Approved MS&TRA For Platform Works
Approved MS&TRA For Platform Works
Approved MS&TRA For Platform Works
Not Subject to
RET=
Approval
Comments:
S.No Comments
Nil
Signed Received
GOPA-intec KEC
Note: The above comments and/or approval do not relieve the OHL Contractor from the obligation in the Contract to ensure
conformance to the Specifications. Any Specification deviations found subsequent to approval are to be corrected by the OHL
Contractor to the satisfaction of the TRANSCO/JV/Engineer.
CS DTS-004.Rev.A Page 1 of 1 20 Jun. 20
REGIONAL OFFICE :
P.O.BOX 27830, ABU DHABI, UAE.
TEL. 02 6394886 FAX 02 6394887
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE 2B Design & Build Contract (Tarif-Seih DTS.
04A
Shuaib) NO.
Note:
Please return with approval Please confirm receipt One copy of each document returned
CONTRACTOR
KEC INTERNATIONAL LTD. GOPA Intec CRCC-GTGC JV
Project Manager
KEC International Ltd.
DOCUMENT DISTRIBUTION:-
1 x GOPA Intec - Abu Dhabi Office + 1 Soft copy 1 x KEC - Abu Dhabi Office
CLIENT
ENGINEER PMC
P.O.Box.
7497
CONTRACTOR'S JOINT VENTURE
SUB CONTRACTOR
P.O Box 27830, Abu Dhabi
United Arab Emirates
Tel: +971 2 6394886
Fax: +971 2 6394887
PROJECT
DRAWN
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
CHECKED SHUBHAM 4-Mar-20 STABILIZATION LAYERS AND CONSTRUCTION ACCESS
ROADS
APPROVED ALN 4-Mar-20
SHEET SIZE
FILE : REV. 01
CLARIFICATION SHEET
DTS TITLE:
METHOD STATEMENT FOR CONSTRUCTION OF TOWER STABILIZATION LAYERS AND CONSTRUCTION ACCESS ROADS
STATUS: “AEN”
Page 1 / 1
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD
CLIENT : CRCC-GTGC JV
Page 1 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD
Under the subject Contract, the Contractor needs to construct the Tower Stabilization
Platform of thickness as per the approved profile but a minimum of 0.5m for each New
Tower & Gantry as per the TRANSCO specification S-TR-CIVIL-OHL (Rev.0-2009).
The purpose of this Method Statement is to describe the methodology involved for
construction of Tower Stabilization Platform and refurbishment of existing Construction
Access Road.
Construction Access Road does not require any Specification & should be constructed
as per the Site requirement.
Refurbishment of Construction Access Road is planned to start from the end of May’20
& construction of Tower Stabilization Platforms is scheduled to start from Jun’20. Both of
these activities are scheduled to finish within 1st week of Aug’20. This depends on the
route approvals & work front availability.
3.0 Terminology:
2.2 Danger
A risk for Human Health, Property & Environmental Damage.
2.6 Supervision
The control and direction exercised by a Competent Person who is present at the
point of work at all times during the progress of the work.
Page 2 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD
• Project Manager:
Overall control and Project Management of all activities at Project level. Distribution
of resources & finance. Review and implement procedure for meeting statutory and
quality requirements. Co-ordination with project co-ordinators and customer/
consultant/ sub-contractors/ sub-vendors/ local statuary bodies at the Project level
and shall have the final responsibility on HSE.
• Construction Manager:
For ensuring all the activities are undertaken and constructed as per the drawings,
coordinate for necessary work permits, all approved QC requirements are met by the
construction team and ensure that all necessary resources are available to meet the
schedule targets.
• Safety Officer:
For ensuring all the activities are undertaken and constructed in a safe manner as
per the approved Method Statement, Risk Assessment & HSE Manual.
• Site Coordinator
For liaising with related authorities for obtaining permission for smooth functioning of
project and facilitate site team.
• Site Engineer:
For ensuring that all the works are executed meeting HSE & QC requirements,
allotment and supervision works to individual groups, conduct Tool Box Talks, Guide
and Monitor the work force for progress, report to the Construction Manager on
regular basis.
Page 3 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD
7.0 Resources:
➢ Construction Access roads shall be constructed as per the Site requirement. And for
sharing of the existing access roads shall be coordinated with all the concerned
stakeholders.
➢ Gatch from approved source should be taken & the following tests are to be carried out
as per the requirements of TRANSCO specifications:
1. Particle Size Distribution/ Sieve Analysis
2. Atterberg Limits (Liquid limit, Plastic limit and Plasticity index)
3. Optimum Moisture content and Dry Density (Proctor Test),
4. California Bearing Ratio (CBR)
5. Acid Soluble Chloride Content,
6. Acid Soluble Sulphate Content
➢ The gatch to be piled-up and stocked ready to be shifted by Shovels at the Tower
locations under the existing Overhead lines.
