Professional Documents
Culture Documents
Fundamentals of Civil Engineering Construction - Abebe Dinku, Alfred Ngowi and Ninatubu Lema Final Version 20.1.2015
Fundamentals of Civil Engineering Construction - Abebe Dinku, Alfred Ngowi and Ninatubu Lema Final Version 20.1.2015
Fundamentals of Civil Engineering Construction - Abebe Dinku, Alfred Ngowi and Ninatubu Lema Final Version 20.1.2015
i
a combined expertise as practiced by the Master Builder. Over time stratification of
the combined expertise took place and resulted into various specializations of
engineering, architecture, quantity surveying, among others.
Chapter Two describes the parties involved in the construction industry and their
roles and professional relationships. The parties that include the client, designer and
constructor are described for different projects and their roles and interactions at
different stages of the projects are described. Chapter Three describes the stages of
civil engineering projects starting from the inception, preliminary design, detailed
design, construction, operation and maintenance. The importance of carrying out
adequate feasibility studies is emphasized.
Chapter Four describes project financial appraisal, depreciation and inflation. The
methods of financial project appraisal and the methods of dealing with multiple
alternatives are described. The causes of depreciation are explained and the methods
of dealing with depreciation are discussed. Chapter Five describes sources of project
finance. It defines development project and list global and regional sources of
finance as well as how such finances are secured, managed and repaid.
Chapter Six describes planning studies before, during and after construction focusing
particularly on the construction process. Pre-tender, pre-contract and contract
planning are described and how their importance to successful construction projects
is shown. Chapter Seven describes planning techniques. Strategic and operational
planning levels are explained; the planning techniques of bar-chart and linked bar-
chart; network analysis; line of balance; the programme evaluation and review
technique and space-time diagrams are explained. Chapter Eight describes the least
cost scheduling and resource levelling, variation of direct costs with time, schedule
compression, resource levelling is described and examples are given.
ii
management. Included in the chapter are: Basic principles of equipment
management, equipment productivity and cost control, estimation of equipment
productivity, and plant and equipment maintenance.
Chapter Fifteen describes occupational health and safety in the construction industry.
The principles of safety management systems in the construction industry, safety
legislation, site practices, as well as current developments in management of
construction safety are explained.
iii
It is the intention of the authors that future titles in the subject will shift towards the
emerging trend of theory-based construction management programmes. It is planned
that a follow-up book will communicate the current delivery of construction
management programmes at an advanced level, before a book that communicates the
paradigm shift to theory-based construction management programmes is authored.
Abebe Dinku
Ninatubu Lema
Alfred Ngowi
iv
ACKNOWLEDGMENTS
We want to sincerely acknowledge with special thanks and appreciation the financial
support of African Network of Scientific and Technological Institutions (ANSTI)
under the auspices of UNESCO that enabled the accomplishment of this textbook.
Special thanks deserve Prof. J. G. M. Massaquoi, ANSTI Director, for bringing us
together and his encouragement in the preparation of the textbook. In addition we
would like to thank Ms Shaza Yahia, Program Assistant for Science and Technology,
UNESCO Addis Ababa cluster office, for coordinating the efforts of the co-authors
who are located at geographically distant places.
We would also like to thank colleagues in the Faculty of Technology, Addis Ababa
University; Faculty of Civil Engineering and the Built Environment, University of
Dar es Salaam; and Faculty of Engineering and Technology, University of Botswana
for their formal and informal contributions in the various chapters of the book as well
as for checking the accuracy of the manuscript.
It is also important to note that the textbook includes contributions from numerous
students of the three universities as well as construction managers in the three
countries as gleaned from professional conversations. We want them to know that
we sincerely appreciate their comments and suggestions. Next, it is important to note
that the works of numerous authors were cited in the body of the text book.
Particularly chapter seven includes techniques such as line of balance that were
developed by other authors. In this case we acknowledge the work of Frank Harris
and Ronald Macaffer.
Finally, we wish to extend our thanks to the three Universities for availing the
opportunity to work on the preparation of the text book.
Abebe Dinku
Ninatubu Lema
Alfred Ngowi
v
TABLE OF CONTENTS
Preface ............................................................................................................................i
Acknowledgements .......................................................................................................v
Chapter 1
Civil Engineering Construction..................................................................................1
1.1 Introduction .......................................................................................................1
1.2 Engineering as a Profession...............................................................................4
1.3 The Role of Education.......................................................................................5
1.4 Engineering Professional Organizations ...........................................................7
1.5 The Construction Discipline..............................................................................8
1.6 Developing an Academic Theory ....................................................................11
1.7 Cost Implications.............................................................................................12
Chapter 2
The Members of The Construction Team ...............................................................14
2.1 The Promoter ...................................................................................................14
2.1.1 The private sector ................................................................................14
2.1.2 The public sector .................................................................................15
2.2 The Construction Process ................................................................................16
2.3 The Construction Team ...................................................................................18
2.3.1 The consulting engineer (the Engineer)...............................................18
2.3.2 The private quantity surveyor..............................................................20
2.3.3 The structural engineer ........................................................................22
2.3.4 The service engineer ............................................................................23
2.3.5 The resident engineer (RE)..................................................................24
2.3.6 The supplier .........................................................................................26
2.3.7 The subcontractor ................................................................................27
2.3.8 The plant hirer .....................................................................................28
2.3.9 Planning control officer .......................................................................29
2.3.10 Factory inspector .................................................................................29
2.3.11 The contractor......................................................................................29
2.3.12 The construction project manager .......................................................30
2.4 The Contractor’s Head Office Structure..........................................................31
2.4.1 The contractor’s quantity surveyor......................................................33
2.4.2 The planning engineer .........................................................................34
2.4.3 The work study engineer .....................................................................35
2.4.4 The bonus surveyor .............................................................................36
2.4.5 The estimator .......................................................................................37
2.4.6 The buyer.............................................................................................38
2.4.7 The personnel officer...........................................................................39
2.4.8 The industrial relations officer ............................................................40
2.4.9 The safety officer.................................................................................41
2.4.10 The plant manager ...............................................................................42
2.4.11 The contracts manager.........................................................................42
2.4.12 The wages and accounts manager .......................................................42
2.4.13 The typing supervisor ..........................................................................43
vi
2.5 The Contractor’s Site Organization Structure .................................................44
2.5.1 The contracts manager .........................................................................46
2.5.2 The site manager..................................................................................47
2.5.3 The general foreman ............................................................................48
2.5.4 The trade’s foreman .............................................................................48
2.5.5 The ganger ...........................................................................................49
2.5.6 The charge hand...................................................................................49
2.5.7 The operative .......................................................................................49
2.5.8 The site engineer..................................................................................50
2.5.9 The site clerk/materials controller .......................................................51
Chapter 3
Stages of Civil Engineering Projects ........................................................................52
3.1 Introduction......................................................................................................52
3.2 Feasibility Study (Investigation and reports)...................................................53
3.2.1 The nature of the feasibility study .......................................................56
3.2.2 Importance and extent of investigation................................................56
3.3 The Engineer’s Terms of Reference ................................................................57
3.3.1 Scope of work statement......................................................................57
3.3.2 Flexibility and consideration of alternatives........................................57
3.3.3 Types of investigation or study............................................................58
3.4 Nature of Investigations...................................................................................59
3.4.1 Technical investigations ......................................................................59
3.4.2 Economic and social investigations .....................................................59
3.4.3 Use of existing information and plans .................................................59
3.4.4 Site exploration ....................................................................................60
3.4.5 Physical data ........................................................................................60
3.4.6 Models .................................................................................................60
3.4.7 Public participation ..............................................................................61
3.4.8 Outline programme ..............................................................................61
3.4.9 Cost estimates ......................................................................................61
3.5 The Engineer’s Report .....................................................................................62
3.5.1 Objective..............................................................................................62
3.5.2 Presentation..........................................................................................62
3.5.3 Form of report......................................................................................63
3.6 Proceeding With The Project...........................................................................63
3.6.1 The next stage ......................................................................................63
3.6.2 Public inquiries ....................................................................................64
3.7 Design and Preparation for Contract Documents ............................................64
3.7.1 Design proper.......................................................................................64
3.7.2 Preparation of contract documents ......................................................66
3.7.3 Overall approach to design and possible alternatives ..........................67
Chapter 4
Financial Project Appraisal,Depreciation and Inflation........................................70
4.1 Introduction............................................................................................................70
4.2 Methods of Financial Project Appraisal ..........................................................71
4.2.1 Straight cost method ............................................................................72
4.2.2 Payback method...................................................................................73
vii
4.2.3 Rate of return method ..........................................................................77
4.2.4 Present value (cost) method.................................................................79
4.2.5 Internal rate of return method..............................................................84
4.3 Dealing With Multiple Alternatives ................................................................88
4.3.1 Mutually exclusive projects.................................................................88
4.3.2 Incremental analysis ............................................................................88
4.4 Postponing an Investment................................................................................90
4.5 Depreciation.....................................................................................................90
4.5.1 Methods of depreciation calculations ..................................................91
4.6 Inflation ...........................................................................................................99
4.6.1 Interest and inflation............................................................................99
4.6.2 Working in real terms ........................................................................100
4.6.3 Working in monetary terms (or numbers of $'s)...............................100
Chapter 5
Sources of Large Development Project Finance ...................................................104
5.1 Introduction ...................................................................................................104
5.2 Sources of Finance.........................................................................................104
5.3 Development Banks.......................................................................................106
5.3.1 African Development Bank group (AfDB group) .............................107
5.3.2 Asian Development Bank (AsDB) ....................................................109
5.3.3 Inter-American development bank (IDB)..........................................110
5.3.4 The World Bank group ......................................................................111
5.4 The World Bank Approach to The Project Cycle..........................................114
5.4.1 Project identification..........................................................................116
5.4.2 Project preparation.............................................................................119
5.4.3 Project appraisal ................................................................................122
5.4.4 Negotiations.......................................................................................123
5.4.5 Project implementation......................................................................124
5.4.6. Project evaluation ..............................................................................128
5.5 Other Approaches to the Project Cycle .........................................................130
5.6 Summary........................................................................................................135
Chapter 6
Planning Before, During andAfter Construction .................................................136
6.1 Introduction ...................................................................................................136
6.2 Pre-tender Planning .......................................................................................137
6.2.1 Decision to tender ..............................................................................138
6.2.2 Pre-tender arrangements ....................................................................140
6.2.3 Site report ..........................................................................................141
6.2.4 Enquiries to subcontractors and suppliers .........................................142
6.2.5 Method and resource statement .........................................................142
6.2.6 Site organization structure .................................................................146
6.2.7 Schedule of preliminary items and site overheads ............................146
6.2.8 Pre-tender programme .......................................................................147
6.2.9 Management adjudication of the estimate .........................................147
6.3 Pre-contract Planning ....................................................................................149
6.3.1 The pre-contract planning process.....................................................149
6.3.2 The pre-contract meeting and arrangements for commencing work .149
viii
6.3.3
The pre-contract meeting - contractor's team ....................................150
6.3.4
Chief estimator...................................................................................150
6.3.5
Contracts manager .............................................................................150
6.3.6
Company buyer or quantity surveyor (In the medium sized
organization) ......................................................................................151
6.3.7 Office manager ..................................................................................151
6.3.8 The pre-start meeting .........................................................................152
6.3.9 Placing orders for subcontractors and suppliers ...............................152
6.3.10 Site layout planning ...........................................................................152
6.3.11 Construction method statements........................................................156
6.3.12 The master programme preparation...................................................157
6.3.13 Preparation of requirement schedules................................................158
6.3.14 The preparation of contract budgets ..................................................160
6.4 Planning During Construction .......................................................................166
6.4.1 Meetings as part of control process ...................................................169
Chapter 7
Planning Techniques ...............................................................................................172
7.1 Levels of Planning in Construction ...............................................................172
7.2 Involvement in Planning................................................................................173
7.2.1 The client (sponsor) ...........................................................................173
7.2.2 The designers .....................................................................................173
7.2.3 The contractors ..................................................................................174
7.3 Planning Techniques......................................................................................175
7.3.1 Bar-charts and linked bar-charts ........................................................175
7.3.2 Network analysis................................................................................179
7.3.3 Line of balance...................................................................................194
7.4 Other Planning Techniques............................................................................203
7.4.1 Programme evaluation and review technique – PERT ......................203
7.4.2 Space-time diagrams..........................................................................209
7.5 Computers and Construction Planning ..........................................................210
7.5.1 Preparing a schedule of activities ......................................................211
7.5.2 Resources ...........................................................................................212
7.5.3 Monitoring and control ......................................................................213
7.5.4 Cost and revenues ..............................................................................214
7.5.5 ‘What-if’ modeling ............................................................................215
7.6 Data Exchange ...............................................................................................216
7.6.1 Estimating ..........................................................................................217
7.6.2 Planning..............................................................................................218
7.6.3 Cost control ........................................................................................218
7.6.4 Valuations ..........................................................................................219
7.6.5 Variations ...........................................................................................219
Chapter 8
Least Cost Scheduling andResource Levelling .....................................................220
8.1 Introduction....................................................................................................220
8.2 Least Cost Scheduling ...................................................................................220
8.3 Important Terminologies ...............................................................................221
8.4 Variation of Direct Costs with Time..............................................................222
ix
8.5 Variation of Direct Costs with Time .............................................................224
8.6 Schedule Compression ..................................................................................225
8.7 Resource Levelling ........................................................................................230
Chapter 9
Human Resources Management.............................................................................246
9.1 Basic Principles of Resources Management..................................................246
9.1.1 Introduction .......................................................................................246
9.1.2 Nature and scope of construction projects.........................................247
9.1.3 Key resources in construction projects and their determination........248
9.1.4 Key tools in the determination of resources for a project..................250
9.2 Human Resources Management and Labour Productivity ............................254
9.2.1 Rationale for human resources management.....................................254
9.2.2 Team building for small projects.......................................................255
9.2.3 Contractor’s organization structure ...................................................257
9.2.4 Labour productivity ...........................................................................270
9.2.5 Scheduling of labour on a construction site.......................................294
Chapter 10
Equipment and Materials Management................................................................298
10.1 Introduction ...................................................................................................298
10.2 Construction Equipment Management ..........................................................299
10.2.1 Basic principles of equipment management ......................................299
10.2.2 Equipment productivity and cost control...........................................309
10.2.3 Estimation of equipment productivity ...............................................319
10.2.4 Plant and equipment maintenance .....................................................329
Chapter 11
Procurement and Management of ConstructionProfessional Services Contracts342
11.1 Introduction ...................................................................................................342
11.2 Principles of Procurement of Construction Professional Services Contracts 343
11.3 Procedures for Selection of Consultants........................................................344
11.3.1 Types of procurement of construction professional services ............344
11.3.2 Quality and Cost Based Selection (QCBS) .......................................344
11.3.3 Quality Based Selection (QBS) .........................................................346
11.3.4 Selection under a Fixed Budget (SFB) ..............................................348
11.3.5 Least Cost Selection (LCS) ...............................................................349
11.3.6 Other methods of selection ................................................................350
11.4 Procedures of Procurement of Construction Professional Services ..............351
11.4.1 Steps in the selection process ............................................................351
11.4.2 Preparation of the Terms of Reference..............................................352
11.4.3 Preparation of the cost estimate and budget for the assignment........354
11.4.4 Advertising for Expression of Interest...............................................355
11.4.5 Preparation of shortlists .....................................................................355
11.4.6 Request for Proposals ........................................................................356
11.4.7 Preparation of Proposals....................................................................358
11.4.8 Receipt and opening of Proposals .....................................................358
11.4.9 Evaluation procedure for Proposals...................................................359
11.5 Criteria for Evaluation of Proposals ..............................................................361
x
11.6 Negotiation and Award of Contract...............................................................363
11.7 Management of Construction Professional Services Contracts .....................364
11.7.1 General principles ..............................................................................364
11.7.2 Supervising consultants .....................................................................365
11.8 Performance evaluation .................................................................................368
Chapter 12
Selection of Contractors andManagement of Works Contracts .........................370
12.1 Introduction....................................................................................................370
12.2 Construction Project Procurement Using the Traditional Approach .............372
12.2.1 Construction project stages................................................................372
12.2.2 Selection of a contractor ....................................................................374
12.3 Construction Contracts ..................................................................................385
12.3.1 General principles on formation of contract ......................................385
12.3.2 Contract documents and their interpretation.....................................391
12.3.3 Conditions of Contract.......................................................................394
Chapter 13
Insurance Requirements inConstruction Industry...............................................410
13.1 Introduction....................................................................................................410
13.2 Historical Background ...................................................................................411
13.3 Principles of Insurance...................................................................................413
13.4 Insurance Policy.............................................................................................417
13.5 Major Types of Insurance Policy...................................................................417
13.5.1 Professional indemnity insurance (PI)...............................................417
13.5.2 Contractor’s all risks policy...............................................................418
13.5.3 Contractors third party liability policy ..............................................418
13.5.4 Contractors employers liability policy...............................................419
13.6 Insurance Requirements in African Construction Sector: Discussion and
Summary........................................................................................................419
Chapter 14
Claims and Dispute Resolution Mechanisms in the Construction Industry ......423
14.1 Introduction....................................................................................................423
14.2 International Projects .....................................................................................424
14.3 International Contracts...................................................................................425
14.4 Definition of Contract....................................................................................426
14.5 Types of Contracts .........................................................................................428
14.5.1 Re-Measurement form of contract .....................................................428
14.5.2 BOT form of contract ........................................................................428
14.5.3 Turnkey Projects ................................................................................429
14.5.4 Lump sum form of contract ...............................................................429
14.6 Forms of Contract Administration.................................................................429
14.6.1 International forms of contract administration ..................................429
14.6.2 The FIDIC form of contract...............................................................431
14.7 Claims in International Projects.....................................................................432
14.8 Classification of Claims.................................................................................433
14.8.1 Claims within the provisions of the contract ...................................434
14.8.2 Claims outside the provisions of the contract ..................................434
xi
14.8.3 Claims in sort...................................................................................434
14.8.4 Quantum meruit (“as much as it is worth”) claims .........................435
14.8.5 Ex-Gratia claims ..............................................................................435
14.8.6 Claims concerning disruption and delay .........................................435
14.8.7 Claims concerning delay on site handoverrights of way.................436
14.8.8 Claims concerning the execution of works......................................437
14.8.9 Claims concerning variations ..........................................................439
14.8.10 Claims concerning importation issues.............................................440
14.9 Assessment of Claims by the Engineer .........................................................440
14.9.1 Delays for which the client is responsible .........................................441
14. 9.2 Delays for which the client is not responsible ...................................442
14.9.3 Evaluating a claim for costs...............................................................442
14.9.4 Evaluating a claim for delay..............................................................442
14.9.5 Concurrent delay................................................................................444
14.10 Dispute Resolution Mechanisms ...................................................................446
14.10.1 Direct negotiation .........................................................................448
14.10.2 Mediation .....................................................................................448
14.10.3 Conciliation ..................................................................................448
14.10.4 Mini-trial ......................................................................................449
14.10.5 Claims review board.....................................................................449
14.10.6 Pre-arbitral review board..............................................................449
14.10.7 Arbitration ....................................................................................450
14.11 Impact of Claims ...........................................................................................451
14.11.1 Financial impact of claims ...........................................................451
14.11.2 Effect of claims on project completion time ................................452
14.11.3 Other effects of claims .................................................................452
14.12 Observations in Selected Ethiopian Road Projects........................................453
14.13 Proposed Changes to the FIDIC Forms of Contract......................................455
14.13.1 Instruction to tenderers.................................................................455
14.13.2 The FIDIC form of contract .........................................................456
Chapter 15
Occupational Health and Safety in the Construction Industry...........................457
15.1 Introduction ...................................................................................................457
15.2 Principles of Safety Management Systems in the Construction Industry .....458
15.2.1 Policy and planning ...........................................................................460
15.2.2 Refurbishing contracts .......................................................................471
15.2.3 Protection from excessive noise ........................................................472
15.2.4 General tools: safe use and handling .................................................473
15.2.5 Working with heavy plant .................................................................473
15.2.6 Demolitions .......................................................................................475
15.2.7 Working near existing services..........................................................476
15.2.8 Personal protection ............................................................................480
15.2.9 Working over water ...........................................................................484
REFERENCES ..........................................................................................................486
xii
Chapter 1
Civil Engineering Construction
1.1 Introduction
During the first Century BC Vitruvius is famous for asserting in his book De
architectura that a structure must exhibit the three qualities of firmitas, utilitas,
venustas – that is, it must be strong or durable, useful, and beautiful. According to
Vitruvius, architecture is an imitation of nature. As birds and bees built their nests,
so humans constructed housing from natural materials that gave them shelter against
the elements. When perfecting this art of building, the ancient Greek invented the
architectural orders: Doric, Ionic and /Corinthian. It gave them a sense of
proportion, culminating and understanding the proportions of the greatest work of
art: the human body. This led Vitruvius in defining his Vitruvian Man, as drawn
magnificently by Leonardo da Vinci: the human body inscribed in the circle and the
square (the fundamental geometric patterns of the cosmic order).
During the eleventh and twelfth centuries, buildings and other structures were
constructed using a master builder system. Masons, carpenters and labourers were
itinerant workers who traveled from job site to job site in search of work. The master
2 Fundamentals of Civil Engineering Construction Management
During the twelfth century a much more formalized system centered on craft guilds
began to develop. By the beginning of the thirteenth century, building industries in
Europe were organized around the craft guild system (Salzman 1952; Harvey 1972).
These guilds took on the responsibility for training building craftsmen. Much as in
earlier centuries, some master masons or carpenters became employers of skilled
craftsmen and took on the responsibility of design, coordination and supervision
(Mitchell, 1977). The structure of the medieval building team is illustrated in Figure
1.1.
Client
Master Builder
Due largely to The Great Fire of London around 1666, the system shown in Figure 1
could not keep pace with the speed of reconstruction required by industry and the
general public (Mitchell, 1977). Individual craftsmen began to form their own
companies and to compete for work. Engineers and architects began to separate from
craftsmen. They usually tended to be formally educated rather than artisans or
craftsmen. Quantity surveyors also began to appear and were generally synonymous
Civil Engineering Construction 3
with architects. The structure of the building industry during this time is shown in
Figure 1.2.
Client
Quantity Surveyor
Architect
Client
Architect
Prior to the Renaissance, there is little evidence of written history proclaiming that
the artist, engineer and architect, were more honourable professions, as viewed by
society, than the stonecutter and labourer. However, during the Renaissance (1400's
to 1600's) intellectuals began to judge, classify, and stratify manual work of which
they had little or no knowledge (Gimpe, 1983). This stratification and classification
are reinforced in the writings of Leonardo de Vinci. It is interesting to note that both
architecture and engineering, as academic disciplines, recognized that in order to
achieve professional status as viewed by society, and in order to be accepted as an
academic discipline they had to first separate themselves from the manual processes
of construction. Additionally, they had to redefine the terms so that architecture and
engineering were not synonymous with construction and with each other.
the Flemish canals; the Dutch sea defenses; the French Gothic cathedrals; and many
other monuments reveal a history of inventive genius and persistent experimentation.
It was not until 1802 when curricula in military engineering were developed at the
Military Academy at West Point, that engineering programs in the United States
were begun. These programs were patterned after the French programs, which
concentrated on theoretically, oriented engineering education (Reynolds, 1991). By
1860 there were only a half dozen successful civilian engineering programs in the
United States. With the passage of the Morril Act in 1862, establishing agricultural
and mechanical colleges, civilian engineering programs grew rapidly. There were
approximately seventy such programs by 1872 and eighty-five by 1880 (Reynolds,
1991). Many of these programs were initially weak and were often not viewed as
scholarly (Pletta, 1984). It was the graduates of West Point who were hired as faculty
during the 1860's that brought both academic respectability and theoretical based
6 Fundamentals of Civil Engineering Construction Management
engineering education to these early programs. By 1868 over one hundred West
Point graduates were faculty in these programs (after the Civil War there was an
abundance of engineers seeking employment who had been trained at the military
academies).
There was, for approximately the next thirty to forty years, a continuous struggle
between apprenticeship and on the job training methods for engineers and academic
engineering education. However, economic forces were again to permanently change
the engineering educational system and the engineering profession. The late
nineteenth century witnessed tremendous growth in American industry.
Apprenticeship and on the job training techniques could not keep pace with the
demand for engineers. Academic engineering programs could meet this demand.
Thus, by the late 1890's, academic methods for training engineers were firmly
established as the predominant method for training engineers in America (Reynolds,
1991). Additionally, what had emerged was a system, which was general, based in
theory but which retained, to varying degrees, some hands on training; i.e.,
labouratory and fieldwork (Reynolds, 1991).
World War II provided the engineering education still in existence today. Prior to
World War II, engineering education still retained some of its hands-on training and
some of its practical focus. However, World War II and later high technology events
sharply tilted engineering education toward science, mathematics, and theory
(Reynolds, 1991). To continuously tap into readily available research money
provided for scientific research to meet new demands, engineering programs needed
graduate programs, graduate students and curricula which prepared undergraduates
for cutting edge research (something academicians had been left out of during World
War II). Thus, in the 1950's and 1960's, engineering schools reduced or eliminated
their hands on and practical courses and added more mathematics and science
courses. By 1970, engineering education closely resembled science education in both
organization and emphasis (Reynolds, 1991). Engineering used this adoption of more
science and mathematics to further distance itself from lower status personnel such
as skilled craftsmen and technicians (Reynolds, 1991). Most of the educational
Civil Engineering Construction 7
laws, provide canons of ethics and provide guidelines for an industry relevant
education are to continue. These organizations’ memberships are low. However, a
study of history shows that the participation and membership of architecture and
engineering societies were also very small (by some estimates less that 10% of the
industry). Yet they were influential in redefining their disciplines and in their
attempts to pass legislation with regards to licensure and registration. Similar to
architecture and engineering professional organizations, construction professional
organizations have extremely low membership and participants when compared to
the entire industry. However, these organizations should learn from the history of
architecture and engineering professional societies and press for change.
Lefkoe (1970) proposes that construction companies should expand their definition
of the meaning of construction. They should not view their services as the on-site
fabrication of the production of products, but as providing value satisfactions. The
satisfaction of a client's desires and requirements for manufacturing products,
treating sick people, generating electricity, housing people, educating people, etc.
should be the goal of the constructor. In lieu of simply building a structure,
constructors should make it as easy as possible for customers to obtain the value
satisfactions that the structure ultimately provides. This definition is consistent with
current efforts to introduce total quality management, partnering, and other modern
management techniques into the industry. Constructors who apply this definition will
take control of the entire construction process (Lefkoe, 1970).
instances, electrical and plumbing and mechanical subcontractors have more actual
risk than the general contractor.
Having been developed by industry, construction programs have never based their
academic discipline on theory. Instead, they were designed to fulfill the immediate
needs of a highly fragmented and diversified construction industry. This resulted in
fragmentation and diversification in the construction programs, which had been
established to specifically address regional needs. Most programs were and continue
to be located in departments such as civil engineering, architecture, industrial arts,
business and agricultural engineering due to the interests and efforts of one or two
faculty members (Construction Industry Cost Effectiveness Report A-5, 1982). The
initially small faculty numbers, the requirements of the wide variety of departmental
locations, the distinct regional industry needs, and the wide variety of faculty
backgrounds, have prevented construction from having a clear focus and from being
accepted as a distinct academic discipline. These same factors have continued to
shape the course content of construction education and thus prevent the development
of any theory-based curriculum. To the present day, this highly diverse curriculum
has adequately served the industry. However, the economic conditions of the past
decade and the rapidity of technological advances have permanently altered the
needs of industry and thus the curriculum requirements for construction programs in
university and college setting. A study carried out by Dorsey (1990) shows that
formal education should be responsible for only 30% of the skills/traits, which are
needed to perform in construction management positions. Dorsey's (1992) study also
shows a hierarchy of priorities for construction curricula, as provided through
surveying industry and academia as follows:
i) Numerical (mathematics, computers, problem solving);
ii) Written Communication;
iii) Oral Communication;
iv) Graphic Communication;
v) Financial Management;
vi) Planning and Control;
12 Fundamentals of Civil Engineering Construction Management
It should be noted that the focus of this hierarchy, is management and not
engineering, architecture, or the wide variety of focuses found in construction
programs today.
Another consequence which must be carefully examined is the result of the adoption
of a common theory based in management. If programs become so theoretically
based, as many programs in architecture and engineering have, then contact is lost
with the construction industry and their needs. This results in construction education
programs failure to provide qualified and respected graduates. If the focus of
educational efforts becomes graduate level study and research as has occurred in
civil engineering, then programs undoubtedly will fall victim to the golden ru1e "The
Civil Engineering Construction 13
one with the gold makes the rules". Care must be taken when basing our curriculum
on theory, that the curriculum does not loose sight of reality. If it loses sight of
reality, programs will lose their industry support.
Lastly, construction programs should consider the question "Is what we're leaving
worth what we're adopting?" Undoubtedly, a widely varied educational curriculum,
which many have viewed as strength, will be sacrificed. This type of program served
the industry well for several decades. However, just as economic forces forced
change in engineering and architecture, economic forces are forcing academia to
change in response to the needs of industry. These revised needs are much more
management based. Today's economy demands certainty as early as possible in the
construction process. This is best accomplished when a constructor is involved as
early in the process as possible. Earlier involvement requires an expanded definition
of construction, an increased emphasis on management skills, and a revised
curriculum to meet these demands.
Insistence on the status quo will only hinder the evolution of the industry in tandem
with developments in other industries such as information technology. The
construction industry has always been slow to react innovation generally mainly
because of the many different sections of the industry. However, these many
segments of industry shall be coordinated better if the industry adopts a common
theory based on management.
Chapter 2
The Members of The Construction Team
The promoter (also known as client) is the most important member of the
construction team without whom work would simply not exist. The word client is
more often used than promoter and, therefore, it will be used throughout the chapter.
The energies of the whole profession revolve around the client. The suggestions by
many people that the role of the industry is to give the client exactly what it wants
are to a large extent valid. However, others would argue with greater conviction that
the client should receive what it needs. For this reason, part of the responsibility of
the industry should aim at the education of the client in order that its real needs are
established. Expertise should be exercised in order that both its short-term and,
equally important, its long-term needs are fulfilled. The client should be given a
comprehensive service worthy of the construction industry. The sources of clients
include the following.
The public sector consists of work commissioned by publicly financed sources that
may include, among others:
(i) a local authority: A local authority may require a contractor to build a library
complex;
(ii) a government department: The department of Employment may approach a
number of contractors to submit tenders for work involving altering of an
existing structure, in order that it may be used for the conducting of Industrial
Tribunals;
(iii) a statutory authority: A region of the power generating board may require a
small generating station to be constructed; and
(iv) a public undertaking: A region of the Water Board may approach a number of
constructors to submit tenders for the construction of a showroom in a small
market town.
The client, as the financier of the work, is the employer of the other members of the
construction team. The consulting engineer, private quantity surveyor, specialist
engineers, resident engineer, clerk of works and contractor are all employed by and
are responsible to the client. Its interests should, therefore, be uppermost in the minds
of all these parties.
Throughout the project, the client would, of necessity, take legal advice from its
solicitor who would also, if requested, advise on financial matters. The client could,
if its own funds are insufficient, seek capital from investing public and financial
institutions.
Effectively, the client pays out large sums of money in the form of stage payments
for a facility, which it has not yet received. The client, therefore, is faced with the
situation of tying up its own funds or borrowing capital in the interim period between
the commencement and completion of the works. Only when the project is handed
over to it on completion does it become available for its use.
The Members of The Construction Team 16
In summary the client’s responsibilities and duties are normally written into the
memorandum of agreement with the Engineer and the contract for construction and
are generally:
(i) to define the functions that the project is to perform;
(ii) to provide information and data held by it and required by the Engineer;
(iii) to obtain the necessary legal authority to allow construction of the project;
(iv) to obtain money to finance the project; and
(v) to acquire the necessary land.
In the private sector, however, the process is different and is represented in the form
of a diagram (Figure 2.1) outlining the roles and relationships of the parties who
form the construction team. To understand the workings of the industry, it is not only
necessary to recognize the major parties, but also to be able to appreciate and
develop a clear awareness of the relationship between (and the duties and
responsibilities of) the individual members of the team.
17 Fundamentals of Civil Engineering Construction Management
Sources
of Client Solicitor
Finance
Consulting Structural
Other
Consultants Engineer engineer
Nominated
Nominated Sub- Resident
Suppliers Contractors engineer
Factory
Main Contractor inspector
Labour-
Suppliers Sub- Plant only Sub-
Contractors Hirers Contractors
Figure 2.1 The main parties involved in the process of civil engineering.
The Members of The Construction Team 18
The construction team is most often composed of the parties listed below; no attempt
has been made to arrange the members by level of importance as they all make a
significant contribution to the process of construction.
i) Consulting engineer;
ii) Private quantity surveyor;
iii) Structural engineer;
iv) Service engineer;(s)
v) Resident engineer;
vi) Clerk of works;
vii) Supplier(s);
viii) Subcontractor(s);
ix) Plant hirer(s);
x) Building control officer;.
xi) Factory inspector; and
xii) Contractor.
The Engineer’s role is complex and brings with it responsibilities to the community
for the environment that he/ she creates, to the engineering profession for upholding
standards of performance and conduct, to the fellow members of the construction
19 Fundamentals of Civil Engineering Construction Management
team for a well designed and documented structure and moreover to the client for the
creation of a structure equal in performance to the standards of his/ her profession.
Engineers are governed by a strict code of conduct, and rigid guidelines govern the
advertising of their services. For ethical reasons they cannot hold directorships
within construction companies. They usually operate as sole traders or partnerships
and sometimes operate as consortia. The main duties of the Engineer are as follows:
(a) Offering advice of a competent nature. As a professional person, the consulting
engineer is liable for his/her actions should he/she show professional
negligence;
(b) Providing services to enable the project to proceed in an efficient manner. The
services include the production of adequate working drawings, site inspections,
approval of workmanship and materials and resolving constructional problems
as and when they occur on site;
(c) Advising on all matters regarding statutory regulations, contractual matters and
other controls, e.g., Planning controls etc.;
(d) Co-ordinating the construction team to ensure that optimum use is made of the
expertise, which is available; and
(e) Supervising the work of the team members and agreeing variations in order to
ensure that the client’s requirements are fulfilled.
Whereas the Engineer has the responsibility to ensure the desired quality is achieved,
it is not the role of the Engineer to instruct the contractor on the method of
construction. The Engineer specifies what is required; the contractor decides how it
is achieved. This may, however, vary in certain situations, usually arising out of the
specific contractual conditions governing the parties.
The strict guidelines governing advertising severely limit the methods by which an
Engineer can secure work (referred to as commissions). In an industry which
experiences severe changes in workload, this can create a huge problem; however,
common methods of securing work are as follows:
The Members of The Construction Team 20
Whichever methods of securing work are used, it is important to bear in mind that
long-term success is best achieved by fulfilling the needs of existing clients. A good
reputation is created over a great length of time, but can be destroyed in a very short
period.
be constructed within predefined cost limits. His/her major objective is to provide the
client with the structure it requires at an economic price, giving it the best value for
its money, at the same time allowing an efficient contractor an equitable profit
margin.
The private quantity surveyor should be appointed at the earliest possible stage in a
project and should play a major role in the design procedure. His/her duties include
the following:
(a) Giving preliminary advice and “approximate estimates” of what a project will
ultimately cost.
(b) Advising on the form, size and standard of structure and finishing that can be
erected within the predetermined sum of money.
(c) Preparing an over-all “cost plan” and “budget” stating exactly where and when
the client’s money is to be expended in a project. This enables the client to
achieve the correct balance of expenditure throughout the whole building, and
also allows a check to be made during the pre-contract period that the money
allocated to be spent within the client’s expenditure limits.
(d) Preparing the necessary tender inquiry documents, including the bill of
quantities, and arranging the necessary formal contract with the successful
contractor.
(e) Preparing and agreeing the valuation of work completed by the contractor and
subcontractors at the interim periods stated in the contract.
(f) Controlling the costs of a project during all stages, and advising the client of
the anticipated total expenditure on the final product.
(g) Preparing and agreeing the final account of the project (the total financial
settlement to the contractor at the completion of the work). The contractor
The Members of The Construction Team 22
should receive equitable payment for all variations or work additional to that
which he/she contracted to undertake.
(h) Analysing the project costs, so as to provide feedback data in order to forecast
the cost of future work.
The consulting engineer decides what is required and the structural engineer suggests
the structural form by which it can be achieved. He is therefore responsible for the
stability of the structure, and will design such elements as foundations, piers,
abutments, pylons, bridge decks etc. The structural engineer must have a scientific
background in order that he/she may apply mathematical concepts to calculate the
sizes and material properties of the various structural components within a structure.
He must be conversant with the relevant Regulations and Specifications relating to
structural methods and materials.
The role of the structural engineer is demanding and his/her duties include the
following:
(a) Investigating and advising on the structural feasibility project at the design
stage. He/she would advise on the material approximate size of the various
structural components.
23 Fundamentals of Civil Engineering Construction Management
(b) Preparing and seeking approval of working drawings schedules. The drawings
would include structural steelwork, concrete work and the related bending
schedules specifying the types and size of steel reinforcement.
(c) Supervising the erection of the structure checking that the correct type, quality
and quantity of materials been used and the workmanship is of a satisfactory
nature.
(d) Checking and advising on the work of other specialists, as piling
subcontractors or pre-cast concrete suppliers.
To comply with comfort from the environment in which people operate, great
demands are placed on the consulting engineer to produce a structure free of
environmental problems that have simply been accepted in the past. No one person
can be expected to be expert in a wide range of activities; therefore, on complex
structures it is common for the consulting engineer to recommend the client to
appoint specialists in some of the following areas of work:
(i) Fire precaution - alarm and sprinkler systems;
(ii) Heating - electrical, gas, oil, solar energy and solid fuel;
(iii) Acoustics - sound insulation and absorption;
(iv) Air conditioning heating and refrigeration;
(v) Sanitation - above and below ground level;
(vi) Telecommunications - switchboards, internal and external systems;
(vii) Lighting natural and artificial;
(viii) Refrigeration freezing compartment and cold storage areas;
(ix) Transportation-lifts, conveyors and escalators; and
(x) Ventilation natural and mechanical.
The engineer(s) should be appointed at the earliest possible stage and it is essential
that the work and drawings of the specialists is coordinated with the efforts of the
other members of the design section of the construction team.
The Members of The Construction Team 24
For example, the sanitation engineer would be required to liaise with the structural
engineer in connection with the sizes of openings he/she would require to allow the
drainage conduit to pass through the structural section of a road. The consulting
engineer would also have to coordinate the work of the sanitation engineer in order
that the conduit passes within one layer of the structural road section.
The duties of each service engineer reflect to the individual service he/she provides
but may include:
(a) investigating and giving advice on the requirements and feasibility of services
at design stage;
(b) preparing and seeking approval of working drawings and related schedules
associated with the provision of services; and
(c) supervising the services element within the structure.
The resident engineer is appointed by the consulting engineer and acts as his/her
representative on site.
The function of Resident Engineer (RE) is to watch and supervise on a day to day
basis the construction and maintenance of the project. Depending on the size of the
project, the RE may have assistant staff under him/her. Such staff, particularly the
clerk of works and inspectors, should be selected with regard to their practical
experience of the type of work to be supervised. While his/her assistants deal mainly
with detail, the RE must plan ahead and discuss future parts of the Works with the
Agent of the Contractor to ensure that the phasing of the Works is properly planned
to suit the approved programme. This close collabouration of RE and Agent also
facilitates consideration of changes proposed by the Contractor, and the subsequent
submission of such proposals to the Engineer for approval. The principal duties of
RE are:
(a) to organize his/her work to suit the approved programme;
(b) to co-operate closely with the Contractor on matters of safety;
25 Fundamentals of Civil Engineering Construction Management
(c) to supervise the Works to check that they are executed to correct line and level
and that the materials and workmanship comply with specifications;
(d) to examine the methods proposed by the Contractor for the execution of the
Works, the primary object being to ensure the safe and satisfactory execution
of the permanent work;
(e) to execute and/ or supervise tests carried out on site, and to inspect materials
manufacture at source where this is not done by the Engineer’s head office
staff;
(f) to keep a diary constituting a detailed history of the work done and of all
happenings at the site, and to submit periodic progress reports to the Engineer;
(g) to measure in agreement with the Contractor’s staff the quantities of work
executed, and to check daywork and other accounts so that the interim and final
payments due to the Contractor may be certified by the Engineer;
(h) in the case of any work for which the Contractor may claim payment as
additional work, to agree with the contractor and record all relevant
circumstances so as to ensure that agreement exists on matters of fact before
any question of principle has to be decided by the Engineer;
(i) to record the progress of the work in comparison with the programme; and
(j) to record on drawings the actual level and nature of all foundations, the
character of the strata encountered in excavation and full details of any
deviations from Drawings which may have been made during the execution of
the Works, i.e., to produce all record drawings.
A competent RE must have three very important qualities integrity, ability and
vigilance. He/she must possess a high degree of tact when dealing with people, the
ability to persuade rather than dominate and above all, he/she must have a sharp eye
for detail. To acquire these assets, many people believe it is necessary to have a great
deal of experience working on construction sites.
It is important for the resident engineer to create a good working relationship with
the contractor’s site manager on the project. The contractor in return must provide
The Members of The Construction Team 26
him/her with every reasonable insight which normally includes the exclusive use of a
site office that is well equipped and has a private telephone.
Satisfactory supply of both raw and manufactured materials is necessary for smooth
completion of any construction project. It is essential that close cooperation is
achieved between the contractor and his/her supplier in order that the client’s needs
are fulfilled. Suppliers are selected not only on the basis of price, but also with
reference to quality and delivery in time.
Three sources of material supply are possible: direct from the source of raw
materials; the manufacturer; and the builder’s merchant or a material agent. Bulk
materials such as sand and stone that may form a major part of a project are often
obtained direct from the source of the raw material, whereas manufactured items,
such as cement, can be purchased from the manufacturer. Agents may also be
appointed by manufacturers, such as paving companies, to supply large quantities of
materials to individual users. The contractor may also obtain materials from a
builders’ merchant; however, this method is not usually favored for bulk supplies
because it usually results in an inflated cost.
In addition to the contractor’s own suppliers, the consulting engineer may specify
that a certain supplier must be used which is therefore term a “nominated supplier”.
Whichever source of material supply the contractor decides to use, it is essential that
an official order is placed, clearly stating the terms and conditions of the transaction.
(e) delivering materials of the required quality and quantity, at the agreed price
and in accordance with the contractor’s delivery requirements; and
(f) advising the contractor on any special storage requirements the materials.
The construction industry is well-known for its wide variety of tasks; however, the
vast majority of contractors only employ experienced operators in major trades such
as machine operators, pavers and occasionally, carpenters. The remaining work,
which can represent between 50 and 75 per cent of the total value of a structure, is
carried out by specialist subcontractors. The contractor generally sublets such trades
as piling, structural steelwork, heating and ventilating, drainage and electrical work.
The subcontractors generally supply and fix their own materials, the main contractor
coordinating their work.
Certain contractors favour the use of labour-only subcontractors. They are often
referred to as “lump labour”, because the self-employed operatives contract their
labour to fix the contractor’s material for a lump sum payment.
The practice of labour-only subcontracting has been the cause of much controversy
over the years. Bodies such as the trade unions suggest that the system of the “lump”
leads to poor standards of workmanship, tax avoidance, and poor conditions of work
for the labour force. Others would argue that the system of labour-only sub-
contracting is a means whereby contractors can accommodate the great fluctuations
in demand and the high cost of employing permanent labour within the industry. As
governments have passed successive legislation such as the Employment Protection
Act and have chosen to impose a wide variety of employment taxes, pressure has
been placed on the main contractor to use such services.
The consulting engineer can also nominate subcontractors to carry out work; these
are therefore termed nominated subcontractors. The main advantages associated with
the use of specialist subcontractors, be they nominated by the engineer or the
contractor, or working on a labour-only basis, are that they have detailed specialist
The Members of The Construction Team 28
knowledge well in excess of the main contractor, have access to specialist advice and
training within their own organizations, they are usually competitive in price, they
employ operatives who are exclusively engaged in the specialist work, and they
eliminate the need to employ operatives for whom the contractor does not have
continuity of workload.
(c) advising contractors on the selection and output of plant in relation to function;
(d) maintaining plant in an efficient working order; and
(e) arranging transportation of the plant in accordance with the contractor’s
instructions.
The success of the whole industry ultimately depends on the contactor, that is, the
firm, who actually carries out the work. All others participants are, either directly or
indirectly, served by the contractor.
restrictions. Part of the work may be wanted first for reasons outside engineering. In
such cases the Engineer usually specifies the necessary requirements, but it may still
be possible and desirable to allow the Contractor to submit alternative proposals for
meeting them.
The significance of cash flow to the contractor hardly needs to be emphasized and it
is not surprising that the incidence of bankruptcy is high. Many contractors
experience rapid growth during which time the practical constructor does not always
mature into an effective financial manager.
Several studies have shown that there is a predominance of small firms within
construction, which no doubt reflects the ease of setting up a business. Often, these
firms set up as a one-man business, but as it expands there is a need to employ
personnel to carry out the increased workload.
To oversee the construction process that has been fragmented over the years the
industry has embraced the concept of the construction project manager and a number
of countries have already taken this on board. The main function of the construction
project manager is to coordinate a construction project from inception to completion
and ensure that it needs the key success parameters of cost, time, utility and quality.
31 Fundamentals of Civil Engineering Construction Management
The countries such as South Africa that have adopted this concept have established
regulatory structures that ensure practicing construction project managers have the
required qualifications and experience.
It is not possible to trace more than a general pattern among contractors’ head office
organizations. Contractors include both public and private companies, and firms
with varying financial and other resources and records of experience. Accordingly
methods of business operation and details of internal organization differ
considerably. The contractor’s head office is usually the centre from which the
board of directors controls the whole of the organization. Clear thought must be
given not only to the duties and grouping of the various sections and departments but
also to the interrelationship between them.
Figure 2.2 Typical organizational chart for a medium to large-size road contractor.
33 Fundamentals of Civil Engineering Construction Management
The major sectors are responsible to the Managing Director who can also be referred
to as the General Manager of the firm. He/she may be advised by the Company
Secretary on legal points and by outside Consultant Firms on matters in general. The
main individuals in the head office structure include the following:
(a) Contractor’s quantity surveyor;
(b) Planning engineer;
(c) Work study; engineer;
(d) Bonus surveyor;
(e) Estimator;
(f) Buyer;
(g) Personnel officer;
(h) Industrial relations officer;
(i) Safety officer;
(j) Plant manager;
(k) Contracts manager;
(l) Wages and accounts manager; and
(m) Office supervisor.
The contractor’s quantity surveyor carries out a parallel role to that of the private
quantity surveyor as the contractor’s “construction economist”. He/she looks after
the interests of the contractor during all negotiations and it is his/her objective, in
conjunction with the management team, to offer advice to ensure that effective
economic decisions are made in order to achieve an equitable profit for his/her
employer.
He/she must possess similar qualities to those of the private quantity surveyor, in
order that he may carry out some of the following duties, which may vary according
to the size or type of firm.
(i) Analysis of “cash flow” associated with the project in order that the contractor
is aware of his/her financial requirements
(ii) Requisitioning the materials to be used in the project.
The Members of The Construction Team 34
(c) Preparing short-term programmes, which review in detail the contractor’s work
over a short period of time. (The programmes are usually of one, seven or
twenty-eight days’ duration.)
(d) Preparing schedules of the contractor’s resource requirements.
(e) Preparing site layouts showing the positioning of huts, compounds, stores etc.
(f) Establishing the most economical methods of working and seeking greater
productivity for the contractor.
(g) Preparing schedules of labour incentive rates in conjunction with (and to be
ultimately issued by) the bonus surveyor.
(h) Establishing feedback information of the actual methods used to carry out the
operations, and their duration for future planning and estimating purposes.
The work study engineer examines work to improve its efficiency and economy, i.e.
its productivity. He works in close liaison with the planning engineer and site
manager to achieve this objective. An increasing number of construction
organizations have work study sections; however, in addition, most managers and
engineers adopt a work study approach in solving everyday problems.
