APPENDIX B: SSHE CONTRACT RISK ASSESSMENT

COMPANY has made a listing of expected activities, related hazards, initial risk level, and control & recovery requirement for contract in the below table. CONTRACTOR
shall review the listing of activities, based on the information provided in the Contract Scope of Works and the SSHE Contract Requirement for completeness and shall
highlight where CONTRACTOR has specific procedures for managing the risks.

Remark: C = CONTRACTOR and SC = SUB-CONTRACTOR

Carried Risk Assessment Level


out by: (Initial Risk Level)

Key Activity Associated Hazards Control and Recovery Requirements

Environment

Reputation
People

Assets
C or SC

• Defensive driving certificate


Mobilization resources i.e. worker, C 8. Dynamic situation hazards: car or 4,C 1,C 1,C 3,C
• Valid driving license (type#4)
machine, etc. via land transportation truck crash/accident
• Speed limit and safety belt
Free Text is acceptable • Journey Management Plan
• Left hand drive vehicle only
• Heavy machinery operating license
Heavy machinery working i.e. compactor, C 8. Dynamic situation hazards: car or 5,C 1,C 1,C 1B
• Heavy machinery safety training
Backhoe loaders and excavators and etc. truck crash/accident
• Inspection of machinery
Free Text is acceptable • JSA and Toolbox Talk
• Barricade working area or control permission of
working area
Carried Risk Assessment Level
out by: (Initial Risk Level)

Key Activity Associated Hazards Control and Recovery Requirements

Environment

Reputation
People

Assets
C or SC

• Follow speed limits, Malaysia road regulations


Mob/De-Mob of service personnel and C Hazards: 4C 1C 1C 1C
and ZETO rules
equipment/valve
• Heavy traffic • Ensure vehicle is good condition
• Ensure only competence driver is in-charged
• Uneven road surface • Ensure manpower is fit and healthy to drive
Consequences:
• Road accident
• Personnel injury
• Work delay

• Correct body posture
Site Preparation C Hazards: 4C 1C 1C 2C
• Ensure erection of the scaffolding is tightened
• Falling object well
• Ensure enough manpower to carry / lift
• Heavy equipment/tools equipment / tools with correct weight
• High Pressure distribution
• Ensure only competence person is allowed to
Consequences: conduct equipment setting and to follow
equipment's manual
• Personnel Injury
• Wear proper PPE i.e. safety boots, hand
gloves, safety glass & ear plug (if required)
• Bunker preparation for high pressure test
Carried Risk Assessment Level
out by: (Initial Risk Level)

Key Activity Associated Hazards Control and Recovery Requirements

Environment

Reputation
People

Assets
C or SC

• To purge the valve to ensure no contaminated


Dismantle, service and installation of the C Physical Hazards: 4C 1C 1C 2C
medium in the valve
components related to valve
• Improper in preparation of • To ensure WD-40 applied to the point by using
tools long spray tube during cleaning activity
• Correct body posture
• Incorrect body posture • Ensure enough manpower to carry / lift
• Falling object equipment correct size crane is used/ tools
with correct weight distribution
• Heavy equipment/tools • Ensure only competence person is allowed to
conduct equipment setting and to follow
• High gas trap pressure
equipment's manual
contains from tubing’s and
fittings upon dismantle. • Wear proper PPE i.e. safety boots, protective
gloves & safety glass
• Contaminated product • Wash hands thoroughly after handling
service in the valve chemical substances
• To brief SDS
Consequences:
• Personnel Injury
Ergonomics Hazards:
• Incorrect body posture
• Correct body posture
Testing of the valve (Functional/valve C Hazards: 4C 2C 1C 2C
• Wear proper PPE i.e. safety boots, hand
Hydrotest)
• Incorrect body posture gloves and safety glass
• Ensure enough manpower to conduct valve
• Sharp object stroking activity
• Falling object • Ensure all the tubing and fittings are tightened
well upon assembly.
• Use the right tools to assist valve stroking
activity
Carried Risk Assessment Level
out by: (Initial Risk Level)

Key Activity Associated Hazards Control and Recovery Requirements

Environment

Reputation
People

Assets
C or SC

• To follow procedure for valve stroking to avoid


• Explosion due to high stuck / supply interruption
pressure of the valve
• To ensure all the equipment are properly
testing
calibrated and have a valid calibration
Consequences: cert.(Pressure gauge etc.)
• Personnel Injury
• Items Damage
• Clear all tools and rubbish from working area
Housekeeping Hazards: 4C 1C 1C 1C
• Dispose rubbish into authorized rubbish
• Falling & sharp object disposal
• Correct body posture when doing the
• Heavy equipment/tools housekeeping
• Carry out housekeeping before, during and
after servicing work
Consequences: • To implement best practice on equipment /
• Personnel Injury tools
• handling & during manual lifting
• Ergonomic issue • Wear proper PPE i.e. safety boots, hand
gloves & safety glass
• To avoid manual lifting of heavy equipment
and to use lifting equipment / machine to avoid
major injury

Prepared By: Sepadu Tech Services Sdn Bhd Date: 14/09/21