Professional Documents
Culture Documents
AEE Merge
AEE Merge
E-mail: ahsanahmed@neduet.edu.pk
Consulting
Place: Mechanical Vibrations Lab
Course's
Title: Applied Economics For Engineers
Course's
Code: MF-303
2
Ahsan Ahmed 1
11/3/2020
Recommended Books
S.
BOOK Author Edition
No
William G. Sullivan, James A
1 Engineering Economy 14/15/16th
Bontadelli
Operation Research An
2 Hamdy A Taha 10th
Introduction
Leland Blank Anthony
3 Engineering Economy 8th
Tarquin
Eugene L. Grant, W. Grant
Principles of Engineering
4 Ireson, Richard S Leaven 9th
Economy
Worth
Engineering Econimics
5 Donald G. Newman 14th
Analysis
3
Ahsan Ahmed 2
11/3/2020
Economics
As a subdivision / discipline of social sciences, economics
deals with allocation or deallocation of resources which
seems to be limited and has alternatives to produce goods
and services which can satisfy human wants and desires
which seems to be unlimited.
Ahsan Ahmed 3
11/3/2020
Ahsan Ahmed 4
11/3/2020
2) Micro Economics:
As a sub-division of social science microeconomics deals with
economic behavior of firm and consumers as they go on
performing day to day activities like buying an selling.
10
Ahsan Ahmed 5
11/3/2020
11
Engineering Economics
Engineers use knowledge to find new ways of doing things
economically
Engineering economy is the dollars-and-cents side of the
decisions that engineers make or recommend as they work to
position a firm to be profitable in a highly competitive
marketplace.
Inherent to these decisions are trade-offs among different
types of costs and the performance (response time, safety,
weight, reliability, etc.) provided by the proposed design or
problem solution.
12
Ahsan Ahmed 6
11/3/2020
13
14
Ahsan Ahmed 7
11/3/2020
15
16
Ahsan Ahmed 8
11/3/2020
Law of Supply
When economists talk about supply, they mean the
amount of some good or service that is available to
consumers.
𝑆𝑢𝑝𝑝𝑙𝑦 = 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 − 𝑆𝑡𝑜𝑐𝑘
Price is what the producer receives for selling one unit of
a good or service.
Law of supply:
“Taking all other things constant,
if a prices of a commodity increases,
its supply also increases and vice versa.”
𝑃𝑟𝑖𝑐𝑒 ∝ 𝑆𝑢𝑝𝑝𝑙𝑦
17
Law of Supply
Supply Schedule (or Supply Curve ):
The supply schedule (or supply curve ) for a commodity shows
the relationship between its market price and the amount of
that commodity that producers are willing to produce and sell,
other things held constant.
The following table shows a hypothetical supply schedule for
cornflakes,
18
Ahsan Ahmed 9
11/3/2020
Law of Supply
The figure, at the right, plots the data from the below table in
the form of a supply curve.
19
Determinants of Supply
If Q= Quantity of Commodity, S= Supply, X= Our Commodity
and Y= Substitute Commodities. Then,
Variable
Constant
20
Ahsan Ahmed 10
11/3/2020
Determinants of Supply
𝒔𝒙 = 𝒙
𝒔𝒙 = 𝒚
,
Or vice versa
𝒔𝒙 = )
,
21
Determinants of Supply
𝒔𝒙 = ) …… (Cont.)
Technological advances, which consist of change that
lower the quantity of inputs needed to produce the same
quantity of output.
For example: It takes far fewer hours of labor to produce
an automobile today than it did just 10 years ago.
𝒔𝒙 = )
Usually, profit-maximization is the most fundamental
goal of a firm.
But modern business firms aim at maximization of sales
revenue (or capturing market share) rather than profit.
22
Ahsan Ahmed 11
11/3/2020
Determinants of Supply
𝒔𝒙 = ) …… (Cont.)
Usually, profit-maximization is the most fundamental
objective of a firm.
But modern business firms aim at maximization of sales
revenue (or capturing market share) rather than profit.
Supply of a commodity under these two broad objectives
is likely to be different.
Thus, the supply of a commodity depends on the goals
or objectives of a firm.
Changes in these objectives of the firms will lead to a
change in quantity supplied.
23
Determinants of Supply
𝒔𝒙 = )
Application of taxes will increase cost of the product
which will decrease profit and supply of the same
product. (e.g. Toyota Cars).
Subsidies (reliefs given by government to the company
to keep the price of a commodity low) decreases the cost
of the product which will increase profit and supply of
the same product. (e.g. Toyota Cars).
𝒔𝒙 = )
If input prices increases, so profit will decrease with
supply of product.
E.g electricity cost, material cost etc.
24
Ahsan Ahmed 12
11/3/2020
Determinants of Supply
𝒔𝒙 = )
Special influences affect the supply curve.
The weather exerts an important
influence on farming
and on the ski industry.
The computer industry has been marked
by a keen spirit of innovation, which has
led to a continuous flow of new products.
Market structure will affect supply, and
expectation about future prices often have
an important impact upon supply
decisions.
25
Shifts in Supply
When changes in factors other than a good’s own price affect
the quantity supplied, we call these changes shifts in supply.
Supply increases (or decreases) when the amount supplied
increases (or decreases) at each market price.
Constant
Variable
26
Ahsan Ahmed 13
11/3/2020
Shifts in Supply
When automobile prices change, producers change their
production and quantity supplied, but the supply and the
supply curve do not shift. By contrast, when other influences
affecting supply change, supply changes and the supply curve
shifts.
We can illustrate a shift in supply for the automobile market.
Supply would increase if the introduction of cost-saving
computerized design and manufacturing reduced the labor
required to produce cars, if autoworkers took a pay cut, if
there were lower production costs in Japan, or if the
government repealed environmental regulations on the
industry. Any of these elements would increase the supply of
automobiles in the United States at each price. The following
figure illustrates an increase in the supply of automobiles.
27
Shifts in Supply
28
Ahsan Ahmed 14
11/3/2020
Law of Demand
Economists use the term demand to refer to the amount
of some good or service consumers are willing and able to
purchase at each price.
Law of Demand:
“Taking all other things constant,
if a prices of a commodity increases,
its demand decreases and vice versa.”
1
𝑃𝑟𝑖𝑐𝑒 ∝
𝐷𝑒𝑚𝑎𝑛𝑑
29
Law of Demand
Demand Schedule (or Demand Curve ):
There exists a definite relationship between the market price of
a good and the quantity demanded of that good, other things
held constant. This relationship between price and quantity
bought is called the demand schedule, or the demand curve.
The following table shows a hypothetical demand schedule for
cornflakes,
30
Ahsan Ahmed 15
11/3/2020
Law of Demand
The figure, at the right, plots the data from the below table in
the form of a demand curve.
