Cgk063-Rfa-mos-m-xxx - Soil & Waste Water Underground Pipe Installation (r.1)
Cgk063-Rfa-mos-m-xxx - Soil & Waste Water Underground Pipe Installation (r.1)
CGK 063
1.0 PURPOSE.......................................................................................................................................................
2.0 SCOPE OF WORK...........................................................................................................................................
3.0 DEFINATIONS................................................................................................................................................
4.0 REFERENCE....................................................................................................................................................
5.0 RESPONSIBILITIES.........................................................................................................................................
6.0 PROCEDURE..................................................................................................................................................
6.1 General Description...............................................................................................................................
6.2 Material..................................................................................................................................................
6.3 Plants, Machinery & Equipment............................................................................................................
6.4 Manpower..............................................................................................................................................
7.0 INSTALLATION UPVC & DICL PIPE PROCEDURES.........................................................................................
7.1 General Guidelines.................................................................................................................................
7.1.1 Pre-Planning Stage..................................................................................................................
7.2 The Process Installation Stage...............................................................................................................
7.2.1 uPVC & Fitting Storage at Site.................................................................................................
7.2.2 uPVC Installation Procedure...................................................................................................
7.2.3 Pipe in Sleeve (Wall)................................................................................................................
7.2.4 Pipe in Slab..............................................................................................................................
7.2.5 DICL Installation Procedure.....................................................................................................
7.2.6 Jointing for uPVC o DICL pipe..................................................................................................
7.2.7 Pipe Leakage Test....................................................................................................................
8.0 APPENDICES..................................................................................................................................................
8.1 Drawing..................................................................................................................................................
As Attached Drawing.............................................................................................................................
8.2 RISK ASSESSMENT (RA)..........................................................................................................................
8.3 INSPECTION TEST PLAN (ITP).................................................................................................................
8.3.1 CGK063-ITP-RFSI - Request for Site Inspection...............................................................................
8.3.2 CGK063-ITP-M.03 - Site General Report..........................................................................................
8.3.3 CGK063-ITP-M.04 - Site Defect Inspection Report..........................................................................
8.3.4 CGK063-ITP-M.01 - Floor Opening/ Pipa Sleeve Inspection Sheet .................................................
8.3.5 CGK063-ITP-M.40 - Drainage & Sewerage Pipe Water Leakage Test .............................................
8.3.6 CGK063-ITP-M.13 - Piping Installation Checklist.............................................................................
8.3.7 CGK063-ITP-M.33 - Undergroung Piping Inspection Test Report...................................................
8.3.8 CGK063-ITP-M.43 – Internal Drainage Flow Inspection Test Report..............................................
1.0 PURPOSE
The purpose of this statement is to document the correct procedure and installation of
soils & waste water underground pipe installation for CGK 063 project, and to ensure
that all concerned are familiar with the sequence of activities, utilization of resources
and execution of the works in compliance with applicable safety, quality procedures
and project documents and specification.
3.0 DEFINATIONS
Terms Definition
Project CGK 063
JO PT Jaya Obayashi
MOS Method of Statement
MSA Material Submission Approval
Table 1: Definitions
4.0 REFERENCE
The following Standards of Practice shall be applicable to the works:
SNI 8153:2015 : System plumbing pada bangunan Gedung (Plumbing
System in Building).
SNI 7511:2011 : The Procedure for Installing Transmission Pipes and
Distribution Pipes and Pipe Crossing Buildings.
SNI 03-1745-2000 : Concerning procedures for planning and installing vertical
pipe systems and hoses for the prevention of fire hazards in
buildings
BS 3974-2 : Specification Pipe Support, Pipe Clamps, Cages, Cantilevers &
Attachment to beams.
BSEN 545 : Ductile Iron Pipe, Fittings, Accessories and their joints for
water pipelines
5.0 RESPONSIBILITIES
No Designation Qty Responsibility
.
1 Project Manager 1 Responsible for overall commercial, contractual
& technical performances associated with
specific project. Reporting to the Project
Director.
2 M&E Engineer 4 Planning and supervising installation activities.
3 QA / QC Engineer 2 Inspect, verify, and prepare work statement for a
quality installation works. Material storage, fit
for use tools and equipment, and installation
works
4 Safety Officer 1 To provide toolbox and guidance to work and to
ensure that work is carried out in a safe manner.