➢ Material to be used for stabilising layers platforms shall be well graded granular material
& It shall be free from contamination.
➢ The surveyor shall set out the centre of the platforms and transfer the reduced level (RL)
of the centre peg to a suitable distance outside the size of platform and working area of
the machines for future reference. The required platform dimensions are then marked.
➢ The height of stabilization in each section shall be decided by Client /Consultant based
on actual site conditions and approved profile.
Page 4 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD
➢ The existing ground at the platforms shall then be prepared for receiving further fill by
levelling the ground by means of a shovel/ dozer and compacted using vibrating roller in
suitable layers not exceeding 25cm compacted thickness and shall be compacted in
layers up to required thickness level for the platforms.
➢ Suitable work platform shall be made for feasibility of positioning the stringing equipment
and erection of tower according to the type of tower. Platform shall be at least extending
5.0m beyond the foundation edges.
➢ The final thickness of platform should be as per the approved drawing and specification.
However, the thickness can be increased after written approval from Client/ Consultant
and as per approved profile.
➢ Compaction test shall be done at one place for every tower platform by approved third
party laboratory as per specification and the test reports shall be submitted for approval.
Hazards identified:
a. Movement of Vehicles including reversing
b. Severe weather conditions
c. Gatch transportation and unloading
d. Filing sand, gatch and levelling & compaction
e. Crossing the existing tracks/roads
f. Demobilization
g. Plant and Machinery
h. Handling of all Irrelevant/ Non-complying tools/ equipment/ materials
i. Working near existing OHL lines
j. Working near existing Gas & Oil pipelines
Further reference is made to Annexure 2 for the identification of hazards and risk
assessment.
For the control measures please refer to the task based risk assessment which is
enclosed in Annexure 2.
• All drivers and Operators to be fully familiarized about the safety rules.
Page 5 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD
➢ Standard Personal Protective Equipment will be worn at all time and will include the
following:
1. Safety Helmet
2. High Visibility Jacket
3. Coveralls
4. Safety shoes
5. Safety goggles – when required
6. Safety gloves
7. Dust masks – when required
8. Ear plugs – when required
➢ All drivers and operators will have UAE valid Driving license.
➢ Vehicles and heavy equipments shall be inspected by Safety Engineer prior to start of
work.
➢ Vehicular movements at the working areas and access points are to be controlled
properly.
➢ Tool Box talks will be conducted daily and will include topics of relevant activity and
about health, environment & safety. Documents shall be maintained and issues
discussed shall be recorded.
➢ During site works, Safety Engineer shall visit the site regularly.
➢ Necessary safety sign boards and height warning gantries shall be installed while
working near live lines along the access roads.
Page 6 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD
Note: - Do not handle the casualty if you are not sure/qualified, to avoid further damage to
the injured personnel.
On Site Equipment: -
❖ Fire Fighting Equipment
❖ Emergency/ First Aid Equipment
❖ Emergency Rescue Kit.
Page 7 of 8
CONTRACT No. C0304 - CRCC/GTGC/JV/PD/0029
ETIHAD RAIL STAGE 2 PROJECT C0304-PACKAGE
2B Design & Build Contract (Tarif-Seih Shuaib)
METHOD STATEMENT FOR CONSTRUCTION OF TOWER
STABILIZATION LAYERS & CONSTRUCTION ACCESS ROAD
RELEVANT AUTHORITY
CIVIL DEFENSE (FIRE) 997
TRAFFIC POLICE 999
AMBULANCE 998/999
TELEPHONE ENQUIRY 180/181
AHALIA HOSPITAL, MUSAFFAH 02-8119119
MAFRAQ HOSPITAL 02-5011111
CENTRAL HOSPITAL, ABU DHABI 02-6214666
Al Samha Healthcare Center 058-1783861
KEC INTERNATIONAL LTD.
KEC HEAD OFFICE, ABU DHABI 02-6394886
A.L.N. ACHARYULU –PROJECT MANAGER 050-6213208
P N PAL – CONSTRUCTION MANAGER 056-4804932
SURESH – COMPETENT PERSON 050-6137402
KOWSIGAN – HSE MANAGER 055-5656163
ANIL KURANE – SAFETY OFFICER 050-6152773
LIST OF FIRST AIDER
SURESH 050-6137402
ANIL KURANE 050-6152773
SIVAN 050-3746221
Page 8 of 8
Annexure 1
PROJECT MANAGER
A.L.N. Acharyulu
050-6213208
FOREMAN
Technicians &
Annexure 2
• Poor condition of Vehicles. • While 1st layer of Gatch filling, always maintain safe 2 3 6 • Competency of operators 1 2 2
Construction of Access Road &
• Incompetent operators distance for dump truck from existing flow line. to be ensured before
Access Road and Platform
• Incompetent Supervision • Never start compaction until minimum filling thickness has deputing on site.