31
Determinants of Demand
If Q= Quantity of Commodity, D=Demand, X= Our
Commodity and Y= Substitute Commodities. Then,
Variable
Constant
32
Ahsan Ahmed 16
11/3/2020
Determinants of Demand
𝑫𝒙 = 𝒙
,
𝑫𝒙 = 𝒚
, ,
Or vice versa
𝑫𝒙 = )
Superior Product Inferior Product
Income , Q Income , Q
33
Determinants of Demand
𝑫𝒙 =
,
𝑫𝒙 =f(population)
,
𝑫𝒙 = )
Special influences will affect the demand for goods.
The demand for umbrellas is high in rainy Seattle but low in
sunny days.
The demand for air conditioners will rise in hot weather.
34
Ahsan Ahmed 17
11/3/2020
Shifts in Demand
Why does the demand curve shift? Because influences other
than the good’s price change.
Constant
Variable
35
Shifts in Demand
For Example: In 1990s, the income
of American rises which will rise the
sale of automobiles. So, that rise in
demand was not due to the price, but
it was due to the income rose.
Now answer the following:
Will a warm winter shift the demand
curve for warm clothes leftward or
rightward?
What will happen to the demand of
social media if young people lose their
interest in it?
What happens to the demand for a
college education if salaries for college-
educated workers are rising rapidly?
36
Ahsan Ahmed 18
11/3/2020
If 𝑸𝒔 = 𝟎,
Note:
𝑄 is always +ve.
i.e. Q > 0 P > c/d
38
Ahsan Ahmed 19
11/3/2020
If 𝑸𝑫 = 𝟎,
39
MARKET EQUILIBRIUM
The equilibrium price comes at the
intersection of the supply and
demand curves. There are no
surplus and shortage over this point.
At high prices: (𝑙𝑖𝑘𝑒 𝑃 ) Supply >
Demand means suppliers want to sell
more than demanders want to buy. The
result is a surplus, or excess of quantity
supplied over quantity demanded.
At low prices: (𝑙𝑖𝑘𝑒 𝑃 ) Demand > Supply means the demanders
want to buy more than suppliers want to sell. the market shows a
shortage, or lack of quantity supplied over quantity demanded.
Under this condition the competition among buyers for limited
goods causes the price to rise.
40
Ahsan Ahmed 20
11/3/2020
MARKET EQUILIBRIUM
The equilibrium price is a price at
which quantity demanded is equal to
the quantity supplied over the same
period.
At equilibrium point, there are no
shortages or surpluses; there is no
tendency for price to rise or fall,
means the forces of supply and
demand are in balance and the price
has settled at a sustainable level.
41
EQUILIBRIUM’s Mathematical
Representation
At equilibrium point,
42
Ahsan Ahmed 21
11/3/2020
EQUILIBRIUM’s Mathematical
Representation
For equilibrium quantity,
43
When the price elasticity of a good is high, we say that the good
has “elastic” demand, which means that its quantity demanded
responds greatly to price changes.
44
Ahsan Ahmed 22
11/3/2020
46
Ahsan Ahmed 23
11/3/2020
47
48
Ahsan Ahmed 24
11/3/2020
49
50
Ahsan Ahmed 25
11/3/2020
Market Structure
There are four basic types of market structure:
1) Perfect Competition
2) Monopoly
3) Monopolistic Competition
4) Oligopoly
51
Market Structure
1) Perfect Competition:
Perfect competition exists when there is a large number of
producers / firms producing homogenous products (i.e; product
with same quality). The maximum output which an individual
firm can produce is relatively very small to the total demand or
the industry product so that a firm cannot affect the price by
changing its supply of output.
Features:
Large number of buyers in the market and no individual
buyer can influence market demand.
52
Ahsan Ahmed 26
11/3/2020
Market Structure
1) Perfect Competition :(Cont.)
Homogeneous goods: Products are homogeneous in
nature. Same quality goods, but different brand name
53
Market Structure
2) Monopoly:
It is a market situation in which there are large number of
buyers but only one seller of the product. It is a situation in
which a seller of a product has no close substitute.
Example: K-electric
Features:
Large number of buyers in the market and no individual
buyer can influence market demand.
Only one seller : and whole market supply is fully
controlled
No close substitute
54
Ahsan Ahmed 27
11/3/2020
Market Structure
2) Monopoly: (Cont.)
Price discrimination : means charging different prices
from different customers for same product like k-electric
different per unit charges for different units consumed
Full restrictions: No entry of new firms
Imperfect knowledge: regarding prices
Price maker : Under monopoly , a firm is a price maker
and not price taker.
55
Market Structure
3) Monopolistic Competition:
It refers to a market situation in which there are many
producers producing goods which are close substitutes of one
another or where output is differentiated (differentiated may be
difference in quality or products for same purpose).
Features:
Large number of buyers in the market and no individual
buyer can influence market demand.
Large number of sellers and no individual seller can
influence market supply
Differentiated goods i.e; goods which differ in terms of
quality for e.g;; soaps and are also called product
differentiation.
56
Ahsan Ahmed 28
11/3/2020
Market Structure
3) Monopolistic Competition (Cont.):
Monopolistic competitive firms follow independent price
policies
Imperfect knowledge due to differentiated goods.
Selling cost : it includes all the expenses made to
increase the sale of the product i.e.; advertisement
Few restriction : Copy right , Patent right etc.
57
Market Structure
4) Oligopoly:
It is a market situation in which there are large number of
buyers but only few sellers of the product & they use their
market influence to set the prices and in turn maximize their
profits. e.g.; mobile companies , cigarette manufacture etc.
Features:
Large number of buyers in the market and no individual
buyer can influence market demand.
Few sellers of the product : Each seller partially controls
the market supply
Interdependence in decision making : If there is fall in
the price of one company’s product , it may lead to fall in
the price of other firms.
58
Ahsan Ahmed 29
11/3/2020
Market Structure
4) Oligopoly: (Cont.)
High barriers to enter : High investment is required
Huge advertisement expense
59
60
Ahsan Ahmed 30
11/3/2020
2) Partnership
Business where there are two or more owners of the enterprise.
ADVANTAGES
Synergy . There is clear potential for the enhancement of value
resulting from two or more individuals combining strength
Spreads the risk across more people, so if the business gets
into difficulty then there are more people to share the burden
of debt
61
Ahsan Ahmed 31
11/3/2020
3) Corporations:
A corporation is a legal entity doing business and is distinct from
the individuals within the entity. Public corporations are owned
by shareholders who elect a board of directors to oversee
primary responsibilities. Shareholders own company. Company
employs directors to control management of business. The
directors may also be shareholders (most are)/
63
3) Corporations:
A corporation is a legal entity doing business and is distinct from
the individuals within the entity. Public corporations are owned
by shareholders who elect a board of directors to oversee
primary responsibilities. Shareholders own company. Company
employs directors to control management of business. The
directors may also be shareholders (most are)/
64
Ahsan Ahmed 32
11/3/2020
65
DISADVANTAGES
Regulatory restrictions. Corporations are typically more closely
monitored by government agencies .Complying with
regulations can be costly
Higher organizational and operational cost
66
Ahsan Ahmed 33
11/12/2019
Introduction
The term capital refers to wealth in the form of money or
property that can be used to produce that can be used to
produce more wealth.