The work study engineer’s work can be divided into two major areas: Method Study
and Work Measurement. When examining an operation, he/she initially carries out a
Method Study, which is a systematic technique concerned with the reduction of the
work content associated with a job, and seeks easier and more efficient ways of
performing the operation. Having established the best method to do the job, the
engineer then carries out the Work Measurement process to eliminate the ineffective
time associated with the job and to establish time standards for the operation. The
“standard time” for a task is the amount of time that it would take an average,
qualified person, working at a natural pace, to complete a job, providing that he/she
is sufficiently motivated and using the correct method. “Organization and Methods”
is a term used to describe the adoption of work study techniques to investigate
problems of an administrative nature in an office situation.
The Members of The Construction Team 36
The work study engineer must develop a clear, logical and objective approach to
his/her work. He/she must be able to listen to, assess the contribution of, and
moreover, gain the co-operation of all personnel within the construction team. In
order to achieve this aim, it is essential that he/she involves the people within his/her
study who are to carry out the operation.
If people are involved in an investigation, they will feel they have contributed
towards the achievement of an efficient method of work. If people are not involved,
the following statement may assume an unfortunate significance: “If people don’t
want to make something work, it never will work.”
The bonus surveyor is responsible for the operation of a contractor’s bonus incentive
scheme. An “incentive scheme” is a system of payment in which the amount earned
over and above a person’s basic wage is dependent on the amount of work
completed, thereby offering the employee an incentive to achieve better results.
The bonus surveyor issues the operative a target or bonus rate for each item of work.
The individual rates are usually fixed by the planning engineer working in
conjunction with the bonus surveyor and/or the work-study engineer. The bonus
surveyor subsequently measures the work and calculates the total value of work
completed over and above the basic amount, and then the balance is authorized as a
“bonus payment”. Most bonus schemes allow a man working at average pace to
achieve a bonus incentive payment of between 25 per cent and 33 per cent of his
basic earnings.
37 Fundamentals of Civil Engineering Construction Management
The advantages associated with an incentive scheme are numerous, arising out of the
high motivation of the participants. Poor timekeeping, slow working and absenteeism
of operatives is kept to a minimum, allowing the project to progress at a faster pace,
thus reducing the duration of the contract and hence the corresponding overhead
costs to the contractor. For example, if by achieving greater productivity the project
is completed a month ahead of schedule, the contractor saves four weeks’ charges for
site cabins, hoardings, site management salaries etc.
The bonus surveyor must be capable of negotiating with operatives at site level and
must adopt a firm but fair attitude to his/her work. The role of the bonus surveyor is
viewed by many as an excellent training ground for the newcomer to the industry.
He/she rapidly acquires knowledge of the technology of construction and develops
an awareness of the intrinsic value of good industrial relations.
In a competitive tendering situation, when the private quantity surveyor has prepared
the bill of quantities, it is sent with the other tender documents to the contractors who
wish to submit a price for the job. The estimator’s major role is to establish the
estimate of the overall cost of the job by calculating a price for items included in the
bill of quantities. He/she does this by analyzing each item into its constituent parts
(labour, plant, materials and equipment) and then applying rates to each part, which
represent the amount that it will cost the contractor to do the job. The estimator must
also include sums of money, normally as a percentage addition, for overheads which
provide for a wide range of items such as head office rent, rates and heating costs,
management salaries, stationery or telephone charges.
The Members of The Construction Team 38
The estimator must also decide which items of work the contractor is not able or does
not want to carry out. The relevant sections of the bill of quantities are normally
photocopied and forwarded to subcontractors for separate quotations. Usually the
most competitive prices are entered into the bill.
When the estimator has priced all of the items in the bill of quantities, he/she submits
his estimate of the over-all cost of the project to the senior management of the firm
who adjudicate on the amount of profit, which is required from the job. The size of
profit to be added will vary from time to time, dependent upon the contractor’s
current workload and the general level of demand within the industry. The estimator
then takes the estimate figure and adds to it the profit margin to give a final price,
which is known as the tender sum of the project.
The estimator plays a vital role in a firm. He/she must be capable of working under
great pressure and must possess a high degree of technical knowledge and
forecasting ability. If his/her calculations are high the contract will be awarded to
his/her competitors; if his/her price is too low, the potential profit may be non-
existent.
On receipt of a requisition form from the contractor’s quantity surveyor, the buyer
invites suppliers and subcontractors to submit quotations to supply materials or carry
39 Fundamentals of Civil Engineering Construction Management
out work. The buyer carefully analyses the quotations in order to isolate the most
beneficial terms for the contractor.
The buyer will often order materials directly from builders’ merchants or, should the
quantities prove sufficient, direct from the manufacturers. By building up long-term
relationships and ordering bulk quantities, the buyer is often able to negotiate
substantial discounts for the contractor. Some building firms allow individuals to
order materials directly from approved suppliers, but it is a normal practice to carry
out the buying function from the central head office in order to secure the best
possible terms for the contractor.
The buyer must therefore possess the skills of a negotiator, the presence of a planner,
the awareness of a technologist and above all must develop skill for a bargain. The
duties of a buyer may include:
(i) inviting and analyzing competitive quotations to allow beneficial orders to be
secured for materials and subcontract services;
(ii) maintaining a list of current costs of materials and services to used for
estimating purposes;
(iii) anticipating and advising management of price fluctuations; and
(iv) maintaining a follow-up system in order to call forward materials when
deliveries are imminent, and to advise subcontractors when their services are
required on site.
Whilst it is rarely possible for the personnel officer to deal with the recruitment and
dismissal of site labour in person, many organizations insist that all changes in work
strength are authorized and coordinated by him/her. The actual physical hiring and
firing of site labour is usually carried out on site by the contracts manager.
As well as supervising personnel procedures, the officer is usually responsible for the
recruitment of all managerial and technical staff. He/she must, therefore, possess a
wide knowledge of all the functions of the members of the team and be perceptive in
reviewing the capabilities of potential employees. The occurrence of these
characteristics is rare and difficult to attain, other than by experience.
The personnel officer’s duties will differ from firm to firm but may include:
(i) selecting and recruiting managerial and technical staff;
(ii) authorizing and coordinating the recruitment, transfer and ultimate dismissal of
site-based operatives;
(iii) advising on all matters relating to employment;
(iv) supervising the training and development of all employees;
(v) maintaining adequate employment records for all personnel; and
(vi) maintaining an effective channel of communication between all employees and
senior management.
The duties of the industrial relations officer are flexible but may include:
(i) negotiating with employee representatives (trade unions) in order to secure
industrial harmony;
(ii) foreseeing potential areas of industrial unrest;
(iii) investigating and advising management on all matters relating to industrial
relations; and
(iv) providing a channel of communication between all parties in connection with
industrial grievances and disputes.
The role of the contractor’s safety officer should not be confused with that of the
factory inspector. The contractor’s safety officer is employed directly by the firm and
as such he/she is the contractor’s representative on all matters relating to safety,
health and welfare. The Factory Inspector is an employee of the Government and has
a legal obligation to ensure that the various legal provisions are complied with: in the
event of non-compliance he/she must take such sanctions as deemed necessary in the
situation.
The plant manager is responsible for all aspects relating to mechanical plant
(machinery) within a firm. He will therefore be required to select the right machine
to carry out a particular function in a certain situation. Although it depends on a
firm’s policy, it is normal practice for a contractor to own items of machinery for
which either there is a continuous use or which are difficult to obtain on hire. Other
plant can be hired so that the contractor only pays for the machine when it is
physically operating. The contractor can thus be sure he/she is using the ideal
machine to perform a particular task and that it is the up- to-date model working at
peak performance.
The wages and accounts manager controls the wages, costing and accounting
functions of a business. Many medium and large contractors make use of computer
techniques in order to carry out the processes in a prompt, efficient manner.
In some firms, all wages and salaries are processed through the wages section;
however, other contractors make use of consultant firms for staff salaries, which are
regarded as confidential in nature. The costing section ensures that all expenditure is
allocated to the source, i.e. site or department, which was instrumental in incurring
the cost. The total expenditure over any period can then be analyzed against the
budgeted (allowed) expenditure or the income from any source. The accounts section
ensures that payment is made to the sources that have supplied goods or services.
The duties of the wages and accounts manager are wide, but may include:
(i) supervising and controlling the wages, costing and accounting functions within
a firm;
(ii) providing financial and statistical data required by outside bodies, e.g. V.A.T.,
P.A.Y.E.; and
(iii) advising management of the current financial position of any site, department,
or of the business as a whole.
The typing supervisor performs an important function in any organization and must
be able to recognize the priority of items of work. The section may also be
responsible for the issue of stationery and reprographic services within the firm.
Civil engineering structures are rarely alike. Consequently each construction site has
an individual organization structure. The organization of construction projects not
only differs from contractor to contractor, but also from site to site within a single
firm. The organization structure of any project is dictated by the size and nature of
the project, the effectiveness of the personnel involved, the needs of the client and
also the current workload of the contractor.
The site organization chart (Figure 2.3) shows a structure designed to meet the needs
of a 5 km road project. Members of the following sections visit the site to carry out
the duties described earlier:
(i) Quantity surveying;
(ii) Bonus surveying;
(iii) Work study;
(iv) Planning;
(v) Personnel;
(vi) Industrial relations; and
(vii) Safety.
The respective representatives work in close liaison with the site manager and act in
a support capacity; however, they are ultimately responsible to their individual heads
of departments for the performance of their function.
On larger projects, the members may be based on site and certain contractors would
arrange that they then become responsible to the resident projects manager for the
duration of a particular contract. The projects manager would have a similar status to
a contracts manager; however, he would carry out his duties on only one, albeit large,
project. At the end of the project, the functional personnel would return to their
respective head office sections and the projects manager would move to a further
contract. Site management would also be able to call upon the remaining service
departments for advice and assistance with relevant problems.
45 Fundamentals of Civil Engineering Construction Management
It would not, however, be normal for the representatives of the following to visit site
on a regular basis: estimating; buying; plant; wages and accounts, and typing.
The site management team is headed by the contracts manager. He/she visits the site
from time to time in order to coordinate and supervise the work of the remaining
members of the team which include the following: site manager, general foreman,
trades foreman, ganger, charge hand, operative, site engineer and site clerk/materials
controller.
He/she and his/her site management team must be proficient in all of the seven
processes of management. The major portion of the contract manager’s time is taken
up with carrying out the “thinking” processes of forecasting, planning and
organizing. The “doing” processes of motivating, coordinating and controlling,
whilst forming an important part of his/her duties, adopt a lower significance.
If the role of the contracts manager is contrasted with the supervisory tasks of the
charge hand, the reverse situation is found. The charge hand is mainly concerned
with the “doing” processes, that is putting into action the plans of senior
management.
The site manager sometimes called the agent, as the contractor’s senior
representative resident on site has complete responsibility all personnel employed on
the site. He/she is directly responsible to contracts manager and his/her aim is to
achieve maximum productivity within the limitation of the resources he/she has
available to him. He/she should be involved with the project at the earliest possible
stage a make a major contribution to the planning of the contract.
In the past, site managers have usually been selected from a craft background, but
with the developments in management education at technician and professional level
the site manager with a academic background is coming to the fore. He/she should
have similar characteristics to those of his/her superior, the contracts manager, but
with a higher emphasis placed on the ability to lead and motivate his/her workforce.
He/she carries out similar duties to the contracts manager, with the addition of;
The Members of The Construction Team 48
(i) providing feedback data in the form of reports to head office, regarding
progress on site, labour engaged on site, information required from the
engineer, additional or variation work carried out on site, urgent material and
plant requirements etc.; and
(ii) achieving safe methods of working on site and maintaining the relevant records
of inspection.
He/she has similar duties and characteristics to the site manager; however, his/her
work is more supervisory in nature. He/she will normally have a craft background to
enable him/her to call on his/her vast experience to solve intricate constructional
problems, which may arise from time to time.
The trade’s foreman is usually appointed to supervise the work of a particular trade
(foreman earthworks, foreman formworks etc.).
The ganger is usually responsible for the supervision of the semiskilled labourers
(drain layers, pavers, concreters etc.) and the general labourers on site. He/she
performs similar duties, and has a similar status, to the trades foreman.
On larger contracts, charge hands may be appointed to assist the trades foreman to
supervise a subsection of a particular trade. For example, the foreman formworks
may have charge hands responsible for timber forms (preparation and installation of
timber forms), proprietary forms (standard forms usually made of steel to fit specific
dimensions), and finishing (finishing according to specifications, particularly fair
face concrete). In addition to supervisory duties, many charge hands also, should
time allow, carry out the normal physical work associated with their trade.
The term “operative” is used to describe the personnel who carry out the physical
work of the construction process, i.e. tradesmen and labourers. No construction work
could ever commence without the construction operative and the value and
contribution of their efforts should never be overlooked or minimized. It has been
The Members of The Construction Team 50
said that the success of a charge hand depends on the quality of his/her operatives;
the trades foreman on his/her charge hands and so on up to the contracts manager. It
would be possible to conclude that the success of a contracts manager is, to a large
extent, dependent on the quality of his/her operatives.
The role of the site engineer, who is sometimes referred to as the land surveyor, is to
ensure that the project is constructed in the right place. The line or position and level
of a structure must be accurate to within tolerances of 2 or 3 mm, and it takes
considerable knowledge and experience to ensure that this takes place.
To assist him/her in this task, he/she uses many tools including tapes, rules, plumb
bobs, spirit levels and lines. His/her most important tools, however, are his/her
surveying instruments. The two most commonly used are the quickset level and the
theodolite. These are optical instruments and allow him/her to achieve great
accuracy. Site engineering, whilst being a respected profession in its own right, is
also the starting position for many careers in other branches of the industry.
The role of the site clerk/materials controller is to carry out all administrative duties
and to control materials on site. On larger projects, the function may form two
separate positions.
3.1 Introduction
The main parties involved in a civil engineering project: the Client (promoter),
Consulting Engineer (Engineer) and the Contractor were discussed in detail in
Chapter Two. This chapter points out the key stages of a civil engineering project
from initiation to completion, and Figure 3.1 illustrates the contractual involvement
of the three main parties and the principal activities in their logical sequence. Only
the conception, preliminary design and design proper stages that lead to preparation
of contract drawings will be treated in this chapter.
Construction projects begin with an idea, resulting from a perception of a need, and
in the process of its provision aim to make a profit. Every project is unique in the
sense that it represents a specially designed effort to develop and use some portion of
the earth’s natural resources at some particular location. In this effort it is needful,
first to conceive the aim of the intended works; second to design them in practical
detail; third to construct them; and fourth to put them into working operation. This
fourfold process may commonly use the labours of hundreds of people; the
knowledge of several specialists gained over many years, and incorporates the
natural and manufactured products of scores of different trades. Owing to their
unique nature, civil engineering works must be commissioned in advance of need;
they are not purchased ready-made. As a result there must be a client who has
defined the need for the works, has resolved to undertake them and agrees to pay for
them, and who will own and operate them when complete. The client has to find the
money to finance the scheme, either from his/her own resources or by borrowing
money from others. It is also possible for the client to seek partners, either in the
Stages of Civil Engineering Projects 53
public or private sector in order to raise finances or other resources needed in the
project.
The Client initiates the project by appointing an Engineer, whom he/she may want to
assess the project requirements and to devise and present alternative schemes for
consideration. Occasionally it may be known in general terms what is required and
will need to have only the details determined and developed.
54 Fundamental of Civil Engineering Construction Management
Decide to proceed
Decide how to raise funds
Prepare Drawings,
Acquire land Specification and Other
Raise funds Contract Documents
Design and contract
Advertise publicly or
invite selected contractors
Documents
to tender
Pay Contractor
Certify payment
Use
Figure 3.1 Activities of the parties to a project (Adopted from Civil Engineering
Procedures, 1986).
Stages of Civil Engineering Projects 55
Besides the regulatory control of EIA, many civil engineering companies are now
looking to control the environmental consequences of all of their operations through
the development and implementation of an environmental management system
(EMS). This allows an organization to manage its operations in line with a clearly
defined environmental policy, objectives and procedures.
A particular challenge for the civil engineering sector is that many of its
environmental impacts relate to the temporary construction phase as well as the
longer-term impacts of the completed project. At any one time, one company may
have environmental responsibilities on a range of sites, distinguished by differences
in client, output, legal and planning requirements and other local factors.
Environmental management practices therefore need to be flexible enough to suit
individual site or project requirements, while achieving overall improvements in
environmental performance.
Thus, the feasibility study must provide the client with assurances that:
(i) the intended project will meet his/her needs in the most satisfactory and
economic manner;
(ii) the estimated cost of the project will be acceptable;
(iii) the project is technically feasible and will give the results intended; and
(iv) any powers needed to construct the project can be obtained.
Although the engineer appointed for the investigation need not be the engineer who
will design the Works nor become the engineer who will supervise the Works, the
continuity achieved if this is so is advantageous to all parties.
56 Fundamental of Civil Engineering Construction Management
The project conception is the Engineer’s first task, which necessitates him/her to
become acquainted with and to review the Client’s requirements, and then to agree a
brief for the investigations to be carried out. The Engineer as principal professional
adviser should enjoy the confidence of the Client and be given timely knowledge of
all the requirements so far as they can be defined. Normally, the Engineer will
inspect the site and consider physical, financial and political constraints, devise
possible solutions and compare them.
In the initial stages, the studies usually concentrate on various options for the
location, design and layout of the project. Accompanying this work there will be
data gathering and analysis, followed by the development and costing of alternative
layouts and designs (preliminary designs), so that the client can be assisted to choose
that which seems most suitable. There will follow further feasibility tests, which
could include substantial site investigations and, if necessary on the very largest
projects, some trial construction. The latter might include construction of some trial
earthworks, sinking of test borings, or some trial tunneling or excavation. Model
tests of hydraulic structures may be required.
Then he/she will submit a report to the Client summarizing his/her findings and
conclusions and, usually, recommending a preferred solution with an estimate of its
capital and likely maintenance costs.
The report on the investigations carried out by the Engineer should recommend the
basis for the economic design of a project. It should therefore review the main
design choices and the major problems, which may affect construction. These
should therefore have been investigated thoroughly by this stage. It is important that
the feasibility studies include a close examination of the client’s needs and the data
on which they are based. Many instances exist where large sums of money have
been saved on a project by carrying out, at an early stage, a critical examination of
Stages of Civil Engineering Projects 57
the basic data the promoter has relied upon. These data might not have been
procured according to the latest techniques or requirements and therefore might not
be sufficiently accurate in the light of current knowledge. They have to be tested for
accuracy, reliability, and correctness of interpretation. Inaccuracies in them or
misinterpretations of them could lead to wasted expenditure, or problems in
construction that are costly to overcome. Indeed, investigations and reports cost only
a small fraction of the total cost of construction, so it is false economy to restrict the
scope or thoroughness of the Engineer’s investigations and design studies.
Site conditions and their possible exploitation often present risks to the costs of
projects, which are not realized by Clients. In such cases the scope of the basic
objectives may be a matter for exploration and advice by the Engineer before the
brief for the project is finalized.
The scope of work statement should permit flexibility so that the Engineer can
consider new developments that may occur while the investigation is in progress.
58 Fundamental of Civil Engineering Construction Management
The extent to which the Engineer may consider alternative solutions should be
agreed. It is generally advisable for the scope of work statement not to indicate a
preferred scheme, as the value of a report can be seriously diminished if it can be
inferred that any matter has been prejudged. This is particularly true when
environmental issues are involved.
The extent, nature and detailed content of the Engineer’s study will vary according to
the value and complexity of the project, the number of solutions to be considered,
and the nature and number of the decision-making processes involved before the
scheme can be constructed. For some projects, a single study with the preferred
scheme and its estimated cost outlined in the report will suffice; others will require a
series of separate studies, each more detailed than the last. Similarly, some studies
will be undertaken wholly by engineers, whereas others will be the work of a team of
specialists of many disciplines.
The studies required to develop a preferred scheme for a major project may be some
or all of the following:
(a) a study which assesses the requirements of a particular sector of a country or
industry in order to identify individual projects for investigation.
(b) a pre-feasibility study which investigates whether or not there is likely to be a
viable demand for the project to be studied, whether or not the required
resources of implementation would be available within acceptable cost limits,
and whether or not a feasibility study would be justified.
(c) a feasibility (or pre-investment) study which involves preliminary surveys to
investigate technical and economic viability, an estimate of capital and
operating costs, and other information to enable the Client to decide whether or
not to finance the project; it does not include detailed design, but may include
some outline design.
(d) a master plan which is a long-term development programme, and which
generally indicates how construction and expenditure can be phased.
Stages of Civil Engineering Projects 59
(e) an environmental impact study which considers the effect the proposed
development would have on the environment.
(f) a geotechnical study which investigates the nature of the ground where works
may be constructed and assesses possible problems.
(g) a project study which develops the preferred scheme in detail, especially its
technical aspects; this is sometimes known as the final design study.
(h) a financing study: in most cases the Client will make the necessary financing
arrangements, but exceptionally the Engineer may be required to identify
possible sources of finance and to assist the Client in establishing the
arrangements for the provision and repayment of the funds needed, in which
cases a special report on the financing arrangements will be needed.
Technical investigations are required to resolve the engineering aspects for a project.
Further investigations will be required on projects likely to affect the environment,
economic, social or environmental studies may need to be undertaken in such cases.
The need for economic, demographic or other studies depends on the type of project
and it’s Client. Although they will generally be carried out under the direction of the
Engineer, they will usually be performed by a specialist in another discipline. The
team for any large study may include several non-engineering specialists.
For all investigations and surveys full use should be made of existing available data,
and topographical maps and marine charts where these exist. It may be necessary to
carryout additional studies to supplement the available information and, in the case
of topographical investigations, to undertake land, air or hydrographic surveys to
60 Fundamental of Civil Engineering Construction Management
make possible the preparation of accurate plans of the sites considered for the
construction of the Works.
Among the items that may require investigation are the conditions of access to the
sites both for permanent use and also during construction, statutory or local authority
restrictions on the sites or the special rights of adjacent landowners, and the
availability of services such as drainage, sewerage, water, electricity and gas. The
source and transportation of materials for construction and operation and the disposal
of waste material should be studied, and data on the climate and the incidence of
storms and flooding collected. The existing ambient noise levels may have to be
measured and studies undertaken to predict, and restrict as necessary, the noise levels
during and after construction.
3.4.6 Models
layout of projects, studying the use of space, and deciding on the methods and
sequence of work in construction. Physical models are valuable for discussing
proposals with a Client’s staff and also for training those who will take over the
operating activities of the completed project.
The execution of most civil engineering projects affects the public in some way.
Although the general public benefit from most projects, there are usually some
people who suffer. For example, the landowner whose land is compulsorily acquired
for a new road scheme, and the householder who experiences noise nuisance as a
result of the construction of a new railway line, may both reasonably have objections
to a proposed scheme. Attempts have been made to involve the public in he
decision-making process at an early stage. Frequently the problem and possible
solutions are publicized, and the public are encouraged to express their views and
preferences, which are duly taken into account during the feasibility and planning
stages. Involvement of the public in the planning stage of a project can reduce
objections and eliminate the need for a public inquiry; it can also produce
construction ideas to the benefit of the project.
The Engineer is usually required to prepare estimates of the capital cost of proposed
schemes, of the land, buildings, plant and machinery involved, and of the operating
62 Fundamental of Civil Engineering Construction Management
and maintenance costs of the project. Some of these estimates may have to be
obtained from or confirmed by outside sources. Capital and annual cost estimates
will have to be drawn up so that the economic viability of alternative schemes or
sites can be assessed and the costs to the Promoter of implementing the schemes
ascertained. When comparing alternatives, economic techniques such as discounted
cash flow and net present value should generally be adopted. It is essential to state
the month and year or other basis on which cost estimates have been prepared, and in
financial plans to indicate the estimated actual expenditure in future years and the
rates of inflation assumed.
3.5.1 Objective
3.5.2 Presentation
The style and form of the Engineer’s report should vary according to the Client’s
needs, the nature of the project and the purpose for which the project was
commissioned. As a general rule the report will review the investigations
undertaken, compare feasible options on technical, economic and financial grounds,
and make appropriate recommendations on which the Client can base future
decisions. The report should be written in a simple and unambiguous form so that it
can be readily understood by the Client and others who may refer to it, who may
neither be able to appreciate the technical detail nor have the time to absorb it. The
report must contain sufficient technical information to convince any other engineer
or specialist of its facts and of the soundness of its judgments.
Stages of Civil Engineering Projects 63
The report should set out in a clear and concise manner what the Engineer has been
asked to do, what he/she has done and his/her conclusions. It is often convenient to
summarize the salient points in one chapter and to include the technical matter in
appendices or in separate volumes.
The client can only decide to proceed with the project after considering the
Engineer’s report that is based on the preliminary design and satisfy himself/herself
that the project is feasible. If he/she finds the project to be feasible he/she must then
take steps to obtain the legal authority to construct the Works. In all cases it is
necessary to obtain planning permission or its equivalent as part of the procedure,
and to seek comment from adjacent landowners or other interested parties who may
64 Fundamental of Civil Engineering Construction Management
have objections to the project. Having obtained this the Client can instruct the
Engineer to proceed with the design of the project and the preparation of tender
documents. This work will usually proceed concurrently with the procurement of
finance and the purchase of the necessary land.
Whereas the questions of need and national policy are generally matters for
Parliament, proposals for a particular project are of concern mainly to those who live
in the area. For many types of project provision is made by statute for holding a
public inquiry, which is a public hearing of objections to a particular proposal. An
independent inspector chairs the public inquiry. At the hearing the Client puts
his/her case for the scheme, calling witness in support as necessary. The objectors
are then heard. Parties are frequently represented legally, and expert witnesses are
called if the scheme is of a high technical nature. As part of his duties, the inspector
visits the site during the proceedings.
After the public inquiry, the inspector writes a report that is submitted to the
appropriate government minister. This report contains an outline of the evidence
given at the inquiry, the inspector’s findings of fact and his/ her recommendations.
In due course the government minister makes decision, which does not necessarily
have to be in accordance with the inspector’s recommendations. Appeal against the
minister’s decision is possible on legal grounds but not on the merits of the decision.
At this stage the Engineer has to prepare designs for the Works and to provide
adequate information on which contractors can be invited to tender. To enable
him/her carry out this task, further site investigations are usually required.
Labouratory tests or model tests may also have to be undertaken, and the approval of
outside authorities obtained for certain aspects of the proposed Works. The Engineer
must give attention throughout to the aesthetic and environmental aspects of the
Stages of Civil Engineering Projects 65
design, and should be free to seek other advice as he/she wishes on these and other
subjects.
Depending on the type and size of project the Engineer may need to employ
specialist firms for consultation and design on certain parts of he Works. The
design of specialist work may be delegated to specialists who may later, with
the Client’s approval, become nominated subcontractors for the detailed
design and construction stages for the project. Equitable arrangements for
payment for specialist design work must be made between the Engineer and
the specialist consultant or contractor. The Engineer should retain ultimate
responsibility for all specialist design work.
Ideally, detailed designs of all the Work should be completed before tenders
for construction are invited. In some cases this is not practicable because of
the urgency of the Works, and the drawings on which tenders are invited are
supplemented by a series of further drawings issued by the Engineer during
construction.
The more complete the drawings, specifications and bills of quantities are at
the time of the call for tenders, the better the tenderers will understand what is
66 Fundamental of Civil Engineering Construction Management
required, the more accurate will be their prices, the smoother the subsequent
execution of the work will be and the lower the cost. Certain information can
be known only when construction is under way, and in such cases redesign or
supplementary design work during the construction phase may be
unavoidable. Examples include excavations in ground which proves to be
different from that inferred from the information available at the time of
design, and structures housing machinery the precise details of which are
unknown at the design stage.
3.7.1.4 Time
The Engineer should advise the Client of the time needed to prepare designs
and Contract Documents, as shortage of time at this stage is highly likely to
lead to delays and additional expenditure. An early decision should be taken
as to the type of contract to be used for construction, as this will affect the
form of the documents the Engineer has to prepare.
already available within its own organization or recruited specifically for the
project. It undertakes all the responsibilities of management and risks of
construction, and pays all wages and expenses as they are incurred. There
may be no contract in the normal sense, unless the Client requires the work to
be undertaken in competition with contractors. More treatment of the topics
on tendering and construction contracts will be given in Chapter 12.
A Client may have sufficient staff to undertake design work “in-house”; or it may
decide to do some work in-house and let out other work in separate “packages” to be
done by others. For large schemes, it may be appropriate to divide the whole project
in “design packages”, which are let out to appropriately experienced consultants,
with overall control exercised by the client’s staff, assisted by a firm of consultants.
Irrespective of how the much design work is let out to others, the client’s own staff
will have to maintain some controlling input to ensure that it stays within the
financial targets set.
On many projects there is a need for specialist design inputs. In some cases
specialist consultants may be brought in; in other cases specialist contractor or
supplier may be consulted at the design stage, especially when some patented or
unique process is considered for use. In some situations it may be appropriate to
employ a contractor to design and construct a discrete part of the works.
68 Fundamental of Civil Engineering Construction Management
Alternatively all design work can be passed to the contractor. In the following
sections the commonly adopted principal design options are discussed.
In this approach the client or his/her consultant draws up outline designs and
a specification of requirements. Separate design firm appointed by the client
then carries out detailed design. This sort of arrangement can be seen in
some management contracts where the management contractor coordinates
both detailed design and the construction. The design can also be let out as
separate packages dependent on the size of the project: for example, design of
an industrial estate may be packaged into roads and drainage, water and
sewerage, electricity supplies etc.
In this approach the promoter specifies functions and supplies layout plans.
The contractor then undertakes the detailed design before proceeding with
construction. The design element may be relatively small, such as designing
the final alignment and levels for a pipeline; or it may be fairly substantial,
such as the structural and reinforced concrete design required for a water
tower or service reservoir.
Stages of Civil Engineering Projects 69
Such design by a contractor may offer some advantages in that the contractor
may design to suit his/her construction methods and the equipment he/she has
available. The disadvantages are that some control over the design is lost to
the client, the design may tend to suit the contractor more than the client, and
time may also be lost, as design cannot start until the contract is awarded. The
contractor also has to take some design risk, for which he/she must increase
his/her price.
3.7.3.4 Detailed design for civil works: Mechanical and Electrical design by others
This method is widely used for projects that combine both civil and
mechanical and electrical works. There are many such projects in the field of
hydro-power, drainage, waste treatment and water supply. The detailed
design of the civil works carried out by the client or its consultant
incorporating requirements to suit the Mechanical and Electrical equipment
being supplied. The Mechanical and Electrical work is normally undertaken
by specialist contractors, who produce detailed drawings of their plant
conforming with the general layout drawings and the specifications they have
received under their contract. Close liaison is needed between the civil works
design team and the plant designers.
This is similar to item 3.7.3.3 above except that the client specifies only the
functions the project is to perform and provides drawings of the location of
the intended works and a tentative layout for them. The contractor then
proceeds to devise the full layout required followed by detailed design in
accordance with the specification, which may set out the design standards
required. This is the basic set-up for design and construct where the
contractor holds most of the design responsibility.
Chapter 4
Financial Project Appraisal,
Depreciation and Inflation
4.1 Introduction
A capital expenditure situation is one in which the company’s or individual's funds are
committed to projects, which will return the invested funds and profits during future
periods. The objective is to evaluate from alternatives the project (investment) which
will promote the profitability and long-range growth of the enterprise.
Before considering the various investment appraisal methods it must be appreciated that
they do not give a definite decision. They simply act as a guide and help communicate
useful information to the decision-maker. The actual decision is based on many diverse
factors, which cannot be incorporated into an overall formula or technique. In making
economic comparisons it is important to ensure that the various alternatives are
substantially equivalent, particularly with regard to their technical specification and
performance characteristics. Factors other than income or expenditure may override a
calculated optimum solution. Personal, social and political factors, for example, may
dictate a ‘prestigious’ construction project, which would be difficult to evaluate in
purely monetary terms.
When two or more alternatives are present, the decision analyst often finds that some
attributes of one alternative are superior to those of the others, while other alternatives
may also have different attributes for which they exhibit superiority. It is these situation
that pose a decision-making dilemma: how to choose? A sound analytical treatment,
which is based upon time value concepts and reliable quality data, would help much in
selecting the “best” alternative option. It should be, however, recalled that modelling
the attributes of an alternative cannot capture all of its relevant details and thus should be
viewed as an aid to sound decision making and should be thought of as just one part of
the overall process of wise, human decision making.
Financial methods of choosing between schemes competing for the same financial
resources are called methods of financial project appraisal. Notwithstanding the
importance of such factors, there are five basic approaches to capital expenditure
evaluation, which will be considered in the following sections.
There are different methods of financial project appraisals ranging from simple rule of
thumb; methods to sophisticated software supported computer analysis that speed up
calculations. In all cases, the worthiness of the methods depend more on the quality of
data used. In this regard, one should put more effort in gathering data from reliable
sources so that the result of the analysis will be representing the reality and guide
investors in selecting the most profitable investment options.
In this Chapter, the following five basic methods of financial project appraisal are
discussed:
1. Straight Cost Method;
2. Payback Method;
3. Rate of Return Method;
4. Present Value (cost) or Net Present Value Method; and
5. Internal Rate of Return Method.
This method deals with the determination of project costs simply from immediate cost
approach and is based on “Which is the cheapest?" concept.
Example 4.1. Three reinforced concrete beam designs have been developed for a
particular section having a length of 8m. All would be equally satisfactory and details
are given as follows:
73 Fundamentals of Civil Engineering Construction Management
If you work it out, you should find that Beam No. 3 is the cheapest, although you
probably would not have thought so. The advantages of the method are its simplicity and
speed. It is suitable when the alternatives have directly equivalent options and when all
cost is actual current price.
The aim of this method is to determine the number of years it takes to pay back the
original investments from profits arising from the investment. According to this method,
projects can be considered on:
a. an accept-reject basis depending on the payback period; or
b. project ranking, where the faster paying-back project is accepted from a number of
mutually exclusive projects.
economically acceptable as it pays back the initial outlay of $200,000 in the 3-year
period.
Table 4.1
Project 1
Year Cash flow ($)
0 -200,000
1 60,000
2 80,000
3 70,000 Payback period
4 40,000
5 20,000
Table 4.2
Project 2 3 4
Year Cash flow Cash flow Cash flow
($) ($) ($)
0 -150,000 -60,000 -200,000
1 35,000 35,000 60,000
2 40,000 25,000 70,000
3 30,000 10,000 50,000
4 25,000 5,000 30,000
This is a simple appraisal method concentrating on speed of return. There are, however,
serious disadvantages with this method. Negative cash flows create a problem in that
the payback period may be ill defined as demonstrated in Table 4.3. Is the initial cash
outflow in Table 4.3 $100,000 or $150,000? (These are both capital outflows). Project
6 (Table 4.4) also highlights similar ambiguities in that it contains negative cash flows.
In the examples given in Tables 4.5 and 4.6, each successive project is more profitable
than the preceding one although the payback period does not show this. It is clear from
these results that the payback method does not make any allowance for the time value of
money.
75 Fundamentals of Civil Engineering Construction Management
Table 4.3
Project 5
Year Cash flow ($)
0 -100,000
1 -50,000
2 +50,000
3 +50,000
4 +60,000
5 +50,000
Table 4.4
Project 6
Year Cash flow ($)
0 -100,000
1 +60,000
2 -20,000
3 +30,000
4 +50,000
5 +80,000
Payback period?
Table 4.5
Project A B C
Year Cash flow ($) Cash flow ($) Cash flow ($)
0 -100,000 -100,000 -100,000
1 50,000 50,000 50,000
2 50,000 50,000 50,000
3 - 50,000 50,000
4 - - 50,000
Payback Period 2 years 2 years 2 years
Table 4.6
Project A B C
Year Cash flow ($) Cash flow ($) Cash flow ($)
0 -100,000 -100,000 -100,000
1 10,000 25,000 40,000
2 20,000 25,000 30,000
3 30,000 25,000 20,000
4 40,000 25,000 10,000
Payback Period 4 years 4 years 4 years
Financial Project Appraisal, Depreciation and Inflation 76
It is worth noting that the technique of payback method should not necessarily be
considered as an investment appraisal technique as such but rather a means of providing
information on the speed of return of the initial outlay.
Example 4.4
Five possible investment projects for a small company with a capital of $100,000 to
invest are given as shown in Table 4.7. Using the payback method, which project would
you recommend?
Table 4.7
Project A B C D E
Year Cash flow Cash flow Cash flow Cash flow Cash flow
($) ($) ($) ($) ($)
2000 -100,000 -100,000 -100,000 -100,000 -100,000
2001 10,000 60,000 30,000 50,000 40,000
2002 10,000 20,000 20,000 50,000 20,000
2003 40,000 10,000 10,000 10,000 10,000
2004 40,000 10,000 20,000 10,000 10,000
2005 20,000 10,000 20,000 10,000 10,000
2006 20,000 10,000 20,000 10,000 10,000
Payback 4 yr. 4 yr. 5 yr. 2 yr. 6 yr.
period
With the return of return method the annual profit is expressed as a percentage of the
capital required to produce that profit. There are various methods of computation
according to the definition of capital and profit. Generally, however, investment is taken
as the initial outlay on the project, while profit is calculated as an average annual figure,
after deduction of depreciation, operating costs and expenses, over the life of the project.
For example, consider example 4.4 discussed above:
Project A:
1 [10,00010,00040,00040,00020,00020,000] X 100
rate of return = 6 100,000
= 23.3%
Project B:
1 [60,00020,00010,00010,00010,00010,000] X 100
rate of return = 6 100,000
= 20%
Financial Project Appraisal, Depreciation and Inflation 78
Project C:
1 [30,00020,00010,00020,00020,00020,000]
rate of return = 6 100,000 X 100
= 20%
Project D:
1 [50,00050,00010,000 10,000 10,000 10,000]
rate of return = 6 100,000 X 100
= 21.6%
Project E:
1 [40,000 20,00010,000 10,000 10,000 10,000]
rate of return = 6 100,000
= 16.7%
Project A is selected since it has a higher rate of return. Note that Project D was rated to
be the best alternative using the payback period method.
The return on capital employed method can assist management in two ways:
1. If a minimum target is set then those projects exceeding it will be accepted and
those below rejected.
2. Projects may be ranked in order of investment preference. The higher a project’s
percentage rate of return the more it is preferred.
Disadvantages:
- Different answers can be obtained by taking average return over
different periods of time and no account is taken of payments outside
the period of the average;
- Similar to the pay back method, no account is taken of: any remaining
asset value; when payments are made - i.e. early or late in the payback
period, and of interest payments; and
- The readily observed weakness of this method (as shown in Table 4.7)
is that it cannot take into account the fact that earnings from the initial
investment may vary from year to year, neglecting the higher returns in
the earlier years.
Table 4.8
Project A B C
Year Profit ($) Profit ($) Profit ($)
0 -100,000 -100,000 -100,000
1 10,000 25,000 40,000
2 20,000 25,000 30,000
3 30,000 25,000 20,000
4 40,000 25,000 10,000
Rate of Return (%) 25 25 25
A major limitation or criticism of the earlier rule of thumb methods has been that they
take little, if any, account of when payments are made. Finance needs to be raised for
Financial Project Appraisal, Depreciation and Inflation 80
most civil engineering projects and that means paying interest on the money that is
borrowed for the time it is borrowed. Even if the finance is readily available it will be
invested while it is not actually required and will be earning interest - which will cease
when it is required. Present value (cost) and Internal Rate of Return methods take
account of time by including this interest.
If you have $ 100 and put it in the Bank (assuming an 8% of interest), after 1 year you
will have
i
$ 100 x ( 1 + ) , where i = rate of interest (%)
100
= $ 100 x 1.08
= $ 108
Conversely The value now (called present value) of $116.64 in two years time at an
116.64
“interest” rate of 8% is = $100. In other words the value of $116.64 in two
1.082
years can be discounted to a present value of $100. Similarly the present value of $100
100
in n years time is only .
i n
(1 + )
100
The present value of $108 in 1 year discounted at 8%
or $116.64 in 2 years discounted at 8%
81 Fundamentals of Civil Engineering Construction Management
i n
or $100 (1 + ) in n years discounted at 8%
100
are all equals $100 and are considered as equivalent. It is assumed that considering an
interest rate of 8% with the firm promise of $108 in 1 year's time, someone would let
you have $100 now.
Example 4.5
Suppose a rich grandfather gives you two options:
i) He will pay $10,000 now into your savings account (at an interest rate of 8%) but
you must promise not to take it out until your 25th birthday in 4 years time.
ii) He will give you $12,000 on your 25th birthday.
Obvious Approach - How much will you get when you are 25?
Considering alternative i) after 1 year savings you will have $10,000 + interest of
8
x 10, 000
100
i.e.: $10,000 (1.08)
and after 4 years you will have $10,000 (1.08)4 = $13,604.90
12,000
x $8,820 .34
(1.08) 4
Therefore, present value of Option (ii) is $8,820.34, which is less that $10,000. Both
approaches are, of course, equivalent.
For comparing schemes or options it does not matter which year you relate or discount
costs to, the result will be the same. But you must obviously use the same year for all
schemes or options you are comparing. The net present value of an investment is the
present value taking account of all cash flows including the original investment, (+ve =
income, -ve = expenditure). When the result is positive it means that the return is greater
than the interest rate used.
Example 4.6. Find the net present value (NPV) of the five projects given below. All
the sums are multiples of $1,000 and assume the cost capital to the company to be 11%.
A B C D E
Year Disc. Cash Disc. Cash Disc. Cash Disc. Cash Disc. Cash Disc.
Factor flow flow flow flow flow
2005 -100 -100 -100 -100 -100 -100 -100 -100 -100 -100
2006 1 10 9 60 54 30 27 50 45 40 36
111
.
2007 1 10 8 20 16 20 16 50 41 20 16
. 2
111
2008 1 40 29 10 7 10 7 10 7 10 7
. 3
111
2009 1 40 26 10 7 20 13 10 7 10 7
. 4
111
2010 1 20 12 10 6 20 12 10 6 10 6
. 5
111
2011 1 20 11 10 5 20 11 - 10 5
. 6
111
NPV -5 -5 -14 6 -23
83 Fundamentals of Civil Engineering Construction Management
Projects A, B, C and E all show negative net present values - i.e. the company should not
invest in any of these projects. Project D shows, however, a net present value of
+$6,000, which is a profitable investment.
Note that project A and B give the same net present value of $ -5,000. If the cost of
capital were 8% then show how project A has a positive net present value (i.e.
profitable); whereas project B has a zero net present value - i.e. break even situation -
neither profitable nor loss making.
These are two slight variants on the present value (cost) method. The capitalised cost is
really the same as the present value (cost) but it is applied to projects, which have a very
long life - (for practical purposes of analysis an unlimited life). For example a sewage
treatment works or power station might be considered to have near unlimited lives
although it may be necessary not only to continually maintain the pumps etc. but also
actually to completely rebuild at about approximately 50-years intervals. Thus the
present cost of the sewage treatment works for evermore would normally be called the
capitalised cost. The capitalised cost is, therefore, the lump sum now, which if
spent/invested at the given rate would be sufficient to provide and maintain the facility
for all time. As one can expect, costs very far in the future are negligible when
discounted at high positive rates.
The equivalent annual cost is the sum, which would have to be paid each year to fund
the service (sewage treatment plant, power station, etc.) assuming a given rate of
interest. It is convenient for comparing with annual income - particularly in the
nationalised industries where cash flows result from long-term budgets and where sales
of electricity, gas etc. are fairly predictable.
Financial Project Appraisal, Depreciation and Inflation 84
The Internal Rate of Return (IRR) is defined, as that rate at which future cash flows
when discounted will equate to the initial investment. This may mean that the present
value for an investment will be zero when cash flows are discounted at the internal rate
of return. In other words “you have to find a discount rate such that the present value is
zero - usually by trial and error - having found it then that discount rate is known as the
Internal Rate of Return.”
t0
At
(1 r ) t
0 [4.3]
where
At = the project cash flow
t = the time period [0 to n]
r = the annual rate of discount.
This formula can be used for projects, the cash flows of which extend up to three
periods. If they extend beyond this, complex polynomial equations are required for
solution. Fortunately a good approximation of a project’s IRR can be found through
linear interpolation. In this method, cash flows are discounted at a series of ‘trial’ rates
of interest to determine the rate of interest at which the value of incomes is exactly equal
to the present value of expenditures.
Example 4.7 If a simple initial investment of $1,000 is expected to produce cash flows
of +$200/year for 6 years, what is the Internal Rate of Return?
85 Fundamentals of Civil Engineering Construction Management
5 (1291515 ) x 5 5.52 %
40 5.52
0
2 4 6 8 10 12
-40
USD
-80
-120
-160
Discount (%)
Example 4.8: A firm has two investment opportunities for which the cash flows are as
given below. Find the Internal Rates of Return for both and recommend which project
should be adopted assuming they are mutually exclusive projects. Show how (by means
of a diagram) a different recommendation could have been made if the present value
method had been used with a low discount rate.
Project A
2 , 969
5 x 5 7.39%
2 , 969 3 , 231
87 Fundamentals of Civil Engineering Construction Management
Project B
= 5
648 x 5 5.27%
648 11308
Therefore Internal Rate of Return for project A is 7.39%, which is higher than the 5.27%
of project B. On this basis, project A is, therefore, preferable. The same is shown in
Figure 4.2.
10000 7.39
Project A
5000
5.27 Project B
D 0
S 0 5 10 15 20
U -5000
-10000
Figure 4.2 Diagram showing IRR values for two projects.
-15000
%
If present values had been used with a discount rate of 2% (or less than 3% as can be
seen from Figure 4.2) project B would be recommended, as it would show a higher
present value.
Financial Project Appraisal, Depreciation and Inflation 88
Most construction and business projects comparison can be accomplished by more than
one method. Invariably, the alternative methods require differing levels of capital
investment, giving rise to different incomes and may in turn have varying economic
lives. The investment of additional amounts of capital in various alternatives usually
results in increased capacity, increased revenue, decreased operating expenses, or
increased life and thus enhances the manager’s chances of obtaining a greater profit. If
mutually exclusive projects are to be compared, then it is not possible to select the
correct project solely on the basis of an Internal Rate of Return analysis.
Suppose a company requires one new factory and three possible sites are under
consideration. The projects are mutually exclusive since only one new factory is
required, so if it is built on site 1, sites 2 and 3 are therefore excluded and vice versa.
Mutually exclusive projects can be defined as those, which compete for acceptance in
that it is not possible or desirable to accept more than one. For instance when two or
more schemes for the use of one plot of land; or two or more financially acceptable
contracts when a contractor has sufficient management staff or labour for only one, can
be considered as mutually exclusive projects.
It is not possible to compare such projects by IRR analysis because the IRR does not
give any indication of either the amount of capital involved in an investment or the
duration of the investment. Discrimination can easily be made, however, on the basis of
incremental cash flows.
Incremental analysis consists essentially of two stages: 1) the subtraction of one cash
flow from another, and 2) the application of a discounted cash flow (DCF) method to the
89 Fundamentals of Civil Engineering Construction Management
Example 4.9 The project with the smaller capital investment is subtracted from the
project with the larger capital investment. Project A seems initially to be preferable to
project B. Project B, however, uses more capital than project A, so it is necessary to
know the profitability of the extra investment. This 8%, which, depending on the
attractive rate of return, may or may not be acceptable. Incremental analysis in this way
is useful for comparison of projects of different sizes and lives because it directly relates
the extra profitability to the extra investment of life.
Table 4.9
Year Project A Project B Increment
($) ($) A-B ($)
0 -2,000,000 -3,050,000 -1,050,000
1 1,000,000 1,500,000 500,000
2 1,000,000 1,500,000 500,000
3 1,000,000 1,200,000 200,000
23.4% 20% 8%
This incremental approach should also be used for comparing three or more alternatives
in order to obtain a true relationship between the merits of each alternative.
Example 4.10
Consider the following alternative investment schemes:
i) Scheme A's initial investment is $5,000 and has annual income of $1,500.
ii) Scheme B's initial investment is $25,000 and has annual income of $6,000.
iii) Scheme C's initial investment is $35,000 and has annual income of $9,000.
iii) Scheme D's initial investment is $48,000 and has annual income of $12,000.
Assuming the life of each scheme is five years and an attractive rate of return is 8%, the
IRR values are summarised as given in Table 4.9.
Financial Project Appraisal, Depreciation and Inflation 90
Table 4.10
A B C D
Capital ($) -5,000 -25,000 -35,000 -48,000
Additional capital ($) - 20,000 10,000 13,000
Annual income ($) 1,500 6,000 9,000 12,000
IRR (%) 15 6 9 8
Increase in income ($) 4,500 3,000 3,000
IRR on increased outlay (%) 4 15 5
Choose scheme C!
