Materials Testing Monitoring
Materials Testing Monitoring
Materials Testing Monitoring
Location: Golden Mile Business Park, Special Economic Zone, Governor's Drive, Carmona, Cavite
Owner: ON Semicon Philippines, Inc.
Subject: Materials Testing Monitoring Sheet - Concrete
COLUMN
No. of Sampling 7 Day Result (psi) (Passed
Design
Sample ID Supplier Structure Location Samples
Strength (psi) Date Time Date Tested
Taken
9:35am
C-1 Readycon Column 5000.0 At GL D/5, D/7. ELEV 1/10/2009
C = 92.50 1 NI
At GL E/5, E/7. ELEV 9:45am
D = 92.50 1 NI
At GL F/5, F/7. ELEV 10:00am
E = 92.50 1 NI
At GL B/5, D/7. ELEV 10:15am
F = 92.50 1 NI
LEGEND:
C - Column
F - Footing
FTB - Footing Tie Beam
B - Beams
G - Girder
C-1 - First pouring in certain structure
C-2 - Second pouring
N.I. - Not included
C-1A, C-1B - Representative sample ID
7 Day Result (psi) (Passed/Failed) 14 Day Result (psi) (Passed/Failed) 28 Day Result (psi) (Passed/Failed) Condition
Theoretical Actual Date Tested Theoretical Actual Date Tested Theoretical Actual Slump (in) Weather Sampling Curing Handling
Nominal S1 S2
Batch Number Delivery Date Grade (ksi) Length (m) No. of pieces unit weight Total Weight (kg) (Frequency = 3 samples / 5 tons)
Dia (mm)
1.0 10/8/2009 28 60
LEGEND:
60.00 28 60.00