The majority of engineering economy studies involve
commitment of capital for extended periods of time, so the
effect of time must be considered.
In this regard, it is recognized that a dollar today is worth
more than a dollar one or more years from now because of the
interest (or profit) it can earn.
Therefore, money has a time value.
It has been said that often the riskiest thing a person can do
with money is nothing! Money has value, and if money
remains uninvested (like in a large bottle), value is lost.
1
Ahsan Ahmed 1
11/12/2019
Simple Interest
When the total interest earned or charged is linearly
proportional to the initial amount of the loan (principal), the
interest rate, and the number of interest periods for which the
principal is committed, the interest and interest rate are said
to be simple.
Simple interest is not used frequently in modern commercial
practice.
When simple interest is applicable, the total interest, I ,
earned or paid may be computed using the formula
𝐼= 𝑃 𝑁 𝑖
where P = principal amount lent or borrowed;
N = number of interest periods (e.g., years);
𝑖 = interest rate per interest period.
4
Ahsan Ahmed 2
11/12/2019
Simple Interest
The total amount repaid at the end of N interest periods is
P + I.
Thus, if $1,000 were loaned for three years at a simple
interest rate of 10% per year, the interest earned would be
𝐼 = $1,000 × 3 × 0.10 = $300
The total amount owed at the end of three years would be
$1,000 + $300 = $1,300.
Compound Interest
Whenever the interest charge for any interest period (a year,
for example) is based on the remaining principal amount plus
any accumulated interest charges up to the beginning of that
period, the interest is said to be compound.
Compound interest (or compounding interest) is interest
calculated on the initial principal, which also includes all of
the accumulated interest of previous periods of a deposit or
loan.
Compound interest is contrasted with simple interest, where
previously accumulated interest is not added to the principal
amount of the current period, so there is no compounding.
Ahsan Ahmed 3
11/12/2019
Compound Interest
The effect of compounding of interest can be seen in the
following table for $1,000 loaned for three periods at an
interest rate of 10% compounded each period:
Ahsan Ahmed 4
11/12/2019
10
Ahsan Ahmed 5
11/12/2019
12
Ahsan Ahmed 6
11/12/2019
13
14
Ahsan Ahmed 7
11/12/2019
Cash-Flow Diagramming
Q) Before evaluating the economic merits of a proposed
investment, the XYZ Corporation insists that its
engineers develop a cash-flow diagram of the proposal.
An investment of $10,000 can be made that will produce
uniform annual revenue of $5,310 for five years and then
have a market (recovery) value of $2,000 at the end of
year (EOY) five. Annual expenses will be $3,000 at the
end of each year for operating and maintaining the
project. Draw a cash-flow diagram for the five-year life of
the project. Use the corporation’s viewpoint.
15
Cash-Flow Diagramming
Ans)
16
Ahsan Ahmed 8
11/12/2019
17
18
Ahsan Ahmed 9
11/12/2019
19
20
Ahsan Ahmed 10
11/12/2019
21
22
Ahsan Ahmed 11
11/12/2019
23
24
Ahsan Ahmed 12
11/12/2019
Here, F = $10,000
N = 6 years
𝑖=8%
Therefore,
𝑃 = $10,000(1 + 0.08) 𝑃 = $10,000(𝑃/𝐹, 8%, 6)
𝑃 = $10,000 (0.6302) 𝑃 = $10,000 (0.6302)
𝑃 = $6,302 (Ans) 𝑃 = $6,302 (Ans)
25
26
Ahsan Ahmed 13
11/12/2019
27
28
Ahsan Ahmed 14
11/12/2019
log(2.1645)
𝑁= = 12.05 𝑦𝑒𝑎𝑟𝑠
log(1.0662)
So, if gasoline prices continue to increase at the same rate, we
can expect to be paying $5.00 per gallon in 2017.
29
Annuity
It is a series of equal amount of cashflows (receipt or payment)
after equal interval of time.
30
Ahsan Ahmed 15
11/12/2019
31
32
Ahsan Ahmed 16
11/12/2019
33
34
Ahsan Ahmed 17
11/12/2019
35
1
(1 + 𝑖) 1−
(1 + 𝑖)
𝐹=𝐴
(1 + 𝑖) 1
1−
(1 + 𝑖)
(1 + 𝑖) − 1
(1 + 𝑖) (1 + 𝑖)
𝐹=𝐴
(1 + 𝑖) (1 + 𝑖) − 1
(1 + 𝑖)
36
Ahsan Ahmed 18
11/12/2019
(1 + 𝑖) − 1
𝐹=𝐴
𝑖
( )
The quantity is called the uniform series compound
amount factor.
Numerical values for the uniform series compound amount
factor are given in the fourth column of the tables in Appendix
C for a wide range of values of 𝑖 and N. We shall use the
functional symbol (F/A, 𝑖%, N) for this factor.
Hence,
𝐹 = 𝐴(𝐹/𝐴, 𝑖% , N)
37
Ahsan Ahmed 19
11/12/2019
39
40
Ahsan Ahmed 20
11/12/2019
41
42
Ahsan Ahmed 21
11/12/2019
43
44
Ahsan Ahmed 22
11/12/2019
45
46
Ahsan Ahmed 23
11/12/2019
47
48
Ahsan Ahmed 24
11/12/2019
49
50
Ahsan Ahmed 25
11/12/2019
51
Solution:
The cash-flow diagram shown below is drawn from the viewpoint
of the bank. Notice that the present amount of $15,000 occurs
one month (interest period) before the first cash flow of the
uniform repayment series.
52
Ahsan Ahmed 26
11/12/2019
53
54
Ahsan Ahmed 27
11/12/2019
55
56
Ahsan Ahmed 28
11/12/2019
57
58
Ahsan Ahmed 29
11/12/2019
And,
59
60
Ahsan Ahmed 30
11/12/2019
61
62
Ahsan Ahmed 31
11/12/2019
63
64
Ahsan Ahmed 32
11/12/2019
9.8975
10.2598 9.8975
65
66
Ahsan Ahmed 33
11/12/2019
67
68
Ahsan Ahmed 34
11/12/2019
69
70
Ahsan Ahmed 35
11/12/2019
71
72
Ahsan Ahmed 36
11/12/2019
73
74
Ahsan Ahmed 37
11/12/2019
75
76
Ahsan Ahmed 38
11/12/2019
77
78
Ahsan Ahmed 39
11/12/2019
79
80
Ahsan Ahmed 40
11/12/2019
81
82
Ahsan Ahmed 41
11/12/2019
or
83
84
Ahsan Ahmed 42
11/12/2019
----(1)
( )
Since,
( ) ( )
∴𝑒𝑞(1)→
( ) ( )
86
Ahsan Ahmed 43
11/12/2019
87
Or
88
Ahsan Ahmed 44
11/12/2019
( )
89
90
Ahsan Ahmed 45
11/12/2019
91
92
Ahsan Ahmed 46
11/12/2019
93
94
Ahsan Ahmed 47
11/12/2019
96
Ahsan Ahmed 48
11/12/2019
97
98
Ahsan Ahmed 49
11/12/2019
99
100
Ahsan Ahmed 50
11/12/2019
101
102
Ahsan Ahmed 51
11/12/2019
103
104
Ahsan Ahmed 52
11/12/2019
105
106
Ahsan Ahmed 53
11/12/2019
107
108
Ahsan Ahmed 54
11/12/2019
109
110
Ahsan Ahmed 55
11/12/2019
Ahsan Ahmed 56
11/12/2019
113
114
Ahsan Ahmed 57
11/12/2019
115
Further Explanation
Consider a principal amount of $1,000 to be invested for three
years at a nominal rate of 12% compounded semiannually. The
interest earned during the first six months would be $1,000 ×
(0.12/2) = $60.