The incremental rate of return method of choosing between alternatives can be extended
to determine whether or not an investment in a project should be postponed. This
problem can only arise where the project’s inflow will be higher (or the capital outlay is
lower) if the project is postponed. For example, capital outlays on new machinery or
plant will often need to be postponed until an increasing level of repairs or operating
diseconomies on the old plant make for profitable replacement.
4.5 Depreciation
The fact that there is, in general, depreciation in value of construction assets (in civil
engineering plant, projects and equipment) is self evident. The depreciation or decrease
in value may be due to, but not limited to, the following:
- passage of time - rusting, deterioration;
- reduced performance - wear, corrosion, decay, more frequent
breakdown, difficulty in obtaining spares,
difficulty in repairing;
- change in requirements;
- change in legislation - no longer meeting stricter Health and
Safety requirements;
- destruction by accident;
- replacement by new technology; and
- replacement by newer more efficient equipment.
91 Fundamentals of Civil Engineering Construction Management
The life span of civil engineering assets varies considerably. It is no easy matter to
know the correct figure and it is easy to think of examples where they got it wrong.
However, typical figures might be:
- dams, tunnels, harbours 50 - 100 years
- breakwaters, bridges, roads 40 - 60 years
- buildings, outdoor cranes, railways, power stations 35 - 50 years
- portable Machine tools, office furniture 10 - 15 years
- construction plant 5 - 10 years
- direct electronic stations 15 - 20 years
- railway station 20 – 35 years
The estimated life span of the asset may be the sensible period over which to depreciate
the asset, but it may be preferable to depreciate its value over a shorter period. It will
depend on the purpose of the depreciation. The need to make allowance for that
depreciation occurs for a variety of reasons such as when:
a) the asset will need replacing at some stage and this will require funds;
b) assessment of profitability or efficiency of the equipment;
c) assessment of profitability or efficiency of the overall organisation;
d) for taxation purposes; and
e) company law.
There are a variety of common methods in depreciation calculations. They each have
advantages and disadvantages and which should, or could, be used will depend on the
application, reason why depreciation is to be calculated and the choice of the user. The
methods are:
1. Assessment of resale value;
2. Straight-line depreciation;
3. Constant percentage (often called declining balance);
Financial Project Appraisal, Depreciation and Inflation 92
To illustrate the different methods, consider the case of Mr Jacob, who is a machine
operator and wins $200,000 on the National lottery and buys himself a small backhoe
excavator. He then becomes self-employed, advertises and obtains work for himself and
his machine working on a series of small building sites. He needs to take account of the
depreciation of his asset, the backhoe excavator, in assessing what his charges per hour
ought to be, or how much he needs to save to replace it, or how much work he needs to
obtain, or how much he can pay himself, or whether his business is profitable etc.
Mr Jacob looks at Construction News and various other local trade journals and sees
from the small advertisements that the apparent going rate for similar second hand
backhoe excavator are as follows:
1 year old $160,000
2 years old $120,000
3 years old $ 90,000
4 years old $ 70,000
5 years old $ 40,000
Advantages
93 Fundamentals of Civil Engineering Construction Management
He could actually sell the asset for the depreciated value of $160,000 at the end
of 1 year. If he obtains the resale value actually at the end of the first year it will
have taken account of inflation.
Disadvantage
It is often difficult to find the resale value. The resale value for a very specialised
piece of equipment might be almost zero, because no one wants to buy it, but the
equipment might have considerable value to you.
I n itia l C o s t S a lv a g e o r r e s a le v a lu e
D e p r e c ia tio n
e s tim a te d life
The method has the advantage since it is easy to work out and constant depreciation
amount each year. However, one of the disadvantages is that the depreciation value (or
book value) is likely to be higher than actual realisable value.
Then S= P(1-D)n
s S 1
1 n 1 ( )n [4.6]
D 1n S / P D=
p P
To illustrate the last point consider the effect of assessing that at 5 years the asset of the
Mr. Jacob’s excavator may be saleable only for scrap or spares at $15,000 instead of
$40,000, and using equation 4.6,
95 Fundamentals of Civil Engineering Construction Management
15,000
1 5 0.404
200,000
D
and first year depreciation = $(0.404 x 200,000) = $ 80,800, which is very different
from $55,000. In fact as final salvage value approaches zero the first year depreciation
tends to be full value. This is nonsense - and hence the constant percentage method
should not be used for zero or very low salvage resale values.
2
= [200,000 - 40,000] = $21,333.33
15
Thus depreciated value after 4th year
= 72,000 - 21,333.33 = $50,666.67
1
Depreciate in the fifth year
15
1
= [200,000 - 40,000] = $10,666.67
15
Thus depreciated value after 5th year
= 50,666.67 - 10,666.67 = $40,000
The method is usually fairly realistic and depreciates asset quickly in the early stages
and is easily calculated. It is not super sensitive to very low scrap values. The fact that
depreciation varies each year can be considered as its disadvantage.
It is the sum which is to be put into an investment account such that it will when added
to the resale or salvage value produce a sum equal to the original purchase price. The
depreciated value of the asset is then taken as the original purchase price less the sum in
the account.
For the backhoe excavator and assuming the account earns interest at 10%, the sum to be
set aside each year is
i
(P S ) [4.7]
(1 i ) n 1
01
.
(200,000 40,000) X
. n 1
11
= $26,207.6
97 Fundamentals of Civil Engineering Construction Management
Check!
- After 1st year $26,207.6 is paid into account.
- After 2nd year the account has 1.1 x $26,207.6 in it and a further
$26,207.6 is paid in to give $55,036.
- After 3rd year the account has 1.1 x 55,036 in it and a further $26,207.6 is
paid in to give $86,746.56.
- After 4th year the account has 1.1 x 86,746.56 in it and a further
$26,207.6 is paid in to give $121,628.8.
- After 5th year the account has 1.1 x 121,628.8 in it and a further $26,207.6
is paid in to give $160,000 which with the 40,000 salvage resale value
equals the $200,000.
The annual depreciation charges calculated by this method are lowest in the early years
and largest in the later years. It is based on the concept that the depreciation recovers
each year are placed in a sinking fund. The method depends on interest rates - if interest
rates were zero, it would of course become identical to the straight-line depreciation.
The method is convenient if concentrating on replacing the asset and is fairly easily
calculated.
Depreciation Methods
Year 4.5.1.1 4.5.1.2 4.5.1.3 4.5.1.4 4.5.1.5
1 40,000 32,000 55,000 53,333 26,207.60
2 40,000 32,000 39,875 42,666 28,828.40
3 30,000 32,000 28,909 32,000 31,710.60
4 20,000 32,000 20,959 21333 34,882.24
5 30,000 32,000 15,195 10,666 38,371.20
240,000
4.5.1.1
200,000
4.5.1.2
4.5.1.3
160,000
Book value
4.5.1.4
120,000 4.5.1.5
40,000
0
0 1 2 3 4 5 6
Time (year)
Fig 4.3 Summary of book values of an asset calculated by the different depreciation
methods.
iii) If he wants to control his business and know how well it is doing, he wants a
system that accurately reflects the value of his assets
4.6 Inflation
The effect of inflation is to increase the price of things. If the rate of inflation is x then
something costing $A will cost $A(1 + x)n after n years, (assuming that its price goes
up at the same rate as inflation. Conversely the numerical sum of $A in n years time will
1 th
only buy (1 x) of what it will now.
Let ireal be the real rate of interest where imon is the monetary rate of interest, and x is
the rate of inflation. If you have $A which you invest, after 1 year you will receive $A x
imon interest so that you have a total of $A(1 + imon).
th
1
But these are in 1 year on $’s, which are only worth 1 x of today's $’s.
(1imon )
So in today's $’s you only have $ A (1 x )
(1imon )
A(1+ ireal) =A (1 x ) or [4.8]
(1 + imon) = (1 + ireal) (1 + x)
In some cases ireal may be -ve. For example investing $100 in the Bank might pay you
8% interest after tax, whereas the rate of inflation could be 14%, i.e. i mon = 0.08 and x =
0 .14
1 i mon
ireal = 1 x
1 11..14
08
1 0 .053
= -5.3%
Financial Project Appraisal, Depreciation and Inflation 100
In the past most people have worked completely in real terms for financial appraisals.
Doing this the price of an item generally remains constant. For instance, a bridge costing
$150,000 today can be replaced by an identical bridge costing $150,000 in 100 years
time.
Doing this the price of an item (measured by the number of $'s) will generally increase -
although in real forms (e.g. measured in today's $) it may remains constant. Thus the
$150,000 bridge (if costs increase at 10%/year) will cost $150,000 x 1.1100 = $150,000
x 137,806 = $2,067 million to replace in 100 years, but since the $'s they use will only
1
be worth 137806 of ours if the general rate of inflation is also 10% it will still cost
$150,000 in today's $'s.
Working in either should give the same answer. Because of the immense difficulty of
estimating rates of inflation (especially over a long time) and because the numbers tend
to get out of hand it is suggested to try and work in real terms, where possible.
Exercise problems
4.1 A contractor is looking back over the last five years and wondering whether,
with hindsight, he should have bought a dozer for $1,350,000 instead of hiring it.
His workload has been such that he would have saved hiring costs of $540,000,
675,000, 585,000 and 450,000 i.e. a total of $2,250,000 over the five years. He
has heard that the hire company has only been involved in costs (maintenance
etc.) of $150,000; 280,500; 250,500; 237,000; 180,500 and is now spending
$55,500 reconditioning it with the aim of selling it for $250,000. Assuming all
costs are real costs and are paid at the end of the relevant year, find what the
101 Fundamentals of Civil Engineering Construction Management
internal rate of return would have been for the contractor’s use if his maintenance
costs etc. had been the same as the Hire Company?
4.3 A contractor is negotiating for a package deal contract including design and
construction of a certain project. He has estimated the times and costs to be as
follows:
- Design and ordering of materials 6 months $500,000
- Fabrication and delivery to site 12 months $2,800,000
- Erection 9 months $2,000,000
The contractor works on a 15% profit margin or mark up on all estimates of cost.
The contractor borrows money at 12% and therefore uses this as the discount rate
when calculating net present value.
a) What would the net present value of the project be to the contractor if he is
paid under the following three different payment arrangements?
i) Paid a lump sum on overall completion.
ii) Paid as costs incurred.
iii) Paid 20% when all materials delivered to works
20% when all fabrications delivered to site.
50% on overall completion, and
10% at end of first year maintenance period.
Financial Project Appraisal, Depreciation and Inflation 102
b) What is the net present value (cost) to the client who works on a discount
rate of 8%?
You may assume that:
i) costs incurred by the contractors are uniform over the period
estimated and may therefore reasonably be lumped half way
through that period.
ii) because of the requirement to check that work is actually
satisfactorily completed before authorising payment, there is a delay
of one month between when payment is due and when it is actually
paid.
4.4 Suppose you have to choose between the following two alternatives: Invest in a
new building of $500,000 now or in two years time. By delaying the investment
for two years maintenance costs on the existing building of $60,000 per annum are
anticipated. For the new building, maintenance costs are estimated as follows:
First year $10,000; second year $15,000 and $20,000 for each succeeding year to
the end of an 8-year study period. If the cost of capital is taken as 12%, which
alternative is preferable?
4.5 The cash flow of two alternative investments is tabulated as shown below in
Table 4.12.
a) Considering 6% interest rate, tabulate cash flows and identify the
preferable options.
b) Repeat question 4.5(a) above with an interest rate of 12%.
c) What would be the result if the projects were compared over a common life
span of four years? (Use the equivalent annual cost method and comments
on your answer).
103 Fundamentals of Civil Engineering Construction Management
Table 4.11
Alternative 1 Alternative 2
Year Cash flow ($) Cash flow ($)
0 -45,000 -53,000
1 +24,000 +15,000
2 +38,000 +25,000
3 - +30,000
4 - +10,000
4.6 Suppose you have received your annual electric bill of $3,000. Since you expect
that electric costs will increase at 20% per year whereas the general rate of
inflation will be 8% you are considering installing solar cell, which should reduce
your electric bills by 30%. You have the necessary $2,500 in the Bank earning
10% interest in the monetary terms. Compare the saving in electric costs with the
interest payments for each year over the next 10 years in monetary terms and real
terms. What are the various payback periods? (Within 5 years, 8 years, 10 years,
never).
5.1 Introduction
Baum and Tolbert (1985b, pp. 333) defined a development project as: “a discrete
package of investments, policies, and institutional and other actions designed to achieve
a specific objective (or set of objectives) within a designated period”. In addition, a
development project is often an essential part of a country’s development plan. In
developed countries similar projects may well go under different names, for example,
“infrastructure investment”, the difference being that development investment is made
specifically to increase capacity, whether it be through structures, organizations or
methods. It is wrong to consider development projects purely as physical investments.
The objective of any development project should be to improve both physical and non-
physical aspects (for example, skill and acquisition).
Large development projects can be financed from several sources. In wealthy countries,
such projects can be funded internally from a single source (mainly from the government
budget). However, this is not possible in most developing countries, as government
funds are often inadequate. If this is the case, development projects will have to be
funded mainly from external sources. These external sources often prefer to finance
only part of the project, while the remainder will have to be financed internally.
Sources of Project Finance 105
There are many international development agencies, which provide extensive funding.
Some of these are presented in Table 5.1.
In most cases, external donors will set a limit on the funds made available. If project
costs are higher than expected, resulting in the donor’s limit being exceeded, a
106 Fundamentals of Civil Engineering Construction Management
considerable burden will be placed on the local economy. If several sources are used to
finance a project, there are additional problems that may have to be overcome, some of
which are discussed below:
i) Each source (donor/lender) has a legitimate interest in monitoring the project and
thus several accountability reports may be required.
ii) Accounts will have to be verified through project audits. Very often one auditor is
responsible for the local component, while another looks after the international
element. If this is the situation, the jurisdiction of these auditors may not be clear
and the local auditor may not be able to review the external element of projects
funded in his or her own country.
iii) As with most construction projects, the executing agency spends money on the
project and then claims it back from the sponsors. Failure to claim back
expenditure is uncommon, but extensive delays in submitting claims do occur.
This results in additional costs due to both the time-value of money, and any short-
term foreign exchange deals that are used to overcome the delay.
iv) Project expenditure may have to be made in several currencies, and it is difficult to
decide how these should be built into the project costs and when they should be
presented as a single currency.
Development banks can be defined in a variety of ways and in practices have little in
common apart from the basic concept. There are many types of ownership, objectives,
and sources of finance, policies and degree of government involvement that can be
adopted. A development bank is considered by the United Nations to be an institution
concerned primarily with long-term loan capital.
However, this vague definition can be applied to most banks. In practice, the main
objectives of a development bank must be to speed up the development process. In most
cases, these institutions have been established by governments mainly to encourage
Sources of Project Finance 107
growth within the private sector of their own economy. International development
banks can be characterized on a geographical basis, i.e. as national, regional (e.g.
African Development Bank – AfDV; Asian Development Bank – AsDB) or universals
(World Bank group) (Table 5.1). The ownership and membership of regional
development banks is not restricted to the regional States, hence entities other than
States can also be included.
The objectives of most regional development banks are generally restricted to economic
development and integration. Some, such as the AfDB, are also concerned with the
encouragement of social progress. In order to achieve these objectives, sections are
often established within the bank, which have one or more of the following functions:
a) to facilitate economic construction or reconstruction;
b) to help development planning and programming;
c) to cooperate with other institutions with similar goals;
d) to provide funds for capital investment;
e) to encourage and promote both public and private investment from abroad; and
f) to generate international capital flow.
Each region has its own problems and regional development banks can produce
solutions to encourage economic development but these have to be restricted to the
individual bank’s scope of activities. A comparison of the approaches taken towards the
construction industry by the different regional development banks would be interesting,
but difficult to achieve without full disclosure from the institutions concerned. The
policies and where possible, the procedures adopted by three different regional
development banks and by the World Bank are highlighted in the following sections.
ii) the African Development Fund (AfDF), i.e. the soft loan window to member
countries with GNP per capital below US$510;
iii) the SIFIDA Investment Company; and
iv) the Nigerian Trust Fund (NTF)
The AfDB Group provides both human and capital resources for the economic and
social development of 51 African countries (1993). In addition to project/programme
lending, it also co-finances projects with the World Bank Group, the European Union
(EU) and many other leading agencies.
AfDB was established on 4th August 1963 in Khartoum. In 1993 it had 51 regional
member countries and 25 non-regional member countries. Loans to poorer counties are
usually repayable after 40 years with a ten-year grace period. Other loans have
maturities ranging from twelve to 20 years with a two-to five-year grace period. The
Bank participation rarely exceeds 50 per cent of project cost.
The project cycle is very similar to that of the World Bank, as discussed in section 5.3.4.
It usually takes between eight months and three years to complete the approval process.
Once the Bank has approved a project involving large and complicated contracts for
construction services, it normally requires pre-qualification for all major supplies. Pre-
qualification is usually based upon:
Financial stability;
Previous experience and performance on similar projects;
Knowledge of local conditions; and
Capabilities with respect to personnel, equipment and plant.
Contractors who have pre-qualified are invited to tender and the contract is awarded to
the lowest evaluated bidder, defined as being “the bid price which appears to be the most
economic after evaluating all terms and conditions of the bid as well as the qualifications
of the bidder”.
Sources of Project Finance 109
The Bank also offers many consultancy services, which include; preparation or pre-
investment studies; detailed design of projects, supervision and control of projects; and
provision of technical assistance.
The Asian Development Bank encourages economic growth and co-operation in Asia
and the Pacific, and also assists in the economic development of its member countries.
It comprises the bank itself and its affiliates such as the Asian Development Fund
(AsDF), which is the soft loan window providing loans with a 1 per cent per annum
service charge, with repayments extending over 40 years including a grace period of ten
years.
The AsDB has traditionally been oriented towards the public sector, but this has started
to change and the Bank’s association with the private sector has grown. Between 1986
and 1989, 18 private sector projects received a total of US$180.7 million from the Bank.
However, the AsDB is still reluctant to provide un-guaranteed loans to the private sector.
Programme lending can be defined as “a lending mechanism through which loans are
provided not for a specific project but for a particular economic programme such as
agriculture diversification, etc.”
Most governments seem to favour programme lending rather than project lending
because of the flexibility that lies within a particular broadband programme. However,
the AsDV prefers predefined projects which its staff understands and can account for. In
110 Fundamentals of Civil Engineering Construction Management
order to overcome this problem and reach a compromise, the AsDV has started to lend
to the private sector with government guarantees, by lending to the national development
banks, which in turn lend directly to the private sector. In addition, the Bank has used
other mechanisms such as venture capital, leasing or co-financing. The power station
recently built in Hong Kong on a Build-Operate-Transfer basis and the equity interest
position in the Nepalese cotton industry are good examples of the AsDB’s new
approach.
The activities of the AsDB involve mainly transport or communication systems but,
where appropriate and possible, funds are made available for education, health and
urban development. It is not usual to identify the construction industry as a separate
sector when funds are allocated. However, the construction element of most industrial
projects usually makes up around 20 per cent of the loan.
Agriculture, rural development, urban improvement and energy development have in the
past been the main focus of the Bank’s lending strategy. Of its total lending, 35 per cent
has gone towards physical infrastructure involving construction works. Until 1987,
lending was traditionally directed towards infrastructure projects, for example, roads,
bridges, dams and ports. Since then, there has been a deliberate shift away from
infrastructure development forwards “basic human needs” such as housing. However,
construction work remains an important aspect of the Bank’s lending policy, even
though the number of major construction projects is decreasing.
Sources of Project Finance 111
The term “The World Bank” is used mainly to refer to both the International Bank for
Reconstruction and Development (IBRD) and its affiliate, the International
Development Association (IDA). There are two other affiliates to the World Bank,
namely the International Finance Corporation (IFC) and the Multilateral Investment
Guarantee Agency (MIGA). These four bodies are collectively known as the World
Bank Group as shown in Figure 5.1.
The World
............vvvvvB
Bank
Projects supported by the World Bank include the construction of dams, roads, bridges,
ports and many other large infrastructure projects. However, there has recently been a
significant trend towards smaller projects in the agricultural and social sectors. In the
fiscal year ending 30 June, 1991, the World Bank provided US$27.7 billion worth of
IBRD loans and IDA credits. Since most projects only receive approximately 35 percent
of the total cost from the World Bank, projects totalling US$60 billion are made possible
each year through the support of the Bank. The aid is used to purchase goods,
112 Fundamentals of Civil Engineering Construction Management
The IBRD’s operations are governed by its charter, which spells out certain basic rules.
It aims to benefit member States by:
Promoting economic development by making loans on favourable terms to
governments for priority productive projects where finance cannot be obtained on
reasonable terms elsewhere.
Providing technical assistance to aid economic development; and
Cooperating with other donors of financial and technical assistance to improve the
effectiveness of the International Development Association (See below).
The IDA aims to promote economic development by providing finance on more flexible
terms and bearing less heavily on the recipient country than conventional loans. In the
fiscal year 1993, the IDA provided credits amounting to US$6,751 million in 43 member
countries. Most funds ($5,921 million in 1993) are provided to countries with an annual
per capital income of less than US$635 (in terms of 1991 United States dollars).
Sources of Project Finance 113
IDA was established on 24 September 1960 in Washington, DC; and is open to all IBRD
member States. It has the same purposes as the IBRD; and primarily focuses on poorer
developing countries. IDA gives balance of payments less importance and loans are
termed as credits. Usually, IDA credits have ten-years of grace periods; and 35 to 50
year maturities. No interest is payable, but there is a service charge of 0.75 per cent.
Funds are obtained through subscription, top-ups from richer countries and transfers
from IBRD profits.
IFC is established on 24 July 1956 in Washington, DC; and has separate entity to IBRD.
Members of IFC must be IBRD members. IFC Provides venture capital to productive
private enterprises without government guarantees.
The main aim of the Multilateral Investment Guarantee Agency (MIGA) is to encourage
flows of investment for productive projects to developing member countries through the
mitigation of non-commercial investment barriers. This is achieved by: providing
coverage for non-commercial risk; heightening awareness of investment opportunities;
enhancing relationships between host governments and foreign investors; and consulting
or negotiating on conditions for foreign investment.
114 Fundamentals of Civil Engineering Construction Management
MIGA is established on 12 April 1988 in Washington, DC. and offers guarantees against
non-commercial risks;. It advises developing member governments on design and
implementation of policies relating to foreign investments; and sponsors a dialogue
between international businesses and host governments.
Most projects and executing agencies have their own characteristics based upon needs
that have to be satisfied. Consequently, the final financial package that is used to service
the project is often unique to that project. In arriving at the final package, several routes
will have to be explored and considerable backtracking may be required. Each funding
agency, including the development banks, has procedures and policies that must be
followed. Although most development banks have a mandate or charter that governs
their actions, and from which its policies evolve, its procedures and policies do change
with time. The controlling factors are, therefore, the policies of the bank, but flexibility
may well exist within its procedures. This flexibility is required because of the varied
nature of the projects encountered.
This approach provides the executing agency with a clear picture of the work, which it
has to perform, and indicates when the development agencies should be approached and
the type of information that should be presented. The whole process is one of
negotiation and should therefore be based upon good communications between the
various parties involved, as well as comprehensive documentation until project
completion.
the final stages should provide the basis for further projects. There are several terms that
can be used to define the different stages of a project cycle.
According to Baum and Tolbert (1985b, pp. 334-335), the World Bank uses the
following:
Identification: - The first phase of the cycle is to identify ideas that appear to
represent a high-priority use of the country’s resources to achieve an important
development objective. Such project ideas should meet an initial test of
feasibility; that is, there should be some assurance that technical and institutional
solutions – at costs commensurate with the expected benefits – will be found and
suitable policies adopted.
Preparation: - Once a project idea has passed the identification “test”, it must be
advanced to the point at which a firm decision can be made whether or not to
proceed with it. This requires a progressive refinement of the design of the
project in all its dimensions – technical, economic, financial, social, institutional,
and so on.
Although large capital projects are selected in order to satisfy effective demand, the
process should involve the consideration of other economic, technical, managerial and
financial issues. Project identification stems from the translation of national
development plans into specific action programmes and investments. In formulating
such plans, potential project will have to be identified and ranked in order of priority.
The aims of individual projects must be clearly defined and agreed at an early stage. It
is essential that all parties involved be consulted, among them the government, the
beneficiaries and the funding agencies. One of the parties involved may be more
interested in increasing export earnings, where another may prefer to see a reduction in
local unemployment and improved distribution of wealth. It is crucial that full
agreement is reached on the project objectives by all parties associated with it. In the
past, failure to achieve this has often generated considerable friction, resulting in poor
project implementation. Individual governments, with assistance from outside agencies,
Sources of Project Finance 117
should therefore take a systematic approach to the identification process, which should
include the following steps:
Thoroughly review the borrower’s country and highlight underdeveloped sectors
with potential for investment;
Formulate general national development plans identifying potential projects;
Compare the potential for development with other countries;
Identify the potential for development in terms of:
- Extraction of domestic natural resources;
- Processing of domestic natural resources;
- Import reduction;
- Export expansion; and
- Expansion of current industries;
- Select specific projects for further considerations;
- Asses selected projects in the basis of market, technical, resource and
financial considerations, and
Formulate a specific national development plan identifying specific projects, their
objectives and an appropriate time-scale.
118 Fundamentals of Civil Engineering Construction Management
Stage Activities
Appraisal
The Bank's responsibilities are to review all aspects of
the project and lay the foundation for implementing the
project and evaluating it on completion. It covers four
major aspects: technical, institutional, economic and
financial.
Negotiation
The Bank and the borrower endeavour to agree on
measures necessary to assure the success of the project.
Agreements are converted to loan documents.
Implementation
and
Supervision Implementation over the construction period and
subsequent operation of the borrower. The Bank is to
assist only.
Evaluation
Ex post audit: review of the investment, i.e. actual
implementation costs and expected benefits
Once the project objectives have been established, it should be possible to present them
in the form of a Project Brief. The World Bank has developed procedures to be
followed during the preparation of a project brief. These enable early agreement to be
achieved between the World Bank and potential borrowers on the following issues:
development objectives of the project;
basic project features;
alternatives still to be considered;
institutional, policy and other matters to be considered during preparation,
appraisal or implementation; and
actions required to prepare the project and the main resources to be employed.
The World Bank, along with other multilateral agencies, offers valuable assistance with
the project identification phase. In some cases, they have regional offices whose main
role is to help identify and prepare projects. Another option is to send identification
missions from the head office. United Nations agencies, including the United Nations
Educational, Scientific and Cultural Organization (UNESCO), the United Nations
Industrial Development Organization (UNIDO), the International Labour Office (ILO),
and the Food and Agricultural Organization (FAO) provide specialized services for both
project identification and preparation.
Another source of financial and technical assistance is the United Nations Development
Programme (UNDP), which provides funds for resource surveys or pre-feasibility
studies carried out in order to identify suitable projects.
Once a project has been identified, the next stage of the cycle involves project
preparation and appraisal. These tasks must be completed before the decision to allocate
funds can be made. The process is not straightforward and is often an iterative process.
120 Fundamentals of Civil Engineering Construction Management
Project objectives and the means of achieving them will have to be refined, several
options will have to be considered and a cost-benefit analysis performed.
The World Bank has tended to adopt a policy of lending at a late stage of project
preparation, very often after detailed engineering aspects have been completed and other
steps have been initiated. Once the detailed economic and financial analyses have been
completed, a valid judgement can be made as to the project’s viability before any funds
are allocated. However, it is important to realize that funds spent during the preparation
stage could produce more concrete results if allocated to the implementation stage.
The cost of a feasibility study varies, but is usually about 5 per cent of the overall project
cost. There can be little doubt that good project preparation reduces the possibility of
problems during implementation. When the process described above is started, there
will be many options available. However, some of these will be eliminated, and when
Sources of Project Finance 121
the alternatives have been reduced to a more manageable number, more detailed
preparation of the remaining projects can be undertaken in the form of a feasibility
study.
A feasibility study provides both national and international decision makers with a basis
for deciding if the project should proceed and identifying the most desirable option
available. It is necessary to perform a feasibility study even when a pre-feasibility study
has been undertaken. Some agencies prefer to use the term “preparation report”, but the
objectives are just the same. There are many aspects that form part of a feasibility study,
including financial considerations, technical problems, environmental impact and many
others. Each of these have to be analysed both separately and in relation to each other.
There are several organizations that can provide technical and financial assistance. If a
project is to be funded from external sources, it is necessary that prospective lenders
provide substantial input into the project preparation. If project preparation is
undertaken without reference to specific lenders, considerable reworking may be
required in order to satisfy the requirements of individual lenders.
Projects funded by the World Bank usually involve the appointment of several
consulting services, such as engineering feasibility and design services or construction
supervision. These services should be procured in accordance with the procedures
outlined in the Bank’s publication Guidelines: Use of consultants by World Bank
borrowers and by The World Bank as executing agency (Washington, DC, 1981), which
recognizes that the selection process should concentrate on the quality of service rather
than minimum price. The UNDP is an important source of finance for feasibility studies
and similar preparatory work. The World Bank finances this type of work through
122 Fundamentals of Civil Engineering Construction Management
several routes; for example, preparatory studies for future projects may be included as
part of funding for current projects. Other organizations such as the FAO and UNESCO
are also valuable sources of funds specifically for preparatory work.
Conducting a feasibility study requires many professional skills. If local staffs are used,
then details relating to the local environment, social conditions and legal aspects can be
included. In some cases, such as agricultural projects, the inclusion of local staff is
essential. The development of the ability to produce feasibility studies and undertake
similar project work can be beneficial to a developing country and is considered to be a
worthwhile objective on its own merit. Some of the more advanced developing
countries have established very strong technical departments, which are able to compile
complex feasibility studies.
Agencies such as the World Bank, the FAO and UNIDO have produced checklists of
topics that should be included in feasibility studies or project preparation reports. Some
of these checklists are extensive and have originated from previous projects. These
should be used only as a reminder or guide and should not be totally relied upon. The
preparation of a feasibility report is a creative process and should not be confined to
areas contained in available checklists. However, if these checklists are used as
intended, the chances of a favourable response to the proposal from the lenders are
increased.
The World Bank relies mainly on its regular staff or appraisal missions for its own
appraisal of each project. Project appraisal reports have to pass through an elabourate
review procedure before the Bank will enter into negotiations with the borrower and
before the application is forwarded to the Board of Executive Directors for their
consideration. The current demand for World Bank funds exceeds supply; consequently,
additional funds have to be sought from other sources, for example, regional
Sources of Project Finance 123
5.4.4 Negotiations
Negotiation is the stage at which the Bank and the borrower endeavour to agree on the
measures necessary to assure the success of the project. These agreements are then
converted into legal obligations. Set out in the loan documents. We may have agreed
with a public utility borrower that, to earn an adequate rate of return and finance a
reasonable proportion of its investments, prices must be increased by say 20 per cent
immediately and 10 per cent in two years time. A financial covenant agreed upon
during negotiation will define the overall financial objectives and specify the necessary
rate of return and the timing of the initial rate increase. If a new project unit must be set
up to administer the project or to coordinate the activities of the various ministries
involved, the loan documents will specify when and how it is to be established and
staffed. In fact, all of the principal issues that have been raised prior to and during
appraisal are dealt with in the loan documents. Thus, the drafting and negotiation of the
legal documents are and an essential part of the process of ensuring that the borrower
and the Bank are in agreement, not only on the broad objectives of the project but also
on the specific actions necessary to achieve them and the detailed schedule for project
implementation.
Negotiations are a process of give and take on both sides of the table. The Bank, for its
part, must learn to adapt its general policies to what can reasonably be accomplished in
124 Fundamentals of Civil Engineering Construction Management
the particular setting to the project, sector, and country. The borrower, for its part, must
recognize that the Bank’s advice is generally based on professional expertise and world-
wide experience, and that the Bank’s requirement that its funds be invested wisely is
computed with the best interests of the project.
Despite the differences that inevitably arise when difficult issues have to be resolved, the
relations that have developed over time between the Bank and its borrowers at this and
other stages of the project cycle are generally very good. Bank staffs have become more
aware of and sensitive to local conditions, which are critical to the successful outcome of
a project. Borrowers have come to appreciate that the Bank’s approach is professional
and objective, that we are in business to lend for well-conceived and well-executed
projects, and that this is indeed our only interest in project work.
After negotiations, the appraisal report, amended to reflect the agreements reached, is
presented to the Bank’s Executive Directors, together with the President’s report and the
loan documents. If the Executive Directors approve the operation, the loan is then
signed in a simple ceremony, which marks the end of one stage of the cycle and the
beginning of another.
The importance of the early stages of the project cycle has already been emphasized.
However, project implementation is the critical part of the project, as it is here that the
earlier plans, designs and analyses are to be tested in the harsh light of reality. Although
the responsibility for project design and implementation lies with the borrower, the
World Bank is deeply involved throughout the process. Implementation begins when
resources are committed to an investment. The start of the implementation stage for
certain projects, such as roads or buildings, is easily identified, but projects comprising a
variety of activities may not have a clear commencement date.
Sources of Project Finance 125
To have received World Bank financing, project proposals will have detailed the
procurement procedures in line with the Bank’s publication, Guidelines for procurement
under World Bank loans and IDA credits (Washington, DC, 1985). These procedures
form part of the Loan Agreement. The borrower plans and schedules the procurement,
prepares bidding documents, evaluates the bids and awards the contracts. The Bank will
pay out its funds only if the terms of the Loan Agreement have been followed, and this
includes the procurement procedures.
Planning the implementation stage of a project has only recently started to receive the
attention it deserves. Previously, work done during the earlier stages concentrated upon
establishing alternatives and assessing their feasibility, along with the preparation of
action programmes.
There is a definite need to plan in clear detail the implementation stages of the project,
ensuring that adequate account is taken of the institutions, which will execute and
operate them. Three main aspects of the implementation stage must be given
consideration if the project is to be successfully implemented. These involve: - (a)
selecting the implementation unit; (b) supervising project implementation; and (c)
establishing the co-ordinating mechanisms. These are discussed in detail, along with (d)
monitoring and evaluation of project implementation.
While this approach lends itself to improve project implementation, it does have its
drawbacks. There are no long-term institutional benefits, as the units; rules and methods
are not easily transferred. Existing agencies may suffer, as their staff may leave to join
these special units. Therefore, this approach should only be taken when the benefits to
be obtained through improved management of the investment are greater than the
disadvantages to existing organizations.
The World Bank (and other external agencies) will often have a supervisory role.
However, this is not a substitute for the country’s own responsibility to ensure that
project implementation is performed effectively and efficiently. Supervision may be
provided from another unit within the same agency, so long as it is administratively
independent of the units doing the work. Alternatively, another unit within the same
agency, so long as it is administratively independent of the units doing the work.
Alternatively, another agency or outside consultants may be used to oversee project
implementation.
In the past, three different coordinating mechanisms have generally been adopted:
i. establish a special project unit which allocates funds to each of the implementing
agencies through a central budget;
ii. appoint one of the implementing agencies at the lead unit, which the remaining
agencies and dispenses some of the funds; and
iii. appoint a committee with the appropriate authority to coordinate the
implementing agencies. The members of this committee must have close contact
with the project. In the past, committees comprising ministers or the like have
not functioned effectively.
128 Fundamentals of Civil Engineering Construction Management
The ex post evaluation is the last part of the project cycle, and is performed once a
project has been completed and has started to operate. The aim of such an evaluation is
to take a broad look at the potential benefits of the project once it has been completed,
and compare these with the original objectives. If the project is allowed to run for a
defined period, the ex post evaluation can be based upon actual project costs, operating
costs and any early benefits. It should determine whether or not the project was
worthwhile and also indicate whether:
Sources of Project Finance 129
The World Bank was the first of the multilateral aid organizations to develop a
comprehensive ex post evaluation methodology and make the findings readily available.
Although all the projects funded by the Bank have to produce a completion report, only
about half of them are subjected to a detailed audit by the Operations Evaluation
Department (OED) (in fact 10 per cent of these will be selected at random). An annual
summary of the evaluated projects is produced by the OED staff, and is published as the
Annual Review of Project Performance Audit results, with country and project omitted
to ensure client confidentiality. There are also certain types of project that may be
specifically selected for a performance audit. These may include: projects that suggest
a poor performance or have had particular problems; projects that are the first of their
type in a particular country; or projects that are similar and can thus form part of a
comparative study. These procedures were designed to satisfy the Bank’s own
requirements, but can easily be adopted by other agencies and comprise two phases:
Phase I
Every World Bank assisted project is reviewed by the operational staff within two years
of final disbursement. Phase I involves the preparation of a project completion report by
the individuals directly involved in the project preparation and implementation.
Phase II
Phase II in the evaluation process is performed by OED staff detached from the
operational side of the project. This phase is required to ensure that objectivity is
achieved during the evaluation process.
130 Fundamentals of Civil Engineering Construction Management
It is inevitable that disagreements will occur between reports and audits produced by the
OED staff and the operational staff. A large proportion of these discrepancies can be
clarified through discussions. However, the OED staffs have the responsibility for the
final audit memorandum, although any remaining disagreements should be noted. The
borrowers are also included in this evaluation process. As part of the loan agreement,
and in addition to other reporting commitments, the borrower has to produce a project
completion report.
Section 5.4 describes the World Bank’s approach to the project cycle. The various
stages are defined and the associated activities discussed. The cycle is deemed to start
with project identification and finish with an ex post audit review of the investment, in
order to assess actual implementation costs and expected benefits. The process is
referred to as a cycle because the results of the ex post audit should be fed into
subsequent project identifications. This concept of the project cycle is not confined to
the World Bank; many other aid agencies take a similar approach.
There are, however, some differences as to how the project cycle is broken down into
the various stages and the activities performed during each stage. To illustrate this
point, the approaches taken by the World Bank, the Kreditanstalt für Wiederaufbau
(KfW) in Germany and the Asian Development Bank (ADB) are presented in Figures
5.2, 5.3 and 5.4.
In addition, the development stages for water supply and sanitation projects are
presented in Figure 5.5 to show how the World Bank’s approach is occasionally
modified. The information contained in these diagrams has been extracted from the
Sources of Project Finance 131
references given, but has been modified into its current form to illustrate the different
approaches taken to the project cycle.
132 Fundamentals of Civil Engineering Construction Management
Stage Activities
Implementing
the project
Assignment of consultants, award of contract, contract
for goods and services, supervision of implementation
by Kfw.
Operating the
project
Responsibility of the executing agency. Supportive
measures where necessary
Stage Activities
Stage ........................................................................................................................................
Identification (selection) of Government request for Bank assistance. Study of country's
project economy and development plans.
Coordination with and agencies
Pre-appraisal mission
Examination of feasibility study. Examination of the need for
further advance action on procurement and consultant
selection.
Appraisal mission
Examination of project's technical, economic and financial
aspects. Determination of loan terms and conditions. Signing
of Memorandum and Understanding.
Preparation of Board
documents
Drafting of President's Report and Recommendation. Bank
internal review.
Dispatch of draft loan documents to government.
Loan negotiations
Loan approval
Project completion
Project benefit
monitoring and
evaluating Detailed examination of socioeconomic impact of project
Preparation of project
Performance audit report
Evaluation of actual implementation against original plan
target. Assessment of economic, financial and social benefits.
Lessons learned to apply to future project preparation and
implementation.
Stage Activities
Identification report.
Identification
Pre-feasibility report.
Feasibility report.
Preparation
Appraisal.
Investment decision.
Approval
Figure 5.5 Development stages for water supply and sanitation project..
Source: Grover, 1983.
Sources of Project Finance 135
5.6 Summary
In most developing countries, there are many major construction projects that would not
have been possible without the financial aid provided by the development banks. This
chapter discusses the approaches taken by many of the national, regional and global
development banks, and outlines the conditions that have to be satisfied if funds are to
be attracted. The project cycle has been discussed at length in order to highlight the
various stages, which must be considered when either putting a case forward or
justifying expenditure once a project has been completed. The project cycle will vary
from bank to bank and it is crucial that such differences are recognized if sufficient
funds are to be obtained at a reasonable cost.
Chapter 6
Planning Before, During and
After Construction
6.1 Introduction
The stages of civil engineering projects including the planning that is carried out by
the Engineer before design and consequently construction were discussed in Chapter
Three. This chapter discusses the planning process: before, during and after
construction and it focuses on the contractor.
Planning is the process that determines what course of action shall be taken to
achieve a specific purpose and it aims to provide the guidelines upon which
management ultimately acts. Logical decisions are taken regarding future events in
order that detailed thought at an early stage can often prevent potential problems
occurring. By its nature, planning deals with the unknown; however, it is the skills
of managers and planning engineers that seek to remove many of the uncertainties.
Planning, by its nature, attempts to make effective use of the resources available
(labour, plant, materials and subcontract services). It can be applied in various
degrees to detail, dependent on the limitations of time and finance at the disposal of
the contractor. Figure 6.1 illustrates the process of planning in construction, which
can be divided into three distinct stages:
(i) Pre-tender planning: The planning considerations during the preparation of an
estimate and its conversion into a commercial bid.
(ii) Pre-contract planning: The planning consideration after being awarded the
project, prior to commencing work on the site.
Planning Before, During and After Construction 137
It is important to mention that the processes explained here are based on the
traditional procurement of construction, there is, however, other procurement
approach, particularly the Design and Build that focuses in combining the design,
permit and construction schedules in order to streamline the traditional design-bid-
build environment. This does not shorten the time it takes to complete the individual
tasks of creating construction documents (working drawings and specifications),
acquiring building and other permits, or actually construction the facility Instead, a
design-build firm will strive to bring together design and construction professionals
in a collaborative environment to complete these tasks at the same time..
Decision to tender
Pre-tender arrangements
Site visit report
Enquiries to subcontractors and suppliers
PRE-TENDER Tender method statement
PLANNING Build up estimate
Pre-tender programme
Build up programme
Build up preliminaries
Management adjudication
Analysis of tender performance
therefore an enquiry for a US$600 000 contract may cost the contractor in the order
of US$3000. Contractors' head office overheads vary of course, but can be as low as
3-5% in a large company and thus tendering costs represent a considerable
proportion of the total. However, without this overhead expense the contractor
cannot win any work.
The following factors will influence tendering policy in general as well as specific
factors that may be due to market conditions:
(i) General tendering policy
Does the work fit into strategic plan of the company?
Current workload in both the contracts division and estimating section - Does
the company have the resources in both financial and management terms to
undertake the work?
(ii) Working capital available to fund the project - effect on company financial
resources.
(iii) Availability of resources in respect of management personnel, labour, plant,
and subcontractor resources. The resources of individual sub-contractors will
also require consideration.
(iv) Contract location - Is it within the working radius of the company’s trading
operations? A contract located some kilometres from head office will often
create management and control problems.
(v) The size, type of work and monetary value of the project will need
consideration.
Contractors often take on contracts that are too big for them. This can result in
placing years of planning and sustained growth at risk. The inherent risk in the
contract failing to make adequate returns and the consequential risk and effect
on the viability of the business needs consideration.
(vi) Extent or value of the contractor's work in relation to that of the subcontract
element of the project.
The main contractor may simply find himself/herself managing subcontractors.
There may be very little profit in the subcontractor element and hence more
risk is placed upon the main contractor.
140 Fundamentals of Civil Engineering Construction Management
When the contractor has decided to submit a tender, the estimating, buying and
construction team will need to be motivated into action. A number of head office
personnel will be involved in assisting with the tendering process in order to ensure
that the bid is submitted on time. Delegation of responsibility for the estimate and
tender preparation is often necessary and could be carried out as below:
Planning Before, During and After Construction 141
Estimator
to deal with the management and pricing of the bills of quantities; and
to deal with subcontract and material price enquiries when there is no
company buyer available.
Contracts Manager
to arrange to visit the site with the Estimator;
to prepare the site visit report;
to prepare the Method Statement and discuss it with the Estimator;
to prepare an assessment of the project plant requirements;
to advise the Estimator on the requirements of the contract preliminaries;
to prepare an assessment of the pre-tender programme - this would be
undertaken in conjunction with the company planning engineer;
preparing an assessment of the project safety requirements in response to the
“Construction Design and Management Regulations"; and
to arrange to view the project drawings, if not included with the tender
documentation.
Senior Management
responsible for overseeing all stages of the estimate;
liaison with the Contracts Manager with regard to major decisions; and
chairing the tender adjudication meeting and taking all necessary decisions on
mark up and profit additions.
The proposed site should be visited and a report prepared giving precise details of the
project including:
142 Fundamentals of Civil Engineering Construction Management
The facts should be recorded on a prepared form and, where necessary photographs
and sketch diagrams should be included. It should be noted that site ground
conditions and the effect on pricing temporary earth support need careful
consideration. This particular item may be treated as an item of contractual risk
within the tender. Many contractors have lost projects because of their inability to
assess contractual risk carefully. Tenders are won on the items that the contractor
does not price and simply put down to contractor risk.
The form is completed to varying degrees of detail and some firms also prefer to
produce two specific documents – a method statement and a separate statement of
resources. This, however, duplicates effort and does not enable the reader to gain an
over-all appreciation of the nature of the work
Management adjudication
Tender
Subcontract mark up
Adjudication
Assess subcontract risk
Submit bid
Project brief
A subcontractor has received an enquiry to undertake the concreting operations to a
two-kilometer stretch of a rigid pavement. Concrete is to be laid 300 mm in thickness
144 Fundamentals of Civil Engineering Construction Management
and each bay is 60 m2 in area. Access to each bay is via a service road. Alternative
proposals for placing the concrete may be considered.
The contracts manager for the subcontract company prepares the method statement in
order to advise the estimator of proposed methods for inclusion in the estimate. The
following points should be considered when preparing the tender method statement:
a list of operations to be included in the statement;
consideration of available resources - labour gang size, plant and supervision
approximate quantities, output rates- per gang, per day, etc.;
bay or pour sizes; and
any reasoned alternatives.
Operation
Handle and place concrete in pavement bays.
Resources:
Plant
1 No.5 meter timber screed board
Planning Before, During and After Construction 145
Labour:
3 No. labourers placing concrete
2 No. labourers leveling and finishing
I No. foreman supervisor
Output and Quantities
Quantity: 18 m3 Class C Concrete per bay. Quantity poured per day: 36 m3
Option Two: Place concrete using Mobile Concrete Pump
Resources:
Plant
I No. hired concrete mixer
I No. vibrating screed board
I No. steel leveling screed
I No. petrol vibrator
4 Nos. dumpers
Labour
3 No. labourer with concrete mixer
4 Nos. labourers placing concrete
2 Nos. labourers leveling and finishing
I No. foreman supervisor
This could be illustrated in the tender method statement and presented in a tabular
format. This has the advantages of showing the operational resource requirements in
a somewhat clearer format.
The estimator or planning engineer would be responsible for assessing the costs of
the alternative proposals and reporting his/her findings to the contracts
Having completed the method and resource statement, it is then necessary to develop
a suitable site organisation structure.
Having defined the site organization, and having due regard to the pre-tender report
and method and resource statement, the preliminary items and general site overhead
costs can be established. In basic terms, this schedule attempts to identify and
quantify all additional costs, which are not included within the measured rates of the
bills of quantities, such as:
(i) site staff and supervision;
(ii) transportation of materials;
(iii) unloading of materials;
(iv) mechanical plant not included in the measured rates;
(v) small plant, equipment and hand tools;
(vi) scaffolding;
(vii) installation and supply of temporary services;
(viii) welfare facilities-first aid and safety provisions;
(ix) site accommodation;
(x) abnormal overtime;
(xi) lodging allowance; and
(xii) cleaning building on completion.
Planning Before, During and After Construction 147
Great care must be taken to ensure that all additional items of expenditure are
included and, at the same time, that any duplication of costs is avoided.
At the tender stage the pre-tender programme is normally presented in bar chart
format. The programme will cover the major stages of the work to be undertaken
based on the information available from the tender drawings. The utilization of
linked bar chart techniques based on project management software will enhance the
programme presentation at this stage. It is now becoming normal practice for the
pre-tender programme and method statements to be submitted with the priced bid.