Platforms Construction Team
• Underground services been met as per specifications. • Supervisors to impart Tool
(10-15 persons)
• Depute banksman. Box Talk before
• Obtain work permit prior to work commencement. commencing job.
• While working near Live OHL, safe work distance will be 9 • Ensure barrication and
meters as per TRANSCO guidelines. safety signages in place
• Proper supervision of the job. for the activities.
• ROW procedures/checklists developed by TRANSCO to
be followed while making ROW.
• TRANSCO safe working clearance must be followed while
working near Live OHL
Task Working with Plant and Machinery
• Slip/Trip/Fall due to • All plant machinery to be inspected and serviced regularly. 3 2 6 • Reporting of all near miss 2 2 4
Construction of Access Road &
manual handling • A maintenance and service schedule is to be established and UA/UC
Access Road and Platform
• Lack of training in handling and implemented. • Conduct Slip/Trip/Fall
Platforms Construction Team
plant & machinery
(10-15 persons) • Use of proper PPE. Awareness training
• Lack of PPE • Training in manual handling of machinery and plant. • PPE compliance to be
• Proper supervision must be done by supervisors. ensured at site.
• Provision of First Aid must be available on site at all time.
• Always maintain good housekeeping on site.
• While working near Live OHL, safe work distance will be 9
meters as per TRANSCO guidelines.
• Handling of all • Before lifting operation, supervisor must inspect all lifting 2 2 4
Construction of Access Road &
irrelevant/Non complying gear, lifting colour code and damage; defective lifting
Access Road and Platform
tools/equipment/materials gears must be disposed off or delivered to store for
Platforms Construction Team
maintenance.
(10-15 persons)
• All lifting gears must be properly controlled, colour coded,
inspected at store before being in use for lifting operation
at site level.
• All lifting equipment is to be certificated and inspected
regularly as per TRANSCO procedure.
• Lifting equipment carrying capacity to be maintained.
• All lifting equipment to be inspected by Safety Engineer
before start of Work activity.
• A maintenance and service scheduled is to be established
and implemented for all lifting gears.
Task Crossing the existing tracks/roads
• Encountering blind spots Operational Controls 3 2 6
Access Road &
Construction of • Unsafe driving • Prepare a Traffic & Transport Management
Access Road and Platform
• Lack of proper signboards Plan/procedure in compliance to OSHAD SF CoP 44 –
Platforms Construction Team
• Poor visibility Traffic Management & Logistics.
(10-15 persons)
• Bad Road condition
FORM: HSE-HS-29-F01 Revision No. : 0
HSE RISK ASSESSMENT Page No. : 03 of 04
• Poor vehicle condition. • All drivers to possess valid driving license & be trained in
off-road & defensive driving.
• All roads crossing point to be properly drawn and letter
submitted for road crossing at least 4 days in advance.
• Temporary diversions to be made appropriate sign board,
warning cones, flashing lights, flagman with reflective
jackets etc. to be positioned on the diversions.
• While working near Live OHL, safe work distance will be 9
meters as per TRANSCO guidelines.
Administrative Controls
• Provision of PPE – Ultraviolet sun glasses are to be used
to prevent stress on the eyes due to hot weather, Safety
helmet, coverall and safety shoe are mandatory.
FORM: HSE-HS-29-F01 Revision No. : 0
HSE RISK ASSESSMENT Page No. : 04 of 04
TYPICAL CLEARANCE DIAGRAM
OPGW
TOP CONDUCTOR
BOTTOM CONDUCTOR
> 8m
0.50 - 2.00
6
Construction Equipments ELEVATION VIEW
EX
No IT.
DI . 59 TW
SM R
AN TO B .
44
+5
00
TL E EX
ED
No IT.
DI . 58 TWR
44
+6
00
EX
EX SM T . IT
IT AN O B No . TW
No . TW TL E . 5 R.
. 6 R. 44
+7
00
ED 7
0
400KV D/C OHTL 2 CKTS ICAD -SHPS 1 & 2
10
44
+8
00
50
44
+9
00
10
EX
EX
45
+0
No IT. T
EX
00
I EX DI . 72 WR I
No T. T No IT.
SM 69 . No T. T
. 7 WR T AN TO . 7 WR
27 .
1 Gatch Dumping Zone DI . 72 WR 45
+1 TL
ED BE
26 .
8
00
SM 72 .
AN TO
TL
ED BE
PLAN VIEW
All Dimensions are in meter.