Total principal and interest at the beginning of the second six-
month period is P + Pi = $1,000 + $60 = $1,060.
The interest earned during the second six months would be
$1,060 × (0.12/2) = $63.60
Then total interest earned during the year is $60.00 + $63.60 =
$123.60
Finally, the effective annual interest rate for the entire year is
116
Ahsan Ahmed 58
11/12/2019
Further Explanation
2nd Method:
he relationship between effective interest, 𝑖 , and nominal
interest, r, is
117
Ahsan Ahmed 59
11/12/2019
119
120
Ahsan Ahmed 60
11/12/2019
121
122
Ahsan Ahmed 61
11/12/2019
Now,
123
2nd Method:
124
Ahsan Ahmed 62
11/12/2019
Solution:
r = 6% per year
t =1 year (assume)
m = 4 quarters (for 1 year) & m = 4 X 10 = 40 quarters(for ten
years)
𝑖 =?
F=?
125
Now,
126
Ahsan Ahmed 63
11/12/2019
2nd Method:
127
128
Ahsan Ahmed 64
11/12/2019
129
130
Ahsan Ahmed 65
11/12/2019
131
Solution:
132
Ahsan Ahmed 66
11/12/2019
𝑟
S. Nominal Rate r% m=CP /PP , for 𝑖 = 1+ −1
Bids 𝑚
No. for 6 months 6 months
for 6 months
3% per 0.06
quarter, 𝑟 = 3% / 𝑞𝑢𝑎𝑟𝑡𝑒𝑟 𝑋 2 2 𝑖 = 1+ −1
2 2
compounded r= 6% per 6 months 𝑚= =2
1 𝑖 = 6.09%
quarterly
134
Ahsan Ahmed 67
11/12/2019
𝑟
S. Nominal Rate r% m=CP for 1 𝒊𝒂 = 1 + −1
Bids 𝑚
No. for 1 year year
for 1 year
0.09
9% per year, 𝒊𝒂 = 1 + −1
𝑟 = 9% 4
1 compounded 𝑚=4
per year 𝒊𝒂 = 9.31%
quarterly
3% per 0.12
quarter, 𝑟 = 3% / 𝑞𝑢𝑎𝑟𝑡𝑒𝑟 𝑋 4 𝒊𝒂 = 1 + −1
2 𝑚=4 4
compounded r= 12% per year 𝒊𝒂 = 12.55%
quarterly
136
Ahsan Ahmed 68
11/12/2019
Solution:
Here r = 12% year & m = 2 (for six months)
For r%:
%
137
Solution:
𝐹 F F
𝐹 = 1000 , 6%, 10 × 2 + 3000 , 6%, 6 × 2 + 1500 , 6%, 4𝑋2
𝑃 P P
𝐹 = $11,634
138
Ahsan Ahmed 69
11/12/2019
139
140
Ahsan Ahmed 70
11/12/2019
For r:
r= 8% / 2 = 4% per 6 months
For m:
m=2 quarters per semiannual period
141
142
Ahsan Ahmed 71
11/12/2019
143
0.12
𝑖 = 1+ −1
4
𝑖 = 0.1255
We calculated annual interest to use formula for annuity
144
Ahsan Ahmed 72
11/12/2019
𝐹 = 1000 18.022
𝐹 = $18,022
145
Ahsan Ahmed 73
11/12/2019
147
148
Ahsan Ahmed 74
11/12/2019
149
150
Ahsan Ahmed 75
11/12/2019
F= $ -357,592
151
Financial Efficiency:
𝐼𝑛𝑐𝑜𝑚𝑒
𝐹𝑖𝑛𝑎𝑛𝑐𝑖𝑎𝑙 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 =
𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
152
Ahsan Ahmed 76
Evaluating a Single
Project+ Comparison &
Selection of Alternatives
Objective:
✓ to discuss and critique contemporary (modern/ current) methods for
determining project profitability.
✓ to compare capital investment alternatives when the time value of money
is a key influence.
By:
Ahsan Ahmed
(Lecturer, MED)
The Present Worth Method
▪ The PW method is based on the concept of equivalent worth of
all cash flows relative to some base or beginning point in time
called the present.
▪ That is, all cash inflows and outflows are discounted to the
present point in time at an interest rate that is generally the
MARR (Minimum Attractive Rate of Return), which is also
known as “hurdle rate” (minimum acceptable rate of return)
▪ A positive PW for an investment project is a dollar amount of
profit over the minimum amount required by investors.
▪ It is assumed that cash generated by the alternative is
available for other uses that earn interest at a rate equal to
the MARR.
Decision of PW Method?
▪ To apply the PW method of determining a project’s economic
worthiness, we simply compute the present equivalent of all
cash flows using the MARR as the interest rate. If the present
worth is greater than or equal to zero, the project is
acceptable.
Dependent Alternatives:
▪ Calculate PW of each alternative at the MARR.
▪ Select the alternative with the PW value i.e numerically
largest (i.e. less –ve and more +ve)
Independent Alternatives :
▪ For 1 or more independent projects, select all projects with
present worth greater or equal to zero 𝑃𝑊 ≥ 0 at the MARR
(i.e. interest 𝑖)
Project is economically justified?
Q)A piece of new equipment has been proposed by engineers to
increase the productivity of a certain manual welding
operation. The investment cost is $25,000, and the equipment
will have a market value of $5,000 at the end of a study period
of five years. Increased productivity attributable to the
equipment will amount to $8,000 per year after extra operating
costs have been subtracted from the revenue generated by the
additional production. If the firm’s MARR is 20% per year, is
this proposal a sound one? Use the PW method.
Solution:
𝑃0 = $25,000, Salvage Value = $5,000= 𝐹5 , MARR = 20% per
year, A = Revenue – Operating Cost= $8,000 per year ,
Project is economically justified or viable = ?
Project is economically justified?
Cash Flow Diagram:
Project is economically justified?
We know that:
𝑃𝑊 = 𝑃𝑊 𝑜𝑓 𝑐𝑎𝑠ℎ 𝑖𝑛𝑓𝑙𝑜𝑤 − 𝑃𝑊 𝑜𝑓 𝑐𝑎𝑠ℎ 𝑜𝑢𝑡𝑙𝑜𝑤
𝑃 𝑃
𝑃𝑊 20% = $8000 , 20%, 5 + $5000 , 20%, 5 − $25000
𝐴 𝐹
𝑃𝑊 20% = $934.29
The Future Worth Method
▪ Because a primary objective of all-time value of money
methods is to maximize the future wealth of the owners of a
firm, the economic information provided by the FW method is
very useful in capital investment decision situations.