The Code of Estimating Practice (1996) indicates a suitable form for the Estimate
Summary, Analysis and Report. One must pose the question “Who attends the
adjudication meeting and what are they supposed to contribute?” Maybe the
management wishes to take all the decisions and simply obtain approval of their
intentions. At the end of the day it is the management who must assess the risk
148 Fundamentals of Civil Engineering Construction Management
inherent in the tender and decide upon a competitive bid price. It is now too late to
blame anybody else.
Assessment of head office overheads (% addition), discounts and addition for profit.
Profit percentages may be in the range of 1% to 20%, especially if you do not wish to
win the tender.
Once decisions have been made on the adjudication, the revisions will have to be
expressed in the submission of a priced bill or form of tender. The form of tender
will have to be signed by a responsible person and submitted in the appropriate
envelope. If alternative proposals have been invited, these should be clearly stated.
Planning Before, During and After Construction 149
It must again be pointed out that no two companies undertake exactly the same
procedures at the pre-contract stage. Procedures are dependent upon the policy of the
company and the need for establishing standard routines, which may be followed on
every new contract. The procedures to be outlined normally apply to the larger company
or the more organized medium sized organization. Within the larger organization a
more formal approach will be taken to the arrangements for commencing work.
The purpose of the pre-contract meeting is to hand over the tender documentation: It is
also to delegate responsibility to those responsible for arranging the commencement of
the project. Prior to the commencement of the project, a pre-contract meeting will also
be called by the client's representative in order to coordinate the start of works on site.
150 Fundamentals of Civil Engineering Construction Management
The pre-contract arrangements outlined here will relate to those undertaken by the
contractor on a traditional contract.
A meeting will be held to announce the award of the contract and allocate responsibility
to the construction team responsible for undertaking the work. All documentation
produced at the tender stage will now become available to the construction section. The
following personnel will normally attend the meeting, which will be chaired by the
Chief Estimator or the Contracts Manager:
To act as meeting chairman, as he/she is fully aware of all decisions taken at the
tender stage. He/she will be responsible for handing over all the estimating data to
the contracts section including:
i) Estimate summary and analysis;
ii) Build up of the 'all-in rates' and net bill rates;
iii) Summary of subcontractors and suppliers quotations. Pre-tender method
statements;
iv) Preliminaries build-up;
v) Pre-tender safety assessment; and
vi) Tender adjudication report.
The contracts manager's responsibilities will also include arrangements for the
transfer of key staff to the project or the recruitment of additional staff to manage the
project. Arrangements will have to be made for the delivery of site accommodation
and the mobilization of plant and equipment for the initial site operations.
Responsible for placing orders for subcontractors and suppliers based on the
information received at the tender stage. It may be the policy of the company to ask
subcontractors and suppliers to re-quote for the work.
In many of the medium sized construction firms, the contract quantity surveyor
undertakes the responsibility for placing subcontract orders and preparing contracts.
This practice enables the surveyor to become familiar with the project from the
outset. The placing of subcontract orders will however continue throughout the
project period. The scheduling of key subcontract dates will need to be tied in with
the master programme and related to the project requirement schedules.
will also be responsible for allocating office staff to deal with wages and material
invoicing. Notices to the factory inspectorate will have to be issued together with
applications for hoarding. licenses, footpath crossings and the provision of temporary
service connections. The necessary insurance requirements for the contract will also
need to be organized.
A client's pre-contract meeting is usually held by the Engineer, design team, client's
representative and the contractor in order to establish initial contact between the
parties. This enables channels of communication to be set up for the issue and
distribution of project information. At the pre-contract meeting the contractor may be
required to present his/her outline programme. This may indicate the requirements
for key nominated subcontract dates, in order that realistic information requirements
may be assessed. Outstanding matters in relation to the contract commencement
dates may be discussed, together with arrangements for the signing of the contract.
As indicated above, it will be necessary to consider the company policy with regard
to the procedures to be adopted for the placing of orders for subcontractors and
suppliers. Within the larger organizations procedures are implemented to award
subcontracts on the basis of standard forms of subcontract.
Within the small and medium sized organizations, subcontracts may simply be
awarded on the basis of a letter of appointment with no formal written contract being
entered into. Nominated subcontracts are let on the basis of standard forms of
contract, such as the Nominated Subcontract Form (NSC/C).
Site notices, instructing personnel entering the site to report to the office,
should be displayed. Site compound areas should be adequately stoned up or
tarmaced and consideration should be given to the site parking of vehicles for
staff and operatives. The site office area may be fenced and provided with
secure gates.
given to the sitting and location of the site signboards and any site component
sample panel areas.
Power supplies to major items of plant such as tower cranes will need
consideration together with the provision of electrical service connections for
site power tools and site temporary lighting.
It may prove opportune to lay hardcore to car park areas at a lower level early
in the contract, in order to use them as temporary hard standings for the
works. Foundations for tower crane bases or tracks will require preparing
early in the contract prior to the erection of the cranes.
The contractor will have to consider the storage and security of plant during
evenings and weekend periods. A locked compound may be provided. The
location and working radius of cranes will require to be marked on the site
layout plan in order to establish the best location for delivery points.
Consideration will also have to be given to site space requirements around the
building for the provision of scaffolding.
Structural timber
To be ordered in cut or stock lengths to avoid cutting waste. May be banded
for ease of handling. Must be stored clear of the ground and protected with
polythene or tarpaulin sheets to avoid changes in moisture content.
Roof trusses,
May be stored on purpose-built, timber or steel storage racks, which support
the trusses clear of the ground. It is preferable to deliver the trusses to site in
phased deliveries in order that they may be lifted directly into position.
Drainage goods
A material which is brittle and easily damaged if mishandled. Drainage
fittings may be delivered to site in a crated form. Pipes may be banded and
stored on timber separators. Materials may be stored adjacent to the works in
a small compound.
The master programme forms the basis of the contractor's budgetary control and
financial forecasting procedures and aids the client in assessing his/her cash funding
requirements at the monthly payment stages. It is also important in relation to the
contract.
Firstly, the contract programme is not usually part of the contract documents. If it was
included as a contract document it would somewhat impair its flexibility and usefulness.
This would involve both parties having to strictly adhere to the programme and the
contractor would be required to start and finish each operation by the programmed dates
and in the programmed sequence. In this respect the programme would lose its purpose
as a flexible contract tool and become unworkable.
gave sufficient detail, it would be a notice of the contractor's requirement for further
information, and so it follows that a post-contract programme is 'a unilateral declaration
of the intention by the contractor, and notice of when he/she requires information.
It is good practice for the contractor and design team to' agree amicably a realistic
contract programme prior to the commencement of the project. This will avoid recourse
to legal threats which only tend to lead to strained relationships which everybody can do
without.
The master programme may be presented in bar chart, network or precedence format
depending upon the programming techniques adopted by the contractor. Contractors
tend to use the programming technique, which best suit, their mode of operations and
works for them. The master programme indicates the sequence of operations and
relationships may be shown between related operations by introducing links in the
form of a linked bar chart.
Copies of the master programme should be circulated to the Engineer for courtesy
approval and to the major subcontractors in order to indicate their approximate
commencement dates and periods on site. The programme is used to record progress
weekly and monthly throughout the contract period in order to achieve the planned
completion date.
Many contractors may consider that 'the claims start here'. This should not be the
reason behind requesting information requirements at this stage of the contract. The
purpose of requirement schedules is to aid the smooth running of the project. The
release of information to the contractor continues throughout the contract; it is no use
asking for information relative to painting schedules at the first week of a project of
one year duration, and then expecting to formulate a claim after six months, simply
because you have not received the information.
Planning Before, During and After Construction 159
Plant Schedule
This schedule indicates key dates for the major items of plant allocated to the
contract (Figure 6.5). The schedule may be presented in tabular format or as a bar
chart programme. The plant schedule enables the plant department to plan its
resources between projects. It enables a balance to be obtained between owned plant
utilization and hired plant suppliers.
160 Fundamentals of Civil Engineering Construction Management
Reference must be made to the allowances for plant within the contract preliminaries
because over spending on plant is a common source of loss at site level.
Sub-contract Schedule
The co-ordination of subcontractors and suppliers is an essential part of project
control. The schedule illustrated in Figure 6.6 enables the site manager to overview
key contract dates with respect to contract progress. Details are also shown relating
to details of the subcontract order, contact address and notification dates. Reference
should be made to the sub-contractor's programme prepared at the contract stage. The
release of key information relative to nominated subcontractors and suppliers may
lead to an extension of time when the delay is caused by the Engineer.
Where information is delayed by the Engineer, the contractor may apply for an
extension of time. The schedule shown in Figure 6.7 allows the contractor to record
the date of the information request, and compare this with the information release
date.
The essential budgets that are prepared by the contractor at the pre-contract stage
include:
The cumulative value forecast - based on the master programme;
The preliminaries budget;
The labour expenditure budget - based on the master programme; and
The plant expenditure budget.
These and other budgets prepared in a contracting organization are monitored and
reported upon as part of the company's control procedures.
162 Fundamentals of Civil Engineering Construction Management
MATERIALS SCHEDULE
PLANT SCHEDULE
SUB-CONTRACT SCHEDULE
SUBCONTRACTOR DETAILS
Trade/ Specialization Nominated Latest Latest Period Comm. Subcontractor Tel. Order Notes
or Inquiry Order Of S/C Date No. No.
Domestic Date Date notice on site
Planning Before, During and After Construction 165
Personnel Involved
MASTER PROGRAMME
STAGE PROGRAMME
Support will be required at site level to monitor the planning in the form of site-based
planning engineers or head office based planners visiting the site. Monthly and
weekly site meetings will assist in standardizing the reporting procedures at site
management and senior management levels. Figure 6.9 indicates the relationship
between the various programmes produced and the reporting and control meetings
taking place at site level.
168 Fundamentals of Civil Engineering Construction Management
Based on agreed commencement and complete date Reports to client on progress situation. Assess
information/ design requirements. Overviews
contract completion date
WEEKS
WEEKS
DAYS or WEEKS
DAYS
Figure 6.9 Relationship between programming and reporting and control meetings.
Source: Cooke and Williams (1998)
Planning Before, During and After Construction 169
Various meetings are held in relation to the construction process in order to develop
communication links between the parties, i.e., the client, Engineer, design team,
contractor and subcontractors. Meetings help in building a team approach to
decision-making and problem solving. The various meetings that may take place
during construction process include:
i) Tender Stage
Pre-qualification meetings (Client/Engineer-Contractor);
Pre-tender meeting (Contractor);
Tender coordination meetings (Contractor); and
Tender adjudication meeting (Contractor).
Meetings may be held on a formal or informal basis. Formal meetings such as the
client’s pre-contract meeting and monthly site meetings have procedures and rules.
Informal meetings such as tender co-ordination meeting and weekly site meetings
with the trades foreman may be of a more casual and relaxed nature. However, all
meetings should have an agenda and minutes should be recorded and circulated.
The meeting agenda is the responsibility of the meeting chairman and it should be
circulated before the meeting in order that the personnel attending are fully aware of
the items to be discussed. Minutes of previous meeting should also be circulated in
order that they can be formally accepted as true record.
Weekly progress meetings are held are held at site management level in order to
review the programme in the short term and to coordinate the activities of sub-
contractors and the contractor’s own trade gangs. Coordination is essential for the
success of the contract and the weekly site meetings are used to discuss the short
term programme and interfaces for the following one or two week period.
PAVEMENT TO A OPERATIONAL
TARMAC ROAD METHOD AND RESORCE STATEMENT…………………… STATEMENT
1 Removal of top soil 600 m3 Removal of top soil Hydraulic 1 – Surveyor Duration
using a bull dozer (CAT Excavator 1 – Operator 1 week
650)
Strategic and operational planning are the two main levels of planning associated
with construction projects. Strategic planning deals with the high-level selection of
overall project objectives, including the scope, procurement routes, time-scale and
financing options. Strategic planning for a project results in broad outlines of what
the project has to achieve and how it is to be undertaken. Operational planning, on
the other hand, involves establishing a method statement for each activity.
Operational planning that includes a tender plan, feasibility plan, and construction
plan, among others, allows a more detailed treatment of the project’s resource
requirements that is not obvious at the strategic level.
Strategic planning by its nature looks at the future and propose a plan of action to
best suit the organization at that particular time. For this reason no tools are
specifically designed to assist the planner. Operational planning for a construction
project, on the other hand, employs various tools and techniques to help the planner
Planning Techniques 173
achieve better optimization for the decisions involved as discussed below: In any
case, operational planning benefits from Work Breakdown Structure (WBS) that
clearly show how the scope of work is broken down into various levels until work
packages and activities are defined.
Planning in the construction industry takes place at all major stages of the
construction process and involves all the key stakeholder organizations, i.e., the
client organization; the engineers or designers; and the constructor as described
below:-
The whole-life cycle of the project requires the client to get involved in all stages in
one way or another. The plan of the overall project from the inception to the use of
the facility is of great interest to the client. The client is interested in the overall
strategic management of the project and the times of cash outflows for which it has
to make provision. Time scales that are most relevant to the client are months and
weeks rather than days. The project plan also enables the client to make decision on
the timing of procurement of key components to the project that may require long
lead-time to process.
The client’s organization will rely heavily on the project’s plan or programme as a
decision aid when considering these and other strategic issues. Later, the client
organization will use the project’s plan to monitor progress.
The Engineer will normally carry the responsibility for preparing the plans used by
the client in taking the strategic decisions. It is around a project plan that the design
team will manage its resources through determining the order in which various
sections of work will be designed, the numbers of designers allocated to each work
section and the cost, in terms of designer-hours, of the design tasks. To bring a set of
174 Fundamentals of Civil Engineering Construction Management
contract documents to conclusion in order to issue them for tendering purposes like
any process of multiple activities, it is necessary to plan, monitor and control.
The role of the estimating process and as part of the projection control process hardly
needs to be emphasized as can be clearly seen in Figure 7.1. In estimating, a project
plan of work is required around which to develop proposed construction methods and
hence estimates. The units of time used in the activities of the pre-tender programme
would normally be weeks or days.
Plans or work programmes are needed by the site manager at the start of the project
to determine their resource requirements. During the execution of the project the site
manager needs plans to assist in directing those resources, to monitor progress, to
evaluate the effect of the changes that may be imposed by varying productivity, by
mistakes, by weather or by the client and their designers. In certain forms of contract
the site manager needs the project plan to determine payments due at interim stages.
At site manager level the unit of time used for activities is usually weeks or days.
The section engineer is usually required to plan the work of their section in great
detail week by week and so may use smaller units of time of days or half days.
Planning Techniques 175
Depending on the size of the organization there may or may not be formal planning
section specifically assigned the task of planning.
Estimating Planning
Cash
flow
The most common and widely used techniques available for planning are bar charts
and linked bar-charts; network analysis, either activity on the node or activity on the
arrow; and line of balance, for repetitive construction work.
Henry Gantt first introduced bar charts in the early 1900s by popularizing the
graphical presentation of work versus time. Bar charts are the easiest to understand
and the most widely used form of planning tool. Even when a more sophisticated
technique like network analysis is used the eventual schedule of work is usually
presented in bar-chart form. They can be used to link the programme prepared at the
tender stage with the master programme and likewise with the short term planning
throughout the contract period. Bar charts are easily and readily updated at weekly
and monthly time intervals.
176 Fundamentals of Civil Engineering Construction Management
The chart consists of vertical column, listing the individual operations on the left-
hand side of the sheet and a time scale on the horizontal axis. The operations are
signified by a series of horizontal bars, the length of which denotes their duration.
The bar chart in Figure 7.2 shows the typical form: a list of activities with the start,
duration and finish of each activity shown as a ‘bar’ plotted to a time scale. The
level of detail of the activities depends on the intended use of the plan. The site
manager may be content with an activity as broad as ‘construct abutment 1’. The
section engineer will break this into a finer level of detail; say ‘excavate’, ‘blind’,
‘fix reinforcement’, ‘erect formwork’, ‘concrete’, ‘strike formwork’ ‘cure’ and
‘backfill’. Similarly the time scale will be chosen to suit the user’s purpose. The site
manager may use weeks while the section engineer may use days or half days.
Figure 7.2 could be used to control the progress of the project. A second bar is
superimposed on the lower section of main bar showing the planned time, to indicate
progress for each activity. At the end of each time period the amount of work done
in each activity is recorded and expressed as a percentage of the planned work for
Planning Techniques 177
that activity. Figure 7.2 shows time now as being end of Week 7, the shading on the
chart shows activities ‘Exc. to found abutment 1’ and ‘Conc. founds abutment 1 are
100% complete. Activity ‘Exc. to founds abutment 2’ is shown as being 67%
complete whereas, to be on programme, it should be 83% complete. This means that
this activity is unlikely to finish at the end of Week 8 as planned. By working at the
achieved rate of progress for that activity, its finishing time will extend by one and
half weeks beyond the planned time. The effect on the other activities would need to
be calculated. This effect would be more easily studied by using an extension to the
simple bar chart such as the linked bar chart.
The linked bar chart, as in Figure 7.3, shows the links between an activity and the
preceding activities, which have to be complete before this activity can start.
Similarly, the links are shown between the activity and the succeeding activities,
which are dependent on the activity being completed. This illustration of
dependency between activities has the advantage that the effects of delays in any
activity are easily seen. The time available for each activity is also displayed: for
example, in Figure 7.3 activity ‘Conc. abutment 1’, is shown as starting on Week 3
and ending on Week 5, but it can be seen that the absolute deadline before it
interferes with the next succeeding activity, ‘Conc. abutment 2’, is end of week 9.
This activity has some ‘float’ or extra time available before any delay affects other
activities. Activity ‘Exc. to founds abutment 2’, for example, has no float and must
be completed by Week 8; this is called a critical activity.
The bar-chart is also useful for calculating the resources required for the project. To
add the resources, say labourers to each activity and total them as in Fig 7.3 is called
resource aggregation. An aggregation chart similar to the one produced in Figure 7.3
for labourers can also be done separately for other resource types such as carpenters
or steel fixers, or cranes.
7
6
5
4
3
2
1
The bar-chart and the resource aggregation charts are useful of estimating the work
content in terms of labour-hours or machine-hours. Similar calculations done on site
may be used to check the work content implied by the estimate, so as to determine
whether the chosen construction methods will result in a profit or loss. Cost control
is more effectively based on such assessment of construction method than on simple
historical cost checks.
(iv) Clearly relates the construction sequence – the use of linking on bar charts aids
the overlapping of related operations
(v) Key milestone symbols may be introduced to highlight critical dates with
regard to key contract stages and information requirements
(vi) Resources may be readily related to the rate of working – labour histograms,
value forecasts (value/time), cumulative labour and plant forecasts in the form
of project budgets
(vii) Requirement under the contract-the contractor is usually required to submit a
programme prior to commencing work on the project. The programme must be
realistic and achievable.
(viii) The “as built” programme may prove an asset to the contractor in the
formulation of contractual claims. The effect on the receipt of late information
on programmed operations can be monitored and reported upon. Copies of the
contract position at the date of a specific occurrence may provide evidence of
the resulting delay
(ix) The programme forms the basis of financial forecasting for both the client and
the contractor
(x) Symbols and signs may be introduced to aid subcontractor and materials
procurement.
On the other hand, the main disadvantages of a bar chart relate to its construction as
follows:
(i) If the bar chart is produced manually, that is, constructed on paper and not as a
by-product of a computer system, then the bar chart is limited in size (say a
maximum of 100 activities); and not easy to update or schedule.
(ii) Does not clearly indicate which operations directly relate to the successful
completion of the project
(iii) Complex interrelationships cannot be clearly shown.
Network analysis also known as Critical Path Analysis (CPA) or Critical Path
Method (CPM) has its origins in 1956 when E.I du Pont de Nemours Company
180 Fundamentals of Civil Engineering Construction Management
The planning data in a network is linked through the logic that defines the
relationships between the activities. Thus changes can be made in the data relating to
individual activities, i.e. the duration, the resources, etc., or changes can be made in
the logical relationships between activities and the consequences re-calculated and
represented. In addition, the steps to produce and process a network plan are more
clearly defined, self-contained and offer a more rigorous approach to planning
complex operations. The greater rigor imposed by the logic diagram produces more
realistic models of the proposed work.
(vi) The effect of changes and variations can be evaluated and time cost
optimization analysis undertaken; and
(vii) Cash flow assessments and valuation forecasting information may be output in
graphical format and readily updated during the project;
The network analysis can be divided into two broad stages: construct network; and
analyze network. The steps that are commonly followed in producing a network are:
(1) Listing the activities;
(2) Producing a network showing the logical relationship between activities;
(3) Assessing the duration of each activity, producing a schedule; and determining
the start and finish times of each activity and the float available;
(4) Assessing the resources required.
In producing a bar chart (2) and (3) are taken in one step and therefore in complex
projects the various alternatives are unlikely to be considered. There are two popular
forms of network analysis: activity-on-the-arrow and activity-on-the-node, the latter
usually called a precedence diagram.
An activity is an operation requiring time or resources, which has a definite
beginning and a definite end. It is portrayed by an arrow and represents the smallest
unit over which control is desired.
An event node is a significant point of time within the project. It is portrayed by a
circle and represents the beginning or end of an activity. No expenditure of
resources is associated with an event.
Subject to the restraints that will be placed upon the sequences of activities by
resources, either labour or plant, the network that satisfies the above questions will
show the logical relationship of all activities. It may be necessary to introduce
dummy arrows, drawn as broken lines, which do not represent any activity but are
simply a logical link. For example, if activity C was dependent on A and B being
completed and activity D was dependent only on B being completed, the network
would require a dummy arrow to represent the logic as shown in Figure 7.4.
A C
B D
The numbering of these events provides a method of identification. For instance, the
“Conc. abutment 2” activity in Fig 7.5 would be called activity 4-5. The numbering
begins at the start of the network and progresses thorough the events in numerical
order until the end event is reached, ensuring that the number at the tail of an arrow
is always smaller than that at the head of the arrow. There may be situations where
two arrows leave the same event and arrive together at another event. In this case the
activities would have the same identification numbers. To avoid this, a dummy is
used and extra event introduced thus ensuring that each activity has a unique
identification. Figure 7.6 gives an example.
8 8
9 11
Figure 7.5 A network showing duration, event numbers and event times
16 18
17 16
17
The time required for each activity needs to be estimated; the estimate of duration
will be based on knowledge of the work, experience, records and work-study. Once
estimated, the duration of each activity is marked against the arrow in the logic
network. The earliest possible time of each event is then calculated and written in
the left-hand square alongside each event. This has determined the earliest possible
start time of each activity.
The calculations are shown in Figure 7.5. For example, the earliest time of event 1 is
0, the earliest time for event 2 is 0 + 2, the earliest time of event 3 is 2 + 6 = 8 and so
on. The point to watch is that where two paths or chains of activities merge, as for
example at event 4, the longest path determines the earliest possible time of the
event. At event 4 the path via event 3 produces an earliest time of 8 + 1 = 9 which is
greater that the path direct from 2 which produces an earliest time 2 + 3 = 5.
Therefore 9 is the earliest time of event 4. The calculation of the earliest event times
is known as the forward pass.
The reverse process, the backward pass, determines the latest possible time for the
event, which is the latest possible time for each activity finishing without delaying
the completion date of the project. The latest event time is calculated and written in
the right-hand square alongside each event. The calculations are shown in Figure
7.5. The latest time of the finish event, event 6 is taken as 16 weeks; the latest time
of event 5 is 16 – 2 =14; and of event 4 it is 14 – 3 = 11. Event 3 has two activities
leaving it, and the latest time of event 3 is determined by the earliest or smaller
calculated latest time, i.e. one calculation for event 3 from event 4 is 14 – 6 = 8 and
the other is 11 – 1 = 10, therefore the latest time of event 3 is 8. If event 3 were any
later than 8 the time to complete activities 3-5 and 5-6 would extend beyond the
project end date of 16.
Having completed the forward and backward passes, the earliest and latest times of
each event are known. From this, the ‘float’ or spare time available for each activity
can be calculated. Critical activities, which have no float, are those whose earliest
and latest times of start event coincide, whose earliest and latest times of finish event
Planning Techniques 185
coincide and the time difference between the start event and finish event equals
duration of the activity.
Figure 7.7 shows an activity extracted from the network in Figure 7.5.
2 2 9 1
3 1
2 4
6
Latest time of
finish event
2 9 11
Total time available for
activity 2-4
Activity 2-4
Total float
Latest
starting
time
Activity 2-4
Earliest Interfering
finishing float
time
The times shown refer to the event times and have the following meanings:
(i) the earliest time of start event is the earliest possible time the activity can start;
(ii) the latest time of finish event is the latest time the activity can finish without
delaying the completion of the project;
(iii) the latest time of start event is the latest time a preceding activity may finish;
and
(iv) the earliest time of a finish event is the earliest time that a succeeding activity
may start.
186 Fundamentals of Civil Engineering Construction Management
Knowing these times, the float can be calculated. Figure 7.7 shows the calculation of
total float and free float.
Total float is the total amount of time by which the activity could be extended or
delayed and still not interfere with the project end date. Total float is the total time
available for the activity less the duration, i.e. the latest time of the finish event less
the earliest time of the start event less the duration.
If the total float for one activity is completely used up by the activity then some of
the total float of the succeeding activity is also used. Free float, however, is the
amount of time by which an activity could be extended or delayed without interfering
with the succeeding activity. Free float is calculated by the earliest time of the finish
event less the earliest time of the start event less the duration. Free float assumes
both the preceding and succeeding activities start as early as possible.
Using the examples in Figure 7.7 the total float of activity 2-4 is 11 – 2 – 3 = 6, and
the free float is 9 – 2 = 4.
The difference between total float and free float is sometimes referred to as
interfering float as shown in Figure 7.7. It is the amount of total float shared by the
succeeding activity. Interfering float is rarely used in any subsequent calculations.
In the first method time analysis will provide the minimum time possible for
completing the project. If the minimum is taken as the time limit, adjustments in the
timing of any activity that may affect resource requirements must be undertaken
within the float available. The steps in assessing the resources required in a time-
limited situation are:
(1) Prepare a list of activities ranked in order of their earliest start dates.
(2) Produce a resource aggregation chart as in Figure 7.8, based on this list of
activities in earliest start order and the resources required as shown in Figure
7.8. This gives the resources required assuming all activities start as early as
possible.
(3) Produce a list of activities ranked in order of latest start dates. (Note: The
latest start date of an activity is the latest time of the finish event less the
duration.)
(4) Produce a resource aggregation chart as in Figure 7.8 based on this list of
activities in latest start order, and starting at these latest start times. These are
the resources required when all activities start as late as possible.
(5) Compare the resource aggregation charts from (2) and (4). These provide the
extremes of resource requirements, all activities starting as early and as late as
possible. Between these extremes a compromise to produce acceptable
resource requirements can be sought by visual inspection and manipulation of
activities within the two extremes.
188 Fundamentals of Civil Engineering Construction Management
The decision rule is a device whereby activities are ranked in the order in which their
resource demand is added to the resource aggregation chart. Each activity is thus
given its appropriate priority in the queue for resources. It is possible that not all
activities can receive the resources they required at the earliest time they require
them. Consequently, some activities will be delayed until the resources are available.
The ordering according to a chosen priority or decision rule ensures that activities
high in the priority list receive their resources first. Activities low in the priority list
may get delayed.
2-4
3-4
Labourers
4-5
3-5
2-3
1-2 Weeks 5-6
3-4
2-4 4-5
Labourers
2-3
3-5
1-2 5-6
2 4 6 8 10 12 14
Weeks
Figure 7.8 Resource aggregation charts for activities starting as early and as late as
possible (based on network in Figure 7.5).
Sorting is the ranking in a priority order, and one of the more common sorts or
decision rules is to sort in order of ‘early start time’. For activities with the same
early start time a second sort is required and this could be in order of total float. The
upper part of Figure 7.8 gives the activities for the network shown in Figure 7.5
ranked in order of early start as the first or major sort and in total float order as the
second or minor sort. This ranking has been used in preparing the resource
aggregation chart shown in Figure 7.9. This example shows that activity 2-4 is the
first to exceed the resource limit and is therefore delayed from starting on week 2 to
starting on week 8.
Labourers
3-4
4-5
5-6
2-3 3-5
190 Fundamentals of Civil Engineering Construction Management
When the resources for all the activities have been entered in the resource
aggregation chart a list of scheduled start dates can be extracted as in the table shown
in Figure 7.9. Figure 7.10 gives similar examples for two types of resource, for
demonstration purposes the decision rule or priority sort used in this case are early
start as the major sort and largest duration as the minor sort. The choice of decision
rule or sort is left to the user of these techniques. The decision rules in common use
are early start-total float, late start-total float, and since each type of decision rule
may load the resources into the aggregation chart in a different order the resulting
resource aggregation chart will be different. The priority list guides the user towards
an acceptable solution
Resource limit 4
2 4 6 8 10 12 14 16 18
Resource
5-6
3-4
4-5
2 4 6 8 10 12 14 16 18 20
1-2
The finish to start limitations or arrow diagrams causes difficulties when, for
instance, one activity is required to start before the preceding activity is completed.
This either means dividing the preceding activity into smaller parts as shown in
Figure12 (a) or introducing a dummy with a time value as shown in Figure12 (b).
Dependency list
Activity Duration Dependency
1 2 Start
2 6 1
3 6 2
4 1 2
5 3 1
192 Fundamentals of Civil Engineering Construction Management
6 3 4 and 5
7 2 3 and 6
8 (6) 14
8 3 14
Latest Activity Latest
start identifier finish
2 (6) 8
14 (2) 16
2 2 8
14 7 16
0 (2) 2
0 1 2 8 (1) 9
9 (3) 12
10 4 11
2 (3) 5 11 6 14
8 5 11
Figure 7.11 Precedence list and diagram showing the same network as in Figure7.5.
A B
a
b A B part 2
B part 1
4 4
B
4
4
C
In precedence diagrams the ‘node’ represents the activity and the link or arrow
represents only the logical relationship. Figure 7.11 shows the precedence network
and the list of activities on which it is based. No dummies are needed to maintain
correct logic or for unique numbering or activities.
Each node representing an activity can be given a single unique number. As for
arrows, the duration of each activity is estimated and the forward and backward
passes are done and the earliest and latest start and finish times of each activity are
entered as shown in Figure 7.11. These times calculated refer to the activity whereas
the calculations for arrows referred to event times. Float can be calculated as before,
for example the total float of activity No. 5 is latest finish time less earliest starting
time less duration, that is 11 – 2 – 3 = 6.
The main difference between activity-on-the-node diagrams and the arrow equivalent
are that node diagrams have no dummies, no change of reference number when
194 Fundamentals of Civil Engineering Construction Management
additional activities are added, and complex relationships. The incorporation of node
diagrams in several commercial software packages has contributed to their increased
use by planning engineers in construction.
A line of balance diagramme comprises a series of inclined lines, which represent the
rate of working between repetitive operations in a construction sequence. It is thus a
planning technique for repetitive work whose basis is to find the required resources
for each stage or operation so that the following stages are not interfered with and the
target output can be achieved.
The interrelationship of the three basic operations can be shown in a simple logic
diagram, as in Figure 7.13(a). To provide for a margin of error in the time taken to
complete each of these operations, a time buffer is usually placed between
operations, as in Figure 7.13(b). This construction plan shows that a total time of 50
days is needed to complete one sequence of operations. The target output of the
project can be expressed in terms of the completion rate of these sequences. For
example, it may be that the quay comprising ten sections has to be completed in 100
days. Thus if a target rate of completion of one section per five-day week was
chosen, the total time taken for ten sections would be 95 days, as in Figure 7.14.
Deck
Pile cap
A A
Planning Techniques 195
A B C
approximately
4 1 section/5-day week
3
2
1
10 20 30 40 50 60 70 80 90 100
Time (days)
Figure 7.14 Time for completion of ten repetitive sequences at the rate of one per week.
196 Fundamentals of Civil Engineering Construction Management
Total time 95 days
P C D
10
9 P – Pile
8 C – Cap
7
Sections
D – Deck
6
5 Completion rate
4 1 Section/ 5-day week
3
2
1
10 20 30 40 50 60 70 80 90 100
Time (days)
Figure 7.15 Logic diagram for each section added to the completion schedule.
The logic diagram or construction plan for section 1 in Figure 7.13 can be added to
Figure 7.14, as in Figure 7.15 for the other sections. The sloping lines added to the
start and finish of each operation to allow dates to be established for each section.
This is the line of balance schedule, if sufficient resources are made available to
maintain the production represented in the schedule.
Note that the schedule shown in Figure 7.15 is only possible if the required number
of teams of operatives is available to start at the scheduled start dates of each section.
The basic approach is to determine the resources available and calculate the rates of
construction that can be achieved. This example only demonstrates the procedure.
If, for example, operation ‘pile cap’ required a team of six operatives to construct the
pile cap in 12 days and two teams of six operatives were employed the output of the
gang of two teams would be 0.83 sections per five-day week and not the one section
per five-day week required by the target. This is because if two teams were
employed, team ‘a’ would start on section 1 on day 23 and finish on day 35 (from
schedule Figure 7.15) and team ‘b’ would start on section 2 on day 28 and finish on
day 40 (from schedule Figure 7.15).
Total time 104
days
Planning Techniques 197
10 P – Pile
9
C – Cap
8
7 D - Deck
Sections
6
5
4
3
2
1 P C D
10 20 30 40 50 60 70 80 90 100 110
Time (days)
Section 3, according to the schedule, is due to start on day 33, but team ‘a ’is not
available until day 35. Therefore the rate of completion of the operation ‘pile cap’
would be less than 1.0 section per five-day week; calculations show this rate to be
0.83 and Figure 7.16 shows the delay to the project.
If three teams were employed on operation ‘pile cap’ the output would be 1.25
sections per week. This is because team ‘a’ completes the first section on day 35 and
moves to section 4, which is not due to start until day 38.
P – Pile
10
9 C – Cap
8 D - Deck
7
Sections
6
5
4
3
2
1 P C D
10 20 30 40 50 60 70 80 90 100 110
Time (days)
Figure 7.17 Effects of scheduling operation ‘Pile cap’ at a completion rate of 1.25 per
week.
198 Fundamentals of Civil Engineering Construction Management
Figure 7.17 shows that the project completion date is in fact later than the original
despite the speeding up of operation ‘pile cap’. This is because operation ‘pile cap’
is no longer in ‘balance; with its preceding and succeeding operations.
20
19
17
15
13
11
Houses
A B C D E
Planning Techniques 199
10 20 30 40 50 60 70 80 90 100
Note: Operations are sequential. Total no. of houses = 20. Target rate of build (or completions) R = 3 per week (one week comprises
five eight-hour days)
(7) Examine the schedule and assess possible alternatives to bring about more
‘balanced’ schedule which might include:
(a) Changing the rate of output of one activity by reducing (or increasing)
the gang size pathway through the project; an example is given in Figure
7.19.
(b) Lay-off and recall one gang; an example is given in Figure 7.20.
(c) Overlap some activities, i.e. have a non-sequential logic diagram, which
means that the schedules shown as sloping lines on the diagrams would
be superimposed. Such schedules become difficult to read and this
severely reduces the effectiveness as a means of communication with
operational staff such as foremen and gangers.
(d) Schedule every activity to work at the same rate. This is known as
‘parallel scheduling’ and involves employing enough resources to ensure
that the rate of output required can be achieved. In the example in Table
4.1, if activities C and E had actual gang sizes one team more than shown
then all activities could proceed at a rate of 3.0 per week. However, this
means that most gangs of operatives are working at less than their natural
rate. The parallel schedule would have a shorter overall duration. Before
employing parallel scheduling, examination would be needed as to
whether the savings in overall duration and hence indirect overheads
offset the extra costs in over-manning.
202 Fundamentals of Civil Engineering Construction Management
17
15
13
11
7
Houses
A B C D E
10 20 30 40 50 60 70 80 90 100
Time (days)
Figure 7.19 Line of balance schedule drawn from data in Table 7.1.
17
15
13
11
7
Houses
A B C D E
10 20 30 40 50 60 70 80 90 100
Time (days)
Figure 20 Line of balance schedule drawn from data in Table 7.1.
Planning Techniques 203
The schedule and the start and finish dates of the various teams on each operation
can be used to monitor progress. Figure 7.18 shows time now as day 25 and the
completion of operations A and B marked on their respective lines of balance. The
situation portrayed is operation A on schedule and operation B ahead of schedule.
The danger from this is the B may run out of work because it is progressing at a
faster rate than A. Action is needed either to speed up A or slow down B.
Updating a line of balance schedule once the project has started, and if the rates of
construction prove to be different from those calculated, can be difficult and quickly
becomes unclear.
Another use for the line of balance schedule is checking material orders or deliveries.
If a deadline for ordering and/or receiving materials is marked on the schedule, as
shown in Figure7.20 for plumbing supplies, then a simple check can be made in good
time.
PERT was developed in the late 1950’s as an integrated planning and control system
to manage the hundreds of contractors involved in the design, construction and
testing of the Polaris Submarine missile system. It was developed to apply a
statistical treatment to the possible range of activity time durations. A three time
probabilistic model was developed, using pessimistic, optimistic and most likely time
durations (Figure 7.21). The three times were imposed on a normal distribution to
calculate activity’s expected time.
204 Fundamentals of Civil Engineering Construction Management
o m p
(ii) Most likely duration (d m ) based on analysis of work from previous projects
and the planner’s experience and judgement
(d p )
(iii) Pessimistic duration maximum time if everything goes wrong
The technique is based on probability and assumes that the probability of exceeding
d 0 is about 99% and d p is about 1%. The following define key activity parameters
de ( d 0 4d m d p ) / 6
Expected duration =
Standard deviation d e = (d p d 0 ) / 6
Variance vd e = (d p
d 0 ) / 6 i.e.d e
2 2
Table 7.2 outlines the optimistic, pessimistic, and most likely time estimates provided
by the planning engineer for the project. It presents the calculated expected duration
and variance for each activity. The expected duration for PERT reflects the activity
times for simple activity-on-arrow and activity-on-node techniques. The
representation of a PERT diagram can either be as an arrow or a node diagram, with
the additional information on activity variances. For convenience of relating the
analysis of the PERT programme to the concepts outlined earlier in this chapter
(forward and backward pass, earliest and latest times) the PERT diagram for our
project is presented here as an arrow diagram.
7.4.1.1 Project duration and critical path
Figure 7.22 shows the PERT programme presented in arrow diagram format. To
establish the project duration and critical activities the activity event times with the
206 Fundamentals of Civil Engineering Construction Management
8 8
3
C
6(16/9)
14 14 16 16
0 0 2 2 6(1/9)
B
D 5 6
1 2 2(0)
1(1/36)
2(1/9)
G
3(1/4)
3/16/9) F
A
E 4
9 11
Figure 7.22 A PERT diagram showing duration, event numbers and event times.
In Figure 7.22 although the planned project duration is 16 weeks, in practice the
completion date for this project will be negotiated with an extra time to cater for any
contingencies that might arise during the execution stage. It is essential that there is
a clear appreciation of the potential to deliver the project within the negotiated
period. This is a measure of the risk associated with the programmed project
schedule, and provides useful information for the Contracts Manager who has to
negotiate a delivery date for the project. This is illustrated by using the project in
Figure 7.22 as an example. The Contracts Manager has negotiated an acceptable
delivery date of 18 weeks after its start time, then the overall project will have a two
week float to cater for contingencies. An estimate of the risk associated with
Planning Techniques 207
delivering the project within the negotiated 18 weeks can be assessed utilizing the
additional information of variances that is provided by PERT.
If it is assumed that the activities of this project are statistically independent of each
other, then the probability that it will be completed within the 18 weeks can be
established. In order to use the areas under a normal distribution curve to do this, the
deviation of the target duration (TD) from the expected project duration (EPD) in
units of standard deviation has to be calculated. The standard deviation (and
variance) represent the degree of spread associated with any distribution. The target
duration (TD) is the desired or agreed project completion time. The expected project
duration, which is the mean duration for completing the project, is the critical time of
the project. This is defined as the sum of expected activity duration (d e ) for those
activities on the critical path. The overall variance of the project (v) is the variance
of the critical path (the sum of the variance vd e for all activities on the critical path).
The expected duration of the whole project can be calculated as: EPF d e for the
critical path and the variance of the overall project as v vd e of the critical
The variance (v) of the overall duration for the activities on the critical path (A-B-C-
G) is
1 16 1 18
0 2
9 9 9 9
For an 18-week target contract period (TD) based on the programmed expected
project duration (EPD) of 16 weeks with a variance (v) of 2 weeks, this yields:
Z = (TD – EPD)/(√v)
208 Fundamentals of Civil Engineering Construction Management
The equivalent probability can be read off a normal probability distribution table.
P ( Z 1.414) = 0.92 which equals 92%
It implies that there is a 92% chance that the project will be delivered within the
negotiated 18-week period. The higher the percentage the lower the schedule risk
associated with the planned project, and vice versa.
where TD95 is the target duration to be negotiated for the project to have a 95%
chance of completion on time; EPF is the expected project duration based on the
critical path; and v is the overall project variance.
This gives
TD95 16 1.65 1.414 18.33 weeks or 18 weeks 2 days
A similar analysis can be undertaken for individual activities by replacing the target
duration (TD) expected project duration (EPD) with the earliest and latest times of
the activity as shown below. The target duration for the activity is the overall period
within which the activity can take place without disrupting the project delivery time.
Then:
Period within which activity can take place = latest finish time – earliest start time
Expected activity duration = d e
Planning Techniques 209
Activity variance = vd e
All activities on the critical path will have a Z value of zero, equivalent to a
probability (P-value) of 0.50. This indicates that all the activities on the critical path
have a fifty percent chance of slipping out of schedule, and presents a higher risk to
the overall project schedule than say activity F for which there is a lesser schedule
risk. By substituting the values of any critical activity with that for activity F the
equivalent probability of completing activity F on time can be obtained as follows:
The introduction of multiple times associated with each activity presents a means of
allowing for the uncertainty associated with project delivery. This main advantage of
the use of PERT is in establishing the schedule risk associated with the planned
proramme. This element is missing from both the simple arrow and node diagrams.
Space-time diagrams for planning construction works were generally utilized before
the advent of computer-based planning packages, which became the norm in
industry. They were normally two-dimensional graphs that represent time (elapsed
project time) on one axis, and a measure for production (chainage or distance, area,
volume of works) on the other axis. The resulting plot then presents a pictorial view
of how the works should progress on site. Used as a planning tool, it allows the
identification of potential constraints in the utilization of resources, such as plant for
210 Fundamentals of Civil Engineering Construction Management
excavation, which can then be re-organized. It also serves as a realistic tool for
communicating information on the programme of works for a project. Space-time
diagrams lend themselves to projects that are essentially linear in nature, for example
road-works, pipe laying, overhead pylon construction, where there is considerable
repetition. However, they can be applied to projects of a non-linear character where
there is considerable repetition of a work package. The main disadvantage
associated with space-time diagrams is the difficulty in effecting alterations for
control and updating purposes. The use of the space-time diagram as a planning tool
is illustrated by the example below.
A new road is required to link a new housing development that is 4 km away from
the main town. The project also includes the construction of a 75 m bridge and two
culverts. The symbols that are used in representing a project in a space-time chart
are line and boxes. A line and a box represent respectively a unit or multiples of
duration and chainage. The width of a vertical box indicates the chainage over which
the activity covers its height represents the time it takes to complete the whole
activity. For inclined boxes, the horizontal length and vertical height across the
incline are taken to establish the chainage and time it takes to complete a unit of the
activity.
Planning without computers is now rare. The key attraction to construction and
project managers is the speed of processing and the manipulative power available.
The arrival of microcomputers and interactive systems resolved most of these
difficulties and the use of network planning based on a computer system is now
much more credible. The installation of the computer equipment on the desk of the
construction managers and the site planner has generated a working relationship
between construction manager and this powerful aid. It is the immediacy of the
results that has convinced manager that computer-aided planning is an indispensable
aid.
Planning Techniques 211
The use of these planning systems varies from the simple programming of activities
up to a complete time, resource and cost modeling system used in analysis of ‘what-
if’ situations and in making forecasts. These are normally organized as separate but
compatible packages that allow data transfer between packages, with each package
focusing on only one aspect of planning. At the other extreme, programming
software comes as one integrated package, which is able to undertake the whole
range of project planning requirements. The choice between an integrated package
and a standalone one will depend on project complexity and size as well as
organizational preference. As the use of the planning system becomes more complex
the data required increases and the computer system required becomes more
sophisticated. The following is a review of these uses.
All systems require project data that describe the overall parameters of the project
before accepting data at individual activity level. This project data relates to ‘time
units’, ‘start dates’, ‘days in weeks’, ‘holidays’, etc.
The data required to prepare a schedule of activities will normally comprise for each
activity:
a. Activity number;
b. Description;
c. Management reporting codes;
d. Duration; and
e. Logic links to other activities
212 Fundamentals of Civil Engineering Construction Management
Later when resources are introduced this activity data will be extended. Some
computer systems will display the network being constructed on the screen. This is
helpful in checking the logic of the network.
From this input the most important report that will be available will be a bar-chart.
This will be supported by reports showing the start and end dates of all activities and
float, if required. The generation of a time-base logic diagram will achieve a basic
planning model and will have developed the planner’s understanding of the project
and interrelationships between the major activities.
7.5.2 Resources
Allocation of the right amount of resources to the basic activities is essential for the
timely execution of the whole project. Most software packages have a facility for
creating a list of resources. The list of resources allows the planner to enter all of the
resource information for the project in a database, which can then be assigned to
activities. Depending on the sophistication of the system available the resource
requirements of each activity will be identified to cover. Individual or groups or
resource types for the duration of the activity and resources shared by other
activities.
The resources will be identified by: resource numbers, descriptions and management
reporting codes. The availability of the resources will be described to the computer
system in terms of total availability or restricted data availability. From this
additional data the computer system will calculate the consequences of the resources
demands. The report will show for each resource the resource requirements for each
time period as a table, histogram or cumulative graph.
These reports allow the planner to assess, in terms of resources used, the implications
of the basic plan. The logic may be reworked in the resource demands are
unrealistic. In practice the most commonly used form of computer-based planning is
to complete the logic diagram and to assess the resource requirements assuming all
activities start as early as possible. The reports produced as bar-charts and resource
histograms are used to take strategic planning decisions. The number of resources
analyzed in this way is, in practice, usually quite limited and well below the capacity
of the existing computer systems.
Equipped with the basic logic model and the resource requirements of each activity
the planner possesses the tools to monitor the progress of the project. As the project
proceeds many occurrences may not be as planned. Thus the computer system needs
to allow updating for each activity by:
- Changing start date;
- Changing duration;
- Changing end date; and
- Changing resource requirements.
The consequences of these changes can be processed and updated and reports
produced. The effect on identified target dates set in the basic plan can be
monitored.
The act of checking actual progress and actual resource usage against planned
progress and planned resource usage is the act of monitoring. The act of taking
decisions to alter the likely future outcome and bring the project back on the planned
scheduled is control.
resource usage in order to update the computer model and monitor progress. This
information can be presented to the construction managers together with suggestions
for re-scheduling. The rescheduling decisions taken by the managers may need
processing before the control decisions are implemented.
Some computer systems allow the cost and revenue to the included. For example, an
activity has the following details:
- Description : Formwork erection
- Duration : 4 weeks
- Carpenters : 3
- Labourers : 1
- Crane : 50%
All this data entered separately and held on file provides the basis for calculating
costs. It also provides a means for exploring the consequences, in cost terms, of any
alterations being considered to re-plan the project.
For example, the number of carpenters may be increased and the overall duration of
this activity reduced; this on its own would be simple enough to calculate but the
consequences on the rest of the project would be more tedious. This is where these
computer systems show their advantages.
Planning Techniques 215
Overheads or on-cost can be held in ‘hammocks’ that span a number of activities and
derive their duration from the interaction of the activities they span. Thus the
manipulation of activity costs can be extended into a grade-off calculation between
direct and indirect costs.
If provision is also made for the activities to hold details on revenue then income
graphs can be produced for the project, for example:
- Description : Formwork erection
- Duration : 4 weeks
- Quantity : 800 m2
- Revenue : US$10.40/m2
With both cost and revenue details it is possible, with additional data relative to
payment conditions and credit delays, to calculate the project’s cash flow. Thus with
the inclusion of cost and revenues the simple planning tool has been extended to be a
basic estimating and cash flow model. Thus all the key elements to managing a
project are present:
- Time;
- Resource;
- Costs;
- Revenues; and
- Cash.
Clients and their designers have found such modeling advantageous to study the
overall development of their project managers; estimators and pre-tender planners;
and by construction managers on site.