5 Supervisor 3-5 Obtain permit to work, control the sequence
according to MOS, approved shop drawings, and
MSA, ensure mechanical aspects of the work are
according to the specifications, ensure safe
practices are followed and ensure quality of
workmanships during execution. Ensure material
temporary storage and protection meet vendor
and standards requirement
No Designation Qty Responsibility
.
. Ensure tools being used for installation are
calibrated and meet vendor and standards
requirement
6 General Workers 10-15 To carry out all the mechanical aspects of soil &
waste water pipe underground installation.
6.0 PROCEDURE
6.1 General Description
The mechanical work for underground soils & waste water pipe installation to
be carried out in the CGK063 project.
6.2 Material
Materials are as below:
2 Paint brush
3 Sandpaper
4 Soft cloth
5 Pipe glue
6 Pencil / marker
Item Descriptions
7 Measuring tape
11 Spanners &Torque wrench
12 Clamps, Jointing Tackles, trimmers & heater plate
13 Thread machine
14 Weld machine
6.4 Manpower
The actual manpower of each type of installation may vary according to the site
condition and requirement.
All workers shall wear appropriate PPE (Hard Hat, Protective Boots, Goggles,
High Visibility Vest and Protective Gloves) and safety harness when working
above 2 meter in height.
For temporary storage on site, the ground should be level and free
from stones or sharp objects likely to damage the pipe. Carefully store
pipe in tapered stacks or cross stacks not more than 1 meter high.
Ensure pipes are not kept along access route and free from rubbish
and debris. Pipes must be stacked properly in a dry area and covered
until required for installation. Ensure pipes size and material used
comply to approved shop drawing and according to coordinated
routing. Ensure internal surface of pipes are clean. CGK063 project for
underground pipe installation plumbing works, air vent, sanitary
fixture installation pipe, waste installation & drain for air conditioning
installation.
Picture 2: The excavator underground pipe line & check the level pipe installation
After the excavation and check the level of the soil is complete,
Instal ground based for pipe installation with concrete and fill
separated part with sand.
Mark the pipe following the depth of the socket, then clean the
inside of the socket and pipe then coat it lubricant with adhesive.
Picture 4: Marking the pipe
Joint Position the pipes correctly, then connect the pipes until
they connect according to the marking. If the pipe size is more
than 4, join the pipe with the tackle.
Picture 7: Jointing pipe uPVC process
Picture 13: Install R-bar & marking the formwork for sleeve
Slope will be 1:100 for pipe size DN80 mm and above. Slope will be
1:50 for pipe size DN80 mm and below. Slope will be 1:100 for all Vent
Pipe. uPVC pipe connection to sanitary fixtures, vent pipes and
inspection chambers shall follow approved shop drawing.
Picture 17. Typical detail of waste for connection basin and floor trap connection
7.2.5 DICL Installation Procedure
Installation Procedure for assembly of push on joint (Comply to SNI
19-6782-2002/Procedure for Storage and Installation Iron Ductile
Pipe).
Jointing Instruction
Before assembling the joint, the spigot of the pipe and interior of
socket of the adjacent pipe should both be thoroughly cleaned.
Insertion of Gasket
The gasket should be wiped clean, flexed and then placed in the
socket with pipa leading. The groove in the gasket must be located
on the retaining bead in the socket, and the retaining heel of the
gasket firmly bedded in its seat. Ensure the gasket fits evenly
around the whole circumference, removing any bulges that
prevents the proper entry of the spigot end.
Picture 19. Sequence of installation for gasket
Process Lubrication
A thin film of lubricant is applied to the inside surface of the
gasket which will be in contact with the entering spigot. In
addition, a thin film of lubricant should be applied to the
outside surface of the spigot end.
Concrete support
Before the concrete haunching is carried out, the underground
pipe must be installed with a concrete support/ saddle block. The
details are in accordance with the approved shop drawing.
Plug low end of pipe main line by ball plug (see drawing detail how
to test - ball plug setting).
Pour the water into other side of the pipe main line and ensure
water visible at the top end of all branch line.
Mark inside pipe as water level indicator by pen and put the ball
on the water.
Check all connection and joints, after 30 minutes of holding.
Check water level which marked, if water level condition below
the indicator mark it is leak.
All leaks shall be repaired after draining of water by removal and
replacement of detective part.
Test shall be repeated after repaired.
Test is acceptable when no leaks are found.
Remove the test ball and draining the water.
Picture 29: Jointing Test Ball Plug Hose & Air Pump