▪ The FW is based on the equivalent worth of all cash inflows
and outflows at the end of the planning horizon (study period)
at an interest rate that is generally the MARR.
▪ Also, the FW of a project is equivalent to its PW; that is, FW =
PW(F/P, i%,N).
▪ If FW ≥ 0 for a project, it would be economically justified.
The Future Worth Method
Q) Solve previous question using future worth analysis.
The Future Worth Method
Solution:
𝐹𝑊 = 𝐹𝑊 𝑜𝑓 𝑐𝑎𝑠ℎ 𝑖𝑛𝑓𝑙𝑜𝑤 − 𝐹𝑊 𝑜𝑓 𝑐𝑎𝑠ℎ 𝑜𝑢𝑡𝑙𝑜𝑤
𝐹 𝐹
𝐹𝑊 20% = −$25000 , 20%, 5 + $8000 , 20%, 5 + $5000
𝑃 𝐴
𝐹𝑊 20% = $2,324.80
The Annual Worth Method
▪ The AW of a project is an equal annual series of dollar
amounts, for a stated study period, that is equivalent to the
cash inflows and outflows at an interest rate that is generally
the MARR.
▪ Hence, the AW of a project is annual equivalent revenues or
savings (R) minus annual equivalent expenses (E), less its
annual equivalent capital recovery (CR) amount,
𝐴 𝐴
𝐴𝑊 20% = $8000 − $25000 , 20%, 5 + $5000( , 20%, 5)
𝑃 𝐹
𝐴𝑊 20% = $ 312.4
Because its AW(20%) is positive, the equipment more than pays for itself
over a period of five years, while earning a 20% return per year on the
unrecovered investment.
Comparing Alternatives
▪ The alternative that requires the minimum investment of
capital and produces satisfactory functional results will be
chosen unless the incremental capital associated with an
alternative having a larger investment can be justified with
respect to its incremental benefits.
▪ Under this rule, we consider the acceptable alternative that
requires the least investment of capital to be the base
alternative.
▪ If the extra benefits obtained by investing additional capital
are better than those that could be obtained from investment
of the same capital elsewhere in the company at the MARR,
the investment should be made.
Present Worth Analysis (Useful life
Equal)
Q) Perform a present worth analysis of equal service machines
with the cost shown below, if the MARR is 10% per year.
revenues for all three alternatives are expected to be the same.
Solution:
For Electric Powered Machine:
𝑃 𝑃
𝑃𝑊 10% 𝐸 = −2500 − 900 , 10%, 5 + 200 , 10%, 5
𝐴 𝐹
𝑃𝑊 10% 𝐸 = −$5788
Present Worth Analysis (Useful life
Equal)
Solution: (Cont.)
For Gas Powered Machine:
𝑃 𝑃
𝑃𝑊 10% 𝐺 = −3500 − 700 , 10%, 5 + 350 , 10%, 5
𝐴 𝐹
𝑃𝑊 10% 𝐸 = −$5936
𝑃𝑊 10% 𝐴 = $1,028
Present Worth Analysis (Useful life
Different
Solution by PW: (Cont.)
For Alternative B:
𝑃𝑊 10% 𝐵
𝑃
= −$5,000 − 5,000 , 10%, 6 + (2,500
𝐹
𝑃
− 1,020) , 10%, 12
𝐴
𝑃𝑊 10% 𝐵 = $2,262
Based on the PW method, we would select
Alternative B
FW Analysis (Useful life Different)
Solution of previous Que by FW:
▪ An assumption used for an investment alternative (when useful life
is less than the study period) is that all cash flows will be
reinvested by the firm at the MARR until the end of the study
period. This assumption applies to Alternative A, which has a four-
year useful life (two years less than the study period), and it is
illustrated in following figure:
FW Analysis (Useful life Different)
Solution of previous Que by FW: (Cont.)
▪ We use the FW method to analyze this
situation of Alternative A:
𝐹𝑊 10%
𝐹
= −$3500 , 10%, 4 + (1900
𝑃
𝐹 𝐹
− 645) , 10%, 4 ൨ × , 10%, 2
𝐴 𝑃
𝐹𝑊 10% = $847
FW Analysis (Useful life Different)
Solution of previous Que by FW: (Cont.)
▪ For Alternative B:
𝐹 𝐹
𝐹𝑊 10% = −$5000 , 10%, 4 + (2500 − 1020) , 10%, 4
𝑃 𝐴
𝐹𝑊 10% = $2,561
Operations Research
It is a scientific approach to determine the optimum (best)
solution to a decision problem under the restriction of limited
resources, using the mathematical techniques to model,
analyze, and solve the problem.
Operations research (OR) is an analytical method of problem-
solving and decision-making that is useful in the
management of organizations.
The central objective of operations research is optimization,
i.e., "to do things best under the given circumstances."
Optimization: Means maximization (of profit) or minimization
(of cost like expense).
Ahsan Ahmed 1
12/9/2019
Linear Programming
Most Prominent Operation Research Technique.
Linear Programming: is a technique, which optimizes linear
objective function under limited constraints.
It is designed for models with linear objective and constraint
function.
It is mostly used for allocation of resources.
Linear Programming is a technique, designed to help
operation managers and make decisions relative to the trade
offs necessary to allocate resources.
Linear Programming
Objective Function:
A mathematical expression in linear programming that
maximizes or minimizes some quantity often profit or cost but
any goal may be used.
Constraints:
Restrictions that limit the degree which manager can pursue
an objective.
May be expressed as inequalities.
Ahsan Ahmed 2
12/9/2019
Linear Programming
A solution of the model is feasible if it satisfies all the
constraints.
It is optimal if, in addition to being feasible, it yields the best
(maximum or minimum) value of the objective function.
The optimum solution of a model is best only for that model. If
the model happens to represent the real system reasonably
well, then its solution is optimum also for the real situation.
The number of constraints and decision variables in objective
function depends on the complexity of problem.
Linear programming maximizes (or minimizes) a linear
objective function subject to one or more constraints.
2) Objective Function:
An equation that is needed to be optimized.
Example: Objective function: 𝑧 = 2𝑥 + 3𝑥 (here “z” can
be profit or revenue.
It tells how much should we produce 𝑥 and 𝑥 to
maximize “z”
6
Ahsan Ahmed 3
12/9/2019
4) Variable bounds:
The variable usually have 2 bound / boundaries. (-,+)
Means they are not infinite.
Methods:
1- Graphical Method (only for two variables)
2- Two or more variables
7
Maximize “z”
Q) Max
Subjected to:
i-
ii- Structural Constraints
iii-
(non negativity constraints it means
our case is in 1st quadrant)
Ahsan Ahmed 4
12/9/2019
Maximize “z”
Solution:
Step # 1: Calculating the extreme points of each structural
constraints:
(i)
When then (0,400)
When then (1200, 0)
(ii)
When then (0,500)
When then (1000, 0)
9
Maximize “z”
Solution: (Cont.)