Clients and their designers have found such modeling advantageous to study the
overall development of their project, the phasing, the timing of the engagement of
their specialists, etc. Questions such as the effects of procurement delays and their
consequences have led to design sequencing being altered to place orders earlier.
Project managers have found the modeling useful to explore the ramifications of the
interdependence between the many contractors involved in major project.
The pre-tender planner finds use in these modeling techniques to explore the effect of
different construction methods on time, costs and revenues. The site manager has
found such techniques useful in controlling sub-contractors and in exploring the
consequences of changes of construction methods even after the project has started.
Although the use of computers has brought a dimension of speed and possibly
efficiency in construction projects, the plethora of software to choose from is one of
the main challenges of the project manager. Any software has some advantages and
disadvantages when compared with others that are available on market. Hence, the
ability of the Project Manager to select suitable software for the project goes a long
way towards ensuring the benefits outlined above.
All the modern computer systems allow exchange of data between the planning
system and other systems. Now that the construction industry is mainly computer
literate, there is a reluctance to do much, if anything, by manual calculation. At a
minimum the computer planning systems are able to pass data files to spreadsheet
packages where the users can generate their own calculation routines for other
purposes such as cash flows. Other examples of data exchange are where the
planning system passes on data to estimating or cash flow systems. The planning
system, itself, could be the recipient of data from other systems. For example, the
Planning Techniques 217
estimating system may hold details on resources and resource costs on a bill item by
bill item basis. By allocating these bill items to activities in the plan the resource
details are passed from the estimating to the planning system. Thus an appraisal of
the quality of computer systems must now include a review of the system’s ability to
pass on and receive data from other systems.
As computer systems become more and more ‘linked’ or ‘integrated’ the sources of
data for the various systems come under scrutiny and it is clear that if contractual
systems were being created with computers in mind certain contractual system as the
one involving bills of quantities would not be created. The nature of the data created
around the bill of quantities is not ideal for use in other systems. It would arguably
be better to construct a contractual system around activities rather than bill items.
However, various attempts at new systems have shown how resilient the existing
contractual systems are.
Forms of contract without a bill of quantities have payment to contractors based, not
on bill items, but on completion of activities in a schedule of activities. This form of
contract, used internationally, offers the contractor the opportunity of using the
planning model’s database in a number of linked functions such as:
- Estimating;
- Planning;
- Cost control;
- Valuations; and
- Variation pricing.
7.6.1 Estimating
The estimating function required information obtained from the outline tender
programme and method statement and the take-off of quantities required for each
activity. The resource required for each activity, labour, plant or materials, were
entered and costed. Also the subcontractors were identified, allocated to activities
and costed. The preliminaries and on-cost calculations are undertaken and allocated
to activities or hammocks as were profit and overheads; the key being that all this
assembly of estimator’s cost data was being structured around the planning model.
218 Fundamentals of Civil Engineering Construction Management
Estimating by this approach required that the planning model be developed to a more
refined stage than in the traditional process. The value of this is that the data so
assembled and structured is available for use in other functions.
7.6.2 Planning
The use of a planning system, which has been used for estimating and contains all
the planning and estimating data, allows the first two items to be executed with speed
and efficiency. The monitoring of progress will identify which activities are
complete and which are partially complete. The entry of this progress data enables
the budget allowances to be calculated. Each activity has allocated to it, at the
estimating stage, the resources (labour, plant, materials and subcontractors) and their
associated costs. Thus if the activity is identified as complete the budget allowance
for the activity is the cost of those resources. If the activity is partially complete the
costs can be calculated on a pro rata basis. Thus the use of a planning based system
Planning Techniques 219
can considerably ease the calculations of the budget allowance for any measured
progress. What such systems cannot do is calculate the actual expenditure. This
must come from the accounting systems that control expenditure on labour, plant,
materials and subcontractors.
What is of value in any actual versus allowances comparison is that the planning
system holds data on: resources; durations; and costs. Thus, if actual expenditure is
significantly different from the budget allowance the data is readily available to
extend the analysis into whether the resourcing was at planned levels or if time
overruns were the cause.
7.6.4 Valuations
In some systems interim valuations are based on completed activities. Since each
activity has had its value allocated or calculated at the estimating stage the
calculation of an interim valuation required only the identification of a completed
activity. Thus the process is reduced to identifying the completed activities, updating
the planning model and calculating the last valuation.
7.6.5 Variations
One bugbear of all contractual systems is the determination of a fair price for
variations. Variation proposals calculated on the same basis as the original
estimating calculations, with the implications and overheads because of any
disruption, are more clearly demonstrated in a planning model than in other systems.
The above brief review thus demonstrates the advantages to be gained in having
systems that are capable of data exchange.
Chapter 8
Least Cost Scheduling and
Resource Levelling
8.1 Introduction
A least-cost schedule is one with optimum project duration such that to lengthen or
shorten it would increase the total cost. Time and cost are the two most important
components of project economy. If time is not important, management can utilise its
resources in the most efficient way. Even stopping work on one project, moving to
another for a while, and then coming back. If money is not important, management
can obtain the best of resources and schedule work around the clock. This process is
usually inefficient but produces a completed project in a minimum time. Both ways
have their uses, but in the normal situation cost effectiveness calls for a study of the
trade-off between time and cost which yields a “least-cost” solution.
221 Fundamentals of Civil Engineering Construction Management
There is no absolute, provable least-cost solution to a real problem because the value
of variables cannot be known exactly in advance. For instance, one cannot determine
exactly what working overtime on a particular activity will achieve. Generally, it is
known that premium pay for overtime will increase direct cost but will reduce the
number of days needed to complete the activity, which in turn, should reduce the
time needed to complete the project, thereby saving some overhead. How much time
can be saved, and the importance of saving that time, must be analysed.
Before going into the details of the subject matter, it is worth understanding the
following important terminologies, which are important in the discussion of least
cost scheduling and resource levelling.
Direct costs, once a target schedule has been developed, increase with either an
increase or decrease in time. To solve the time/cost problem, i.e. searching for a
least-cost solution, one must make some assumptions. Let us consider an activity A
that normally would require 6 days at a direct cost of $8,000. We estimate that by
adding more equipment or more labour hours per day (more workers or over-time)
we could reduce the time to 3 days at a new direct cost of $14,000. We also estimate
that the same activity can be done in 5 days for $10,000 or in 4 days for $12,000.
Therefore, the “normal” duration for activity "A" considering our available resources
is 6 days, and the “crash” duration is 3 days. There is an implicit assumption that to
increase the duration beyond 6 days would not result in a direct cost reduction
because of underutilisation of resources - otherwise the “normal” duration would not
have been 6 days. To summarise, we have a choice of 6 days at a cost of $8,000, 5
days at $10,000, 4 days at $12,000, or 3 days at $14,000. For simple compression
we consider that the direct cost curve for each activity is linear, so these figures
result in the time/cost curve shown in Figure 8.1.
223 Fundamentals of Civil Engineering Construction Management
16,000
Another scenario would be that 6 days cost $8,000, 5 days cost $9,500, 4 days cost
$11,000, and 3 days cost $15,000. This is often the case because 1 day can be saved
with overtime, while to save 2 days requires new hires and to save 3 days requires
more equipment. For complex compression we consider that the direct cost curve for
each activity is non-linear, so these figures result in the curve shown in Figure 8.2.
16,000
Direct cost ($)
14,000
12,000
10,000
8,000
2 3 4 5 6 7
Time (Days)
Once we know the cost of shortening each activity, we can see the effect on the
project schedule. Shortening some activities - those on the critical path - may result
in advancing the completion date, while shortening other activities may simply add
more float. Sometimes it is advantageous to shorten an activity to free up a resource,
but it is almost always beneficial to shorten an activity that would cause the
Least Cost Scheduling and Resources Levelling 224
completion date to be advanced, if the cost is not too great. In the subsequent
sections we will only consider taking action to shorten the project duration.
Generally, overhead costs vary directly with time; i.e. increase in time causes an
increase in overhead costs, and vice versa. So far we have only discussed about
increasing our direct cost while shortening a project’s duration, but along with this
project shortening there is a cost benefit. For example, if we finish a project 1-week
early, we save on security cost at the job site, management costs, equipment rental
costs, insurance, etc.- these are overhead costs.
Like direct costs, overhead costs may be linear or non-linear. For simplicity,
consider a case where overhead costs are linear at a cost of $1,000 per workday, as
shown in Figure 8.3.
7,000
6,000
Overhead cost ($)
5,000
4,000
3,000
2,000
2 3 4 5 6 7
Time (Days)
For the cases mentioned above, the total cost is the sum of direct costs plus overhead
costs and is shown in Figure 8.4 (a) and (b). For the linear direct and overhead costs
(Figure 8.4(a) the optimum time is 6 days with a least cost of $14,000
225 Fundamentals of Civil Engineering Construction Management
(=8,000+6,000), and for the non-linear direct and linear overhead costs (Figure 8.4(b)
the optimum time is 5 days at a least cost of $14,500 (=9,500+5,000).
17,000
16,000
15,000
14,000
13,000
2 3 4 5 6 7
Time (Days)
19,000
18,000
Overall cost ($)
17,000
16,000
15,000
14,000
2 3 4 5 6 7
Time (Days)
linearly with time, we have simple compression, while if we have one or more costs,
which vary nonlinearly, we have complex compression.
Since the critical path is the longest route through the network it is these activities to
which attention is initially directed. It must be remembered that when shortening the
contract duration the position of the critical path may change. The planner and/or
manager will select the actual activities to be shortened depending on cost and
practicability. As an example, if two activities on the critical path can be shortened
by 1 week and the costs of shortening are $2,000 and 3,000/week, then the former
obviously takes priority for crash costing.
Consider the network shown in Figure 8.5 and its normal and crash durations and
respective costs are shown in Table 8.1. As activities on the critical path are
shortened, the float associated with activities, which are not critical, may be reduced
depending on the location of such activities. As further shortening takes place these
non-critical items become critical.
227 Fundamentals of Civil Engineering Construction Management
13
3
B
13
0 8 13 18
5
A C E
1 5 6
2
5 6 5
0 5 D 13 18
9
4
4
13
.
Table 8.1 Normal and crash durations and their respective costs.
Activity Normal Crash time Normal Crash
time (days) (days) cost ($) cost ($)
A 5 3 2,000 2,400
B 8 2 2,500 4,500
C 6 4 3,000 4,500
D 4 4 2,000 2,000
E 5 3 1,000 3,500
As shown in the Table 8.1 and Figure 8.5, the normal completion time is 18 units of
time and normal cost of completion is $10,500. In order to determine the activity,
which should be crushed initially, it is suggested to calculate the cost slope, i.e. the
cost per day of speeding up each activity, using Equ. 8.1.
The summary of contract durations and costs are given in Table 8.3 and the
completely crushed network is shown in Figure 8.6.
3
B
7
0 3 4 7 12
A C E
1 5 6
2
3 4 5
0 D 7 12
3
7 2
4
4
7
Figure 8.6 Network based on crushed duration and cost.
The increase in direct cost with weeks saved is shown in Figure 8.7. Suppose the
indirect costs are assumed to be $500 per week, then over the normal contract
duration this would have been $9,000 as shown in Figure 8.8.
15,000
14,000
Direct cost ($)
13,000
12,000
11,000
10,000
10 12 14 16 18 20
Time (Days)
12000
The direct cost graph (Figure 8.7) and indirect cost graph (Figure 8.8) are combined
in order to determine the optimistic contract duration. This optimum time/cost
relationship is 14 weeks duration resulting in a cost of $9,566. Both a shorter and a
longer contract duration increases cost as shown clearly in Figure 8.9.
11,500
11,000
Overall cost ($)
10,500
10,000
9,500
9,000
10 12 14 16 18 20
Time (Days)
Figure 8.10 shows a qualitative simple bar chart with each activity needing the same
resource. The resource histogram indicates the peak resources as well as the pattern
of demand. By rescheduling activities within their float times it is possible to smooth
out the resource demands. As a guide, initial priority is given to those activities with
least float during scheduling. The rescheduled (levelled) chart and resource
histogram is shown in Figure 8.11. Resource scheduling enables management to plan
for regular gang sizes, etc. to be used on site with minimum fluctuation in demand.
Activity
A
B
C
D
E
F
G
H
E
F
G
H
Resource
s
Figure 8.10 Bar chart and resource histogram before resource scheduling.
Least Cost Scheduling and Resources Levelling 232
A
B
C
D
E
F
G
H
Resources
Resource levelled
within float time
Time
Figure 8.11 Bar chart and resource histogram after resource levelling.
Levelling the daily labour allocation may be desirable for several reasons, some of
which include:
1. Fixed crew size: Obviously, if the schedule demands more workers per day
than are available or if we have workers standing around without jobs, we have
a problem;
2. Learning curve: When a new hire is trained, there is a loss of productivity. So,
it may be recommended to keep the trained people and reduce the number of
new hires;
3. Start-up problems: Every project suffers from start-up problems of some sort.
At this time the supervisors are very busy trying to get everybody working in a
productive manner. Therefore, if we can start with a small crew and increase
its size gradually, we will eliminate some of the start-up problems;
4. Completion congestion: Most projects suffer from congestion around project
completion time because of reduced work areas. Thus, if we can gradually
reduce the crew size as we approach project completion, we can improve
productivity by reducing congestion.
233 Fundamentals of Civil Engineering Construction Management
In order to take advantage of labour allocation techniques, the planner must assign a
minimum crew size to each activity (less than or equal to the normal crew size). This
minimum crew size represents the least number of workers per day that are needed to
complete the activity within the planned worker-days (workers times days).
0 2 2 6 6 8 8 12
A B C E
0 2 2 6 6 8 8 12
2 4 2 4
2 4
D
6 8
12
D
10 B
Resource No
A
8
6 B E
A C
4 A
2
A C
A
Day 1 2 3 4 5 6 7 8 9 10 11 12
Table 8.4 Resource requirement for the network shown in Fig 8.12.
10
8
6 D
4 B E
2 Levelled
A resources
C
DAY 1 2 3 4 5 6 7 8 9 10 11 12
A further example will be used to illustrate the technique when there is a limitation
on resources as shown in Table 8.5 for analysed precedence diagram shown in Figure
8.15. Let in this case the maximum number of resources available at any one time is
five. A bar chart is derived from the analysed precedence diagram. It can be seen
from the resource schedule (Figure 8.16) at the bottom of the bar chart that resources
exceed the maximum available.
Table 8.5 Resource requirements for the network shown in Figure 8.15.
1 3 2 1 1
0 3 3 7 7 12 12 15 15 19 19 23 23 26
A B E H K N O
0 3 3 7 7 12 12 15 15 19 19 23 26 26
4 5 3 4 4 3
3
7 9 9 11 11 14
D G J
12 14 14 16 16 19
2 2 3
A
B
C Critical activity
H
K
N 26 days
O float
C
D
F
G
I
J
L
M
RESOURCES 22237778843444111112222222
A labour resource graph is prepared from the network based on the extremes of early
start and latest finish for non-critical activities. A labour resource chart showing the
possible rescheduling limits within activity floats is shown in Figure 8.17.
Scheduling within these extremes is logical and feasible. The rescheduled resource
graph and bar chart are shown in Figre 8.18 and 8.19, respectively with a maximum
resource requirement of five.
I
5 M
F
No. of
4 C
rces
D J L
3 M
B L
A C
2
N O
1 2 4 6 8 10 12 14 16 18 20 22 24 26
DAYS
Least Cost Scheduling and Resources Levelling 238
Figure 8.17 Typical labour resource chart showing the possible rescheduling
limits within activity floats.
5 C
4
Resources
D L I F
3 J
2 B M
A
1 N O
E H K
DAYS 2 4 6 8 10 12 14 16 18 20 22 24
26
Figure 8.18 Resource requirements after levelling.
A
B
E
H
K
N
O
C
D 2 2 2 3 3 3 3 4 4 4 4 5 5 5 5 5 4 4 4 2 2 2 2 2 2 2
F
G
I
J
L
M
DAYS 2 4 6 8 10 12 14 16 18 20 22 24
26
Figure 8.19 Rescheduled bar chart.
of availability of resource and gradually increase this until the contract completion
date is reached.
Figure 8.20 shows a network for a small project together with resource requirements
as shown in Table 8.6.
2 6 6 8 9 11
B D F
3 7 7 9 9 11
4 2 2
0 2
A
0 2 11 15
G
2 11 15
2 5 5 9
C E 4
2 5 5 9
3 4
Table 8.6 Resource requirements for the network shown in Figure 8.20.
Activity Resource
A 2
B 3
C 2
D 2
E 3
F 2
G 3
Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Activity
A 2 2
B 3 3 3 3
C 2 2 2
D 2 2
E 3 3 3 3
F 2 2
G 3 3 3
20 days
2 2 3 3 3 3 2 2 2 2 2 3 3 3 3 2 2 3 3 3
Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Activity
A 2 2
B 3 3 3 3
C 2 2 2
D 2 2
E 3 3 3 3
F 2 2
G 3 3 3 3
16 days
2 2 5 5 5 5 5 3 3 3 2 2 3 3 3 3
241 Fundamentals of Civil Engineering Construction Management
Exercise problems
8.1 For the normal and crash costs of activities given in Table P8.1 and the
network shown in Figure P8.1, determine the optimum time and cost if the
overhead costs are $100 per day. Plot the direct cost, indirect cost and
combined values in one figure.
A
D
B
E
C
F
Figure P8.1
Table P8 .1
Duration (days) Cost ($)
Activity Normal Crash Normal Crash
A 4 2 400 500
B 8 5 800 980
C 3 2 600 700
D 10 6 500 600
E 8 6 800 950
F 7 4 700 1000
8.2 Using the normal and crash costs of activities given in Table P8.2, completely
crash the network schedules shown in Figure P8.2 and find the optimum time
and least cost. Consider overhead costs to be $60/day.
B
F G
C E
Figure P8.2
Table P8.2
Least Cost Scheduling and Resources Levelling 242
8.3 Using the normal and crash costs of activities given in Table P8.3, completely
crash the network shown in Figure P8.3. Assuming overhead cost of $120 per
day, find the optimum time and least cost.
B D
A
F
C E
Figure P8.3
Table P8.3
Duration Cost ($)
Activity Normal Crash Normal Crash
A 6 4 600 780
B 10 7 500 875
C 12 8 600 900
D 8 4 800 940
E 6 3 600 795
F 4 2 800 850
8.4 Using the normal and crash costs of activities given in Table P8.4, completely
crash the network schedules shown in Figure P8.4 and find the optimum time
and least cost. Assuming overhead cost to be $150 per day, plot the direct cost,
indirect cost and combined values in one figure.
E
B
F A C
243 Fundamentals of Civil Engineering Construction Management
Figure P8.4
Table P8.4
8.5 Using the data given in Table P8.5, completely crash the network shown in
Figure P8.5. Assuming overhead cost to be $80 per day, find the optimum time
and least cost and plot the direct cost, indirect cost and combined values in one
figure.
D
F
H
A
E
B G
I
Figure P8.5
Table P8.5
Duration (days) Cost ($)
Least Cost Scheduling and Resources Levelling 244
8.6 Using the network shown in Figure P8.5, and data given in Table P8.6,
completely crash the following network schedules and find the optimum time
and least cost. Assuming overhead cost to be $100 per day, plot the direct cost,
indirect cost and combined values in one figure.
Table P8.6
Duration (days) Cost ($)
Activity Normal Crash Normal Crash
A 4 2 400 570
B 5 2 350 455
C 11 6 1020 1145
D 4 2 525 575
E 6 4 825 935
F 6 5 610 650
G 6 4 430 570
H 3 2 1250 1325
I 5 3 390 450
8.7 Completely crash the network schedules shown in Figure P8.6 using the data
provided in Table P8.7, and find the optimum time and least cost. Assume
overhead cost to be $100 per day.
A F J
B D H I
C
G
E
245 Fundamentals of Civil Engineering Construction Management
Figure P8.6
Table P8.7
Duration (days) Cost ($)
Activity Normal Crash Normal Crash
A 6 3 610 700
B 8 4 1020 1140
C 5 3 525 625
D 4 2 430 550
E 2 2 350 350
F 3 2 400 425
G 8 5 615 675
H 3 2 1250 1315
I 4 2 390 480
J 3 2 825 850
Chapter 9
Human Resources Management
9.1.1 Introduction
CLIENT
Develop
SURVEYOR/COST
ARCHITECT/
Cost
QUANTITY
ENGINEER
ENGINEER
SITE Design
Construct
CONTRACTOR
Figure 9.1 Relationship between the construction team and the site.
247 Fundamentals of Civil Engineering Construction Management
Within the above relationship, it should be appreciated that the Client through his
Consultant has the initial responsibility in determining the resources needed for the
project. The specifications prepared by the Consultant may specify the materials and
method of work to be adopted in the project. This decision on the materials and
method of work need to be made very carefully taking into consideration not only the
suitability for the work, but also availability. Contractors sometimes face problems to
provide the resources required for the project simply because no detailed
consideration was made during preparation of specification for use of the materials.
Construction projects, unlike others, range from discrete projects of relatively long
duration, constructed outside and geographically dispersed and fixed. They normally
fall under two groups:
Civil works including roads and bridges, power stations, large steel and
reinforced concrete structures, water and gas mains, electricity cables, dams,
airports, etc.
248
Human Resources Management
The majority of such projects are tailor-made to a Client’s requirements, designed
upon prescribed fee scales and built for a price established mainly through a
competitive tendering system. This system creates an unusual situation in which the
product i.e. a building or a road is sold before it is produced. Other characteristics of
construction projects include:
the product is normally manufactured and left fixed on the clients’ premises i.e.
the construction site;
many parties are involved in the production process;
many projects are of one-off designs and lack any prototype model; and
the location of production area changes constantly and is subject to interference
from weather.
The main resources required for the execution of a construction project can be
termed as the 4 M’s. These are: MONEY; MANPOWER; MACHINERY; and
MATERIALS.
However, money is different from other resources. It is the resource that enables the
contractor to provide all other resources. Adequate financial resources are very
important for successful implementation of any project.
249 Fundamentals of Civil Engineering Construction Management
Before the start of the project, a contractor will therefore be required to determine
with accuracy, his requirements for labour, machinery (plants and equipment) and
materials. With the knowledge of the quantities and prices of these three resources, it
is then possible to compute the amount of money required to procure them.
To determine the resources required for a project, some basic documents are required
by the Contractor:
a) Drawings: The drawings are important to show all the details of the
constructed facility. The drawings will provide all the necessary details
required to enable the contractors determine mainly the work to be performed
and the methods of work to be adopted.
b) Bills of Quantities: The Bills of Quantities (BOQ) describes uniquely the
nature and quantity of all components of the finished project. It thus forms a
common basis for determining the labour, materials and equipment needed for
the construction project.
c) Specifications: The specification describes in detail the work to be executed,
the character and quality of materials and workmanship, any special
responsibilities of the contractor that are not covered by the conditions of
contract. It may also lay down the order in which various portions of the work
are to be executed, the methods to be adopted, and particulars of any facilities
to be afforded to other contractors. This document is therefore important to
determine the type of materials, labour and plant required for the work
d) Conditions of Contract: The conditions of contract define the terms under
which the work is to be carried out, the relationship between the Client and the
Contractor, and the powers of the Consultant in the contract. The conditions of
contract may require the contractor to provide some facilities like fencing,
security, signboards, workers protective gears which may not be included in
250
Human Resources Management
the BOQ. Thus, it is also crucial to enable the contractor to determine the
resources required.
A contractor should therefore make sure that he has read all the above documents
carefully to enable him come up with realistic resource requirements for the project.
A comprehensive format for method statement is shown in Table 9.1 This can be
used to indicate method and plant considerations that enable the quantity, output and
operational duration to be assessed.
Example 9.1
A method statement for reduced level excavation for a housing project; area is about
200 m x 150 m with average depth of excavation of 0.6 m to be carted away to a
nearby tip is presented in Table 9.1.
252
Human Resources Management
Table 9.1: Method statement for reduced level excavation for a housing project
METHOD STATEMENT
Contract:
Tender No.
No. OPERATION QUANTITY METHOD SEQUENCE OF PLANT & OUTPUT DURATION
OPERATIONS LABOUR
1 Excavate to 200 x 150 x 2 D6 bulldozers to excavate and push the Level grid to be 2 D6 dozers 120 m3/h per 15000 = 62.8 h =
reduce levels 0.5 = 15,000 material into spoil heaps adjacent to the established prior machine = 240 8
(0.500 m m3 access roads. 2 draglines fitted with 2 m3 to excavation 2 x 120 =
deep) buckets to be located on top of each spoil 240 m3/h 8 machine days
heap. Lorries to use existing access roads
for loading 1 banksman 75 m3/h 15000 = 100 h =
2 draglines = 75 x 2 150 8
4 lorries per = 150 m3/h
machine 12 machine days
1 Alternative 15000 m3 3 hydraulic tracked excavators fitted Level grid to be 3 hydraulic
method with a backactor arm. Machine fitted established prior excavators 45 m3/h 15000 = 112 h
with 2 m3 bucket. Load lorries direct and to excavation 135 8
remove to tip off site 3 lorries per 45 x 3 =
Note on output in relation to lorries machine = 14 machine days
conveying excavated material to tip 135 m3/h
Machine output 45 m3/h. Time taken to 1 banksman
load 9 m3 lorry
= 9 x 60 min = 12 min
45
Travel to tip and return allow 24 min
Therefore allow 24/12 = 2 lorries + 1 = 3
lorries required for balance of resources.
253 Fundamentals of Civil Engineering Construction Management
In most cases, however, for the purpose of preparing resources schedules a bar chart
will always be useful. A contractor in many cases will be required to transform his
programme into a bar chart to allow for easy determination of the resources required
for the project.
In the following sections, effort is made to discuss how a contractor can make the
best use of his workforce in order to improve his business.
255 Fundamentals of Civil Engineering Construction Management
For most contractors, their organizations are usually subdivided into two main parts -
technical and non-technical. The responsibilities of the technical sections are likely to
include the following:
a) All civil engineering/building services, including the preparation of designs for
temporary and permanent structures and the planning and programming of
works;
b) Estimating and tendering, preparation of specifications and quantities,
interpretation and application of contract conditions, negotiations with the client;
c) Supervision of construction work, monitoring progress, preparation of reports,
liaison with the client, purchasing of materials and equipment, preparation of
monthly valuations;
d) Quality control, site investigations and geotechnical processes;
e) Operation of central plant and transport depots with workshops and repair
facilities, routine inspection of plant and equipment, and purchases and sale of
plant; and
f) Staff training.
Since the success of site operation will very much depend on the head office, it is
important that recruitment of head office staff be made very carefully. This can be
achieved through proper manpower planning.
A company needs to have readily available adequate information about its employees,
including such aspects as age breakdown, skills analysis, succession plan, training
needs and labour turnover analysis.
The project manager has to forecast human resources requirements for his site, taking
into account the availability of the various categories of labour, including subcontract
257 Fundamentals of Civil Engineering Construction Management
labour, the need to avoid sharp fluctuations in manning levels and the overall resource
pattern of the project. In small projects where a small number of workforces are
required it is particularly important that selection of human resources for the work
should be done very carefully to ensure that people who can work together as a team
are selected.
The contractor should have sufficient experienced technical and clerical staff on site at
the start of the contract to ensure that all necessary preparatory work is undertaken on
site. The full component of site staff on a large project can be extensive and the
principal members of staff and their main functions are described below.
For a small contractor, obvious he will need a small site organization. The key
principle is to have members of staff in line with the proposed organization structure,
which is shown in Figure 9.2. The structure is typical of any contractor, however small
contractors may skip some of the positions indicated.
Both technical and non-technical staff supports site agent with their number and duties
dependent on the size of the project. For example, the personnel might comprise an
engineer, general foreman, plant and transport foreman, cashier, timekeeper and
storekeeper. Larger contracts require proportionately larger number of staff. The
allocation of duties will be influenced by many factors including the locality and
nature of the work, the amount of assistance from head office, and the experience and
capability of the available personnel. The allocation of duties should seek to ensure
smooth and effective communication and the ability to introduce checks at critical
points.
9.2.3.4 Sub-agents
Sub-agents are often appointed to control various work sections of a large project,
and they, in their turn, may have a number of section engineers responsible for them
for the supervision of the actual operations. The direct control of labour and
operation of plant and transport is usually undertaken by various grades of foremen.
The chief civil engineer is responsible for the accuracy of the works through section
engineers. He needs to check the co-ordination of drawings received from the
engineer and then issue them to the relevant personnel in the appropriate sections of
the project. He also carries out any local designs that may be required, particularly
those relating to temporary works, and gives general technical guidance where
necessary to personnel on the site.
The chief production control and costing engineer keeps routine progress records and
costs and normally operates through departments controlled by sub-agents. He is
often responsible for the routine measurement of work on site.
SITE AGENT
Concrete plant
Scaffolding
Steel bending yard
Joiner’s shop Sub-agent for
Sub-agent for
Plant and transport other works
preliminary works
Engineers Services
General
General Technicians
Staff
Figure 9.2 Typical site organization structure of a medium size construction project
270 Fundamentals of Civil Engineering Construction Management
His department also controls the payment of wages through timekeepers and cashiers
and the purchasing and checking of receipt of materials and components, in addition
to the checking of accounts, insurance, safety precautions, site welfare and other
matters relating to labour relations.
Section engineers are usually engineers with experience of both design and
fieldwork, who, although ultimately responsible to the engineer, report to the chief
civil engineer on the accuracy and control of the civil engineering works. Each
section engineer will liaise with his foreman to plan the work of his section and
report on matters of detail to the managing surveyor or the quantity surveyor engaged
on the project.
As far as construction site is concerned, production covers every activity that goes into
construction e.g. setting out, digging foundations, making blocks, pouring concrete etc.
Improving productivity for these operations means carrying them out at either lower
cost, in less time, with fewer workers or with less equipment.
Human Resources Management 271
Cost, time, workers and equipment are examples of what you put into production. The
less you put in compared to what is produced, the higher the productivity. Productivity
can be raised in four ways:
a) The same is produced, but less is put into production;
b) More is produced with the same inputs;
c) More is produced and less is put into production; and
d) More is produced and more is put into production, but the increase in production
is bigger than the increase in inputs.
Apart from adding to contractor’s profits, there are also other reasons why it is worth
looking into improvements in productivity. Some of these are:
a) Worker satisfaction – some measures lead to a more satisfactory job for the
workers, such as improved methods that make the work easier, better methods
of payment, improved management and worker relations;
b) Client impression – clients who visit contractor’s site and observe that it is run
efficiently, realize that the contractor is good. This may mean more future
contracts, not only for that client, but he may pass the word to other clients;
and
c) Contractor’s own development – to develop the company, make it bigger,
make it more competitive and perhaps expand and become a big firm requires
proper management. Improving productivity involves the use of management
techniques, which are important for the development of the company. By
learning the techniques for productivity improvement and then applying them,
a contractor will be able to develop his company.
General
Monitoring of labour productivity on site is very important to allow the contractor to
establish areas where there is low productivity and the reasons contributing to low
productivity. This will enable him devise measures that will enable him to overcome
the problem of low productivity.
Monitoring of labour productivity entails extensive record keeping of work done and
people involved in doing the work. This can be best achieved by using Work-Study
Techniques.
Work-study
The purpose of work-study is to work out ways of improving methods of work and
productivities on construction sites. It is divided into two major areas:
Activity level
The level of activity on site is a measure of how busy the workers are. This means
finding out how much time is spent working and how much time is idle. The lower the
activity level, the higher the loss on the contract. Workers, who stand idle, either
274 Fundamentals of Civil Engineering Construction Management
because they have nothing to do or they are waiting for another operation to finish, still
have to be paid. Moreover, the lower the general activity level on site, the longer the
project will take. This also means the contractor will lose money because the extra
time taken to complete the project could have been spent starting up a new contract.
With higher activity level, more money is earned on the contract. When more money is
earned on a contract, the more of it can be paid to workers, which gives them
motivation to work harder.
Activity sampling
In order to improve activity level on site, it is necessary to be able to measure it. The
method used to record the activity level is called Activity Sampling. If it were possible
to look down on the whole construction site continuously throughout the day or the
week and record the output of every worker and machine, a complete picture of
effective and ineffective time for the site could be obtained. But to do this would take
up too much time and money.
Instead a series of tours of the site are made. Each time it is noted, for each worker,
whether he is working or not working. Alternatively, one can stand in a place where he
is able to observe the workers. However, they know that they are being watched, they
will find a way of looking busy. What is needed is a true picture of what is happening,
so as to check up on the scope of improvement. At first there may be some difficulties
in deciding in borderline cases whether someone is “working” or “not working”, but it
becomes easier after a little practice.
The more rounds of recording made, the more accurate will be the results. Since the
sampling distributions using large samples are either normally distributed or nearly so,
it is possible to use the properties of a normal distribution to derive a measure of
confidence that a particular estimate of a statistics, such as a mean, will fall between
two given values. For a normal distribution, 68.27 per cent of the values fall between
1 standard deviation from the mean, 95.45 per cent between 2 standard deviations
from the mean, and 99.73 per cent between 3 standard deviations from the mean.
These values are called the 68.27 per cent, the 95.45 per cent, and the 99.73 per cent
confidence limits. An alternative way of looking at the confidence measures is that 95
per cent of the values will fall between 1.96 standard deviations from the mean and
99 per cent will fall between 2.58 standard deviations. Other values for different
confidence limits can be found by using normal curve area tables. The standard error
of the sampling distribution of proportions, n can be assumed to be the total number of
observations (each being considered as a sample). The formula to enable the number
of observations to be computed for any desired level of confidence is as follows:
p(1 p)
n [9.1]
p
2
Where p
2
is the standard error of the sampling distribution of the proportions
Let it be assumed that the confidence limits for a particular situation are set and it is
decided the allowable limit of error is 5 per cent either side of the true value. The
limit of error, k, is the assessment of the accuracy that is required in the result to be
276 Fundamentals of Civil Engineering Construction Management
confidence limits determine the number of standard errors either side of the true value
within which the result will fall and the tolerance or limit of error prescribes the same
limits but in terms of proportions. Therefore,
z p k [9.2]
k = limit of error
Thus, if confidence limits are set at 95 per cent which a limit of error of 3 per cent,
the values obtained must fall within 1.96 standard errors of the true value, and
therefore
1.96 p 0.03
p 3 / 1.96 1.53
p(1 p) z p k
Returning to formula n and substituting from for
p
2
1
p
2
Human Resources Management 277
z 2 p(1 p)
n [9.3]
k2
Example 9.2
Establish the number of observations that are required to determine the proportion of
100 operatives who are ‘active’ as opposed to ‘inactive’ on a construction site. The
result is required within confidence limits of 95 per cent and within a tolerance of 2.5
per cent.
The observation rounds should be made at random intervals. Recording should only be
carried out during typical periods, in which work is not being held up due to factors
that are beyond control, such as bad weather, major plant breakdown etc.
When doing an activity sampling, a form such as the one shown in Table 9.2 below
may be used. Some of the boxes have been filled in to show how it is used.
278 Fundamentals of Civil Engineering Construction Management
It is possible to record in detail what the worker is doing in more detail. Instead of
recording just “working” or “not working” you can use letters to describe what he is
actually doing. Letters that can be used are, for example:
The activity level is the percentage of time, which the workers are recorded as
working. Depending on how heavy the work is, climatic conditions, etc., the activity
level should be 60-80 percent. If it falls below this level, the cause of the inactivity
should be examined.
Example 9.3
In the activity sample above, the number of times the workers are recorded as working
and the number of times they are recorded as not working are counted. The results are
summarized in Table 9.3.
According to these records, workers 1, 2 and 6 are okay but workers 3, 4 and 5 are
working below an acceptable level. The reason for this has to be found. If all workers
were working on the same gang, then the activity level for the gang is 53%, which is
still below the acceptable level.
Remember that for a sufficient sample, the number of recordings should be at least 400
if the level of accuracy required is 5% and the level of confidence is 96%. In this
example the total number is 60, which is too small to give results to an acceptable
accuracy level.
Example 9.4
Assume in the examples above that workers were involved in excavation for strip
foundation (700 mm wide, and 800 mm deep) and that the records were taken for
duration of two hours. At the end of two hours the work done was measured, and it
was established that the workers had excavated a length of 5 meters of the strip
foundation.
Th e actual productivity rate is in this case twice the overall productivity rate since
the workers were spending half of their time only doing the work. If this idle time is
eliminated they are able to produce twice as much. This information is very important
for a contractor when establishing labour requirements for a construction project.
To be able to calculate actual productivity rate, the contractor must establish the
proportion of time that is used productively on the work. Contractors who assign their
works on a piecework basis can however establish figures, which largely reflect the
actual production capacity of workers. In any case, it is necessary to allow for
sometime for resting in determining realistic productivity.
A contractor should know these factors when deploying his work force and provide for
some facilities that will enable some of those human factors being minimized.
Motivation of Workers
Labour can be motivated to produce more. It is possible to improve production by
increasing manpower. However, it is a good practice for the management to ensure
that the existing workforce is producing to the maximum capacity before they can look
into the alternative of employing more people.
Motivation theories
Maslow suggests that man seeks to satisfy his needs subsequently as shown in Figure
9.4. He argues that as each of these needs is gratified then a new set of needs emerges.
The implication is that man is self-motivating.
Basic needs
Firstly by securing a job the worker is able to purchase food, clothing, housing and so
on. These basic needs once satisfied, in the course lead to the desire for better working
conditions such as shorter hours, holiday with pay, security of work, etc.
Higher needs
Maslow postulated that people like to feel necessary in their jobs; they wish to gain
respect, both from their employer and fellow workers, and in many instances positively
wish to identify with a particular skill.
Construction companies, in general, fair badly with regard to this need to belong. The
turnover of staff and workmen in many companies is high, although it is true to say
that many workers remain in the industry and more particularly take some pride in
being associated with one particular skill.
Human Resources Management 283
SELF-ACTUALIZATION NEEDS
To achieve total self development
SECONDARY NEEDS
ESTEEM NEEDS
Prestige, status, recognition, self-confidence,
appreciation and respect
SOCIAL NEEDS
Belonging to a group, love, and acceptance
SECURITY NEEDS
Safety, avoidance of pain, financial security,
PRIMARY NEEDS
protection
PHYSIOLOGICAL NEEDS
Food, drink, rest, air to breathe, shelter, satisfactory
temperatures, sex
Many workers are dissatisfied with their jobs simply because there is no opportunity
for self-expression. Unfortunately, with the present emphasis on output as opposed to
craftsmanship, it is possible such needs cannot be reached and therefore full potential
of many skilled workers not realized.
Finally, Maslow tops his hierarchy with the need for self-fulfillment. It is difficult to
see any hope for satisfaction of this desire, outside purely creative work, and on this
basis it would be limited to the self-employed, the very senior posts in an organization
and purely independent workers.
284 Fundamentals of Civil Engineering Construction Management
Maslow’s higher needs can be grouped under the heading “Motivating Needs”. On the
other hand, Fredrick Herzberg discovered some interesting pointers to motivation and
identified the contributory factors presented in Table 9.4.
Job satisfaction is the extent to which a person feels satisfied with the work they have
to carry out, with their place in the hierarchy in relation to the colleagues with whom
they work and with the general environment in which they carry out their work.
Herzberg called the first motivating factors and the second hygiene factors. He
concluded that hygiene factors had little positive effects on job attitudes but served
primarily to prevent job dissatisfaction. Thus, if a company fails to provide adequate
hygiene factors, the worker is dissatisfied no matter how adequate are salaries, working
conditions etc., the worker will not be satisfied until all other motivations are also
satisfied.
Non-financial incentives
These involve in particular the fulfilment of 'motivating' needs. Thus, the incentives
offered should acknowledge the importance of the individual and recognize his need
for group participation to provide social satisfaction.
Semi-financial incentive
These do not rely on cash motive but concentrate on fringe benefits such as canteens,
sport facilities, medical facilities, pension schemes etc.
MOTIVATION
Non-Financial Financial
i.e. social,
psychological via self-
esteem and job
satisfaction Basic wage salary Bonuses
Financial incentive
These rely on cash motive and are widely used, but are often a source of contention
and dispute between management and workforce. The schemes enable workers to earn
bonuses over and above the normal rate of pay for achieving a rate of output at or
above a predetermined standard. It is not always easy to work out what this standard
performance should be, so that the output targets set by management on which the
bonus earnings depend are often inaccurate.
a) To improve productivity;
286 Fundamentals of Civil Engineering Construction Management
c) Piecework: In this type a worker is paid a uniform price per unit of production.
As the worker increases his output his earnings increase proportionately. For
example, if a person is paid 10US$ for each item or unit produced and he
completes 10 units, his payment will be 10 x 10 = 100 US$. The system is best
installed on repetitive type activities where the standard time for doing the
work can be accurately fixed. Hence, in the construction industry it is more
workable in the production of materials sector;
d) Task rate or job and finish: In this case, the worker is offered a lump sum of
money to complete an operation. It is useful on large concrete pours or similar
work, where the gang will complete the work as quickly as possible and then go
home but is paid for the full day’s work and any bonus earned;
e) Standard time or hour system: Essentially this is the same as piecework system,
but the targets for the work are expressed in time units rather than money. For
example, if a worker is given a target of 8 hours to complete an activity. He
completes it in 6 hours. His payment will be 8 x hourly rate. He can now start
the next unit 2 hours earlier and thereby increase his overall earnings. The
advantage of this system is that if new hourly rates are negotiated, the time
standards remain unchanged;
f) Plus rate or spot bonus: A minimum bonus, sometimes called a fallback bonus
is paid to workers whatever the output. Such an incentive is always used to
attract labour from other work in the area. It can also be used to pay a
competitive rate when the basic rate is low; and
g) Group schemes: Much of the work carried on construction sites is in gangs,
making it almost impossible to apply individual bonus schemes. But at the same
time the different classes of workers in the gang need to be acknowledged in the
scheme. This can be done by apportioning the bonus on a share basis, usually
the gang foreman being paid slightly more than others.
b) The worker's output will be higher, so that the job should be completed in less
time, with a more predictable performance and at lower cost;
c) The system encourages self-discipline and supervision can concentrate on
quality rather than output;
d) The worker himself will try to improve the efficiency of the method. Where a
gang is given a bonus, it will organize itself for maximum efficiency, and the
better workers will encourage inexperienced or less hard-working members; and
e) The operation of the scheme should keep site management on its toes, since the
workers will protest against any delays or mismanagement that reduces their
opportunity to earn bonuses.
d) The rates set should be high enough for an average worker who does a good
day's work without over-exertion to be able to earn a reasonable bonus above the
ordinary daily rate;
e) The workers should not be penalized for matters outside their control (e.g.
delays), and where workers are required to work a full normal day they should
never receive less than the daily rate for a normal day's work;
f) The bonus rate should be offered to individuals or small groups of workers rather
than to large groups, so that individual earnings do not become dependent on the
efforts of other workers;
g) Dangerous work should not be offered on a bonus work basis;
h) Since bonus schemes can lead to substandard work, penalties for such work must
be enforced. Very high-quality work should only offered on a bonus work basis
if the supervision is adequate to ensure no loss of quality;
i) Any dispute about earnings should always be investigated fairly and at once;
j) Care should be exercised when setting bonus work rates for raw, in experienced
workers; and
k) All the above-mentioned ways can induce men to give their best performance. It
is the management responsibility to find the best solution, for example financial
incentives can be offered to manual workers and non-or semi-financial
incentives to managerial and clerical workers.
d) Activities need to be planned well in advance and materials and plant required
carrying them, being well prepared. This will to a large extent reduce the idle
time by workers due to waiting of materials and plants.
Supervision
Proper supervision is necessary for a workforce to operate efficiently. It is needed at
various levels, but it is particularly important at site agent and foreman level.
There may be also other levels, for example gang leaders supervising their respective
gangs and who report to their respective foreman. The number of levels that are used
depends on the type, size and complexity of the project. A large project generally
needs more levels of supervision than a small one. A technically complicated project
also needs more levels of supervision than a simpler one.
right. Then, he should observe as the work progresses to see how well the
individual supervisors cope with the workers allocated to them. One way of
making observations is to conduct a short activity sampling study to establish
the activity level.
Below is a simple example of a daily record which is useful for either the supervisor
or the foreman, depending on the size of the project (Table 9.5).
Labour
Description of Activities Category Number of No. of hours
Workers worked
Delays and Urgent Labourers
reasons requirements
Bricklayers
Carpenters
Plumbers
Painters
Electricians
Others
Materials, Amount Ordered or Plant and equipment
Received
Concrete
mixer
Poker vibrator
Plate
compactor
Visitors and comments made by them
From the above, it should be appreciated that a good site agent can ensure that a
project is executed without any cost or time overruns. On the other hand, a poor site
manager can cause great losses to the contractor through high site costs and long
delays. A very bad site agent can even force the company into bankruptcy. For this
reason, it is important that training is offered to site agents and foremen to enable
them carry out effective supervision.
9.2.5.1 General
In order for the contractor to establish the resources required for the work he needs to
prepare a method statement (as discussed in section 9.1.3) of every activity that will
be executed in the project. He would also need to have a programme of works
showing the timing of various activities.
Figure 9.6 illustrates a simple bar chart to which has been added the total labour
requirement on a weekly basis for each individual operation. Along the bottom of the
bar chart the totals are added up, forming a labour aggregation. These totals may be
plotted in graphic form as indicated below the bar chart to form the labour
histograms.
WEEK 1 2 3 4 5 6 7 8 9 10 11 12
Operation
Excavation 10 10
Foundations 8 8 6
296 Fundamentals of Civil Engineering Construction Management
Floors 4 6
External Walls 10 10 10 8
Roof 6 6
Wiring 5
Windows 2 1 2
Plastering 6 6
TOTAL LABOUR 10 18 8 10 16 10 10 14 8 6 8 6
20
Labour
10
In case of many resources being used for a project, it is still possible to prepare a
resource aggregation combining of all resources as shown in Figure 9.7.
In the next chapter, the concepts presented in this chapter will be extended to other
key construction resources - equipment and materials.
Chapter 10
Equipment and Materials Management
10.1 Introduction
The trend towards greater use of plant in construction has been in place for many
years. This is due to the following factors:
The alternative techniques for construction could be best defined by their extremes.
At the lower end of the spectrum is essentially labour intensive method, where output
and quality are, for all practical purposes, determined solely by labour productivity.
In this case the term equipment would be applied loosely to non-mechanical hand
held tools, such as: hoes, spades, shovels, pick-axes, hand rammers, wheelbarrows,
human-drawn rollers, mattocks, watering cans and the like.
Borrowing words of one ILO expert: "Given a job, a labour intensive technology
expert would first determine the number of people needed for the job and then the
equipment to supplement the human labour. On the other hand an equipment
intensive technology specialist would first determine the equipment needed and then
work out the number of people needed to supplement the equipment".
Between the two extremes, there are a number of labour-equipment mixes that might
be employed, and the degree to which labour or equipment productivity dominates
overall output and quality is the degree to which the technology mix is deemed
labour or equipment intensive.
Labour is almost used in all activities. Even in the so-called equipment intensive
construction, labour is still needed to operate the equipment. There is usually a high
use of labour in building works compared to civil engineering projects, unless a
decision has been taken to use labour intensive methods for construction. The use of
labour in construction works helps to provide employment and therefore alleviates
poverty. On the other hand, the use of labour is associated with longer completion
periods.
contractors however, opt to buy some of the plant for convenience. Careful decisions
should be made to acquire plant for profit. Plant should be a capital-intensive
business and requires a central organization to provide all the facilities for
maintenance, cost accounting, hiring, etc. For large construction companies, these
may as well be relatively independent entities with clear set of operational
procedures.
It is therefore a major management task to set principal policies for the supply and
organization of plant holdings associated with company’s activities, so that the
objectives for all the company’s operations may be achieved. The basic principles of
equipment management revolve around proper selection, maintaining high
availability levels, ensuring high utilisation levels, setting profitable hire rates, and
disposing when it is no longer profitable to keep the equipment. Without these, the
plant fleet may become a hidden obligation and with constraints on financial
resources. These basic principles lead to a rational sourcing of construction
equipment and the factors influencing their selection. It is also important to
appreciate that most construction equipment cost large sums of money not only to
buy or rent but also to operate and maintain. It is therefore extremely important to
keep construction equipment fully utilised. It is important to remember that idle
equipment costs money.
