Professional Documents
Culture Documents
Epm Presentation
Epm Presentation
Epm Presentation
REVIEW AND
CONTROL
BY: MONIKA DOBRIYAL
PROJECT CONTROL : INTRODUCTION
Project controls are processes for gathering and analyzing project data
to keep costs and schedules on track. The functions of project controls
include initiating, planning, monitoring and controlling, communicating,
and closing out project costs and schedule. Ultimately, project controls
are iterative processes for measuring project status, forecasting likely
outcomes based on those measurements and then improving project
performance if those projected outcomes are unacceptable.
FUNCTIONS OF PROJECT CONTROL
Apart from above Providing the information about the various activities of the project to the team members.
mentioned Assisting in the process of Project planning/ Control sessions.
primary functions, Formulating the project Schedule and work breakdown structure.
it also includes
some functions of Tracking and analysing project costs.
secondary nature: Documenting and Delivering Project status Information.
The project control process involves five phases:
1. Initiating a project
2. Controlling a stage
4. Managing change
PROJECT 5. Closing a project
CONTROL
PROCESS
1.Initiating a project: The primary task of project manager is to ensure that the scope of the project should
be decided before starting the initial stage. It is a critical stage and basically comprises of three main
activities:
a) Accepting the project
b) Preparation for the first stage
c) Seeking authority to proceed
2.Controlling a stage: In this step it is ensured that the project should be planned on day to day basis which
includes delivering the products, monitoring the progress, managing all the risk and risky tasks etc.
3.Managing stage boundaries: It is a mid way approach which not only reviews the current stage but also
confirms that it is completed as per specifications and proper planning has been done for the next stage.
4.Managing change: In this phase, the ongoing changes of the project are properly managed and
controlled in a systematic manner.
Change can take place at any moment of time and from any side but the things to be kept in mind are;
(a) Change should be captured at early stages and must be assessed properly.
(b) Changes should be accepted or not should always depend upon the time and circumstances.
PROJECT REVIEW : INTRODUCTION
2. Payback Period: It is an important method to determine whether the project should be undertaken or not. It
is the length of time required to pay for the project.
Payback period = Cost of Project
Annual cash Inflows
In this, the individual investments are ranked according to their relative payback period.
3. Benefit Cost Ratio: Benefit cost ratio (BCR) is the ratio of present worth of benefits to present worth of cost. It
takes into account the proportion of monetary gain which is realized by performing a project versus the
amount spent on the project to execute the same.
Benefit Cost Ratio = Sum of present worth of benefits
Sum of present worth of cost
4. Net Present Value: NPV of a project includes comparing the present amount invested with that of present
value of future cash receipts from the investment. It is the present value of net cash including salvage value
and excluding the amount of initial investment of the project.
NPV = Present value of benefits - Present value of cost
5. Internal Rate of Return: It is the discount rate used for project evaluation in capital budgeting that makes the
net present value of all cash flows from a particular project equal to zero. Higher the IRR of project the more
desirable it is to undertake the same. In case more than one project is there then the project with the highest
IRR would probably be considered the best and undertaken first.
IRR = ∑$!"# (Bn-Cn) / (1 + i)" = i.e. NVP = 0