(iii) (700,0)
Step # 2 : Plotting
these points in a graph
10
Ahsan Ahmed 5
12/9/2019
Maximize “z”
Solution: (Cont.)
Step # 4 : Optimum Solution (always lies on any
one of the vertices) Optimum Point
Point Coordinate 𝑧 = 5𝑥 + 8𝑥
0 (0 , 0) 𝑧 =5 0 +8 0 =0
a (0 , 400) 𝑧 = 5 0 + 8 400 = 3200
b (600 , 200) 𝑧 = 5 600 + 8 200 = 4600
intersection of i and ii
c (700 , 150) 𝑧 = 5 700 + 8 150 = 4700
d (700 , 0) 𝑧 = 5 700 + 8 0 = 3500
11
Maximize “z”
Solution: (Cont.)
Step # 5 : Result / Conclusion
12
Ahsan Ahmed 6
12/9/2019
A market survey indicates that the daily demand for interior paint
cannot exceed that for exterior paint by more than 1 ton. Also, the
maximum daily demand for interior paint is 2 tons.
Reddy Mikks wants to determine the optimum (best) product mix
of interior and exterior paints that maximizes the total daily
profit.
13
14
Ahsan Ahmed 7
12/9/2019
15
Hence
Usage of raw material M1 by both paints = 6𝑥 + 4𝑥 tons/day
In a similar manner,
Usage of raw material M2 by both paints = 1𝑥 + 2𝑥 tons/day
16
Ahsan Ahmed 8
12/9/2019
Ahsan Ahmed 9
12/9/2019
19
20
Ahsan Ahmed 10
12/9/2019
21
22
Ahsan Ahmed 11
12/9/2019
23
24
Ahsan Ahmed 12
12/9/2019
25
26
Ahsan Ahmed 13
12/9/2019
27
Ahsan Ahmed 14
12/9/2019
30
Ahsan Ahmed 15
12/9/2019
Decision: The associated minimum cost of the feed mix is $437.65 per
day at 𝑥 = 470.6 and 𝑥 = 329.4.
31
Furniture Model
Q) Aadat Company uses 03 machines to construct tables and
chairs as follows
Machine Chairs (hrs) Tables (hrs) Available hrs / week
M1 3 3 36
M2 5 2 50
M3 2 6 60
If Aadat company gets a profit of $20 / chair and $30 / table. Then
find the total no. of chairs and tables which should be sold by
Aadat company to get the maximum profit.
32
Ahsan Ahmed 16
12/9/2019
Furniture Model
Solution
The Aadat company model is
Maximize 𝑧 = 20𝑥 + 30𝑥
Subjected to
3𝑥 + 3𝑥 ≤ 30 -------------(1)
5𝑥 + 2𝑥 ≤ 50 -------------(2)
2𝑥 + 6𝑥 ≤ 60 -------------(3)
𝑥 ,𝑥 ≥0 -------------(4)
33
Furniture Model
Solution: (Cont.)
Step # 1: Calculating the extreme points of each structural
constraints:
For eq. 1: 3𝑥 + 3𝑥 ≤ 36 when 𝑥 = 0, 𝑥 = 12 (0,12)
when 𝑥 = 0, 𝑥 = 12 (12,0)
34
Ahsan Ahmed 17
12/9/2019
Furniture Model
Solution: (Cont.)
Step # 2 : Plotting these points in
a graph
35
Furniture Model
Solution:(Cont.)
Step # 4 : Determination of the Optimum Solution:
Point Coordinate 𝑧 = 20𝑥 + 30𝑥
o (0 , 0) 𝑧 = 20 0 + 30 0 = 0
a (0 , 10) 𝑧 = 20 0 + 30 10 = 300
b (3, 9) 𝑧 = 20 3 + 30 9 = 330
c (8.67 , 3.33) 𝑧 = 20 8.67 + 30 3.33 = 273.3
d (10 , 0) 𝑧 = 20 10 + 30 0 = 200
Ahsan Ahmed 18
12/22/2019
Payback Period
Payback Period is a measure of
the speed with which an
investment is recovered by the
cash inflows it produces.
Payback period is the time in
which the initial cash outflow of
an investment is expected to be
recovered from the cash inflows 𝑃𝑎𝑦𝑏𝑎𝑐𝑘 𝑃𝑒𝑟𝑖𝑜𝑑 =
𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
generated by the investment. It 𝐶𝑎𝑠ℎ 𝐼𝑛𝑓𝑙𝑜𝑤 𝑝𝑒𝑟 𝑃𝑒𝑟𝑖𝑜𝑑
Ahsan Ahmed 1
12/22/2019
Payback Period
Case-I: For Even Cash Flows:
𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
𝑃𝑎𝑦𝑏𝑎𝑐𝑘 𝑃𝑒𝑟𝑖𝑜𝑑 =
𝐶𝑎𝑠ℎ 𝐼𝑛𝑓𝑙𝑜𝑤 𝑝𝑒𝑟 𝑃𝑒𝑟𝑖𝑜𝑑
Case-II: For Uneven Cash Flows:
When cash inflows are uneven, we need to calculate the
cumulative net cash flow for each period and then use the
following formula for payback period:
𝐴
𝑃𝑎𝑦𝑏𝑎𝑐𝑘 𝑃𝑒𝑟𝑖𝑜𝑑 = 𝑌 +
𝐵
Where, Y= last period with a negative cumulative cash flow,
A= absolute value of cumulative cash flow at the
end of the period Y,
B= total cash flow during the period after Y
3
$105 million
𝑃𝑎𝑦𝑏𝑎𝑐𝑘 𝑃𝑒𝑟𝑖𝑜𝑑 =
$25 million per year
Ahsan Ahmed 2
12/22/2019
11
𝑃𝑎𝑦𝑏𝑎𝑐𝑘 𝑃𝑒𝑟𝑖𝑜𝑑 = 3 +
19
Ahsan Ahmed 3
12/22/2019
Ahsan Ahmed 4
12/22/2019
10
Ahsan Ahmed 5
12/22/2019
−106,462
𝐷𝑖𝑠𝑐𝑜𝑢𝑛𝑡𝑒𝑑 𝑃𝑎𝑦𝑏𝑎𝑐𝑘 𝑃𝑒𝑟𝑖𝑜𝑑 = 5 +
320,785
11
Ahsan Ahmed 6
12/22/2019
14
Ahsan Ahmed 7
12/22/2019
If 𝑖 > 𝑖 :
NPV < 0
PWB – PWC < 0
PWB < PWC
Hence Project is rejected
15
16
Ahsan Ahmed 8
12/22/2019
𝐵% − 𝐴% 𝑖 % − 𝐴%
=
𝑎−𝑏 𝑎−0
𝑎
𝑖 % = 𝐴% + (𝐵% − 𝐴%)
𝑎−𝑏
17
18
Ahsan Ahmed 9
12/22/2019
Let 𝑖=15%
𝑁𝑃𝑉 %
𝑃 𝑃
= $2,310 , 15%, 5 + $2,000 , 15%, 5 − $10,000
𝐴 𝐹
𝑁𝑃𝑉 % = −$1,262
20
Ahsan Ahmed 10
12/22/2019
𝑖 % = 10.5%
21
22
Ahsan Ahmed 11
12/22/2019
23
24
Ahsan Ahmed 12
12/22/2019
25
Solution:
26
Ahsan Ahmed 13
12/22/2019
27
Ahsan Ahmed 14
12/22/2019
29
30
Ahsan Ahmed 15
12/22/2019
𝑖 % = 12.3%
Since 𝑖 < 𝑀𝐴𝑅𝑅, so reject the challenger and accept the
defender.