Hire purchase
One way of obtaining the use of fixed assets without initial borrowing is to resort to
hire purchase finance for plant and vehicles. This is a mixture of buying and hiring
which can be quite useful. The contractor pays a deposit and agrees to purchase the
item outright at a future date. In the meantime, he has the use of the plant, but has to
go on making monthly payments until the debt is completed. The hiring company
naturally includes an interest charge in its hiring rates, and it should be realised that
this is rather higher than would be charged by the bank. However hire purchase can
be very useful way of buying plant for a firm that is sure that it can keep it profitably
employed throughout the period of hire.
A contractor who takes the advantage of this facility avoids both the responsibilities
for maintenance, care of the plant and tying up his capital. Other advantages include:
Plant can be hired as required and for short periods;
Hire firms are responsible for repairs and replacements; and
Contractor is not left with expensive plant items on his hands after the
completion of the contract.
Equipment and Materials Management 305
However, hire rates depend on market forces and are largely beyond the control of
the contractor, except for limited negotiation between competing firms. This could
affect a contractor quoted price for work and the costs incurred later when the work
is carried out.
Selecting the correct equipment for the job ideally forms part of the construction
planning process and equipment should be chosen for a particular task only after
analysis of many interrelated factors. The important considerations for selecting
equipment include the examinations of:
a) The function to be carried out: for example the choice of equipment in many
instances will be dictated by the need to cope with combinations of horizontal,
vertical and mobile movement. A crane can provide both horizontal and vertical
movement, but is rather poor in manoeuvring, whereas most earthmoving
machinery is mobile and will transport materials very efficiently over long
distances, but cannot be used for lifting;
b) The capacity of the machine: the volume of material to be moved related to the
time available in the construction programme is important. But for cranes and
other lifting operations, the practical weight and size of the units as dictated by
the design are most important factors;
c) The method of operation: the distance and direction of travel, speed and
frequency of movement, sequence of movement, state of the ground etc. must be
taken into account;
d) The limitations of the method: for many earthmoving operations, the choice of
method may be limited by the cost of temporary work facilities, for example haul
306 Fundamentals of Civil Engineering Construction Management
General
A contractor using equipment is normally required to determine the total “all-in” cost
of each major plant item as an hourly or weekly rate. This will form a basis of cost
control later during the use of the equipment item in the project. The determination
of this all in cost depends on the method of acquisition of the equipment. As
discussed previously the equipment may be hired or bought. Hiring is the more
common and construction companies either hire from their own equipment division,
from other contractors or from specialist independent equipment companies.
Hired equipment
For hired the basic cost is the rate quoted by the equipment hire company to which
the contractor must add the cost of all additional running costs not covered by the
hirer’s quotation. These running costs include: the emoluments of the operator; fuel;
oil; grease; and other consumables.
Most hired equipment is provided with an operator but the contractor may have to
allow for additional moneys to bring the operator rate up to that covered by any site
agreement. Where no operator is provided, the full all in operator must be added.
Fuel costs are normally calculated on the basis of an estimated number of litres per
hour for the equipment. To estimate this, contractors normally use their own records
and data obtained from equipment manuals. However, data obtained from equipment
Equipment and Materials Management 307
manuals should always be treated with care as in many cases they assume the
equipment of being in perfect condition which is not always necessarily the case. Oil
and grease are allowed for as an allowance per hour of equipment time or a
percentage addition to the fuel costs. Other consumables are allowed for by a
percentage addition.
Bought equipment
Where the contractor owns the equipment item the rate used must cover both the
ownership and operating costs. Through this costing it will be seen that a contractor
owning a equipment will incur ownership costs irrespective of whether the
equipment is in use or not, hence the need to increase utilization levels of equipment
through contractor’s own use in several projects or by hiring out to other contractor.
Where this is not possible, then it may be advisable to hire equipment instead of
owning. Example 10.1 illustrates how hire rates can be computed.
Operating Costs
Fuel cost: 10 litres per hour for 2,000 hours per year 10,800
= 10 x 2,000 x US $ 0.540
Oil @ 10% of the fuel cost 1,080
Repairs 10% of US$ 50,000 5,000
The above calculation allows for the generation of sufficient income to replace the
asset, cover operating costs and provide a return on the initial capital invested. If the
company equipment division is run a profit centre and is expected to contribute to
head office overheads and profit, then additional allowances for profit and overheads
must be added.
Equipment and Materials Management 309
If on the other hand it is not possible to utilize equipment for 2000 hours per annum,
and instead it is only utilised for only 1500 hours, then the hire rate has to raise to
US$ 16.603 per hour. In other words, if the equipment is hired at US$ 13.937 per
hour, it will be losing about US$ 2.666 every hour. This underlies the significance of
equipment utilization.
We have seen that most construction equipments are expensive, and when a decision
is made to use a piece of equipment on site it must be ensured that it is used as
economically as possible. Equipment productivity, like labour productivity looks at
how efficiently equipment is used on site. Equipment productivity relates to its
ability to produce a given quantity of work over a planned period of time as well as
its availability.
completion of the project, to a large extent it is how effectively these plants are
utilized that will determine effective completion of the project at minimum costs.
A small well-balanced fleet of construction plants will produce more than a large fleet,
which is not well balanced. One golden rule in managing construction plants is to have
a fleet of plants in such combinations that will ensure minimum idle time for all the
plants forming the fleet. This is in no way a small task. In some cases simulation of the
anticipated situation on site needs to be carried out to obtain the most economic
combination of construction fleet.
Apart from balancing the fleets of construction plants used in any construction site, the
following points must be observed to enable economic and effective utilization of
construction plants:
There are different ways of classifying equipment, but the most common way used in
construction is by the type of work to be performed by the equipment. Some of these
classifications include:
312 Fundamentals of Civil Engineering Construction Management
Hauling machines
These are pieces of equipment used for massive transport of construction materials
from one location to the other. Examples of such equipment include trucks, dumpers,
tractors, etc. Figure 10.1 illustrates a typical dump truck
Excavating machines
Equipment in this category are requisite in most construction project. They are used
to loosen and stockpile or load the earth material to dumpers. They can also be used
for short haulages of up to 250 meters long. Examples of such equipment include
backhoe excavators or loaders (see Figure 10.3), draglines, draggers, drag shovels,
clamshells, etc.
Concrete machines
These machines are sometimes called concrete mixers though this is not a general
name because some are used for transporting concrete. In this classification there are
various types, such as:
Batching machines: they use the materials to prepare proportions of
cement, sand, coarse aggregates and water by themselves. These are
mostly stationary and are generally referred to as concrete batching plants
(see Figure 10.6).
Concrete transporters: they are in the form of trucks or dumpers and are
used to transport fresh concrete from the mixing point to the placing site.
Care is normally taken with regard to hauling distances and durations so
as reduce possibilities of segregation and setting of the fresh concrete.
316 Fundamentals of Civil Engineering Construction Management
Hoisting equipment
Such equipment are used for lifting or vertical transportation of loads on construction
sites. These can either be mobile or stationary. Examples of hoisting equipment
include:
Cranes:
o Gantry crane used in the workshops;
o Tower cranes (see Figure 10.8(a)); and
o Mobile cranes (see Figure 10.8(b)).
Jacks: these are used for regulating small heights.
Winch hoists:
o Chain hoist or jib hoist; and
o Chain pulley blocks.
Equipment and Materials Management 317
In general, for most construction activities, there is probably a machine that can
be used for the purpose. It is for the engineer to evaluate whether is better to use
equipment or labour for the purpose depending on the specific circumstances.
The most popular type of equipment relevant to civil engineering are earth works
equipment. In the next section, a more detailed treatment of earthworks
equipment shall be presented
.
Practical capacity
This is the average capacity, and is calculated from theoretical value by
adjusting it to make it closer to the real capacity. Adjustments are made by
introducing factors, which often depend on specific circumstances. Factors
such as operator experience, soil type, terrain, specific job type, etc.
The Bank Cubic Meters (BCM): If measurements are made to the soil
at its natural state, the unit is called bank cubic meters. It is used in
cases where excavations are made of soil in its natural state.
The Loose Cubic Meter (LCM): When soil is excavated the soil
particles are loosened and the volume of the soil normally increases. The
extent of increase depends on the soil bulking factor. The unit of measure
of the soil at this state is loose cubic meter. For instance, when
transporting soil, the measurements are made in loose cubic meter; and
Compact Cubic Meter (CCM): This is the way of measuring the soil in
compacted state, where the volume is reduced from loose form. For
instance, when measuring volume of compacted soil on site.
Conversion can be done from one state to the other using some factors, which depend
on the type of soil. These factors are normally discussed under soil mechanics or
similar topic.
This assumes the conditions to be ideal, and the calculations are taken from the
specifications of the machine. For example, manufacturer’s specifications for site
Equipment and Materials Management 321
clearing using a bulldozer may be 2000 m2/hour, and therefore in this case, the
conditions are considered to be ideal, but if the topography is bad or the soil is wet or
both, productivity will be lower. Soil type will also affect productivity. Therefore
factors taken for different sites or even for the same site but at different times are not
necessarily the same.
Qbasic q x N [10.1]
Where,
q = output in cubic meters per cycle, measured in a loose excavated
materials determined from the machine ratings.
N = number of cycles made in a particular operation in one hour.
N = 60/Cm, [10.2]
Where constant Cm = Cycle time in minutes.
Example 10.2
Consider an excavator of bucket size, q = 0.85m3 excavating soil with a cycle time of
0.45 minutes. In an ideal situation, the excavator can perform N = 60/0.45 cycles per
hour. The productivity for the excavator is the load per cycle x the number of cycles
per hour:
The same work may be done by different machines e.g. one can use a bulldozer to
move earth as well as for excavating. Selection of the right equipment for the job is a
matter of judgement based mainly on experience. In the absence of experience, it is
best to judge from manufacturer’s specifications and consulting available literature
as a starting point. With time, it is possible to gather experience that will enable one
to judge as to what is possible with a particular type of machine.
E f1 xf 2 f 3 ........ f n [10.3]
Example 10.3
If we consider the standard excavator output of 113.3 m3/hr computed in example
10.2, it is necessary to adjust it to a realistic level if for example the site condition is
excellent but the machine condition is poor, (therefore f1 = 0.7) and that the worker is
highly motivated but has average experience, (therefore f2 = 0.85):
A bulldozer is the most often equipment used at construction site as it can perform a
number of activities such as:
a) Stripping of top soil;
b) Cleaning vegetation;
c) Shallow exaction;
d) Pushing scrapers;
e) Maintaining haul roads;
f) Opening up pilot roads;
g) Spreading and grading; and
h) Ripping, which is the loosening of hard surface.
One of the drawbacks of wheeled bulldozer over tracked bulldozer is that it requires
enough traction force to make it move. It therefore requires a more powerful engine
to produce the same effect as that of tracks or crawler bulldozer.
Bulldozers are fitted with steel blade in front connected to the dozer by two sets of
hydraulic controls. One set for tilting and the other set for lifting and lowering the
blade.
Equipment and Materials Management 325
Types of blades
There are four (4) blades types that are usually attached to the bulldozer:
a) Straight blade: the blade is horizontal with respect to horizontal axis;
b) Angled blade: if looked from top, the blade will be seen angled. It is used for
backfilling;
c) U- blade: It is much deeper such that it forms u-shape. The advantage of this is
that it can take a higher volume as compared to other blades; and
d) Push blade: Difference between type (a) and (d) is that in (d), the blades are
attached with shock absorbers and reinforced to maintain strength during
pushing. This type can be used to push scrappers.
Productivity of a bulldozer
The estimated productivity of one cycle is
q L x H 2 x 0 .5 a [10.4]
Where :
L = blade width;
H = height of blade;
a = blade factor; and
0.5 = takes care of the geometry of the blade, which is of triangular
section, thus
volume = ½ x base x h x L
= 0.5 H2L
since b = h = H
a f e xf f xf b [10.5]
Where:
ƒe = earth volume conversion factor.
ƒf = blade fill factor; and
ƒb = factor considering the loss of earth at the blade edge;
It is possible to develop factors that apply for different soil types. The factor a for
such different soil types is presented in Table 10.3.
Soil type ƒe ff fb
Sand, fine i.e., fine sand 0.90 0.40-0.50 0.40-0.50
Gravel 0.85 0.60-0.70 0.60-0.70
Gravel, coarse 0.70 0.90 0.70-0.80
Loam, sandy 0.74 1.0-1.3 0.70-0.80
Loam soil, plastic 0.69 1.0-1.4 0.80-0.90
Clay, plastic 0.72 1.0-1.4 0.80-0.90
Clay, hard 0.66 1.0-1.2 0.80-0.90
Top soil, loose 0.81 0.90-1.10 0.70-090
Top soil, with grass roots 0.87 1.3 0.90-1.00
Rock, well blasted 0.66 0.75 0.70-0.80
Rock, poorly blasted 0.60 0.65 0.60-0.70
Source: Peurifoy, 2005
The formula q = L x H2 x 0.5a is for 1 cycle. For a bulldozer the time needed to
complete one cycle depends on the following:
Cm = time in forward motion + time in reverse motion + time for gear shifting;
D D
Z measured in min [10.6]
F R
The hourly output is the product of number of cycles per hour and the output per
cycle, therefore, an hourly theoretical productivity for the bulldozer, Qth is as follows:
Qth q x N [10.7]
60
But N, number of cycles per hour =
Cm
60
Q pr q x xE [10.8]
Cm
Where:
Qpr = Practical productivity;
q = Theoretical productivity per cycle (m3)
Cm = Cycle time (min); and
E = Job efficiency factor based on site and machine conditions,
operator skills and motivations and other factors (Tables 10.1 and
10.2 respectively).
60
It should be noted that the highest possible productivity, Qmax Qtheor q x ;
Cm
328 Fundamentals of Civil Engineering Construction Management
60
Practical productivity, Q pr q x x E.
Cm
Table 10.4 Typical bulldozer blade sizes for different engine sizes.
Engine Size (Hp) 700 450 400 335 300 200 100-150 60-70
Machine Weight 520 340 298 250 224 149 75-112 45-52
(Tons)
Engine size (kW) 85 50 45 35 25 20 10-14 5-8
Blade length (m) 5.5 5 4.5 4 45 3.5 3.5 3.0
Blade height (m) 1.8 1.8 1.8 1.5 1.5 1.2 1 0.8
U-blade capacity 20 18 14 13 9 7 4 2
(m3)
Source: Peurifoy, 2005
Example 10.4
Determine the theoretical and practical productivity for a bulldozer whose engine
capacity is 400Hp working on a site with hard clay. Assume that the machine
condition is poor but the site condition is excellent. Further, the machine operator is
highly motivated although he is of average skill. Further, it is estimated that the cycle
time for the bulldozer is 3.5 minutes.
However, if the same conditions apply but soil type is fine sand, the practical
productivity decreases significantly to only 1.05 m3 per cycle. If on the other hand
the soil type is top soil, with grass roots and that the operator is highly skilled as well
as highly motivated, and the machine is in excellent condition, the other conditions
being the same, then practical productivity increases significantly to 6.23 m 3 per
cycle.
Operation synopsis
Specification
Maintenance philosophy
Performance
330 Fundamentals of Civil Engineering Construction Management
Contractors owning equipment have to appreciate the basic assumptions made at the
previous stages. The inherent assumptions have implications on equipment use and
maintenance in order to sustain a high level of output. It is therefore particularly
important for equipment owners to adhere to equipment maintenance manuals that
presumably have taken into consideration equipment specifications, design,
manufacture and use.
Repairing; and
Maintenance.
If the owner decides to cut down costs by providing only minimum maintenance, the
results can be unexpected breakdown, lost production and inefficient machinery.
Maintenance of facilities is needed because of the factors that generate that need.
These factors are broadly divided into two groups:
Man made maintenance factors; and
Natural maintenance factors.
Man-made factors are failure(s) created by the daily human interaction with the
facilities. These factors include:
Faulty design, material and manufacturing defects:
o Such type of fault can be built into the item at the time of its
construction/manufacturing process;
o Some of these faults may be built into the item and does not arise
until a certain operation is performed;
o These can be avoided through good design, proper selection of
materials and good selection before buying the item;
o Design/construction, which takes into account the operating
condition, is also important; and
o If possible, modification of the item at early stages can be done
based on the past experience.
Incorrect handling of facilities:
Exposing an item to actions and or stresses not designed for, like overloading
leads to failure. Operation of items need:
o Training;
o Modification;
o Reduction of human stresses; and
o Good instruction on the use of equipment.
Random failures are distributed in time such that they cannot be predicted. Examples
include failure due to overload and mismanagement. This framework is presented in
Figure 10.11.
Observable – PM inspection
with necessary corrective
Time-dependent action
failures
Not observable – periodic
replacement
Preventive maintenance systems can take different forms, but all have basic essential
requirements.
Note that, it is important that the measuring instruments must be properly calibrated
and regularly checked and the measured results must be compared with the machine
specifications to determine any deviations.
Tools, like fingers, are the extensions of the hand. Being expensive but very essential
to any craft, the owner has to strive for cost reduction in the investment he makes on
hand tool by careful selection of quality tools. Though price is an important issue
when selecting a product, its value is the real determining factor. The best quality
hand tool has a higher price, but is the least costly in the long run. The best/top
quality tools forestall:
Breakage;
Excessive wear; and
Premature failure.
Adequate range-tools should be selected so as to cover the whole range of work
components to be encountered. It is advisable to organize (and in fact it is a good
practice) tools in sets and this saves time that can be lost in getting forgotten tools.
Note that a right tool is to be used / purchased for the right job.
Safe and economical operation is a result of proper use of the tools. Incorrect use of
tools lead to accidents, for example, the use of pliers as substitute for wrenches or
screwdrivers being used as levers can result not only in the damage of the tool and
/or equipment, but it can also lead to accidents.
Another very important aspect is care of hand tools. Longer usages of hand tools
require safekeeping and a good state of repair. This will require:
Equipment and Materials Management 339
A good storage place (room, building, container or other space used for
storing and issuing tools);
Regular inspection to assess the tools (working condition and the state of
corrosion and wear for the moving parts);
Cleanliness;
Lubrication: When properly done, lubrication gives the following advantages:
o Reduced loss of energy by friction;
o Raises the efficiency of the tools or equipment;
o Reduction of wear and tear;
o Increased serviceable life;
o Maintains accuracy; and
o Ensures smooth and efficient operation.
Proper handling and packing, for example, tools that need sharpening should
be properly sharpened.
CHECK
Bearings X
Clutch X
Brake(s) X
Motor
Rolls X
INSPECTED
BY: C.T. C.T C.T
DATE: 6/1/2005 6/2/2005 6/3/2005
KEY:
DE – Defective;
OK – Okay.
Where the item is found defective, a separate record should be kept to indicate the
type of defect.
Chapter 11
Procurement and Management of Construction
Professional Services Contracts
11.1 Introduction
This is the definition adopted in this chapter that also draws heavily from the
guidelines in Consulting Services Manual published by the World Bank in 2006. The
philosophy, terminologies and procedures presented in this chapter are those
presented in the manual.
The main principles guiding the procurement of consulting services are as follows:
Transparency – the procedure for advertising, receipt of proposals from
prospective consultants, evaluation and award of the contract should be clearly
known to the consultants and should be followed in the process;
Value for money: value for money can be obtained where the best services are
obtained at least cost. This is assumed to take place where there is wide
competition. It is therefore necessary to ensure that there is indeed competition
and that where consultants are selected after intensive competition, the value for
money is obtained. It has to be stated here the this principle assumes market
forces in play; and
In the following sections, the different procedures that will be discussed will revolve
around these principles.
Consultants are mainly selected on the basis of first, the quality of their services and
secondly, their costs. The main reason for this approach is that technical decisions
made by consultants early in the project life would have significant cost implications
later in the life of the project. If wrong decisions are made, this may have disastrous
consequences later in the project. If sound decisions are made during preliminary and
detailed design stage, the client is likely to save money not only during the
construction stage but also during the operation and maintenance stage. It is therefore
logical to give priority to quality rather than cost at the design stage.
There are several methods for the selection of consultants each suitable for a specific
situation. In this chapter four methods will be discussed in detail. These are:
Quality and Cost Based Selection (QCBS);
Quality Based Selection (QBS);
Selection under a Fixed Budget (SFB); and
Least Cost Selection (LCS).
The choice of the appropriate method of selection is related to the nature, size,
complexity, likely impact of the assignment, technical and financial considerations,
and on the particular circumstances of the client. It is therefore necessary to carefully
define the consulting assignment, in particular the objective and the scope of the
services, before deciding on the selection method.
Quality and Cost Based Selection (QCBS) is a method based on the quality of the
proposals and the cost of the services to be provided. It is the method most frequently
used to select consultants in public projects. Since under QCBS the cost of the
proposed services is a factor of selection, this method is appropriate when:
The scope of work of the project can be precisely defined and the terms of
reference (or tasks to be performed by the consultant) are well specified and
clear; and
The client and the consultants can estimate with reasonable precision the staff
time as well as the other inputs and costs required of the consultants.
Under QCBS the technical and financial proposals are submitted at the same time in
separate sealed envelopes (two-envelope system). Proposals received after the
submission deadline are rejected. Evaluation of proposals is carried out in two stages:
first quality, and then cost. The technical envelopes are opened by a committee of
officials of the Client immediately after the closing time for submission of proposals;
the financial proposals remain sealed until the technical evaluation and the evaluation
report are completed. The financial envelopes of those consultants who submitted
responsive technical proposals meeting the minimum qualifying mark are opened in
the presence of the consultants or their representatives. The proposals are then
evaluated. Once the financial proposals are evaluated, a combined evaluation of the
technical and financial proposals is carried out by weighting and adding the quality
Procurement and Management of Construction Professional Services Contracts 346
and the cost scores, and the consultant obtaining the highest combined score is
invited for negotiations. The principles of negotiation are presented later in this
chapter.
QCBS permits the client to select a preferred trade-off between cost and quality and
to benefit from price competition, even if only to a limited extent. Transparency is
increased under QCBS with public opening of the financial proposals. Another
advantage is the possibility that contract negotiations will be easier because of the
limited scope for financial negotiations.
QBS is based on an evaluation of the quality of the proposals and the subsequent
negotiation of the financial proposal and the contract with the consultant who
submitted the highest ranked technical proposal. QBS is appropriate if:
the quality of the services becomes of overriding importance for the outcome
of the project;
the scope of work of the assignment and TOR are difficult to define because
of the complexity of the assignment, or the need to select among innovative
solutions, or due to particular physical, social, or political conditions;
the assignment can be carried out in substantially different ways, such that
cost proposals may not easily be comparable; and
347 Fundamentals of Civil Engineering Construction Management
In some cases the choice between QBS and QCBS may be difficult. In situations of
strong uncertainty and/or risk for the project, QBS should be adopted because quality
is the key element.
A possibility under QBS is for the client to request submission of the technical
proposals only. After receiving the technical evaluation report, the consultant with
the highest-ranking technical proposal is invited to present its financial proposal.
However, the client may wish the financial proposals to be submitted at the same
time as the technical proposals but in separate envelopes (two-envelope system). In
that case, the financial proposals should be kept safely until the technical evaluation
is received. Only the financial proposal of the winning consultant is opened; the
others are returned unopened after negotiations with the winning firm are
successfully concluded.
Since the TOR of assignments under QBS are generally less defined and relatively
more complex than under QCBS, contract negotiations with the winning consultants
may be lengthy and complicated and should be handled very carefully.
Occasionally, the public projects, such as hospitals, schools and colleges and
research centres which have an aesthetic component that has to be taken into account
at the moment the consultant or architect is selected. Design Contest (DC) is a
selection procedure very similar to QBS under which a client invites consultants to
present a plan or design for a project on the basis of a concept provided by the client.
The winner is selected on the basis of quality, with or without prize award, by an
Procurement and Management of Construction Professional Services Contracts 348
evaluation committee. DC procedures are a tool for selecting the best available
architects, engineers, and planners for specific projects with important aesthetic
contents.
Consulting assignments for major projects that can be implemented through DC are:
terminals of airports, and railway stations;
public buildings such as hospitals, theatres, concert halls, university
campuses, art and sport centres, exposition and fair complexes, and
government buildings; and
Rehabilitation of large obsolete structures, to create multipurpose centres for
public use.
Selection under fixed budget (SBF) is based on disclosing the available budget to
invited consultants in the RFP and selecting the consultant with the highest-ranking
technical proposal within the budget. Because consultants are subject to a cost
constraint, they will adapt the scope and quality of their services to that budget. The
client must therefore ensure that the budget is compatible with the terms of reference
and that consultants will be able to perform the tasks within the budget. SBF is
appropriate only when:
Under SFB, consultants are requested to submit their technical and financial
proposals in separate envelopes. Technical proposals are evaluated first, using the
same procedure followed for QCBS and QBS, and then the financial envelopes are
opened in public. The consultant who has submitted the highest ranked technical
proposal among the remaining proposals is selected.
Since the budget is predetermined, the consultant’s TOR cannot change substantially,
and technical negotiations shall cover minor aspects. SFB allows clients to plan a
budget early on, rather than wait for the uncertain outcome of negotiations.
Furthermore, it allows clients to receive better quality proposals than under QCBS
because it is easier for consultants to maximize quality under a fixed budget. SFB
also requires a shorter time for negotiations than QBS. SFB is also convenient for
consultants because the pre-established budget allows them to determine in advance
whether they are interested in competing for the proposed assignment, and to develop
the best proposal consistent with that budget.
More than with QBS and QCBS, the SFB method requires the TOR to be consistent
with the established budget and to contain a well-specified scope of work in order for
consultants to present clear and responsive proposals. One risk of using the SFB is
under budgeting the TOR and by doing so discourage good consultants from
participating, and receive poor performances from the awarded consultants.
Under this method a minimum qualifying mark for quality is established and
indicated in the RFP. Short listed consultants have to submit their proposals in two
envelopes. The technical proposals are opened first and evaluated. Proposals scoring
less than the minimum technical qualifying mark are rejected, and the financial
envelops of the rest are opened in public. The consultant with the lowest evaluated
price is selected.
The LCS method is more appropriate for small assignments of a standard or routine
nature where well-established practices and standards exist and from which a specific
Procurement and Management of Construction Professional Services Contracts 350
and well-defined outcome is expected, which can be executed at different costs, for
example:
engineering designs and/or supervision of simple projects;
repetitive operations and maintenance work and routine inspections; and
simple surveys.
Clients may adopt this selection method when they wish to capture cost benefits from
mature technologies or new methods for which quality risks for the final output are
considered negligible.
Once a project is identified, the Client decides on the nature and scope of consulting
services needed, taking into consideration the institutional strength, and technical
knowledge of the executing agency. Prior to issuance of any request for proposal, the
proposed plan for the selection of consultants under the project shall be furnished for
its review and approval. Depending on the selection method adopted, the selection
process carried out by the Client includes the following steps:
Preparation of the terms of reference (TOR) of the assignment;
Preparation of the cost estimate to determine the budget of the assignment;
Advertising to invite expressions of interest from consultants;
Short listing to identify consultants qualified for the assignment;
Preparation and issuance of the request for proposal (RFP);
Preparation and submission of proposals by the consultants;
Evaluation of technical proposals, i.e., quality evaluation;
Evaluation of financial proposals, i.e., cost evaluation;
Final combined quality and cost evaluation to select the winning proposal
specifically where QCBS is used; and
Negotiations and signing of contract between the client and the consultants.
The Terms of Reference (TOR) explains the objectives, scope of work, activities
and/or tasks to be performed, the respective responsibilities of the client and the
consultant, and expected results and deliverables of the assignment. They help reduce
the risk of unnecessary extra work, delays, and additional expenses for the client. In
addition, they help reduce the risk of ambiguities during the preparation of consultant
proposals, contract negotiation, and execution of services.
Preparation of the TOR requires expertise with the type of assignment and the
needed resources. If the needed qualifications to produce the TOR are not available in-
house, the client can hire a specialized independent consultant. TOR has to be written
by experts who have only the interest of the client in mind.
The level of detail and quality of information that can be contained in the TOR
influence the selection method to be adopted. The authors of the TOR should be
familiar with local natural and social conditions such as climate, topography,
institutions, people, customs, holidays, remuneration levels, and transportation
systems. Seasonal variations, together with the peculiarities of the region where the
assignment will take place, should be considered if they can affect the execution of
fieldwork. Both project and logistic related aspects of the project should be
researched.
353 Fundamentals of Civil Engineering Construction Management
The TOR should clearly define the output and deliverables required of the
consultants, e.g., reports, maps, drawings, or software, and should list information
that the client will furnish to the consultants. This information may include past
studies, aerial photographs, maps, or records of surveys carried out in the assignment
area. The TOR also should identify the client’s executing agency and clarify
institutional arrangements for the supervision of consulting work. Additionally, the
TOR should specify the facilities and counterpart staff to be provided or designated
by the client.
available by the client for use by the prospective consultant. The TOR also
should describe the client’s available software and computer models to be
used by the consultants. Facilities to be provided by the client may include
office space, vehicles, survey equipment, office and computer equipment, and
telecommunication systems; and
Institutional arrangements - the TOR should define the institutional setup
surrounding the assignment, indicate the role and responsibilities of
everybody involved, and specify the type, timing, and relevance of
everyone’s participation, including the Client’s. The TOR should define the
hierarchy and level of authority of counterpart personnel as well as the
requested level of experience of the Client’s personnel who will be integrated
into the consultants’ team.
The TOR will then form the backbone of the request for proposal sent to prospective
consultants to prepare their proposals.
11.4.3 Preparation of the cost estimate and budget for the assignment
The cost estimate is based on an estimate of the man power (expert per month)
required for carrying out the services, taking into account the time required by each
expert needed, and then making estimates for each of the related cost components. It
is important to define these inputs as well as possible.
The client prepares a shortlist comprising normally three to six firms. The client
Procurement and Management of Construction Professional Services Contracts 356
reviews the credentials of those who submitted expressions of interest and give first
consideration to those that possess the relevant qualifications. Additional reliable
consultants can be added to the list if there is insufficient number who submitted
their expressions of interest.
Since preparation of the shortlist should be the exclusive responsibility of the client.
The client carries out a diligent review of key aspects such as:
qualifications in the field of the assignment;
technical and managerial capabilities of the firm;
core business and years in business;
qualifications of key staff;
client references; and
administrative and financial strength.
In principle, short-listed consultants can be allowed to associate with each other, only
with the permission of the Client but this should not override the principle of
competitiveness.
The request for proposal for a specific assignment provides all the information
necessary for the short listed consultants to prepare their proposals. It identifies the
evaluation criteria, selection method, and procedures that will be used to evaluate
them. The RFP also contains the TOR and the draft contract for the assignment. The
RFP can be adapted for any of the selection methods described in section 11.3. A
typical RFP includes the following sections:
Section 1: Letter of Invitation (LOI) - the LOI states the intention of the client to
enter into a contract for a given assignment and informs the short listed
consultants that they are invited to submit a proposal for the assignment.
It provides basic information regarding:
the name of the client and the sources of funds to finance the
357 Fundamentals of Civil Engineering Construction Management
consulting services;
the names of the short listed consultants;
a brief description of the objectives and scope of the assignment;
the method of selection; and
the date, time and address for submission of proposals.
SRFP also includes two samples that may be used for smaller contracts
under time-based or lump-sum remuneration.
The Client should give consultants enough time to prepare their proposals.
Depending on the type and size of the assignment, a period of time of four weeks for
simple assignments and up to three months for complex assignments is normally
allowed. These periods refer to actual preparation time, and additional time
(sometimes not negligible) should be allowed to include deliveries of the RFP and
the proposals. During this period consultants may seek clarifications on the
information or provisions contained in the RFP. Clarifications may help consultants
submit responsive proposals. Consultants must submit their requests for clarification
to the Client in writing, by facsimile or e-mail. Clients must respond promptly, also
in writing, and send a copy of the query and its response to all short listed consultants
who have confirmed their intention to submit proposals. The Client should not
identify the source of the inquiry. When the clarification results in important changes
to any part or provision of the original RFP, the Client extends the deadline for the
submission of proposals to enable the consultants to take into account the responses
to their questions.
Under QCBS, SFB, LCS, SBCQ, and SSS, both technical and financial proposals
must be submitted at the same time. Under QBS, although financial proposals may
be submitted together with technical proposals, the practice is to require submission
of the technical proposal first, followed by submission of the financial proposal by
the consultant whose technical proposal is ranked the highest (two envelope system).
Proposals must be submitted at the designated place (exact address, office, and room
number to avoid any ambiguity), no later than the date and time indicated in the RFP.
Under QCBS, SFB, and LCS, since price is a factor of selection, proposals received
after the deadline for submission are disqualified and must be returned to the
consultants unopened (any delay by a specific firm in submitting its proposal could
359 Fundamentals of Civil Engineering Construction Management
be used to tamper with other proposals or to allow the firm to modify its proposal
price). Under SBCQ and SSS, where technical and financial proposals are requested
from only one consultant, a certain degree of flexibility is acceptable when a minor
delay for reasons beyond the control of the applicant occurs.
After the proposals have been received and opened, the evaluation process begins.
Each evaluation is normally carried out individually. Each member of the evaluation
committee establishes, as part of the evaluation process, whether the proposals are
substantially responsive, that is, if there are no important omissions or deviations
from the stated objectives, TOR, or other key requirements of the RFP. The
evaluation also establishes whether a proposal passes the minimum qualifying mark
provided in the RFP.
By applying the criteria and sub criteria specified in the RFP, committee members
should establish the absolute, not the relative, quality of the proposals. In fact, even in
a set of poor proposals one is the best; a relative evaluation singles out the best
proposal on a relative scale and still leaves the Client with a poor choice. On the
contrary, the evaluation should single out the proposal with the best objective quality.
Procurement and Management of Construction Professional Services Contracts 360
The way to establish such quality is to define the grades of the rating system as
clearly as possible.
After each committee member has independently completed the evaluation, the
committee should meet to review and if necessary discuss the merits of individual
evaluations and scores. For each proposal, the Evaluation Committee calculates the
average of the scores allocated by all members under each criterion, establish the
technical ranking of the proposals, and identify the best. The evaluation report must
include the joint as well as the individual evaluations. The evaluation process should
include comments on the strengths and weaknesses of all proposals that have passed
the minimum technical qualifying mark indicated in the RFP. This will help identify
any issues in the winning proposal that need to be clarified during negotiations. The
report of the outcome of the evaluation is then submitted to the relevant authority for
further decisions.
The opening the financial proposals, is open in public after verifying that they have
remained sealed until then. The name of the consultant, the quality scores, and the
proposed prices are read aloud and recorded as each financial proposal is opened. No
modifications to the financial proposals are permitted.
The evaluation committee should first review the proposals for arithmetical errors
and consistency between the financial and technical proposals (e.g., omissions of
items included in the technical proposals). Arithmetical errors should be corrected,
omitted items evaluated, and the corresponding adjustments made to the offered
prices to obtain the final evaluated prices. For the purpose of comparing proposals,
evaluated prices should be converted to a single currency using the exchange rate,
date, and source indicated by the Client in the RFP. The scores of the evaluated
prices should then be calculated according to the formula provided in the RFP.
If QCBS is the method of selection, the evaluation committee combines the scores of
the technical and financial proposals to obtain a final ranking of the proposals and
recommendation for award. Those data are recorded in the Financial and Final
Evaluation Report, which is delivered to the decision-making authority. The
authority revises the report, confirms the recommendation for award, and obtains any
additional clearance that may be required under local regulations.
After Final Report to determine if the evaluation is consistent with the provisions of
the RFP, the Client invites the top-ranked consultant to negotiations. The Client then
informs the other consultants of the name of the selected firm and that negotiations
with that firm will begin. If the Client believes that negotiations could fail or could
go beyond the proposal validity period, he should ask the consultants to extend the
validity of their proposals.
Once the contract is awarded, firms may want to learn the reasons why they were not
selected. The Client should provide reasonable, prompt, and satisfactory replies to all
such requests. The Client should not discuss the details of any other proposals.
Briefing losing firms helps them to understand why they lost, encourages them to
continue submit proposals in the future and to improve their quality.
The project objectives and the underlying TOR determine the qualifications and
experience required from the consultants who will carry out the assignment. In
adopting evaluation criteria, the Client seeks to ensure that the proposal selected will
offer the best quality for the services required. The following criteria shall be used as
a basis for evaluation of technical proposals:
specific experience of the consultants relevant to the assignment;
adequacy of the proposed methodology and work plan in responding to the
TOR;
Qualifications and competence of key staff for the assignment; and
Other criteria specific for a particular situation.
Procurement and Management of Construction Professional Services Contracts 362
Table 11.1 shows a range of points that may be allocated to each criterion on a scale
from 1 to 100. The weights may be adjusted for specific circumstances. The actual
distribution should depend on the type of assignment and the relative importance
each criterion has for the success of the assignment. A good practice is to have those
who prepared the TOR advice in the selection of sub criteria and relative weights.
Total 100
Each of the criterion may be subdivided further into sub-criteria. For example, the
criterion “Qualifications and competence of key staff” is divided into the following
three sub criteria:
General qualifications;
Adequacy for the assignment; and
Experience in region.
In any case all the sub criteria should be clearly stated in the request for proposal.
Since sub criteria and their weighting determine the outcome of the evaluation, they
should be chosen considering the aspects that are critical to the success of the
assignment. Evaluation criteria and sub criteria, associated points, and the rating
system form an arithmetic model to assess the technical merit of the proposals. The
more reliable the model, the more accurate the evaluation, and the greater the
363 Fundamentals of Civil Engineering Construction Management
possibility that the Client will select the proposal of the consultants who are best
suitable for the assignment.
The client appoints a negotiating team whose members should be fully familiar with
the TOR, the consultant’s proposal, the comments and suggestions of the evaluation
committee relating to the technical and financial evaluation reports, and
recommendations of the decision-making authority. Negotiations are based on a
mutually agreed upon agenda composed of the main items to be negotiated, that is,
methodology, work plan, proposed staff, inputs, financial terms, and special
conditions of the contract.
Depending on the selection method and proposed type of contract, technical and
financial items that may be negotiated, within the limits, include:
scope of work;
technical approach and methodology;
work plan and activity schedule;
organization and staffing, and time schedule for key staff;
deliverables;
Procurement and Management of Construction Professional Services Contracts 364
counterpart staff;
counterpart facilities and equipment;
contract special conditions;
staff unit rates;
reimbursable expenses; and
Proposed contract price.
Contract negotiations for small assignments are usually completed within one or two
days. However, for large assignments at least one full week should be allowed.
Negotiations may even be carried out in phases when decisions are needed from
other authorities. The client should keep the minutes of the negotiations. If the issues
to be negotiated are many and complex, significant points can be initialed by the
counterparts as negotiations progress as these may form part of the contract in case
negotiations are completed successfully.
Because the quality of the technical proposal of the selected consultants is either the
main or the predominant factor in ranking the consultants, the discussion shall not
substantially alter the original TOR or terms of the contract to reduce the proposed
price. The limit of the negotiated proposal is no change in the initial ranking of the
evaluated proposals. There are also limits to financial negotiations. They should be
used by the client to achieve consistency between the quality and the price of the
offered services, and not just a price reduction at all costs. For instance, if staff rates
proposed by a consultant are consistent with market rates for similar services, the
only negotiable item would be the fee component of the rate, and this cannot be cut
unreasonably. Details of technical issues in negotiations are beyond the cope of this
book.
Consulting assignments are generally of intellectual nature. Contracts that govern the
execution of such assignments are designed as such. It is also assumed that
365 Fundamentals of Civil Engineering Construction Management
Consultants can seldom begin work immediately after signing the contract. A signed
contract, which has received approval by higher authorities, or compliance with
certain prerequisites (e.g., funding requirements) are met. To enable consultants to
begin work promptly, the Client should make arrangements for supervision of the
assignment, in particular:
appoint the counterpart staff;
prepare for provision of items to be provided by client as per contract;
inform all concerned institutional parties;
effectuate advance payments; and
obtain authorizations, data, and background material.
The Client should designate a counterpart project manager with adequate technical
qualifications, managerial experience, and power of authority. In certain instances,
for large and politically complex projects, a project steering committee composed of
high-level representatives of the Client and the consultants may be formed to
exercise arm’s length supervision over the assignment through the counterpart
project manager and the consultants’ team leader. The steering committee can be
particularly useful when the Client’s executing agency and the consultants have to
coordinate their work with other agencies of the Client. The opportunity to report on
a regular basis to such a committee can facilitate collaboration and understanding
between the Client and consultants on disputes over important technical and
contractual issues. The steering committee should convene for specific purposes and
at important assignment or contractual deadlines.
Amendments
The Client or the consultants may propose amendments to the contract when either
unforeseen events or the Client’s decisions make it necessary to modify the TOR or
the consultants’ scope of work. Such amendments should be approved by appropriate
bodies in the client’s organization.
Disputes
During execution of the assignment, disputes may arise between the client and
consultants. The parties involved should attend to such disputes promptly and
constructively. Unresolved disputes relating to technical and administrative matters,
such as interpretation of the contract, payment of services, or replacement of
personnel, should be treated in accordance with the provisions of the contract.
Unsatisfactory Performance
Poor performance may involve one or more particular staff of the consultants’ team,
or the whole team. Based on the provisions of the contract, the Client will advise the
consultants to take the necessary measures. Poor performance should not be
tolerated, and the consultants should act quickly to comply with a reasonable request
367 Fundamentals of Civil Engineering Construction Management
to improve the performance of the team or to replace any particular staff member
who is not performing adequately. If the consultants fail to take adequate corrective
actions, the Client may terminate the contract in accordance with the provisions of
the contract.
Delays
Consulting services may be delayed for a variety of reasons. The consultants should
notify the Client of such delays and explain the causes of the delay. If corrective
action requires extra work, and the delay cannot be attributed to the consultants, the
extra work should be reimbursed in accordance with the contract.
The consultants collect and review the comments made by all parties and, in
agreement with the Client, address these comments in the final report. If additional
work is necessary to address important comments, such work may have to be
financed with or without a contract amendment, out of the contingencies provided for
in the contract, by government funds, or additional financing.
Any mistake or incomplete work on the part of the consultants should be remedied at
no cost to the Client. Furthermore, the consultants are responsible for the technical
integrity and objectivity of their findings and recommendations. The preferred way
to handle significant disagreements on technical matters is to substantiate dissenting
views in the report. Prior to the final payment, the consultants must have completed
the services, and the Client must have acknowledged completion of the assignment.
Procurement and Management of Construction Professional Services Contracts 368
The Client is responsible for ensuring that funds used to finance consulting services
are properly spent. Consultants’ performance should be monitored during the
assignment, but a final opinion should be formally expressed only upon its
completion. Official comments by Client staff should pertain only to the assignment
and take into consideration the views of the Client. The following procedures are
recommended to assess performance during the assignment:
Closely monitor consultants’ performance during supervision missions and
report on performance in the supervision reports; and
If the consultants’ performance is found to be unsatisfactory during execution
of the assignment, the Client should inform the consultants in writing and give
them the opportunity to comment.
Successful conclusion of the contract occurs when each party to a contract has
completed his/her obligations and received his/her rights. Likewise in any consulting
contract, a contract can only be deemed to be successfully concluded if the
consultant has completed all the tasks in the terms of reference in accordance with
the contract or its amendment and he has received all payments as per contract.
369 Fundamentals of Civil Engineering Construction Management
Chapter 12
Selection of Contractors and
Management of Works Contracts
12.1 Introduction
This chapter will present the procedure used for selection of contractors for works
using the traditional project delivery approach. However, it is first necessary to
consider the alternative ways in which a construction project can be organized, which
vary from doing everything in-house to handing the total responsibility to a
contractor who will finance, design, build and operate the project. However,
whatever the method of project organization is adopted, two things are essential:
A sound contractual relationship between the owner and each of his consultants
and contractors; and
Cooperation and trust between the people from different organizations and
professions who are working together on the project.
Any project starts when someone decides that they need something that must be
constructed.
This may be a village deciding that they need a new water borehole, the Ministry of
Works deciding that a new road is needed, or a company decides to build a new high
rise building. They will start by considering:
Where they will obtain the money to pay for the project; and
How they will procure the project.
Selection of Contractors and Management of Works Contracts 371
The finance may already be available, in which case the Owner can proceed to
decide on his procurement method. Alternatively, if the finance needs to be raised or
borrowed then the necessary arrangement must be put in place, which may mean
negotiating with a bank or international funding agency.
If finance must be borrowed, the lending agency will probably impose restrictions on
the project and the method of procurement. For example, The World Bank normally
insist that the project is constructed using the International Federation of Consulting
Engineers (Fédération Internationale des Ingénieurs-Conseils – FIDIC), Conditions
of Contract – commonly referred to as FIDIC Conditions of Contract, modified to
include some standard World Bank Clauses. For government-financed projects, it
may be necessary to use standard tender documents adopted to suit certain specific
political and economic conditions in the respective country.
The project owner will need to decide how much of the work he will do himself in-
house and how much he will contract out to consultants and contractors. The range of
options includes:
All work in-house;
Design in-house and construction by a contractor;
Initial design brief in-house, design by a consultant and construction by main
contractors who will use subcontractors as necessary. This is the traditional
method which used with FIDIC Conditions of Contract;
Initial design by a consultant, with detail design and construction by a contractor
– this method is also commonly known as the traditional approach;
All design and management by a project manager, using several trade contractors
whom work directly for the owner; or
Raising the finance, design, construction and operation by a single contractor,
who employs consultants and subcontractors as necessary.
The choice of which procurement method to use will depend partly on the facilities
which the Owner has available in-house, but also on the size and type of the project.
A large organization, which requires a succession of projects, may employ a team of
372 Fundamentals of Civil Engineering Construction Management
For any system of procurement, the Owner must decide what he wants. This may be
a very broad requirement, such as a hospital with 400 beds and all the usual
departments, or it may be a detailed requirement for a building to be occupied by the
Owner himself.
It is essential that the Owner establishes his requirements right at the start of the
project. The detailed requirements may develop as the design develops, but changes
of mind must be avoided. Any changes to the requirements, after instructions have
been given to a consultant or contractor, will result in additional work, which means
delay and additional costs. These costs will eventually be paid by the Owner. In
principle, the extent to which the Owner wishes to influence the detailed design and
the way in which he sees the design developing will influence the choice of method
of procurement.
Construction projects, like many other types of projects, pass through various typical
stages right from inception to commissioning stage. Typically, the stages include:
Conception stage – at this stage it is realized that there is a problem that requires
a constructed facility to solve it. This may be a road, water supply project, an
Selection of Contractors and Management of Works Contracts 373
Briefing Stage – the promoter of the project converts the concept into a project
description that he thinks will meet the expected needs. This description would
form the basis for the next stage of the project;
Tendering stage – this involves the selection of a contractor who will undertake
the construction. At the end of the tender stage a contract is entered into with the
contractors selected for the construction of the project;
Use and maintenance for the constructed facility is the last stage of the project.
374 Fundamentals of Civil Engineering Construction Management
12.2.2.1 Objective
The procedure used to select a Contractor who will execute a particular construction
project is in many cases referred to as TENDERING PROCEDURES. The aim of
this procedure is to select a Contractor who will complete the project at the required
TIME, to achieve the right QUALITY and optimum COST thus providing value for
the employer's money.
In special cases, it is possible to select only one contractor to undertake the project
without the need for advertising. This is known as single source selection. This can
be used where there are unlikely advantages for tendering or there is only one
contractor who can undertake the project. In this section, only those projects where a
clear need for tendering has been justified.
Client’s name;
Title of the project;
The name of the Engineer/Architect;
An outline of the project, scope and scale of work;
Location of the work;
Anticipated programme (i.e. award of contract, completion and any other key
dates);
Tender reference and title;
Expected date of issue and submission of tenders; and
Any other eligibility conditions such as class of contractors.
Open tendering
This procedure offers the advantage of full competition in terms of price and
completion period from all interested contractors. It can however, result in the
submission of a large number of tenders with much abortive tendering and waste of
resources. It could also result in tenders being awarded to contractors who are not
adequately equipped financially or technically to undertake the work. Except in small
projects where there are few tenderers expected to respond, this method is not
recommended.
Selective tendering
Selective tendering ensures that only few contractors are invited to tender for the
works. It tries to balance the level of competition for the works and the cost involved
in the whole tendering process. The Client can use any of the following two
approaches:
This approach is not open enough to give equal opportunity to all contractors and
selecting one who is best for a particular project. It limits the range of contractors
who are considered for the project. It therefore excludes contractors who are not
known to the employer, or who are new to the business.
