Professional Documents
Culture Documents
Kunzvi Dam Report
Kunzvi Dam Report
COURSE: HYDRAULICS
LEVEL: 5.2
Introduction
On the 13th of September 2022, The University of Zimbabwe was represented by The Chairman
of the Civil and the Built Environment Eng. Shumba, the department is represented by Dr. Mhizha,
Dr. Misi, Miss Nyakutsikwa, Miss Kutekwa, Mrs. Madamombe, and the final year students’ body
visited the Kunzvi Dam construction site.
Engineer: ZINWA
Main Dam
The embankment has a central impervious core and a one (1) meter wide Chimney drain. The core
is supported by the pervious fill zones on both upstream and downstream faces. The upstream at a
slope of 1:2.5 is protected by a 1.5m wide rip-rap and downstream by a 1m wide rip-rap. The
Downstream rock toe is incorporated to assist in drainage.
Intake tower
a hexagonal structure enclosing 2 x 100mm diameter vertical steel pipes. Draw-off points are at
various levels in the reservoir. The lowest drain-off points are at level 1194m comprising of two
1m diameter pipes for the Rip drain Downstream users. The sliding Gates will be operated from
the Tower House.
A 384.5m long by 5.4m wide x 5.1m high structure leads from the intake tower to the valve house.
It carries 2 x 1000mm diameter and 1 x 400mm diameter steel pipes. It provides access from the
valve house to the intake tower.
Valve house
houses 400mm diameter butterfly valve inserted before the discharge valve.
Spillway
It is a 100mm long ogee overflow section on the extreme left bank of the dam embankment with
a concrete-lined return channel. It shall be capable of passing the maximum probable flood.
(1:10000yr) without overtopping and shall pass the 200-year flood with the dry freeboard.
1. Year 1- commence excavation of left and right bank cut-off followed closely by grouting
operations and possibly backfilling.
2. Year 2- Construction work to concentrate on the River Bed cut-off, excavation, grouting,
and backfilling to, at the minimum, ground levels and let the coming wet season flood pass
over.
3. Year 3- river bed area is expected to be raised to the crest level
NB. The above-mentioned operations are those critical per year but other operations e.g. Rip-Rap
placing of upstream and downstream faces. Rockfill placing would be done concurrently with
critical areas operations.
Challenges
1. The challenges faced at hand include an old river bed that had not been anticipated which
is delaying the project because the sand silt material needs to be completely excavated to
improve the stability of the foundation.
2. Resettlement of the residents occupying the anticipated dam area may take time hence
delaying the project and date and may eventually result in increasing the project budget.
SHEQ REPORT
1. There is a boom gate at the entrance of the site separating the locals from the site
2. During blasting adequate warning signs are placed on site
3. The contractor employed a she officer to ensure safe working conditions to the employees
and to ensure the public do not enter prohibited zones
4. The site office is properly established with proper fencing