TD Comentation India Limited
MODIFICATION AND REFURBISHMENT OF TERMINAL -| adani
2 BUILDING AT SARDAR VALLABHBHAL PATEL
INTERNATIONAL AIRPORT AHMEDABAD.
IED THLE-PM-003,REV: 00
FORMAT NO: AIAL-ITD-CIVIL-FW-VITRIFU
CHECK LIST FOR FLOORING WORK
Vitrified Tile Work
| BRU Aras Drawing No.
Jerianos CB/L 40 CH/L
NOTE: Pls tik (¥) mark appropriate box anor gv lanicaton in Remark clu if egies
To be Checked MEP Clearance
Served Goer Boor Ware ae,
Gna ef Cee Ge =
Bosom REC Sib tel By ees
es
Top Screed Floor level
ey
is all the materials 1 be used are approved?
No
JAre the complete clearances received i fi
Ar the complete ved respect of plumbing, lst
fittings, chipping if required for | tiling or others from concerned agency”
Surface Preparation (As per Methodology)
[Check no diffrence in colour, crack, stain and chipped off deected
Tiles to be soaked before laying
Check the average Thickness of moran Gemeni:d soar sand) 40mm oF
[Check the thickness of Adhesive
[Check the level of floor before laying
[Check the level of floor after laying.
[Check the verticality of wall
[Check the joint portion properly levelled or not
|Check the joint thickness as per specifications or not
[Curing ~ floor shall be kept wet minimum period of 7 days
Checked by
ITD Cem
= Eman
“
Signature
Date