31
Ahsan Ahmed 16
1/12/2020
Replacement Decision
By:
Ahsan Ahmed
(Lecturer, MED)
Ahsan Ahmed 1
1/12/2020
Ahsan Ahmed 2
1/12/2020
Decision:
The present worth of challenger is greater than present worth
of defender. Thus the old pressure vessel should be replaced
immediately.
Ahsan Ahmed 3
1/12/2020
Ahsan Ahmed 4
1/12/2020
10
Ahsan Ahmed 5
1/12/2020
𝐴 𝐴
𝐸𝑈𝐴𝐶 10% = −5,340 − 750 , 10%, 9 + 200 , 10%, 9
𝑃 𝐹
𝐸𝑈𝐴𝐶 10% = −5,340 − 750 0.1736 + 200 0.0736
𝐸𝑈𝐴𝐶 10% = −$5,455
11
𝐴 𝐴
𝐸𝑈𝐴𝐶 10% = −16,000 , 10%, 9 − 3,320 + 3,200 , 10%, 9
𝑃 𝐹
𝐸𝑈𝐴𝐶 10% = −16,000 0.1736 − 3,320 + 3,200 0.0736
𝐸𝑈𝐴𝐶 10% = −$5,862
12
Ahsan Ahmed 6
1/12/2020
13
14
Ahsan Ahmed 7
1/12/2020
Solution:
15
16
Ahsan Ahmed 8
1/12/2020
17
18
Ahsan Ahmed 9
1/12/2020
Depreciation
By:
Ahsan Ahmed
(Lecturer, MED)
Depreciation
Depreciation is the decrease in value of physical properties
with the passage of time and use.
More specifically, depreciation is an accounting concept that
establishes an annual deduction against before-tax income
such that the effect of time and use on an asset’s value can be
reflected in a firm’s financial statements.
Basic Requirement for Depreciation Properties:
In general property is depreciable if it meets the following basic
requirements:
It must be used in business or held to produce income.
It must have a determinable useful life, and the life must be
longer than one year.
Ahsan Ahmed 1
1/12/2020
Depreciation
It must be something that wears out, decays, gets used up,
becomes obsolete, or loses value from natural causes.
It is not inventory, stock in trade, or investment property
Depreciable Property:
Tangible property can be seen or touched, and it includes
two main types called personal property and real property.
Personal property includes assets such as machinery, vehicles,
equipment, furniture, and similar items. In contrast, real
property is land and generally anything that is erected on,
growing on, or attached to land. Land itself, however, is not
depreciable, because it does not have a determinable life.
Intangible property is personal property such as a
copyright, patent, or franchise.
3
Ahsan Ahmed 2
1/12/2020
Ahsan Ahmed 3
1/12/2020
Ahsan Ahmed 4
1/12/2020
Types of Depreciation
There are following major types of depreciation:
1) Normal Depreciation
a) Physical depreciation
b) Functional depreciation
2) Monetary Depreciation
a) Physical Depreciation:
Physical depreciation is due to decrease in the physical ability
if the property or asset to produce desire results and the main
cause of physical depreciation is wear and tear.
Types of Depreciation
b) Functional Depreciation:
Functional depreciation is due to decrease in demand for the
function of asset (that the property was designed to serve).
The main cause of functional depreciation are change in
technology and change in taste or fashion.
2) Monetary Depreciation:
During the inflation, when the price of the property increases,
then recovery of capital is too difficult, and the recovered
capital will not be sufficient to provide an identical
replacement due to increase in price limit and decrease in
worth of capital.
10
Ahsan Ahmed 5
1/12/2020
Methods of Depreciation
There are following methods of depreciation that apply
(directly and indirectly) to the depreciation of property :
11
12
Ahsan Ahmed 6
1/12/2020
13
Data:
P = $ 4,000
N =10 years
SV= 0
14
Ahsan Ahmed 7
1/12/2020
4,000 − 0
𝐷=
10
𝐷 = $400
15
Ahsan Ahmed 8
1/12/2020
Solution:
The total SL depreciation at the end of 5th years is determined
by:
𝑃−𝑆
𝐷 = ×𝑛
𝑁
$4,000 − 0
𝐷 = ×5
10
𝐷 = $2,000
17
𝐵𝑉 = $4,000 − $2,000
𝐵𝑉 = $2,000
18
Ahsan Ahmed 9
1/12/2020
Depreciation factor for any year is the reverse digit for that
year divided by the sum of the digit years.
n 0 1 2 3 4 5
Reverse digit - 5 4 3 2 1
19
n 0 1 2 3 4 5
Reverse digit - 5 4 3 2 1
(𝑇𝑜𝑡𝑎𝑙 𝑑𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑖𝑜𝑛) = 𝐷
20
Ahsan Ahmed 10
1/12/2020
21
22
Ahsan Ahmed 11
1/12/2020
23
24
Ahsan Ahmed 12
1/12/2020
For K:
𝑆
𝐾 = 1−
𝑃
$350
𝐾 =1−
$20,000
𝐾 = 0.3969
25
Ahsan Ahmed 13
1/12/2020
2
𝐾=
10
𝐾 = 0.2
27
Ahsan Ahmed 14
1/12/2020
Solution:
29
0 - - - -
1 $4,000.00 $800.00 $400.00 $800.00
2 $3,200.00 $640.00 $355.56 $640.00
3 $2,560.00 $512.00 $320.00 $512.00
4 $2,048.00 $409.60 $292.57 $409.60
5 $1,638.40 $327.68 $273.07 $327.68
6 $1,310.72 $262.14 $262.14 $262.14
7 $1,048.58 $209.72 $262.14 $262.14
8 $786.43 $157.29 $262.14 $262.14
9 $524.29 $104.86 $262.14 $262.14
10 $262.14 $52.43 $262.14 $262.14
30
Ahsan Ahmed 15
1/12/2020
31
32
Ahsan Ahmed 16
1/12/2020
Selecting
Depreciation Rates
From table 7-3 for
10 years (useful
life)
33
Ahsan Ahmed 17
1/12/2020
35
Ahsan Ahmed 18
1/18/2020
Cost
Cost: The value of the sacrifice made to acquire goods or
services. All costs of a manufacturing organization may be
divided according to functional areas into:
1) Manufacturing cost: These are related to the production of
an item. They are the sum of direct material , direct labor
and factory overhead cost.
