platform by approved third
party laboratory as per specification and the test reports shall be submitted for approval.

10.0 Main Hazards

Hazards identified:
a. Movement of Vehicles including reversing
b. Severe weather conditions
c. Gatch transportation and unloading
d. Filing sand, gatch and levelling & compaction
e. Crossing the existing tracks/roads
f. Demobilization
g. Plant and Machinery
h. Handling of all Irrelevant/ Non-complying tools/ equipment/ materials
i. Working near existing OHL lines
j. Working near existing Gas & Oil pipelines

Further reference is made to Annexure 2 for the identification of hazards and risk
assessment.

11.0 Control Measures:

For the control measures please refer to the task based risk assessment which is
enclosed in Annexure 2.

Specific control measures for the work location include:

• All drivers and Operators to be fully familiarized about the safety rules.

• Tool Box talk to be conducted at site before starting of work.

• Regularly check up of vehicles.

• Provide high visible jacket to all persons.

• Sign boards and demarcation of working area.

Page 5 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD

12.0 Safety Measures to be Implemented

➢ Standard Personal Protective Equipment will be worn at all time and will include the
following:
1. Safety Helmet
2. High Visibility Jacket
3. Coveralls
4. Safety shoes
5. Safety goggles – when required
6. Safety gloves
7. Dust masks – when required
8. Ear plugs – when required

➢ All drivers and operators will have UAE valid Driving license.

➢ All the machinery should have valid documents & Insurance.

➢ Vehicles and heavy equipments shall be inspected by Safety Engineer prior to start of
work.

➢ Adequate markers shall be erected wherever required at critical areas with


flags/signboards to indicate the edges of access roads and platforms for the overall
safety of all vehicular movements during the progress of work.

➢ Vehicular movements at the working areas and access points are to be controlled
properly.

➢ Tool Box talks will be conducted daily and will include topics of relevant activity and
about health, environment & safety. Documents shall be maintained and issues
discussed shall be recorded.

➢ Work area shall be clearly demarcated and barricaded.

➢ First Aid kit shall be provided at site.

➢ During site works, Safety Engineer shall visit the site regularly.

➢ Good housekeeping shall be maintained at all times.

➢ Safety clearance from overhead lines shall be maintained.

➢ Necessary safety sign boards and height warning gantries shall be installed while
working near live lines along the access roads.

13.0 Emergency Procedures / Contact Details

12.1 Inform Safety Department/ Call Operator – Dial 055-5656163 /02-6394886 by


any communication means giving following information:
13.1.1 Nature of incident

Page 6 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD

13.1.2 Location of incident


13.1.3 Name and employment number
12.2 Shut down all power operated equipments.
12.3 Switch off all electrical equipment/ connections before leaving the site.
12.4 Do not try to collect personnel belongings.
12.5 All personnel of affected area (other than those nominated for specific duties
during an emergency) must report to the assembly Area and wait for further
instruction.
12.6 Supervisory staff should remain in the areas till completion of evacuation to
ensure strict adherence of the instruction by Emergency Team.
12.7 All employees shall remain at the Assembly Area until further instructions are
given.

Procedures to be followed in the event of Traffic Accident:

A. If you are first to arrive on the scene of an accident:


1. Inform Safety Department/ Call Operator – Dial 055-5656163 /02-6394886 by any
communication means giving following information:
a) Nature of incident
b) Location of incident
c) Name and employment number
2. If safe to do so, turn off the engine of a crashed vehicle.
3. Make the area safe by putting safety cones, warning triangles etc.
4. Park your vehicle safely.
5. Assist any injured.
6. Wait for Emergency Team to arrive.

B. If you are involved in an accident:


1. Inform Safety Department/ Call Operator - Dial 055-5656163, 02/6394886 by any
communication means giving following information:
a) Nature of incident
b) Location of incident
c) Name and employment number
2. Remain at the scene of any road accident until police give permission to go.
3. Wait for Emergency Team to arrive

Note: - Do not handle the casualty if you are not sure/qualified, to avoid further damage to
the injured personnel.

C. Off – Site Hazardous Emergency: -


Off site Hazardous emergencies may include the following: -
1. Any off – Site fire likely to affect on – site operations.
2. Severe weather conditions are likely to affect on site operations.
3. Law enforcement emergency alert.
Employee must report any sighting of severe weather such as heavy winds, Rain flooding etc.
immediately. Please identify the condition, approximate speed and direction of the weather
patterns.

On Site Equipment: -
❖ Fire Fighting Equipment
❖ Emergency/ First Aid Equipment
❖ Emergency Rescue Kit.