Having received the replies to the pre-qualification questionnaire, the Client must
study and check the information. This may be a lengthy process, particularly if the
project includes manufactured items and a visit to the factory is considered to be
necessary. The Client will also take up references and visit other projects.
Having established the list of companies who will be asked to submit tenders, the
Client sends them the “Tender documents” and may require payment. The tender
documents will comprise of:
A covering letter and invitation to tender;
The instruction to tenderers;
The form of tender and appendix;
The proposed contract documents;
Information data; and
Schedule of additional information;
The covering letter and invitation to tender
The covering letter should only comprise the invitation to submit a tender, with a list
of documents that are enclosed. All other information should be given in the tender
documents. For practical reasons, certain facts, such as the date for the return of
tenders, may not have been known when the other tender documents were printed
and so are stated in the letter.
Instruction to tenderers
378 Fundamentals of Civil Engineering Construction Management
The instruction to tenders are normally issued with the tender documents for the
purpose of drawing attention to the conditions applying to the invitation to tender and
the procedures to be followed/ complied with by contractors when compiling and
submitting their tenders. They also convey information and instructions that will
apply during the tender preparation and evaluation periods.
The Appendix to the Form of Tender includes facts and figures relating to certain
clauses in the Condition of Contract, which must also be completed by the Client
before the documents are issued to tenderers.
Selection of Contractors and Management of Works Contracts 379
upon the tenderers. Amendments should be issued only if the Client is convinced that
the pricing of the tenders will be so seriously affected as to distort the balance
between the tenderers. Unless significant changes have to be made, amendments are
best withheld and dealt with either as post tender clarification or as part of the
administration of the contract after acceptance.
Amendments made to the documents should be sent out by means of addenda letters
or notices that must be numbered consecutively and accompanied by an
acknowledgement slip. Tenderers should be instructed to return counter-signed
copies of each letter or notice with their tender, so as to confirm that the addenda
were received and acted upon as part of the tender and the contract documents.
Tender period
Tender periods must be sufficient to allow tenderers to familiarize themselves with
the documents and sites, obtain quotations, decide the best construction methods and
price the items. Tendering period is the busiest for contractors and it is in the best
interest of Clients to allow adequate time from the outset.
Short tendering periods have a disadvantage in that, tenderers will have insufficient
time to plan the work properly and economically and price it in a realistic manner.
Unreasonable tender times may also contribute to the receipt of unreasonable tenders
that would not have considered substantial foreseeable risks and have not allowed
tenders to plan their operations with sufficient flexibility.
Queries
Selection of Contractors and Management of Works Contracts 381
Site Visits
The Client should arrange for site visits for the tenderers. Preferably this
should be done at once with all tenderers, perhaps at the same time as a pre-
tender meeting. If tenderers make separate visits then the Client must ensure
that the same information and facilities are given to all the tenderers.
Pre-tender meetings
Pre-tender meetings are arranged to clarify points of doubt and uncertainty
that may have arisen during the tender period. These meetings and/or site
visits are best arranged in the form of group meeting of all tenderers. All
information provided on such occasions must be properly recorded and
confirmed in writing to all tenderers.
Tenderers have the right to modify their tenders in writing at any stage before
the appointed submission time.
Opening of tenders
Tenders are opened officially by the Client at the fixed date and time. The Client
should check and display the sealed condition of each tender before it is opened.
After each tender envelope is opened, the Chairman of the meeting should announce:
Tenderers name;
Date and time of receipt;
Tender price (and completion time where applicable); and
Price of alternative tender, if appropriate.
This information should be recorded on a suitable form and signed by the Chairman
and appropriate witnesses. Following this, the names of any Tenderers disqualified
due to late or non-receipt of tenders should be announced.
Evaluation of tenders
After tenders are opened, they are passed on to the Engineer or selected Client’s
technical staff or committee for detailed evaluation and recommendation of the
tenderer to be selected.
The tender with the lowest evaluated cost should be recommended as the most
advantageous offer financially, when other factors are satisfactory such as technical
competence.
Tender negotiation
There is generally a need for some pre-contract negotiation, for whatever reason,
particularly with the lowest tenderers. This will involve meetings and an exchange of
letters and other information. The Client may want further information about the
Contractor’s proposal and the Contractor may want to suggest alternatives to the
contract requirements.
To maintain the principles of the tender process, it is essential that any negotiations
are only to clarify the tender. If major changes are being negotiated then it may be
necessary to give other tenderers the opportunity to re-submit their tenders or even to
re-tender the project.
Award of contract
The successful tenderer should be notified immediately if a decision has been made
to accept his offer. The successful tenderer should also be advised of the action to be
taken.
Letter of intent
Selection of Contractors and Management of Works Contracts 385
Letter of acceptance
A legally binding contract is established when the tender is formally accepted
by or on behalf of the Client. The Engineer will proceed to prepare a Letter
of Acceptance of the tender setting out any agreed conditions during tender
period. This letter should be issued by the Client.
Once the contract has been let, all unsuccessful tenderers should be
individually notified of results, including the amount of the successful bid.
Once the Letter of Acceptance has been issued, it is the Engineer’s duty to
instruct the Contractor to proceed with the works and to declare the starting
date. The Form of Agreement can now be drawn and signed and sealed by the
Client and the Contractor at this stage.
12.3.1.1 Introduction
386 Fundamentals of Civil Engineering Construction Management
In general, parties to a contract are free to make any terms they choose, but the law
or the norms of society in which they live may place certain limits upon them. Apart
from such limits courts of law will attempt to implement contracts according to the
terms agreed. However unjust the terms might be or become the courts have no
power to rewrite them. Thus if a Contractor has contracted to carry out works at
such prices that he is bound to make a loss, he must still carry out the works or pay
damages for breach of contract. There is no other way out.
the conduct of the parties or a combination of all these. The intention of the parties
is gathered from the express terms of the agreement.
In order to discover whether agreement was reached between the parties, the
negotiations are analysed into offer and acceptance.
12.3.1.4 Consideration
388 Fundamentals of Civil Engineering Construction Management
Even where offer, acceptance and consideration exist, the contract might not be
binding if the parties had intended not to create legal relations. This is not
uncommon say in family arrangements where it is presumed that domestic
agreements are not intended to create legal relations. In commercial agreements the
parties concerned normally intend to be legally bound. Construction contracts will
invariably include a clause specifying the Country or State the law of which is to
apply to the interpretation of the Contract.
The final step in the formation of a contract is the identification of the terms and their
effects. These are in essence its contents and determine the extent to which the
parties are in agreement. Accordingly, the terms of the contract define rights and
obligations arising from the contract. Contractual terms may be expressed or
implied. Express terms being material statements made by the parties by which they
intend to be bound while implied terms are those which have been implied by law
either according to the provisions of a statute or to give effect to the presumed
intentions of the parties. In building and engineering contracts express provisions in
the contract documents often cover most of the terms so that there may be no case for
further implication.
12.3.1.7 Discharge of contract
Discharge of contract is the general terms used to denote the bringing to an end of a
contract and the release of all contractual obligations. Contracts do not cease
Selection of Contractors and Management of Works Contracts 389
automatically and must be brought to an end by some of the parties to the contract.
There are four ways whereby discharge can be effected and these are by: -
performance;
frustration;
acceptance of breach; or
or agreement.
a) Performance: A contractual obligation is discharged by a complete performance
of an undertaking. In construction it is when the contractor has completed the
work including his obligations as to maintenance, the architect or engineer has
issued all the requisite certificates and the client has paid all sums due.
b) Frustration: General contractual obligations are absolute and a party to a
contract is not discharged from his obligations merely because performance has
become more onerous, expensive or impossible due to some unforeseen
circumstances. There are however exceptions to this general rule of absolute
contractual liability in certain events of supervising impossibility. Frustration
will apply where due to some event outside the control of the parties; the
fundamental purpose of the contract is rendered impossible to perform so that
any attempted performance would amount to something quite different from
what was originally contemplated by the parties. Examples in construction are
very are and terms within the contract take care of this eventuality as regard
payments.
c) Breach of Contract: Occurs where a party fails to perform his obligations or
where he expressly or impliedly repudiates his obligations without justification.
The other party not in breach is entitled to sue for damages and if the breach is
sufficiently serious it gives the option of treating the other party in breach as
having repudiated the whole contract. The innocent party may then bring the
contract to an end by accepting the repudiation and refusing further
performance.
d) Discharge by Agreement: There is no reason why parties to a contract should
not agree mutually to release each other from their obligations at any time
during the currency of the contract. This can occur by either entering into
390 Fundamentals of Civil Engineering Construction Management
For the traditional approach of project delivery, there are essentially two major
contracts that the client enters into:
Supervision contract with the consultant/engineer/project manager: This
is entered into for purposes of supervision of construction of the works.
This could be already incorporated in the design contract, if the same
consultant who carried out the design would also undertake the
supervision. Otherwise, the contract is signed for purposes of supervision
only. On the other hand, the main consultant may also enter into
supervision sub-contracts with specialist consultations.
Construction contract with the contractor: This contract governs the
construction of the works. The contract, although signed between the
client and the contractor, it gives powers to the engineer or project
manager to supervise the works in accordance with the conditions of
contract. It should be noted that the engineer has no contract with the
contractor. The contractor may also enter into subcontracts with general
and specialised subcontractors.
Client
Supervision Construction
Contract Contract
12.3.2.1 Introduction
Thus, the contractor's tender is an offer to client for executing whatever the clients
wants on the terms offered by the client. The documents necessary to define the
scope of contract will in most cases include the following:
instruction to tenderers;
form of tender and its appendix;
bill of quantities;
tender drawings;
conditions of contract both general and specific;
Specifications; and
form of agreement.
In case where pre-qualification of contractors has already been done, the particulars
of the legal, financial status and technical experience of the tenderer may not be
required.
The Form of Tender is the tenderer's written offer to execute the work in accordance
with the other contract documents, and states the total tender sum, the time for
completion and other salient particulars of the offer. Normally the tenderer must
submit a tender complying fully with the Specification, but in some cases he may
also offer alternatives.
The Conditions of Contract define the terms under which the work is to be carried
out, the relationship between the client and the contractor, the powers of the Engineer
and the terms of payment. The conditions of contract fulfil two separate functions,
they allocate the risks and liabilities between the parties and set up the administrative
framework for the contract.
12.3.2.5 Specifications
The Specifications describes in detail the work to be executed, the character and
quality of the materials and workmanship, and any special responsibilities of the
Contractor that are not covered by the Conditions of Contract. It may also lay down
the order in which various portions of the work are to be executed, the methods to be
adopted, and particulars of any facilities to be afforded to other contractors. The
Selection of Contractors and Management of Works Contracts 393
The Bill of Quantities is a list of items giving brief identifying descriptions and
estimated quantities of the work comprised in a Contract. Its objectives are:
a) to provide such information of the quantities of work as to enable tenders to be
prepared efficiently and accurately; and
b) when a contract has been entered into, to provide for use of the priced Bills of
Quantities in the valuation of the work.
12.3.2.7 Drawings
Ideally drawings should detail all the contract work. For many reasons this is not
always practicable, but tenderers must be given sufficient information to enable them
to understand what is required and thus submit considered tenders. All available
information on the topography of the site and the nature of the ground should be
made accessible to tenderers, preferably by being shown on the drawings.
forward claims for increased rates during the contract. It is in the interest of both
Employer and Contractor that as much detail as possible should be made available to
the contractor for him to price his tender.
The form of Agreement is a legal undertaking entered into between the Promoter and
the Contractor for the execution of the work in accordance with the other Contract
Documents.
The form of tender and acceptance of it are all that is necessary to form a binding
contract. The Form of Tender actually provides for this. To complete the
formalities, a contract is normally signed after the contract has been entered into.
12.4.3.1 General
In this manuscript, we will discuss the latest addition of the FIDIC Conditions of
Contract (commonly referred as FIDEC 1999). The reason for choosing these
conditions of contract is based on the fact that there are the conditions of contract
used in most of the internationally tendered projects. However, before we discuss the
FIDIC Conditions of contract, it is necessary to examine briefly the history of FIDIC.
The first edition of the Red Book for civil engineering works, was published in 1957.
The fourth edition was published in 1987 and this edition has been reprinted twice, in
Selection of Contractors and Management of Works Contracts 395
1988 and in 1992, with editorial amendments. The latest FIDIC conditions of
contract, on which the rest of the presentation in this chapter is based, was published
in 1999.
The essential feature of this contract, unlike the so-called lumpsum contracts is that it
creates a re-measurement or measure and value contract. The Contractor is paid at
the rates for the actual quantities of work executed.
Under FIDIC Conditions parties involved in the contract are the Employer and the
Contractor. They are supported by the Engineer on the administration of the contract.
The Employer
The Employer gives all authority for the administration of the contract to the
Engineer. The Employer's functions are restricted to paying the Contractor sums of
money certified by the Engineer, and agreeing to matters that require a change to
contract itself.
The Contractor
General obligation
The Contractor is the person whose tender has been accepted, and is the second party
to the contract. The Contractor is fully responsible for the construction of the works
and their security until they are taken over by the employer. The Contractor general
obligation is to construct, complete and maintain the works, and to supply everything
that is required for their completion.
Safety of people
The Contractor is responsible for the safety of all people on the site and for the care
of the works until the issue of the certificate of completion. He is responsible for
398 Fundamentals of Civil Engineering Construction Management
seeing that the works are no danger to anyone. He must supply lights, fences,
warning signs and, if necessary watching.
Contractor's Superintendence
The Contractor is required to provide all necessary superintendence, which means
site management, and is required to appoint competent and authorised agents.
Contractor's Rights
Having mentioned the above list of obligations that the Contractor has towards the
contract and therefore to the Employer, let us briefly summarize some of his rights: -
The Contractor has right to prompt and full payment of certificates from the
Employer;
The Contractor has right to prompt and full provision of all construction details
from the Engineer;
Selection of Contractors and Management of Works Contracts 399
The Contractor has the right to prompt inspection and approval of the works by
the Engineer;
The Contractor has the right to claim from the Engineer for delays causing loss
and expense; and
The Contractor has the right to claim from the Engineer for extension of time.
As stated earlier, the Engineer is not a party to the Contract, but derives all his
powers to control the Contractor from it. Sometimes he is described as 'a creature of
the Contract'. This is because the Contractor agrees in the contract to accept
decisions and directions from the Engineer. It follows therefore that the Engineer is
only able to instruct the Contractor provided one of the clauses in the contract gives
him that power.
The Engineer derives his power to act as agent for the Employer from his contract
with the Employer for the design and supervision of works.
Engineer’s general powers to instruct include:
obligation to issue further drawings to the Contractor which he thinks in his
opinion are necessary for proper execution of the works;
obligation to ensure that the works are executed by the Contractor to his
satisfaction;
it is important to note that the Contractor is required to take instructions only
from the Engineer and not from the Employer;
in addition to general powers discussed above, there are other specific powers
given to the Engineer. These include:-
- Appointing of Engineer's Representative;
- Appoint assistants to the Engineer's Representative;
- Delegate powers to the Engineer's Representative;
- Consent to sub-letting;
- Correct ambiguities in the documents;
400 Fundamentals of Civil Engineering Construction Management
Engineer's Representative
The Engineer's Representative, can be appointed by either the Engineer or the
Employer, but it is the Engineer who in either case, has to notify the Contractor in
writing of the name of the Engineer's Representative and the functions he is to
perform. Until the Contractor has been notified in writing, the Engineer's
Representative has no powers under the contract.
Without delegated powers from the Engineer, the Engineer's Representative may
only inspect the works, and see that they are carried out in accordance with
specification and the contract. However the Engineer may delegate to the Engineer's
Representative most of the powers vested in the Engineer under the contract. If he
does delegate his powers, such delegation has no effect until the Contractor has been
notified in writing of the matters delegated. It is important that the Contractor also be
informed of any restrictions placed upon the Engineer's Representative in respect of
such delegation.
402 Fundamentals of Civil Engineering Construction Management
There are however specific limitations on what may be delegated. The Engineer may
not delegate under the following:
valuation of costs of delay for artificial obstructions and adverse physical
conditions;
award of extension of time;
issue of the completion certificate;
the certification of the final certificate;
the issue of maintenance certificate;
certification of the Contractor's default; and
settlement of disputes.
Most of the details on payment procedures are normally given in specific conditions
for Particular Application. The details include matters concerning advance
payments. How and when they should be made together with method to be adopted
for repayments.
Interim Certificates
A contractor is entitled to monthly account payments for work carried out. The work
is valued at the rates in the Bills of Quantities. The Contractor makes out his monthly
statement and sends it to the Engineer, who then checks it and certifies the money
due.
After the receipt of the monthly statement, the Engineer must certify and the
Employer pay within a fixed period, or else the Contractor is entitled to interest.
The Employer can terminate the services of the Contractor upon giving 14 days'
notice in writing without voiding the contract when the contractor becomes bankrupt
or when the Engineer shall certify that the contractor has defaulted in any of the
following items:-
has failed to remove materials from the site or to pull down and replace work for
twenty eight days after receiving from the Engineer written notice that the said
materials or work has been condemned and rejected by the Engineer, or
despite previous warnings by the Engineer, in writing, is not executing the works
in accordance with the contract, or is persistently or flagrantly neglecting to carry
out his obligations under the contract, or
has, to the detriment of good workmanship, or in defiance of the Engineer's
instructions to the contrary, sub-let any part of the contract.
Termination of the services of the Contractor does not terminate the contract and the
parties are still bound by its terms. Procedures for valuation and payments forfeiture
are set out but all the foregoing does not relieve the Contractor of his obligations
under the contract. Where Employer cannot fully recover from the Contractor, the
Performance Bond affords additional security. To cover for the continued use of
plant and materials brought on site by the Contractor in such eventuality provision
for vesting the Employer's interest in the said plant, temporary works and materials.
The Contractor can similarly terminate his employment after giving 14 days notice to
the Employer with a copy to the Engineer should the Employer be in breach of
contract in the stated events mentioned below: -
fails to pay the Contractor the amount due under any certificate of the Engineer
within thirty days after the same shall have become due under the term of the
contract, subject to any deductions that the Employer is entitled to make under
the contract, or
interferes with or obstructs or refuses any required approval to issue of any such
certificate, or
becomes bankrupt or, being a company, goes into liquidation, other than for the
purpose of a scheme of reconstruction or amalgamation, or
gives formal notice to the Contractor that for unforeseen reasons, due to
economic dislocation, it is impossible for him to meet his contractual obligations.
Selection of Contractors and Management of Works Contracts 405
Such termination will not relieve the employer from his obligations to pay the
contractor nor prejudice the right of the contractor to exercise any other rights or
remedies he may be entitled to either in lieu of or in additional to the rights and
remedies.
After the determination the contractor must promptly remove huts, plant, tools and
materials that have not been paid for by the employer. Cost of such removal,
including demobilisation of personnel as well as direct loss or damage to the
contractor and/or any terminated subcontractor is recoverable.
12.4.3.6 Variations
The Engineer can order a variation to the works. He may not order variations to
the contract, which can only be done by agreement between the Employer and
the Contractor;
The Engineer "shall" order variations that are necessary for the completion of the
works. Such a requirement is mandatory; and
It must be remembered that the power to order variations is restricted to
variations in the works. The works are defined in the contract and are usually
described in brief description at the beginning of specification, or Bills of
Quantities.
The Engineer therefore cannot order work that is not defined within the scope of the
contract. If he does, he is acting outside his powers, and two things follow:
The Contractor need not carry out the instructions, and
The Employer need not pay. The Contractor's only right then would be to sue the
Engineer personally for the cost of the work. Alternatively, the Employer might
be able to sue the Engineer for the cost to him of such works.
Variations must be issued in writing, and the contractor has the right to confirm
verbal instructions from the Engineer. Such confirmation is itself defined as an
Engineer's Instruction
Normally at the time the Contractor submits his tender he is very conscious of the
time available within which he required to complete works. If he fails to complete
the Employer is entitled to deduct liquidated damages at the agreed amount in the
appendix of tender.
There are three categories of delays that may happen in a construction project:
a) Delays that are the Employer's fault, for example, delays in respect of variations
ordered by the Employer, late instructions by the Engineer etc.;
b) Delays that are no one's fault, for example, exceptionally adverse weather
conditions, strikes, lockouts, riots etc.; or
c) Delays are Contractor's fault, for example, brought by inefficiency or bad
planning or programming.
The FIDIC Contract does not allow for extensions of time where the delay is the
direct fault of the Contractor.
The FIDIC Contract gives events, which, if they occur, and cause delay, may entitle
the Contractor to an extension of time. The events referred to are the following: -
The amount or nature of extra or additional work;
any cause of delay referred to in the conditions e.g.:
- adverse physical obstructions or conditions;
- discovery of fossils etc;
- contractor carrying out tests which show the work is in accordance
with contract;
- engineer suspending the works;
- employer failing to give possession of the site
408 Fundamentals of Civil Engineering Construction Management
If any of the above occur and are such as to fairly entitle the Contractor to an
extension of time, the Engineer after due consultation with the Employer and the
Contractor shall determine the amount of such extension and notify the Contractor
accordingly.
However, the Engineer is not bound to determine an extension of time unless the
Contractor has:
within twenty eight days after the event having first arisen notified the Engineer
with a copy to the Employer; and
within twenty eight days or such other reasonable time as may be agreed by the
Engineer, the Contractor must submit detailed particulars of any extension of
time to which he may consider himself entitled in order that such submission can
be investigated at the time.
Interim extensions
There is a further provision that where the event has a continuing effect so that it is
not practicable for the Contractor to submit detailed particulars within twenty eight
days he shall nevertheless still be entitled to an extension of time provided he has
submitted interim particulars at intervals of not more than twenty eight days and the
final particulars within twenty eight days of the end of the effects resulting from the
event. When the event has ceased to operate, the Engineer carries out a final review
which cannot however result in a decrease of any extension of time already given.
difference between the Employer and the Contractor then they must refer their
dispute or difference to the Engineer to make a decision. The reference to the
Engineer could well of course and often is the result of the Engineer’s owns decision
contained in an instruction or opinion etc. In this case the Engineer will have to
review his own decisions and if he agrees with it he must say so and similarly if he,
upon reflection, changes his mind and disagrees with his earlier instruction or
opinion or decision then he must say so.
It is in this relation that the independent role of the Engineer is absolutely vital and it
is exactly this situation that the Employer in practice brings great pressure to bear
upon the Engineer who of course he pays.
If either part is dissatisfied with the decision of the Engineer then they can give
notice of arbitration and provided this is done within seventy days of the decision
being given they can take the matter before an Arbitrator. If they miss the time limit
they may find themselves completely time barred.
Chapter 13
Insurance Requirements in
Construction Industry
13.1 Introduction
It has been recognised that construction industry is one of the micro sectors of an
economy of a country, which accounts for not less than 15% of the GNP of both
developed and developing countries. It is hardly possible to site any economic
venture that does not pre-require construction investment. Construction work by
nature is hazardous, and accidents are frequent and often severe. The annual toll
of deaths, personal injuries and property damage in the world construction
industry is extremely high. The potential severity of accidents and the frequency
with which they occur require that consultants and contractors protect themselves
with a variety of complex and expensive insurance coverage. Without adequate
insurance protection, the contractor would be continuously faced with the
momentary possibility of serious or even ruinous financial loss.
Insurance Requirements in Construction Industry 411
A history of the earliest civilizations reveals that mankind has an early instinct to
develop and perfect codes of conduct. The valley between Tigris and Euphrates
rivers in present day Iraq is considered as the cradle of civilization, and some of
the earliest codes of conduct were developed there. These codes covered all forms
of activity, including exchange rates, wages, rules of behaviour, physical and
monetary penalties, and even specifications for materials. As far back as 2000
BC, the Laws of Eshnunna decreed:
58: If a wall is threatening to fall and the authorities have brought the
fact to the knowledge of its owner, (if nevertheless) he does not
strengthen his wall, the wall collapses and causes a free man’s death,
then it is a capital offence; jurisdiction of the king.
The Code of Hammurabi, circa 1700 BC, also contained punitive construction
codes:
412 Fundamentals of Civil Engineering Construction Management
229: If a builder constructed a house for a seignior1, but did not make
his work strong, with the result that the house that he built collapsed
and so has caused the death of the owner of the house, that builder
shall be put to death.
230: If it has caused the death of a son of the owner of the house, they
shall put the son of the builder to death.
231: If it has caused the death of a son of a slave of the owner of the
house, he shall give slave for slave to the owner of the house.
The present day construction codes are basically derived form the past codes
of conduct, but enriched with experience and modern scientific research
outputs. The development of insurance has also its own part in history. For
instance, Marine insurance is considered to be the oldest known type of
insurance. Something similar to it was practiced at least 1000 years before the
Christian era while the present day form of marine insurance probably began
around the eleventh or twelfth century. The early development of life
insurance was closely linked with that of marine insurance. The industrial
revolution in Europe necessitated the development of fire and accident
insurances. Then came motor, engineering and aviation insurances (Hansell,
1974). In all cases, community based activity is considered as the origin of
modern age insurance which grew as a huge commercial sector covering a
wide range of policies in all spheres of engagement. Despite the advancement
1
A man of rank or authority.
Insurance Requirements in Construction Industry 413
Whilst insurance exists, in principle to combat risk, there are certain legal,
commercial and moral considerations which make it impossible to insure every
conceivable kinds of risk. In addition to the common law of contract, the
following rules in particular are considered to be the basic principles of insurance:
a) Utmost good faith (Uberrimae fidei): In an insurance contract the principle
of Utmost good faith applies. The proposer must disclose all material facts
to the insurer;
b) Insurable interest: The insured must have an insurable interest in the subject
matter of the insurance. The subject matter of the insurance can be property,
life, potential liability, etc.;
c) Subrogation: This means that the insurer after paying a claim has the right
of standing in the place of the insured and availing himself of all the rights
and remedies of the insured whether already enforced or not, but only up to
the amount of the insurer’s payment to the insured;
d) Indemnity: Most policies are indemnity policies. This means that the object
of these insurance’s is to place the insured as nearly as possible in the same
position after a loss as he was immediately before the happening of the
insured event;
414 Fundamentals of Civil Engineering Construction Management
When looking at an insurance policy look first at: Who is insured? What risk is
insured against? What period is the policy effective over? These are vital since a
person cannot claim under a policy unless,
a) he/she is insured by it (or some other reason is entitled to enforce the
policy);
b) the loss was covered by the insured risk; and
c) the policy was effective at the time of the occurrence of the event leading to
the loss.
Only when these points have been checked is it worth going on to the small print
which will include other important details such as: limitation of time for notice of
a claim; amount of cover available and whether an excess payment by the insured
is applicable.
Due to the fact that different bodies are involved in a typical civil engineering
project (clients, consultants, contractors, sub-contractors, suppliers, employees,
financiers, member of the public, etc.), it is important for every body to be sure
that insurance is given proper attention and covers the expected risks
satisfactorily without paying for unnecessary cover or duplication of cover. It
reflects obviously on the professional competence of the insurer to discover after
Insurance Requirements in Construction Industry 415
the occurrence of some disastrous event that the insurance premium one has been
paying did not cover the incidence.
Design
Construction Maintenance
A B C D E F G H
I J K
L M N O P Q R S T U V
One weakness in the system is that the client has usually to prove negligence. A
more important weakness in this system is that the PI insurance may be valid and
adequate but might be discontinued after construction was completed. Thus a
latent design fault, which was discovered after completion of construction and
after the PI insurance policy had been allowed to lapse, would not of course be
covered. The designer would still be liable. Most consultants in the developed
countries do of course keep this PI insurance policy continuously running.
This policy covers loss or damage from what so ever cause to the contract works
or materials whilst on the contract site(s) and in use in connection with the
contract during the performance of the contract and the period of maintenance.
The FIDIC (Fédération Internals des Ingénieurs Conseils: International Federation
of Consulting Engineers) Conditions of Contract require the Contractor to take
out such a policy in the joint name of the client and the contractor. The policy is
“All Risk” and is therefore all-inclusive, with the exception of what are called the
“Excepted Risks”, meaning not accepted.
This policy covers loss or damage to third party persons or property arising out of
the construction or maintenance of the works. As the name indicates, third party
Insurance Requirements in Construction Industry 419
means anyone who is not a part of the insurance contract. The FIDIC Conditions
of Contract require the contractor to take out such a policy.
Consultants shall be liable for any damage that could arise due to their failure in
design works. They should be insured or indemnified by insurance should claims
arise against their work for professional duty (self protection). Unfortunately,
most consulting firms are not willing to shoulder this responsibility and are not
ready to buy Professional Indemnity insurance policy. Some of them even
consider insurance as a redundant act and not as a part and parcel of their
business. In the Ethiopian context, contractors are required to have at least a
Performance Bond. Though lasts usually for only one year, contractors
performance bond acts primarily for the protection of the owner to check whether
his structure is built in accordance with the terms of the contract.
Since most of the time clients do not have the proper knowledge of insurance they
do not ask for adequate insurance coverage from the construction firms they
select for their projects. Clients should keep in mind that it is absolutely essential
to check for sufficient insurance coverage of the professionals involved in their
project, in case they have to be indemnified. There were numerous cases
worldwide where consultants and/or mainly contractors have no money to pay
during indemnity. Consultants, who act on behalf of clients are responsible to
help their clients by giving them technical and managerial assistance. It has now
become normal, especially in the developed world, to appoint Management
Consultants, who act on behalf of the client and help in selecting competent
consultant and contractor, and administer the project without involving
themselves directly in the design and construction works.
The above points reveal that the major parties in the construction industry, i.e.
clients, consultants; contractors, concerned local and federal government
authorities; law makers, financiers, etc. share responsibility for the non-existence
of appropriate insurance guidelines in the construction sector of a nation.
Moreover, systematic efforts have to be made by insurance companies to
Insurance Requirements in Construction Industry 421
advertise and impress upon the public and the concerned parties on the need for a
relevant insurance cover in the construction industry.
It has thus become clear that the need for suitable insurance policy is, therefore,
unquestionable to satisfy the interest of the client; to achieve the required quality
and standard; to provide safety of the workers and the general public during and
after construction, and for proper utilization of the nations resource. A study made
in the Ethiopian construction sector indicates that most of the construction firms
are making their business with no or without adequate insurance coverage. Some
of the reasons for not having the required insurance policies are summarized as
follows:
a) Lack of proper understanding on the importance of relevant insurance
policies by construction firms and their clients; lawmakers; legal
professionals and the society in general;
b) A tendency to underestimate the risks associated with construction projects
by all parties involved in a construction project;
c) Construction firms are not required by their clients/consultants or by the
concerned authority to provide adequate insurance coverage;
d) Most construction firms do not have a well-organized management system
that can evaluate the risk involved in a particular project;
e) Contractors are reserved to buy insurance policy(ies) unless they are
required to procure one or more policies;
f) Some important policies, like the Professional Indemnity insurance policy,
are not understood by the society in general, by designers/consultants and
even by some insurance companies in particular;
g) Premiums of some insurance policies are very expensive; and
h) Insurance companies are not efficient in responding to client’s claims.
Based on the results of the study, made in the Ethiopian construction sector the
following recommendations are forwarded to ensure a better appreciation for the
risks associated with the construction of civil works:
a) Prior to finalization of tender documents, clients should appoint duly
422 Fundamentals of Civil Engineering Construction Management
d) All parties in a construction project should accept that some risk is attached
in their activity;
g) The duty and functions of consultant and contractors in realizing the interest
of the client should be properly defined;
14.1 Introduction
Claims are an inevitable fact of life in the construction industry. Whether in local or
international contract projects, the issue of claims remains the same. In the context of
civil engineering projects, claims are requests or demands for payment of money or
request for time extension or both to which a contractor believes, rightly or wrongly,
he/she is entitled. They result as a consequence of various factors. Some of them are
due to incomplete information in the initial tendering documents, unforeseen
circumstances, and inadequate contract administration. There have been significant
occurrences of claim cases in major international construction contracts in Africa.
Some have been handled by international arbitration, while the rest are settled locally.
The nature of civil engineering projects makes them unique in that they are site
specific and custom built. No standardized approach can be utilized in all cases. This
makes it difficult to tell ahead of time exactly how a project will turn out or how much
it will cost. Upon execution of the contract, many unforeseen circumstances and
problems arise that necessitate revision of the work progress and rectification, usually
at a given cost. Hence, the issue of claims arises.
424 Fundamentals of Civil Engineering Construction Management
The current trends of globalization and the free trade agreements being ratified by
many nations have encouraged the participation of many contractors in the
international construction industry. Han et.al. (2001) argued that “International
construction markets have changed dramatically during the last decade. Agreements
such as the Uruguay Round in the General Agreement on Tariffs and Trade (GATT)
system have fundamentally changed the structure of the construction industry.
Signatories to the GATT system have to open their domestic markets to foreign
competition
The basic features of a project may remain the same regardless of the geographic
location. The elements of culture, governmental issues (such as importation, taxation,
foreign currency transfer policies etc.), financial (exchange rates) requirements,
Claims and Dispute Resolution Mechanisms in Construction Industry 425
Projects will also be located in different places with varying conditions of accessibility
and availability of data related to the projects. These factors will also play a crucial
part in the implementation of the project. In addition to this, major civil engineering
projects require the participation of many trades and specialties adding to the
complexity and the involvement of many specialist companies. In major international
projects, financers usually require that loans be disbursed according to their
requirements and international contractors also prefer to be administered on
internationally recognized and accepted legal documents.
Many major civil engineering projects in most of African countries are financed
through loans with bilateral or multilateral financial arrangements whereby the
financing agencies cover a major portion of the financial requirements whilst the
respective government normally covers a small portion of the total project cost, in the
range of 10-20 %. One of the most important steps in the implementation of a civil
engineering project is the selection of a suitable contractor, with the requisite financial
and technical expertise to accomplish the project objective. In many cases, financing
agencies require competition as an aid to selecting competent contractors and many
construction contracts are awarded on the basis of competitive bidding. Among the
major financing institutions of the world, the World Bank the International Monetary
Fund, (IMF) and the African Development Bank (ADB) occupy a central role.
A contract is called international if the parties concerned have their places of business
or habitual residence in different states (Bunny, 1991). This may mean that a
426 Fundamentals of Civil Engineering Construction Management
contractor residing in yet another country may build a project financed by an agency
whose official residence is outside the home country of the client. Few international
construction projects, therefore, take place today without bilateral or multilateral
financing and often both are utilized (Jaynes, 1991). Bilateral agreements involve the
agreement of two governments; whereas multi lateral agreements involve more than
two governments. Whenever such financing is available, the lending institution
normally requires some procedures to be carried out in the implementation of the
works.
The basic document in a project is the contract document, where, requirements of the
work, the duties and responsibilities of the parties concerned are set out in detail. The
type of the implementation of the project dictates the form of the contract. For
instance, Article 1675 of the Ethiopian civil code, for example, defines contracts as “A
contract is an agreement whereby two or more persons as between themselves create,
vary or extinguish obligations of a propriety nature”.
Article 1678 further states that “No valid contract shall exist unless,
(a) the parties are capable of contracting and give their consent sustainable at law;
(b) the object of the contract is sufficiently defined and is possible and lawful; and
(c) the contract is made in the form prescribed by law, if any.”
Furthermore, Article 1679 stipulates “A contract shall depend on the consent of the
Claims and Dispute Resolution Mechanisms in Construction Industry 427
parties who defined the object of their undertaking and agree to be bound thereby”.
Hence the law defines it as an agreement. That means two parties agree voluntarily to
define an agreement between them, with full consent. Such consent is also to be
documented in written form. The provisions of the Ethiopian law are based on such a
stipulation. As in Ethiopian law, forms of international contracts basically follow the
same principle. This is very much the same in countries in the East, Central and
South African region. Fundamental to the contract is the principle that it is a binding
legal document. This means that, all activities agreed upon by the parties must be
carried out. It is not possible to dismiss terms or requirements merely because they are
onerous or overlooked (Heisler, 1994).
In international projects the same principles apply. The form of agreement or contract
takes more or less the same form. Whilst the basis of voluntary agreement (consent of
both parties and capability of contracting parties to carry out their agreement) is valid,
the form of contract and the settlement of disputes, if any, are to be carried out in
international terms and conditions. There are a number of international contract forms
specifically designed for international construction contracts to be carried out outside
the home country of the main contracting company. This is done to mediate the
variability of the laws of the home country of each partner in the construction contract,
as well as to give a fairly broad coverage so that both parties know their obligations.
Some of the currently available forms of construction contracts include, the FIDIC
form, the ICE and the AIA conditions of contract.
In normal circumstances copies of the proposed contract documents are issued as part
of the tender documents to the tenderer so that they are aware of the provisions of the
contract. This is further updated or amended as required during the tendering and
negotiation period. A contract in itself, however, does not achieve anything without a
qualified contract administration expertise.
After contract provisions have been completely discussed, agreed
428 Fundamentals of Civil Engineering Construction Management
The basic contract documents will normally contain the agreement between the owner
and the contractor, conditions of contract, construction drawings, and specifications.
Also included in the contract documents are addenda issued prior to implementation of
the contract and other documents, which may be listed in the agreement, and any
modifications, issued after execution of the contract.
There are many types of contract forms in the administration of civil engineering
projects the most common ones and those widely used in the African construction
industry include: measurement form of contract, Build-Operate-Transfer (BOT),
Turnkey, Lump sum form of contract.
In this form of contract, the contractor is paid based on the amount of work he does, as
compared to the prices detailed in the Bills of quantities (BOQ). This is the most
widely used form of contract for both local and international contracts in most of
African countries.
This is a form of contract where the contractor builds, operates and transfers (BOT)
the project to the client for a fee. This type of contract is also widely used in the
developed world where the capacity of contractors in executing projects on their own
finance is very high.
Claims and Dispute Resolution Mechanisms in Construction Industry 429
In this form of contract, the contractor agrees to do the job for a fixed sum. In this
case the contractor is responsible for the preparation of all details.
In order to streamline the diverse activities in the construction sector there have been a
number of attempts to produce a standard form of contract for civil engineering works.
These standard forms of contract were initially drawn up by independent professional
organizations (Bunny, 1991) In Europe, and more particularly in the United Kingdom
and in Ireland such forms were produced as early as the nineteenth century. A standard
form for building contracts was used under the aegis of the Royal Institute of British
430 Fundamentals of Civil Engineering Construction Management
Architects (RIBA), some time towards the end of the nineteenth century. This led to
what became known as the 'RIBA Form’, which was published in successive editions
between 1909 and 1957. It later developed into what became known as the JCT form
(Joint Contracts Tribunal).
In civil engineering contracts, various forms were used by different employers prior to
the Second World War. These were combined by the Institution of Civil Engineers
(ICE), and the Federation of Civil engineering Contractors in the United Kingdom into
an agreed standard document. This was published in December 1945, and the
document was thereafter known as the General Conditions of Contract and Forms of
Tender, Agreement and Bond for Use in Connection with Works of Civil engineering
Construction, in short the ICE form. In January 1950 it was revised and issued with
the added agreement of the Association of Consulting Engineers, UK. Other revisions
followed later (Bunny, 1991).
To the credit of those responsible for drafting the ICE form, many professional
Institutions all over the world modelled their own conditions of contract on its text,
making only minor amendments to accommodate differences in local matters of law
and nomenclature. The ICE form was, however, drawn up mainly for the domestic
scene in the UK, and so in August 1956 the Association of Consulting Engineers in the
United Kingdom, jointly with the Expert Group for the Constructional Industries in the
UK, and with the approval of the Institution of Civil Engineers, prepared a document
for use outside the UK which became commonly known as the Overseas (Civil)
Conditions of Contract (The ACE form). Although in text and format this latter form
differed only slightly from the ICE form, there were some minor changes in forty
clauses as well as a small number of major alterations (Bunny 1991).
The ACE form as published in 1956 included a standard form of Tender, an Appendix,
Claims and Dispute Resolution Mechanisms in Construction Industry 431
and a standard form of Agreement. It was published in a blue cover, which helped to
distinguish it from the ICE form. It was perhaps the first standard form of international
conditions of Contract for civil engineering works. In concept and style, however, it
remained faithful to the original domestic form.
It had only been used for a short period of time when the Conditions of Contract
(International) for Works of Civil engineering Construction was published in August
1957. This was based on the ACE form described above, and was also published in
two parts. Perhaps because of its long title, in a very short time it became popularly
known as the 'Red Book' (its cover was printed in red). It was prepared by the
Federation Internationale des Ingenieurs Conseils (the International Federation of
Consulting Engineers, FIDIC) and the Federation Internationale du Batiment et des
Travaux Publics (the International Federation of Building and Public Works, now
known as the International European Construction Federation, FIEC).
As discussed above, and because of the concepts included in the FIDIC form of
contract, as a result of the many years of experience and input from different
professional organizations the FIDIC or “Federation Internationale des Ingenieurs
Conseils” has become a form of engineering contract that is becoming popular for
international projects. Prepared initially in 1958 it is now in its fourth edition, and
continues to be updated. The FIDIC form of contract is a development of the ICE form
of contract and in this form of contract, the Engineer plays a central role in the
administration of the contract and dispute settlement. As a widely used form of
contract in the international contracts in Ethiopia, the FIDIC form of contract endows
the Engineer to settle differences, or in some cases to give decisions on disputes that
may arise. Therefore as a primary administrator of the contract the Engineer is the
mediator between the owner and the contractor, which form the parties to the contract.
432 Fundamentals of Civil Engineering Construction Management
It has been repetitively stated that claims are inevitable in construction projects. They
may occur when the terms and conditions of the contract change in such a way that the
contractor is unable to recover expenses and profits. In other cases, when the
provisions of the contract documents and specifications lack clarity, a correct
interpretation of the documents may result in extra expenditure, which a contractor is
forced to cover through claims.
In some cases, where the form of contract transfers the risks to the employer rather
than to the contractor, the contractor may be tempted to claim. Such occurrences
happen depending on the form of procurement of the services. In the traditional form
of procurement of services, where the employer provides the designs and
specifications (prepared through a consultant) to the tenderers, the successful tenderer
may not assume the responsibility for the completeness of the documents and hence
may tend to claim for extra time and money, depending on the discrepancies that he
may discover in the contract documents. Being cognizant of this, the FIDIC form of
contract provides a number of clauses that entitle the contractor to claim for extra time
and money.
In the other form of contract, such as the BOT, and fixed fee forms of contract, the
design and construction of the projects is largely the responsibility of the contractor.
The risk is then transferred from the employer to the contractor, with the result being
lesser likelihood of the occurrence of claims.
rather than an antagonistic approach. Even then claims will still be unavoidable, but
such a step will go a long way into reducing them. The causes of claims are many and
varied. Depending on the particularities of site and geographic location they may have
differing causes and impacts.
It is a widely known fact in the construction industry that no civil engineering project
is completely designed so as to make any design changes unnecessary. So many
unknown factors make the execution of civil engineering projects at best
unpredictable. The contractor is, therefore, forced to cover himself against any
possible risks in his initial bid and later on to cover any financial losses through
claims. These facts are widely known such that current construction contract
documents make provisions for claim submission and resolution of such disputes.
Recognizing the inevitability of claims many international civil engineering projects
provide means of handling claims. In order to avoid ambiguity in the handling of
claims, the FIDIC form of contract sets out detailed procedures for claims. These
include:
that the contractor give his intention to claim within 28 days after the event
giving rise to the claim has first arisen, keeps contemporary records on the
claim issue, that the Engineer examines such contemporary records, That the
contractor submit detailed particulars of the amount claimed and the grounds
upon which the claim is based and finally the Engineer to make determination
based on the available contemporary records. It can also be noted that whilst
there is a definite time limitation for the submission of claims the contractor
may nevertheless withdraw his claims at any time.
Although there are many types of claims some of them may be classified and
discussed as follows.
These are Claims made under the expressed provisions of a contract fall under this
category. They arise and dealt with under the provisions of the contract. Such types of
claims form the largest part of claims and the terms of the contract define the
situations in which they may be made and how they may be handled. For instance the
employer may institute a design change, and if such an unforeseen event occurs there
is a procedure set out in the contract where the contractor may claim restitution by
submitting a straightforward contractual claim. Certain common breaches of contract,
such as denied access or late information are also covered by claims procedures
included within the claim clauses of the contract.
These claims are those which are either not made under the conditions of contract or
are those allegedly made under them but considered legally unenforceable by the
employer on the basis that they do not fall within their provisions Haswell et al.
(1989). Such claims are invariably concerned with the recovery of damages and even
though they may be outside the scope of the contract, they are nevertheless subject to
resolution within it.
The law of tort (from Tortum-latin for wrong) is concerned with civil duties and
relationships. Tort is a legal term used to describe the various wrongs, which may
give rise to civil proceedings, mainly in the form of an action for damages. Although
the law of tort regulates a wide variety of unlawful behaviour, those related to
construction include, nuisance, slander, libel, trespasses and negligence. For example,
Claims and Dispute Resolution Mechanisms in Construction Industry 435
excessive dust, noise, vibration, fumes, seepage, gasses, smoke etc. produced by
someone may expose him to liability for nuisance. The court may order the nuisance
to be stopped by an injunction or may award damages or both (Bunny, 1991).
Quantum Meruit claims are claims where work has been done but no contract or price
has been agreed. Then it may be claimed that the work should be valued and paid for
what it is worth. A quantum meruit claim may also arise, for example where work is
done on the basis of a letter of intent and there is no contractual liability.
These are claims made with no foundation in the contract or at law but only in a sense
of “fairness” or equity. Such claims depend upon ‘ex-gratia’ or 'kindness payments'
by the employer made in the particular circumstances; sometimes-such payments are
made to avoid or to terminate claims negotiations or a dispute. An ‘Ex-gratia’ claim
might be made to recover cost incurred by the contractor, the expenditure of which
gave benefit to the employer, but for which there are no grounds for recovery under
the contract.
One of the most common causes of claims in international contracts has been the late
issue of information and drawings by the consultant to the contractor. Most contracts
are carried out on the principle that the bidding documents include fairly adequate
details of drawings to enable the contractor to carry out the works but that working
drawings necessary for the implementation of the works be prepared on site by the
contractor. These drawings are then checked, approved and then returned to the
contractor for implementation. In the event that the contractor suffers delays due to
the late issue/approval of the drawings, then he may claim for it. Design changes may
436 Fundamentals of Civil Engineering Construction Management
In principle, fundamental changes in the overall design of a project should not occur,
unless there was a major oversight in the initial design preparation stage of the works.
In spite of this, however, there have been observations in numerous projects that
claims could result from the change in the design of the work. This type of claim can
be mitigated by investing adequate time and money in the pre-tendering and design
stages of the work. Such effort, among other things, will have to focus on obtaining
adequate site investigation reports and other pertinent data.
One of the major causes of claims in the developing countries construction industry,
particularly in international projects has been the late handing over, or rights of way
related issues. As indicated in the FIDIC, the contract documents do make a provision
in the event that the Client/Engineer fails to exercise his obligation in handing over of
the site, and thus causes the contractor to incur additional costs, the contractor is then
entitled to claim costs of delay. In such an event the contractor must produce evidence
that the costs that he claims due to the delay can be substantiated by an accurate
programming. In most cases, it may not be easy to accurately describe the delay
caused by programming. On the other hand, the actual delay due to the fault of the
Client/Engineer or that due to the contractor's own fault must also be clearly
differentiated.
In most international projects in developing countries, this has been the most common
form of cause of claims. It stems partly from a wrong understanding of the provisions
of the contract, and the desire to start the work as soon as possible. Whilst the
provisions of the contract demand that the site be handed over in a reasonable time,
Claims and Dispute Resolution Mechanisms in Construction Industry 437
most clients do not seem to understand the depth of the problem that a late handover
may cause. This apparent contradiction has been the cause of claims in some projects.
Such changes are changes, which arise from acts that are directly attributable to the
owner. Such acts result in more work or more time on the work and for which the
owner may not grant a formal variation order.
A contractor may be required to accelerate the works, when the owner requires that the
works be completed sooner than is required by the contract or orders a work to be
finished on the original completion date but fails to grant time extension, despite
entitlement.
Perhaps the most extensively used clause for the submission of claims in the civil
engineering industry relates to the clause referring to unforeseen site circumstances.
The intention of this clause is that a contractor is not asked to price for unforeseen
risks and the client is also protected from high bid values that a contractor may submit
to protect himself. In essence therefore the inclusion of this clause contributes to a fair
administration of a contract.