2) Marketing cost: These are incurred in promoting a product
or service.
3) Administrative cost: These are incurred in directing,
controlling and operating a company and includes salaries
paid to management and staff.
4) Financing cost: These are related to obtaining funds for
the operation of the company. They include the cost of
interest that the company must pay on loans, as well as
the cost of providing credit to customer.
2
Ahsan Ahmed 1
1/18/2020
Elements of a Product
Expense : A cost that has given benefit and is now expired.
Elements of a Product: The cost elements of a product or its
integral components are direct materials, direct labor and
factory overhead.
Elements of a Product
Materials : These are the principal substances used in
production that are transformed into finished goods by the
addition of direct labor and factory overhead. The cost of
materials may be classified into direct and indirect materials
as follows:
Direct materials: All materials that can be identified with
the production of a finished product, that can be easily
traced to the product and that represent a major material
cost of producing that product. An example of direct material
is wood to build a basketball bat.
Direct materials: All materials involved in the production
of a product that are not direct materials . Indirect materials
are included as a part of factory overhead. An example of
indirect material is the glue used to make furniture.
Ahsan Ahmed 2
1/18/2020
Elements of a Product
Labor cost: Labor is the physical or mental effort expended
in the production of a product. Labor costs may be divided
into direct and indirect labor as follows:
Elements of a Product
Factory Overhead:
This all inclusive cost pool is used to accumulate indirect
materials, indirect labor and all other indirect manufacturing
costs which cannot be directly identified with specified
products. Examples of factory overhead costs beside indirect
materials and indirect labor are rent , light and heat for the
factory and depreciation of factory equipment.
Ahsan Ahmed 3
1/18/2020
Elements of a Product
Factory Overhead:
This all inclusive cost pool is used to accumulate indirect
materials, indirect labor and all other indirect manufacturing
costs which cannot be directly identified with specified
products. Examples of factory overhead costs beside indirect
materials and indirect labor are rent , light and heat for the
factory and depreciation of factory equipment.
Elements of a Product
Prime Cost : Prime cost are direct materials and direct labor.
Prime costs are directly related to production.
Conversion cost : These are costs concerned with
transforming direct materials into finished products.
Conversion cost are direct labor and factory overhead.
Fixed cost : Those costs which in total remain constant over
a relevant range of output while the cost per unit varies
inversely with output. Beyond the relevant range of output ,
fixed cost will vary. Upper management controls the volume of
production and is therefore responsible for fixed costs.
Variable cost : Variable costs are those in which the total
cost changes in direct proportion to change in volume or
output within the relevant range ,while the unit cost remains
constant. Variable cost are controlled by the department head.
8
Ahsan Ahmed 4
1/18/2020
Elements of a Product
Those costs which change in total in direct proportion to
changes in volume and whose unit cost remains constant,
within the relevant range.
Terminologies
Differential cost : A differential cost is the difference
between the costs of alternative courses of action on an item
by item basis. If the cost is increasing from one alternative to
another , it is called as incremental cost ; if the cost is
decreasing from one alternative to another it is called a
decrement cost.
Opportunity Cost : Where a decision to pursue one
alternative is made , the benefits of other options are forgone.
Benefits lost from rejecting the next best alternative are the
opportunity cost of the chosen action. They are relevant costs
for decision-making purposes and must be considered in
evaluating a proposed alternative.
This concept is often encountered in replacement decision.
Opportunity cost is a comparative term we should have.
10
Ahsan Ahmed 5
1/18/2020
Terminologies
Sunk cost : Cost that has already been incurred and that
cannot be changed by any decision made now or in future. It
is a consequence of past decision and now irretrievable and
irrelevant in the analysis and comparison. However, its
existence can assist to make better decision.
Standard cost or Average cost or budgeted cost:
Standard cost are those which should be incurred in a
particular production process under normal conditions.
Standard costing is usually concerned with per unit cost for
direct materials, direct labor and factory overhead.
Controllable costs : Controllable costs are those which may
be directly influenced by unit managers in a given time
period. Most variable costs are considered as controllable cost.
11
Terminologies
Non-controllable costs: Non-controllable costs are those
costs which are not directly administered at a given level of
management authority. Most fixed cost are non-controllable
costs.
12
Ahsan Ahmed 6
1/18/2020
13
14
Ahsan Ahmed 7
1/18/2020
𝑇𝑅 = 𝑎 − 𝑏𝐷 𝐷 = 𝑎𝐷 − 𝑏𝐷
From calculus, the demand,𝐷 , that will produce maximum
total revenue can be obtained by solving
𝑑𝑇𝑅
=0
𝑑𝐷
15
𝑎 − 2𝑏𝐷 = 0
Thus
𝑎
𝐷=
2𝑏
16
Ahsan Ahmed 8
1/18/2020
17
18
Ahsan Ahmed 9
1/18/2020
19
20
Ahsan Ahmed 10
1/18/2020
21
22
Ahsan Ahmed 11
1/18/2020
23
24
Ahsan Ahmed 12
1/18/2020
25
26
Ahsan Ahmed 13
1/18/2020
27
Ahsan Ahmed 14
1/18/2020
Public Projects
Public projects are those authorized, financed, and operated
by federal, state, or local governmental agencies.
Such public works are numerous, and although they may be
of any size, they are frequently much larger than private
ventures.
Since they require the expenditure of capital, such projects
are subject to the principles of engineering economy with
respect to their design, acquisition, and operation.
Because they are public projects, however, a number of
important special factors exist that are not ordinarily found in
privately financed and operated businesses.
The differences between public and private projects are listed
in Table on the next slide.
2
Ahsan Ahmed 1
1/18/2020
Ahsan Ahmed 2
1/18/2020
Ahsan Ahmed 3
1/18/2020
Ahsan Ahmed 4
1/18/2020
10
Ahsan Ahmed 5
1/18/2020
11
12
Ahsan Ahmed 6
1/18/2020
13
14
Ahsan Ahmed 7
1/18/2020
Solution:
15
16
Ahsan Ahmed 8
1/18/2020
17
$490,000
𝐵−𝐶 =
1,200,000(𝐴/𝑃, 10%, 20)+$197,500
18
Ahsan Ahmed 9
1/18/2020
$490,000−$197,500
𝐵−𝐶 =
1,200,000(𝐴/𝑃, 10%, 20)
19
20
Ahsan Ahmed 10
1/18/2020
21
22
Ahsan Ahmed 11
1/18/2020
$490,000 − 100,000
𝐵−𝐶 =
1,200,000(𝐴/𝑃, 10%, 20)+$197,500
23
$490,000
𝐵−𝐶 =
1,200,000 𝐴/𝑃, 10%, 20 +$197,500 + 100,000
24
Ahsan Ahmed 12
1/18/2020
25
26
Ahsan Ahmed 13
1/18/2020
27
28
Ahsan Ahmed 14
1/18/2020
29
30
Ahsan Ahmed 15
1/18/2020
31
32
Ahsan Ahmed 16