Page 7 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD

D. Emergency Contact Telephone Numbers: -

RELEVANT AUTHORITY
CIVIL DEFENSE (FIRE) 997
TRAFFIC POLICE 999
AMBULANCE 998/999
TELEPHONE ENQUIRY 180/181
AHALIA HOSPITAL, MUSAFFAH 02-8119119
MAFRAQ HOSPITAL 02-5011111
CENTRAL HOSPITAL, ABU DHABI 02-6214666
Al Samha Healthcare Center 058-1783861
KEC INTERNATIONAL LTD.
KEC HEAD OFFICE, ABU DHABI 02-6394886
A.L.N. ACHARYULU –PROJECT MANAGER 050-6213208
P N PAL – CONSTRUCTION MANAGER 056-4804932
SURESH – COMPETENT PERSON 050-6137402
KOWSIGAN – HSE MANAGER 055-5656163
ANIL KURANE – SAFETY OFFICER 050-6152773
LIST OF FIRST AIDER
SURESH 050-6137402
ANIL KURANE 050-6152773
SIVAN 050-3746221

Page 8 of 8
Annexure 1

Site Responsibility Chart


ANNEXURE - 1

KEC International Ltd., UAE


CONTRACT NO. C0304 - CRCC/GTGC/JV/PD/0029: ETIHAD RAIL STAGE 2 PROJECT C0304-
PACKAGE 2B Design & Build Contract (Tarif-Seih Shuaib)

SITE RESPONSIBILITY CHART FOR CONSTRUCTION OF TOWER STABILIZATION LAYERS AND


CONSTRUCTION ACCESS ROADS

PROJECT MANAGER
A.L.N. Acharyulu
 050-6213208

HSE MANAGER CONSTRUCTION MANAGER


Kowsigan P.N. Pal
 055-5656163  056-4804932

HSE ENGINEER CIVIL ENGINEER/


Anil Kurne COMPETENT PERSON
 050-6152773 G. Suresh
 050-6137402

FOREMAN

Technicians &
Annexure 2

Task Based Risk Assessment


FORM: HSE-HS-29-F01 Revision No. : 0
HSE RISK ASSESSMENT Page No. : 01 of 04

Risk Evaluation Risk Evaluation


Additional Control Measures
Activity Hazard / Aspect Group Exposed Existing Control Measures (with existing CM) (with additional C M)
(If required)
P S R P S R
Task Vehicle Movement/ Transport
• Poor Visibility • All passengers on board to fasten seat belts. 3 2 6 • Implement the procedure 2 2 4
Construction of Access Road &
• Bad Road condition • Limit the number of passengers to be limited to the “Transport Management
Access Road and Platform
• Poor Vehicle condition number of serviceable seat belts. Plan”.
Platforms Construction Team
• Blind spots • Always engage 4-wheel drive. • All the access roads must
(10-15 persons)
• Maintain the tyre pressure as per the requirement. be designed to avoid
• Mobile phones not to be used while driving. reversing/blind spots.
• Night driving is prohibited. • Follow the Journey
• Speed limit in desert should not exceed 60 km/hr. Management system.
• Always drive within the speed limit, in desert < 60 km/hr
and on Black top < 100 km/hr.
• Flag poles shall be provided in vehicles.
• All drivers will have mobile phones.
• On the road crossings, banksman on either side of road
will be there.
• All vehicles and equipment to be fitted with reverse alarm.
• While working near LIVE OHL, safe work distance will be
9 metres as per TRANSCO guidelines.
• Severe Weather • Work to be stopped at a wind speed above 15 knots. 4 2 8 • In case of poor 4 1 4
Construction of Access Road &
Conditions • A system of convenient interval of work breaks to be visibility/sand storm/rain
Access Road and Platform
followed for the comfort of the technicians during peak etc., job to be stopped.
Platforms Construction Team
summer. • Ensure enough drinking
(10-15 persons)
• Welfare facilities are to be properly available during all water and electrolyte
along the period of performing the job. solution is present at site.
• Ensure shade for adequate rest.
• All necessary refreshments are to be provided at the
location & closely supervised.
Task Gatch Transport
• Improper • Traffic rules for Fog/low visibility to be followed. 3 2 6
Construction of Access Road &
loading/unloading • Short cut not allowed, only approved crossings to be used.
Access Road and Platform
• Poor condition of lifting • Gatch to be properly covered by appropriate
Platforms Construction Team
equipment cover/tarpaulin while being transported.
(10-15 persons)
• Over speeding of Vehicles • ROW procedures/checklists developed and distributed by
• Tyre puncture TRANSCO to be followed while making ROW.
• Exceeding vehicle load • Identify the route and in case of any O/H line crossing,
capacity TRANSCO approval to be taken and safety measures
such as goal post erection to be done on the crossing
points.
• While working near Live OHL, safe work distance will be 9
meters as per TRANSCO guidelines.
Task Filling sand, Gatch and Levelling & Compaction
FORM: HSE-HS-29-F01 Revision No. : 0
HSE RISK ASSESSMENT Page No. : 02 of 04

• Poor condition of Vehicles. • While 1st layer of Gatch filling, always maintain safe 2 3 6 • Competency of operators 1 2 2
Construction of Access Road &
• Incompetent operators distance for dump truck from existing flow line. to be ensured before
Access Road and Platform
• Incompetent Supervision • Never start compaction until minimum filling thickness has deputing on site.
Platforms Construction Team
• Underground services been met as per specifications. • Supervisors to impart Tool
(10-15 persons)
• Depute banksman. Box Talk before
• Obtain work permit prior to work commencement. commencing job.
• While working near Live OHL, safe work distance will be 9 • Ensure barrication and
meters as per TRANSCO guidelines. safety signages in place
• Proper supervision of the job. for the activities.
• ROW procedures/checklists developed by TRANSCO to
be followed while making ROW.
• TRANSCO safe working clearance must be followed while
working near Live OHL
Task Working with Plant and Machinery
• Slip/Trip/Fall due to • All plant machinery to be inspected and serviced regularly. 3 2 6 • Reporting of all near miss 2 2 4
Construction of Access Road &
manual handling • A maintenance and service schedule is to be established and UA/UC
Access Road and Platform
• Lack of training in handling and implemented. • Conduct Slip/Trip/Fall
Platforms Construction Team
plant & machinery
(10-15 persons) • Use of proper PPE. Awareness training
• Lack of PPE • Training in manual handling of machinery and plant. • PPE compliance to be
• Proper supervision must be done by supervisors. ensured at site.
• Provision of First Aid must be available on site at all time.
• Always maintain good housekeeping on site.
• While working near Live OHL, safe work distance will be 9
meters as per TRANSCO guidelines.
• Handling of all • Before lifting operation, supervisor must inspect all lifting 2 2 4
Construction of Access Road &
irrelevant/Non complying gear, lifting colour code and damage; defective lifting
Access Road and Platform
tools/equipment/materials gears must be disposed off or delivered to store for
Platforms Construction Team
maintenance.
(10-15 persons)
• All lifting gears must be properly controlled, colour coded,
inspected at store before being in use for lifting operation
at site level.
• All lifting equipment is to be certificated and inspected
regularly as per TRANSCO procedure.
• Lifting equipment carrying capacity to be maintained.
• All lifting equipment to be inspected by Safety Engineer
before start of Work activity.
• A maintenance and service scheduled is to be established
and implemented for all lifting gears.
Task Crossing the existing tracks/roads
• Encountering blind spots Operational Controls 3 2 6
Access Road &
Construction of • Unsafe driving • Prepare a Traffic & Transport Management
Access Road and Platform
• Lack of proper signboards Plan/procedure in compliance to OSHAD SF CoP 44 –
Platforms Construction Team
• Poor visibility Traffic Management & Logistics.
(10-15 persons)
• Bad Road condition
FORM: HSE-HS-29-F01 Revision No. : 0
HSE RISK ASSESSMENT Page No. : 03 of 04

• Poor vehicle condition. • All drivers to possess valid driving license & be trained in
off-road & defensive driving.
• All roads crossing point to be properly drawn and letter
submitted for road crossing at least 4 days in advance.
• Temporary diversions to be made appropriate sign board,
warning cones, flashing lights, flagman with reflective
jackets etc. to be positioned on the diversions.
• While working near Live OHL, safe work distance will be 9
meters as per TRANSCO guidelines.
Administrative Controls
• Provision of PPE – Ultraviolet sun glasses are to be used
to prevent stress on the eyes due to hot weather, Safety
helmet, coverall and safety shoe are mandatory.
FORM: HSE-HS-29-F01 Revision No. : 0
HSE RISK ASSESSMENT Page No. : 04 of 04
TYPICAL CLEARANCE DIAGRAM

EXISTING TOWER 1 EXISTING TOWER 2

OPGW

TOP CONDUCTOR

BOTTOM CONDUCTOR

> 8m
0.50 - 2.00

6
Construction Equipments ELEVATION VIEW
EX
No IT.
DI . 59 TW
SM R
AN TO B .
44
+5
00

TL E EX
ED
No IT.
DI . 58 TWR
44
+6
00
EX
EX SM T . IT
IT AN O B No . TW
No . TW TL E . 5 R.
. 6 R. 44
+7
00
ED 7
0
400KV D/C OHTL 2 CKTS ICAD -SHPS 1 & 2
10

44
+8
00
50

44
+9
00
10

400KV D/C OHTL 2 CKTS MOSG - WMZD & ASWG - WMZD

EX
EX
45
+0
No IT. T
EX
00

I EX DI . 72 WR I
No T. T No IT.
SM 69 . No T. T
. 7 WR T AN TO . 7 WR
27 .
1 Gatch Dumping Zone DI . 72 WR 45
+1 TL
ED BE
26 .
8
00

SM 72 .
AN TO
TL
ED BE
PLAN VIEW
All Dimensions are in meter.