438 Fundamentals of Civil Engineering Construction Management
The employer may for some reason, suspend the work, or terminate the contract. This
may be due to bad work or failure to perform, on the side of the contractor. If the
contractor can prove that the termination benefited the employer, then he may claim
profits on work completed and cost of demobilization.
Subsequent to the enforcing of a contract, legislation may be instituted that may cause
an extra financial burden on the contractor. In such a case he may argue that since he
was not aware of such legislation nor could he have been able to foresee its
implementation during the preparation of his tender, he has incurred additional
expenses for which he is requiring reimbursement. In many instances, contracts make
provision for certain items that may by legislation be varied during the course of the
contract execution. Such items include the costs of fuels and lubricants, which may
vary during the course of the contract and have a direct impact on the costs that a
contractor may incur for the execution of the works.
The FIDIC form of contract stipulates that in the event of exceptionally adverse
climatic conditions, the Engineer may (after due consultation with the employer and
the contractor) determine the amount of any extensions that may be granted to the
contractor.
14.8.9.1 Additions
Directed variations are variations resulting from the Engineer’s directions changing
the quantity, quality of work or the time of execution and sequence of the works.
Traditional forms of contract in the construction industry are based on a re-
measurement type of contract. This means that all the parties to a contract agree that
the quantities are estimates only and that the actual money to be paid will be based on
the site measurement of quantities.
As a favoured form of contract administration, this has now come into picture in most
international contracts in Eastern and Central Africa. Whilst it gives a measure of
control on payment certification, in that the actual money paid out reflects that of the
actual work done, nevertheless, there is a negative side to it that the quantities in the
initial (tendering period) bills of quantities may not reflect the actual site quantities.
In such an event, should the actual quantities exceed those of the bills of quantities by
a substantial amount or by a certain percentage (15% in the case of FIDIC) most
contracts provide a means whereby the contractor is reimbursed for his additional
costs through the suitable adjustment of the contract rates. This is done on the
assumption that the rates that the contractor assumed in the preparation of the tender
are no longer applicable since the quantities have significantly changed. This is
usually done through the revision of applicable bill rates.
440 Fundamentals of Civil Engineering Construction Management
14.8.9.2 Omissions
Whilst it is understandable that the addition of a significant volume of work may give
rise to claims on the grounds that the contractor demand that the previously agreed
rates be revised to reflect the change of the volume of work, there is also another case
in which the omission of a significant volume of work will give rise to claims on the
basis that the contractor is forced to scale down or keep idle equipment and manpower
which may cause extra cost.
The Engineer decides on the validity of claims. He may accept the claim in full, or part
or reject it totally. If the contractor does not accept the Engineer’s ruling on a claim,
then he is always able to take the matter to arbitration if contractual or to arbitration or
litigation if extra contractual. Once a claim is settled it ceases to be a claim. There are
two distinct stages in the assessment of claims:
Contractual claims must be based on contract document. It is important to see what the
contract says – not what you think it ought to say or what you would have liked it to
say, or even what you think is fair. The contract was agreed between both parties to
the contract and it is taken to be a statement of the terms of the contract. If the contract
states that the contractor is to be responsible for something, then the contractor is
responsible however unfair it may seem later.
The majority of claims involve delay of some form. Time is particularly important
since a contractor is bound by the contract to construct the works in a specified time
and is liable to pay liquidated damages for late completion. Acceptance by the
engineer of the validity of a claim for extension of time means that the contract
completion date is extended.
If delay occurs for which the client is responsible, then the contractor will be entitled
to an extension of time. If, as a consequence, the contractor incurs extra costs then he
will be entitled, in general, to reimbursement of those extra costs.
442 Fundamentals of Civil Engineering Construction Management
If delay occurs for which the client is not responsible, then the contractor will not be
entitled to compensation although he may be entitled to an extension of time. He may
be entitled to an extension of time in cases of strikes, bad weather, etc. He would not
be entitled to an extension of time because of his own incompetence, or breakdown of
his plant since these are supposed to be within his control.
Once the validity of the claim has been accepted then consideration can be given to the
valuation of claim. If costs cannot be claimed there may be little point in calculating
them.
This is a matter of assessing what were the actual costs incurred and how much did
these exceed those that would have been payable if there had been no reason for the
claim. If, as an example, 200m3 of concrete Grade C-30 were specified and if the
engineer instructed the contractor to use Grade C-40 instead, then the quantification
would consists of the extra cost of the Grade C-40 concrete over the Grade C-30 for
the 200m3.
Delays may be caused by the client (eg. Changing his requirement, late delivery of
drawings, etc.) or by the contractor (eg. Inadequate resources, use of unsuitable
methods, etc.) or be partially or totally outside the control of either party (eg. Political
change, weather, national strike, etc.). The contract, as previously stated, classifies
them into those for which the client is responsible and those for which he is not.
Claims and Dispute Resolution Mechanisms in Construction Industry 443
If a single cause makes a whole project stop, then it is reasonably easy to assess all the
costs unavoidably incurred as a result. Costs might include standing time of labour,
plant, including sub-contractors, actual cost of site overheads, staff, depreciation on
site items, maintenance, etc.
If a single cause stops only some operations, then it is more difficult to assess the costs
and/or delay attributable. Was the operation on the critical path or did it come on to it?
Standing time of labour, plant, etc. could be claimed but only insofar that they could
not be employed on other work. It is the duty of an injured party to mitigate the
damage so far as possible. Hence the contractor should try and use his idle plant and
labour elsewhere.
If an operation is stopped, there is not only the actual period of delay but there may
well be some allowance for regaining the tempo of the work. If an operation is slowed
down rather than stopped it may be convenient to assess an equivalent delay.
Calculation of the total period of delay and equivalent delay are shown schematically
in Figure 14.1 and Figure 14.2, respectively.
Expenditure
Plan Actual
A B
Time
Period of delay = A+B
A = Duration of cause
B = Allowance for regaining tempo of work.
Figure 14.1 Schematic representation of the total delay calculation.
444 Fundamentals of Civil Engineering Construction Management
Expenditure
A
Time
Frequently, there are different causes of delay, which overlap, and there is a problem
in assessing the different delays and costs attributable to each cause. A fundamental
principle is that if a job is totally stopped by one cause it cannot be any more stopped
by another cause – unless and until the original cause is removed or overcome. Table
14.1 shows the position for concurrent delays and whether a claim for extension in
time and/or extra costs would be allowable. It is to be noted that under different
circumstances, time and cost claims assessment can have alternative possibilities. The
schematic concurrent delays shown in Table 14.1, however, describe cases under
normal hypothetical conditions.
Claims and Dispute Resolution Mechanisms in Construction Industry 445
i) C.
E.
I.
Time:
Cost: No Claim for extra cost incurred.
j) C.
E.
I.
Time:
Cost: No Claim for extra cost incurred.
k) C.
E.
I.
Time:
Cost:
l) C.
E.
I.
Time:
Cost:
It is to be noted that in the table above, C stands for the Contractor; E for the Employer
and I for independent. In the event that financial claims are to be paid, costs of claims
can be generally classified as follows:
i) Labour: Total amount actually paid to the men including bonus, travel expenses,
lodging allowance, insurance, etc.;
ii) Plant: Depreciation rate, or cost of sending away and bringing back;
iii) Materials: Deterioration, storage;
iv) Sub-contracts: As i) to iii) above;
v) Site overheads: Actual costs – staff, depreciation of site huts, telephone, etc.;
vi) Head Office overheads: Actual costs; and
vii) Financing costs
In general the purpose of claims by contractors is to seek additional money over and
Claims and Dispute Resolution Mechanisms in Construction Industry 447
above the contract prices. For the Client, however, it means additional costs, which in
the end may make the project commercially unviable. Such a differing interest in the
execution of a project will inevitably lead to disputes. Considering the unavoidability
of such problems, dispute resolution mechanisms are placed in many forms of
contracts. Current dispute resolution mechanisms stipulated in the FIDIC forms of
contract place the Engineer as the central element in the dispute resolution mechanism.
Prior to an amicably negotiated settlement, the contract documents usually require the
contractor to place his claim demands at the jurisdiction of the Engineer. The
Engineer is also required to act impartially. Should both parties consider the decision
of the Engineer to be fair then the parties will agree to settle the issue. If one or both
parties, however, do not accept the decision of the Engineer, then an alternative
dispute resolution mechanism is instituted. This usually leads to negotiating amicable
settlement or finally to arbitration.
Such occurrences of claims are the source of disagreements and may sometimes result
in disputes that could lead to arbitration proceedings. In case a dispute occurs, forms
of contract, such as the FIDIC form, set out details of the submission and resolution of
claims. These can be summarized as follows:
a) Submission of claims by contractor;
b) Review of claims by the Engineer;
c) Decision by the engineer;
d) Negotiation and/or amicable settlement;
e) Disputes review expert/board; and
f) Arbitration.
The above stages of formulation and/or submission, assessment, repudiation,
negotiation of claims is in itself a complicated process. In order to avoid a
complicated costly and time consuming arbitration proceedings, parties to a contract
may institute an Alternative Dispute Resolution (ADR) as an option of claim
settlement mechanism, which may include (Bunny 1991): direct negotiation,
448 Fundamentals of Civil Engineering Construction Management
mediation, conciliation, mini-trail procedure, claims review board (CRB); and pre-
arbitral review board. In the event the above options fail, then, arbitration proceedings
may follow.
Settlement of disputes through arbitration is a very costly process. Before the case is
even heard in court, the parties to a dispute may spend a substantial amount of money
in legal fees. Besides the substantial amount of money spent in pursing legal ground
to the claim relations at work may be strained.
Being cognizant of such an effect on the overall project implementation, the FIDIC
form of contract provides for room for an attempt for negotiation to be implemented in
an attempt to carry out an amicable settlement. This is also a form of an out-of-court
settlement, and may maintain a conducive working atmosphere between all parties.
This form of negotiation or amicable settlement is carried out between the parties to a
claim, normally without a third party. In case the parties jointly agree to the
involvement of a third party, however, then this process is called mediation.
14.10.2 Mediation
In the event that direct negotiations fail, then a third party is involved as a mediator
between the parties to a claim and help in the settlement of the claim. A mediator
engages in the task of persuading the disputants to change their respective positions in
the hope of reaching a point where these positions coincide (Bunny, 1991).
14.10.3 Conciliation
Conciliation is a dispute resolution procedure where the parties sit together in the
presence of a third party to discuss the way out. Usually the conciliator will draw up
and propose a solution, which represents what, he believes, is a fair and reasonable
Claims and Dispute Resolution Mechanisms in Construction Industry 449
compromise of the dispute, after having discussed the case with the parties concerned.
14.10.4 Mini-trial
In this option of dispute resolution process, the parties to a claim appoint a neutral
person (such as a retired judge) who will give a non-binding decision.
The dispute review board usually consists of a three-member board, who are
independent of the contracting parties. The board is formed as soon as the contract is
signed. Each of the parties appoints one person and the two jointly assign a third
person. In times of disputes, the board gives recommendations as to their resolution.
through arbitration. This is enumerated through what is called the arbitration clause.
14.10.7 Arbitration
Whenever a dispute arose in a civil engineering contract, it was assumed that the
technical disputes require the involvement of technically qualified arbitrators. The
arbitration process was initially designed to give a speedy and inexpensive alternative
to the court system, which tends to become lengthy and expensive. Many disputes
that arise in contracts tend to contain substantial legal issues rather than technical
issues, necessitating the involvement of lawyers. In reference to this fact current forms
of the FIDIC contract contain what is called an arbitration clause. Such arbitration is
carried out under the rules of conciliation and arbitration of the International Chamber
of Commerce.
The FIDIC form of contract provides arbitration as a form of dispute resolution, and
unless otherwise specified in the contract, under the “Rules of Conciliation and
Arbitration of the International Chamber of Commerce by one or more arbitrators
appointed under such Rules”.
This provision does specify international arbitrators but does not rule out an alternative
dispute resolution arrangement in the host country. As an alternative therefore
building up a council of domestic arbitrators, will not only reduce the expenses
involved in the resolution of the dispute but will also contribute to the enhancement of
domestic expertise and speedy resolution of disputes.
The domestic law also needs to be enhanced to take into consideration provisions
related to administration of international contracts and resolution of related disputes.
This will also contribute to a healthy understanding of claims and create confidence in
their handling by avoiding the aversion to international arbitration and the tendency to
go for amicable settlement for fear of such an action.
At best claims are undesirable. They are not, however, avoidable. Besides incurring
unwanted legal expenses, they strain the relationship between all parties and affect the
working atmosphere. Each party sees the other as an enemy, which affects the future
of the works, and can result in the parties being defensive. In such an atmosphere
more claims may be inevitable.
The most significant effect of claims in international projects is the financial impact on
projects that have been a subject of such claims. Many cases can be cited where the
final project cost is over 50% more than the previously agreed sum. For instance, the
452 Fundamentals of Civil Engineering Construction Management
contractor for a large road project in the region has demanded about 40% of the project
cost. This will significantly increase final project cost.
In addition to the financial effects of claims on the total cost of a project, a significant
portion of claims focuses on the extension of time on project completion. In the
various international projects being carried out in region, there appears to be a
common perception of accepting time extensions more favourably than increased
financial expenses.
A study made in Ethiopia indicated that the majority of construction works carried out
by international construction companies have not been completed on time. Rather all
of them have been granted a time extension. Whilst time extensions may appear to be
necessary in some cases, few, if any, professionals view the issue of time extensions as
a serious claim case. In this aspect it is necessary to instil in the minds of the
practicing engineers and consultants that time extensions do also mean money. The
more a project is delayed the more costly it is and the income or revenue that may
have been obtained from a timely completed project is lost.
Another significant effect of the claim process is the effect it may have on the project
execution itself. Once the claim issues are referred to arbitration, the parties begin to
see each other as enemies and that will have a far greater impact, probably more
severe than the financial impact that will have on the total project life. Therefore
whilst maintaining a firm stand in the handling of possible claim cases, responsible
bodies should endeavour to maintain an atmosphere of good working relationship in
the interest of the project.
Claims and Dispute Resolution Mechanisms in Construction Industry 453
Kahsay (2003) studied selected major road project reports and consulted relevant
professionals and observed the following main points, which need to be given
adequate attention in all stages of construction:
1. One of the most critical and frequently appearing problems seems to be those
related to late handing over of site /rights of way problems. It appeared that
contracts are awarded to tenderers with out first of all clarifying the rights of
way problems. This has caused a number of disputes time extension and
financial claims, and has affected the time of completion of projects;
2. Difficulties associated with late issue of drawings and related information is a
frequent occurrence in many of the projects;
3. Delayed response to contractor’s claim, or related technical issues has been one
factor observed in the analysis;
4. Great differences between the actual site conditions and the conditions that the
contractor expected while referring to the bidding documents during tender
preparation. This may be indicative of incomplete bidding document
preparation;
5. The involvement of the Client in settling or giving a final decision in the issues
of claims, although it may not be advisable, on the basis of the FIDIC form of
contract;
6. The lack of sufficient trained manpower in the contract administration of the
projects has been a key problem. Not only has this contributed to the lack of a
proper administration of the claims but also contributed indirectly to
encouraging contractor’s to claim more;
7. Professionals involved in the contract administration sector lack proper training
in the areas of construction law. This has also contributed to delegating the
handling of the claim issues to the legal department. Has this been jointly
handled with the legal department in cooperation with the engineering
professionals with adequate training in construction law it would have
454 Fundamentals of Civil Engineering Construction Management
The FIDIC form of contract is prepared in light of international contracts held in the
developed world. In the context of developing countries, the documents need to be
slightly modified to take account of the local conditions. Although the FIDIC form of
contract takes this into account by providing a section for “conditions of particular
application” this section is normally prepared by the consulting Engineers, which are
in most cases foreign consulting firms and may not have detailed information in
respect of prevailing local conditions. This calls for possible modifications in certain
sections of the FIDIC form of contract. Accordingly, the following sections of FIDIC
deserves further considerations:
Duties of the Engineer: the duties of the Engineer in the authorizing of variation
orders or settlement of claims need to be limited to a given percentage of the total
project cost. Otherwise such decisions need to be carried out following the approval
of the Client.
Adverse weather conditions: the wording of this clause does not give particulars of
what an adverse weather condition means. It would be better if the particular weather
condition or the amount of rainfall were compared, say with the average amount in the
last 5-10 years. This will avoid subjectivity and address such claim issues properly.
Substantial completion: the wording of this clause is ambiguous and subject to
interpretation differences, therefore the term needs to be described in more clearer
terms so that no ambiguity is created.
Issuing a variation order: the authority of the Engineer to issue variation orders
seems to be open ended. Such a provision gives the Engineer a free hand in the
financial matters and may not be preferable. Therefore a financial limit needs to be
included. In the event that the variation order passes the limit, then the Engineer
should be required to seek the approval of the employer.
Chapter 15
Occupational Health and Safety
in the Construction Industry
15.1 Introduction
Occupational Health and Safety (OHS) is concerned with ensuring that work, working
environment, working tools/machines, working stations and the workers are in a manner
that will minimize occupational diseases, illness, injuries, accidents and fatalities. OHS
is the responsibility of employers (management), employees (workforce), government
and the general public to ensure that work is carried out in a safe and healthy
environment.
These include the Booth and Lee (1995) SMS model, attributed by four key functions
which are: Policy and Planning; Organization and communication; Hazard management;
and Monitoring and review. The British Standard BS 8800 (1996) SMS model whose
fundamental elements are Initial and periodic status review, Preparation of the Safety
Policy, Organizing of the activities, Planning and implementation, Measurement of the
performance, and auditing. Figure 15.1 below illustrates this model.
External Internal
Factors Factors
Policy
Audit Organizing
Planning and
Implementing
Measuring
Performance
The most recent SMS model is the one documented by ILO-OSH (2001). The core
elements of this model are; policy; organizing; planning and implementation; evaluation;
action for improvement. Figure 15.2 below illustrates this model.
460 Fundamentals of Civil Engineering Construction Management
According to ILO-OSH (2001), hazard refers to the inherent potential to cause injury or
damage to people’s health. It is therefore a condition with the potential of causing injury
to personnel, damage to equipment or structures, loss of material, or reduction of the
ability to perform a prescribed function. Whereas, risk, is a combination of the
likelihood of an occurrence of a hazardous event and the severity of injury or damage to
the health of people caused by an event. It is thus the chance of injury or loss and it takes
into account the likelihood of a loss and its magnitude.
Hazard identification
Identification of hazards usually is targeted to one or more physical areas of the
company and it can cover several different types of hazards. Depending on the
requirements, the analysis can be general or detailed. Some analysis techniques would
thus require more expertise than others. Checklists are the simplest techniques, which
can be used in simple analysis whereas for complicated analysis such as when potential
major accident hazards are assessed in a process plant, its analysis requires the use of a
systematic method and a group of several professionals, including plant engineers,
chemists and automation system experts. Commonly used methods for hazard
identification include workplace checklists and risk analysis methods.
Risk assessment
Risk Assessment is a method whereby the severities of the identified hazards are
evaluated. BS 8800 (1996) stipulates the basic steps of a risk assessment and these
include:
- identification of hazards;
- estimation of the risk from each hazard; and
- decision if the risk is tolerable.
After the hazards identification step, estimation of the risk from each hazard can be done
using a risk matrix as shown in Table 15.1.
Occupational Health and Safety in the Construction Industry 463
The last step of making a decision as to whether the risk is tolerable or not is indeed
difficult to define without a basis. Hence it is more practicable to determine which
activities the company should take in connection with each risk level. Appendix D of BS
8800 (1996), presents a table whereby each risk level is given actions and a time-scale.
organizations; the results of hazard and risk identifications and assessments; the result of
performance monitoring and measurements; the investigation of work-related injuries,
diseases, ill health and incidents, and the results and recommendations of audits; the
outcomes of management review; the recommendations for improvement from all
members of the organization, including the safety committee; changes in national laws
and regulations, voluntary programmes and collective agreements; new relevant
information; and the results of promotion programmes.
Safety Legislation
The purpose of safety legislation is to reduce the number of work related accidents and
ill health. Legislation can include state, provincial or national legislation, or the
conventions or recommendations of the International Labour Organization (ILO).
According to ILO, legislation should consist of Acts; Codes of Practice; and Guides. The
Factories Act comprises legal statements of the general health and safety principles and
responsibilities, made and approved by the government; therefore it is fully supported by
law. Codes of Practice provide general guidance to employers and workers on how to
comply with the minimum standards and objectives that are detailed in the regulations.
The ILO develops codes of practice, which many governments adopt for their
guidelines. While guiding, it provides official technical information and
recommendations to help employers comply with health and safety regulations. ILO
Codes of Practice generally contain practical recommendations intended for all those
466 Fundamentals of Civil Engineering Construction Management
with a responsibility for occupational safety and health in both the public and private
sectors. Codes of Practice are not legally binding instruments and are not intended to
replace the provisions of national laws or regulations, or accepted standards. They aim to
serve as practical guidelines for public authorities and services, employers and workers
concerned, specialized protection and prevention bodies, enterprises and safety and
health committees. Examples include Guidelines on Occupational Safety and Health
Management Systems, 2001.
Among the existing legislation, the Occupational Health and Safety Act, 2003 is the
main legislation making provisions for health, safety and welfare of persons employed in
factories and other workplaces and for matters incidental to, and connected with it. The
Act applies to factories and all other work places as defined under the Act unless
exempted by the relevant authority in accordance with the provisions of the Act. It has
an objective of making better provisions for health, safety and welfare of persons at all
workplaces in the country. While; the general principles remain the same, there are
slight variations from one country to another. It is important for practitioners to be
conversant with specific safety and occupational safety and regulations that apply in
their own countries.
Occupational Health and Safety in the Construction Industry 467
Ladders
- Ladders are main means of access on the construction sites. They often cause
accidents because they are misused. When using a ladder one should ensure that:
- it is in good condition and free from obvious defects;
- it is properly secured near the top and bottom, even if it is only in use for a short
period;
- it is set at the correct angle i.e. to be inclined at 1 metre horizontal for every 4
metres in height ( 1 in 4 ).
- it rises at about 1.0m above the landing position;
- it is properly positioned for safe access and it is standing on a firm, level base;
- when landing and using ladders, there are no overhead power lines in the vicinity.
468 Fundamentals of Civil Engineering Construction Management
Scaffoldings
- Falling is a major cause of fatal accidents in the construction sites and a large
number of such fatalities are falls from scaffolds. The law requires that scaffolding
work be carried out under the supervision of a competent supervision. Before using
a scaffold one should ensure that:
- it has been inspected and found to be in good condition;
- timber sole plates are used, of adequate dimensions to provide safe bearing;
- metal base plates are used under all standards;
- joints between tubes are staggered vertically and horizontally;
- the correct type of couples are used for all connections;
- scaffold boards are in good condition;
- standards are upright and set out in accordance with the sketches provided;
- alternate pairs of standards are provided with ledger bracing to the full height of
scaffolding. Exceptions may be made for bottom and top lifts where access is
required;
- the scaffold is adequately tied to the structure; and
- working platforms are fully boarded and complete with guard rails and toe boards.
Working on roofs
Working on roofs carries a high risk of accidents unless proper procedures are followed
and precautions taken. Before working on any type of roof one should know the rules
set out below and follow them:
- For work on a roof at a height from which men or materials can fall more than 2m
guardrails and tow boards must be provided along the roof edge. They must be
securely fixed in position and be of adequate strength;
- For work on a sloping roof of more than 30 degrees (or less than 30 degrees, but
which is slippery) crawling ladders or crawling boards must be provided;
- There may be circumstances where the use of a safety harness is the only safe way
of working. Such a decision will be made by management, and one must use the
safety harness in the conditions specified;
Occupational Health and Safety in the Construction Industry 469
- All opening in the roof must be securely covered or suitably guarded by guardrails
and toe boards. Any cover provided should either be securely fixed in position or
clearly marked to indicate its purpose;
- Access provided to the roof must be checked before use to see that it is safe and
sufficient;
- One must not pass across or work on very fragile materials without using ladders
of crawling ladders, or crawling boards or duckboards;
- One must not pass or work near fragile materials unless guardrails or suitable
covering is in position to prevent anyone falling through. It is illegal to walk along
a valley gutter or use the valley as a ladder support with fragile materials on either
side, if these precautions have not been taken; and
- If one has to pass across a sloping roof to get to their workplace, suitable and
sufficient crawling boards or ladders must be provided on the roof and used. All
ladders and crawling boards must be securely fixed in position. The anchorage at
the top of a ladder should not rely on the ridge cap but should whenever possible
bear on the opposite slope of the roof by means of a ridge iron, and, where
necessary and practicable, secured by rope as an extra precaution.
Excavations
- Under adverse conditions, most excavated grounds collapse, unless are temporarily
supported, safely battered back, or are geologically stable rooks. If the sides of an
excavation collapse accidentally while people are in, there may be no escape.
Death by crushing or suffocation, and injuries that cripple pelvis and legs, are
common to consequences of accidents in excavation.
- For excavation work, the following guidelines should be taken into account so as to
achieve and maintain a safe working place:
- Do not enter into an excavation unless it has been supported or inspected and
confirmed safe to do so.
c) Dangerous atmospheres can arise when there is a lack of oxygen or when toxic or
flammable gases are present. These may be due to exhaust gases from plant and
transport, chemical reactions in the ground, decomposition of sludge in a sewer,
leaks from gas mains, or the presence of petrol and various kinds of wastes from
factories and trade premised, welding operations and so on;
d) A deficiency of oxygen can render one unconscious, toxic fumes can cause
dizziness and a feeling of sickness, and gases can be flammable or explosive;
e) Adequate fresh air ventilation must be provided in appropriate circumstances;
f) All necessary safety and rescue equipment must be available on site at the actual
location. Check that it is so;
g) It is essential that no less than two persons work on a confined space operation. (it
is important to ensure that accident assistance is readily available);
h) When working at a manhole in the road or public area, ensure that guard stands are
provided and the appropriate traffic signs are displayed;
i) Ensure that assistance is readily available in an emergency (i.e. telephone or two-
way radio); and
j) If proper procedure for rescue in an emergency situation has been laid down with
specific jobs for specific persons, make sure that workers clearly understand what
they are required to do.
Refurbishing the existing properties has given rise to new health and safety problems. In
some cases the situation is made more difficult by the property remaining occupied
whilst refurbishment is being carried out.
When working in occupied premises, the health and safety of the occupants must be
considered as well as that of the workforce. In addition to all the above points the
following should be observed:
a. Do not block fire escape routes or access ways from occupied areas;
b. Do not leave toxic or dangerous materials or sharp tools unattended in places
where children have access;
c. If it is necessary to remove floorboards, warn the occupant and have the
floorboards replaced as soon as possible;
d. In housing, services will have to remain connected for the convenience of the
occupants. Beware of bare live electrical terminals temporarily uncovered;
e. Do not leave ladders in such a way that children can gain access to scaffolds;
f. Never leave work unguarded at the end of the day if it likely to be a danger for the
tenant; for example, holes in floors, missing staircase hand nails, live electric wires
and so on; and
g. At all times treat the occupants and their homes with respect. Clean up as you
leave.
Excessive noise emitted from plant, processes and tools can cause, over a period of time,
progressive and irreversible loss of hearing. It can cause a ringing or rushing noise in the
ears, which will not disappear. Hearing loss can also make communication difficult,
Occupational Health and Safety in the Construction Industry 473
which in turn may lead to accidents through instructions either not being heard, or being
mis-heard.
Proper precautions should be taken to protect hearing, and before working with noisy
plant or in a noisy environment, the following should be considered:
a. If is necessary to shout to be heard by someone about 1m away, it is likely that
there is a noise problem requiring action;
b. Ask if noise levels have been checked to see if ear protection is needed;
c. Where noise levels are shown to be excessive, personal ear protections must be put
on at all times. Whether earplugs or ear protectors are used, they must fit perfectly
and be treated carefully; and
d. It has been alleged that ear protectors make it more difficult to understand speech
or hear warning signals. Generally speaking, ear protectors reduce both unwanted
noise and any alarm signals equally, the signal can actually be heard more easily.
Many accidents occur through hand tools falling from heights, being tripped over, or
placed in such a position that the cutting edges cause injury. When not in use, make sure
that any hand tools are stored in a manner unlikely to be hazardous to others.
a. Make sure all cutting edges, teeth etc. are adequately sheathed and otherwise
protected;
b. Do not lay tools down so that they can fall, roll or be knocked over; and
c. Do not leave tools lying in walkways or any place where they could be tripped
over.
15.2.5.2 Cranes
Any work in association with a crane can be a source of hazard. If one has to work in
association with a crane or if one is working within the radius of a crane the following
safety rules should be observed:
a. Keep clear of the tail swing of mobile and crawler cranes. It is easy to forget and
either be struck or crushed between the crane and an adjacent building or
obstruction;
b. Avoid standing under a swinging load;
c. While waiting for materials, concrete skips, formwork etc., to be swung into
position, never turn your back on the load - always keep it in your vision;
d. In windy conditions, beware of formwork or other light but large area items being
spun in the wind; and
e. Never signal to the driver - that is the bank man’s job. It can only confuse and may
cause an accident.
Occupational Health and Safety in the Construction Industry 475
15.2.5.3 Excavators
When carrying out work in association with excavators, one can be subjected to hazards,
which often arise without any warning.
Always observe the following rules:
a. Remember that, with modern hydraulic machines, all motions - dig, slew, raise,
boom, etc are much faster than non- hydraulic equipment;
b. The tall swing and the boom swing cab can be sudden and lethal if you are in the
way. Stand well clear of both the operating boom and the tail swing;
c. Stand well clear of lorries and vehicles being loaded;
d. Always face excavating machinery-never turn your back on it. This is particularly
important if you are in a supported trench and the excavator is removing the loose
material for you;
e. Do not work in an unsupported trench unless a competent and experienced person
declares it safe;
f. Excavators may be used as cranes only when handling of materials is associated
with the trench work. This means support materials, pipes, manhole rings, etc.
when working the excavator as a crane make sure that suitable slings and fixing
points are used and that slinging method has been carried out property. Check that
the specified capacity of the machine is not exceeded;
g. Never stand under the load when using the excavator as a crane; and
h. If more than one of you is working with an excavator, agree with the driver on
who will be responsible for signals and instructions.
15.2.6 Demolitions
Demolition cannot be only one of the most dramatic operations in the construction
industry, it can also, by its very nature, be one of the most dangerous. Demolition work
varies very widely from the controlled collapse of large structures, using explosives, to
476 Fundamentals of Civil Engineering Construction Management
the hand demolition of walls. Be aware of the need for shoring or temporary support at
any stage of the work.
Accidental contact with live overhead power lines causes many serious injuries and
some fatalities. Such accidents are particularly related to cranes working or travelling
near or under overhead cables. If you have to work near overhead power lines observe
the following rules:
- Treat all overhead lines as 'live' unless you have been specifically instructed
otherwise; get to know any maximum clearance requirements specified by the
Electricity Authority;
- Do not try to circumvent ‘goalposts’ or barriers or other warnings;
Occupational Health and Safety in the Construction Industry 477
- If work has to be carried out under overhead wires, special precautions must be
observed as laid down by the electricity authority. Make sure you have been
instructed as to what they are; and
- When working near power lines check that crane jibs, for example, cannot
encroach on the safe clearance specified. Barriers should have been provided at an
adequate distance to prevent this.
Damage to underground electric cables is a frequent occurrence, which can result in fatal
or serious injuries. In addition the interruption to supplies may have both damaging and
expensive consequences.
Before commencing any excavation, supervisors should ensure that enquires have been
made from the Electricity Authority to see if any cables are in the vicinity. If so
remember that the location shown on a plan may not necessarily be accurate. You should
always follow the rules given below:
- Seek management and Electricity Authority instructions on whether the cables are'
dead' or have to be maintained 'live';
- Hand-dig trial pits carefully wherever possible along any indicated line and look
for marker tiles above the cable. Finally establish exact location.
- Once exposed, protect cables from damage and support them effectively where
necessary;
- In the event of accidental damage, even if only apparently superficial, all persons
should defer the work until the Electricity Authority has examined and rectify the
damage;
- When backfilling make sure you have been instructed as to the Authority's
requirements.
- Replace marker tapes or tiles in their original positions;
478 Fundamentals of Civil Engineering Construction Management
- If hand held power tools are used to break up concrete areas or other paved
surfaces, avoid breaking thick layers at a time. This is one common source of
accidents when cables are buried underneath;
- The use of picks, pins and forks is permissible to free lumps of stone etc. and break
hard ground, but picks should not be used in soft soil where cables are present; and
- Never use exposed cable as steps or handholds and do not attempt to alter the
position of any cable unless instructed to do so.
While electricity cables constitute the majority of cables existing in ground, do not
forget telephone cables as well. Today, apart from telephone cables, there are television
landlines. Television and telephone cables are highly complex and expensive, thus
damage to such cables would have high cost implications for repair works.
When excavating near such cables, follow the rules given for underground electricity
cables. Remember also, that many of such cables will have been laid in earthenware
ducts to allow easy installation and replacement, which need to be protected as well.
General
Locating gas and water mains, as well as sewers, needs the same care as locating electric
cables. As with electricity, the particular public utility company should have been
contacted to determine where such services are located on the site. Check with your
supervisor that this has been done. The locations given should only be taken as
approximate and more accurate means should be used to fix their line.
Gas mains
When excavating near a gas main:
Occupational Health and Safety in the Construction Industry 479
Water mains
While a water main does not carry significant risks to life and limb inherent in electricity
and gas services, the fracturing of a small pipe can cause great inconvenience. If a large
high pressure main is breached, the results can be spectacular and very costly. A great
deal of flooding can take place before the water is switched off and perhaps an area may
be left temporarily without water.
If the line of mains has been properly established by trial pits, stop cock locations etc.
and you have to carry out excavations in the vicinity, you should:
- Work adjacent to and around the pipe with care, using hand tools;
- Do not leave a length of pipe unsupported which is more than the unsupported span
specified - even temporarily;
- Do not confuse smaller plastic pipes with plastic sheathed electric cables; and
follow the water authority's backfilling specification with care; if the main is
damaged accidentally in any way - however superficially - have the Water
authority called at once and explain what has happened.
480 Fundamentals of Civil Engineering Construction Management
Sewers
All sewers should be located by tracing manhole covers and confirming that the sewer
does, in fact, run between any two. The main risk to employee’s health will be if they
are working in trench and break into a foul sewer. One should leave the trench
immediately to avoid the possibility of asphyxiation and should not return until adequate
ventilation has been provided and the area declared safe for work.
Have any damage reported to the Sewer authority at once. If you break a storm water
sewer and rain is falling, vacate the excavation as it may flood from the sewer at any
time.
15.2.8.1 General
Many accidents occur because people on side do not pay sufficient attention to their own
health and safety. Workers can do a great deal to protect themselves simply by knowing
what is available, wearing the correct clothing and using the protective equipment
appropriate to the job circumstances.
- Employers are obliged by law to provide, without charge the following items of
personal protection, when circumstances demand their use:
- Suitable protective clothing for persons working out of doors in rain, snow, sleet of
hail;
- Suitable protective clothing for persons working with asbestos based materials (if
adequate exhaust ventilation is impracticable);
- Insulating screens, boots and gloves to prevent danger of electric shock;
- Eye protectors or shields, where specified processes are being carried out;
Occupational Health and Safety in the Construction Industry 481
At the same time, employees are required by law to wear such clothing and equipment
where the circumstances demand it.
The sections below provide detailed information on the protection of various parts of the
body.
15.2.8.2 Hands
Many of the hand injuries, which occur every year would have been avoided, or would
have been much less serious, if the correct industrial gloves had been worn.
Industrial gloves will also protect the hands from substances, which can damage the skin
such as certain chemicals regularly used on construction sites. The correct type of glove
for the situation is essential as no gloves give protection from all possible hazards.
Suitable gloves should be used, for example when:
- Handling objects with sharp or rough edges bricks, paving slabs, glass etc.;
- Work in dirty or contaminated areas; and
- Using chemicals and other hazardous substances.
15.2.8.3 Eyes
482 Fundamentals of Civil Engineering Construction Management
Probably one of the most traumatic accidents that can occur is a person being blinded at
work. Such accident should never happen, as there are specific legal requirements on
employers to issue eye protection for persons involved in certain operations.
Equally, employers are required to use that protection. Either partly, by not fulfilling
their obligations, can be liable to possible legal proceedings.
15.2.8.4 Feet
Injuries to the feet through treading on sharp objects such as nails or having items
dropped on the feet are always high in the construction industry. Safety footwear is
essential on construction sites, and will protect the feet from serious injury in most of the
common types of site accidents. It comes in many different styles from fashionable
shows to heavy-duty boots.
All styles have steel safety toecaps, and spring steel midsoles to protect the sole of the
foot are incorporated if required. Rubber boots are also available with toes cape and
midsoles. Plimsolls and soft shoed should never be worn on site.
Always buy safety footwear to suit the type of work you are involved in. There are many
companies who make the wearing of safety footwear a requirement of their safety
policies, and some will not allow operatives on site in anything but the correct footwear.
15.2.8.5 Ears
Excessive noise at work can cause serious damage to your nearing. In some cases an
employer is required by law to protect operatives from the effects of noise, while other
employers give protection on a voluntary basis. Whichever is the case, one should wear
the hearing protection provided wherever it is considered necessary to safeguard ones
hearing.
Occupational Health and Safety in the Construction Industry 483
15.2.8.6 Backs
One problem which causes a great deal of lost time in the industry is what it generally
referred to as 'backache' - a term which covers a variety of complaints. Many of these
back problems are not caused by lifting heavy loads, as it is often thought, but by
constant exposure to wet and cold. Employers will provide wet weather clothing, but it
is up to the employee to dress correctly with warm clothing in cold weather, with special
consideration being given to protecting the back.
The head is particularly vulnerable to injury, and accidents to the head are often fatal or
involve very serious injuries, such as brain damage or fractured skull. Over the years it
has been proved beyond doubt that many deaths and head injuries could have been
prevented, or their severity reduced, by wearing safety helmets. Site personnel must
wear safety helmets at all times when in the vicinity of construction work, unless
company or site rules or notices make exceptions.
Site management is responsible for seeing that safety helmets, which conform to the
appropriate standard, are made available. The following Working Rule should be for
maximum safety and comfort:
- The headband should be adjusted to suit the head size;
- Check that the outer shell and harness is in good condition, without indentations or
cracks;
- Never paint the shell, as some paints weaken the plastic used;
- Only the recommended harness should be used to ensure proper clearance for
deflection of the shell under impact and for ventilation;
- Chain straps should be used to avoid the possibility of the safety helmet falling off
when bending down, or in high winds;
484 Fundamentals of Civil Engineering Construction Management
- Holes must not be punched into the shell or attaching unauthorized equipment.
Various attachments for ear defenders, eye protection or visors are available and
should only be used in accordance with the manufacture's instructions or advice;
and
- Any helmet should be replaced if it sustains a heavy impact, as the shell may be
weakened locally and affect the strength of the helmet.
Falling into the water and being drowned or carried away by water current is an ever-
present danger when working over or adjacent to water. Even though workers may be
good swimmers, the following precautions should always be followed:
- Make sure that the working platform is secure and has no tripping hazards (tools,
wire, timber etc.);
- Check that guard rails and toe boards are firmly fixed in position;
- Check that access ladders are securely lashed to prevent movement;
- Life jacket should be worn, and ensure that they are properly fastened up;
- When required, use the safety nets or safety harness provided by management;
- Check that lifebuoys are ready to hand for immediate use, and fitted with lines;
- Make sure that the safety boat is manned while you are working above;
- Ensure that you know the routine for raising the alarm and for rescue drill; and
- Do not work alone over water.
Among the current developments of construction safety is the integration of safety and
quality management. In the world of diminishing resources, integration of similar
aspects is preferred and beneficial to organizations. Programs of quality and programs of
safety have the same components. After all, safety is a dimension of quality, after
everything, the elimination of defects includes the elimination of practices of unsafe
work. If one looks at safety as a consequence of making things well, then the program
Occupational Health and Safety in the Construction Industry 485
will undoubtedly bear quality. When quality management and safety management are
combined, management and employees can usually identify with a much simpler plan.
This is beneficial since for management there is only one system to oversee, one that
fully integrates quality and safety into company operations and continuously improves
performance. For employees it is easier to work within a management framework that
presents a single message about the right way to work. Therefore integrating quality and
safety into a single program streamlines operations and creates synergies that improve
results.
Safety management also has many parallels with other organizational management
activities. These organizational management activities include Total Quality
Management (TQM) and environmental hazard management. BS 8800 (1996), stipulates
links between Safety Management activities and activities in ISO 9001 Quality system.
Safety management can be included in the sphere of quality management if a TQM
approach comprising requirements from all the relevant stakeholders, not only
customers, is adopted.
REFERENCES
Chapter 1
Bersidge, J, (1976) Everyday life in the Roman Empire, B.T.Bastsford Ltd, London.
Dorsey, R W. (1990). The Acquisition of Skills and Traits Among Construction Personnel. Austin,
Texas: the Construction Industry Institute.
Dorsey, R W. (1992). Evaluation of College Curricula Which Prepares Management Personnel for
Construction. Austin. Texas: the Construction Industry Institute.
Harvey, J. (1972). The Medieval Architect. New York, N. Y.: St. Martinlhs
Leflcoe, M. R (1970). The Crisis in Construction. Washington, DC: The Bureau of National Affairs
Inc.
Management Education and Academic Relations, Construction Industry Cost Effectiveness Project,
Report A-5, The Business Roundtable, New York, N. Y., June, 1982.
McManamy, R, Schriener, J., Ichniowski, T. & Angelo, W. J. (1994, June 06). Design Build Goes
Back to the Future. Engineering News Record, pp. 26-28.
Pletta, D. H. (1984). The Engineering Profession. Lanham, Maryland: University Press of America,
Inc.Press, Inc,.
Reynolds, T.S. (1991) Overview: The 19th Century America. In T.S. Reynolds (Ed.), The Engineer in
America, A Historical Anthology from Technology to Culture pp. 169-190, Chicago,
Illinois: The University of Chicago Press.
Salzman, L. F. (1952). Building in England Down to 1540. Oxford, England: Oxford University
Press.
Chapter 3
Civil Engineering Procedure (1996) 4th Edition, The Institution of Civil Engineers.
Chapter 4
Abebe Dinku, Construction Management and Finance, a teaching material, AAU Printing press, April
2003.
Dalton, D.C., Unpublished lecture notes on Construction Management, University of Leeds, UK,
1987.
Chapter 5
Ackroyd, P.J. 1991a. The Design and appraisal of bilateral aid proposals, Office Instruction, GAPE 1
(London, Overseas Development Administration (ODA), 3 June).
487 Fundamental of Civil Engineering Construction Management
_______. 1991b. Sources of advice on the design and appraisal of aid proposals, Office Instruction,
GAPE2 (London, ODA, 3 June).
African Development Bank (AfDB). 1990. African Development Fund: In brief. (Abidjan).
Akroyd, D. 1985. “Policy priorities for agricultural development in Africa with particular reference
to agricultural project planning” in Agricultural Administration (Barking, Essex), No. 10,
pp. 101-113.
Asian Development Bank (AsDB). 1991a. Asian Development Bank: Basic information (Manila).
_______. 1991c. Asian Development Bank: What it is: What it does: How it works (Manila).
Baum, W.C. 1982. The project cycle (Washington, DC, World Bank).
Baum. experience”, in Finance and Development (Washington DC), Vol. 22, No. 4, Dec., pp. 26-36.
___;___. 1985b. Investing in development – Lessons of World Bank experience (Oxford, Oxford
University Press).
Coleman, G. 1987. “Project planning. Logical framework approach to the monitoring and evaluation
of agricultural and rural development projects”, in Project Appraisal (Guildford, Surrey)
Vol. 2, No. 4, Dec., pp. 251-259.
European Investment Bank. 1990. Annual Report 1990 (Brussels).
_______. 1991. Financial facilities under the Fourth Home Convention (Brussels).
Feinberg, R.E., et al. 1986. Between two worlds – The World Bank’s next decade. (Oxford,
Transaction Books).
Grenfell, J. 1991. Business opportunities in projects financed by the World BankGrover, B. 1983.
Water supply and sanitation projects preparation handbook: Guidelines, World Bank
Technical Paper No. 12 (pairs, World Bank).
Hurni, B.S. 1980. The lending policy of the World Bank in the 1970s: Analysis and evaluation
(Boulder, Colorado, Westview Press).
operations: Sectoral programs and policies (London, Johns Hopkins University Press).
______. 1988. The International Bank for Reconstruction guidelines: Use of consultants by World
Bank borrowers and by the World Bank as an executing agency (Washington, DC, World
Bank).
Jain, P.K. 1989. “Assessing the performance of a development bank”, in Long Range Planning
(Elmsford, New York), Vol. 22, No. 6, pp 100-106.
Kreditanstalt für Wiederaufbau (KfW). 1990. Cooperation with developing countries. The
procedures followed in the financial cooperation of the Federal Republic of Germany
(Frankfurt).
LeGault, R. 1984, “An exploration into overseas development”, in Real Estate Finance Journal
(Boston, Massachusetts), Fall, pp. 52-56.
Management of international construction projects. 1984, Ch. I, “Project finance. The multilateral
development banks” (London, Thomas Telford).
References 488
The World Bank. 1980-91. The World Bank Annual Report (Washington, DC), various years.
______. 1981. Guidelines: Use of consultants by World Bank borrowers and by the World Bank as
executing agency (Washington, DC).
______. 1985. Guidelines for procurement under World Bank loans and IDA credits (Washington,
DC).
_______. 1988. Procurement and co-financing: Methods and procedures (Washington, DC).
_______. 1991. Bidding for contracts in World Bank financed projects (Washington, DC).
United Nations. 1979. Development banking in the 1980s, Proceedings of the UNIDO/World Bank
Symposium, Zurich, June.
Water Companies Associations, United Kingdom. 1991. Water Aid Annual Review.
Westlake, M. 1993. “Development Banks: Only the best will do”, in The Banker (London), May, pp.
23-29.
Chapter 6
Code of Estimating Practice (1996) 6th Edition, Chartered Institute of Building (CIOB), Englemere,
UK.
Cooke, B. and Williams, P. (1998) Construction Planning, Programming and Control, Palgrave, New
York, N.Y.
Chapter 8
Cormican, D., Construction Management : Planning and Finance, Construction press, Longman
group limited, London and New York 1985.
Kleinfeld, I.H., Engineering Economics: Analysis for Evaluation of Alternatives, John Wiley and
Sons, 1993.
Chapter 11
World Bank (2002). Consulting Services Manual – A Comprehensive Guide to Selection of
Consultants, Washington, D. C.
Chapter 13
Goetze, A. (translator), “The Laws of Eshunna,” in The Ancient Near East, J.B. Pritchard, Ed.,
Princeton University Press, Princeton, NJ, 1958, pp. 138.
489 Fundamental of Civil Engineering Construction Management
Meek, T.J. (translator), “The Code of Hammurabi,” in The Ancient Near East, J.B. Pritchard, Ed.,
Princeton University Press, Princeton, NJ, 1958, pp. 163.
Managing construction projects, A guide to Processes and Procedures, ILO, Geneva, 1995.
Haswell, S.K and Desilva, D.S; Civil Engineering Contracts Practice and Procedure, 2nd. Edition,
19.
Fédération Internationales des Ingénieurs-Conseils (FIDIC) FIDIC Conditions of Contract, 4th edi.,
Lausanne, Switzerland, 1987.
Abebe D., Insurance Requirements and Practices of Ethiopian Construction Sector, Journal of
Engineers and Architects, Vol. 17, pp.26-42, 2000.
Chapter 14
Haswell, C.K et. al., 1989, Civil engineering contracts, practice and procedure, Butter Worth Pub.,
London.
Heisler, S.I., 1994, The Wiley Project Engineers Desk Reference. John Wiley And Sons, Inc. New
York.
Marsh, PDV., 1988, Contracting For engineering And Construction Projects, Gower Publishing
Limited, Hampshire England.
Bunny, N.G, 1991, The FIDIC form of contract, Blackwell science, Oxford, England.
O’Leary, F. A., 1992, Construction Administration in Architectural practice, McGraw Hill, Inc. New
York.
Cox P.A., 1991, Civil engineering Project Procedure In The EC (proceedings of the institute of civil
Engineers) Thomas Telford, London.
Hawker, U.T., et. al., 1986, The Institution Of Civil Engineers Arbitration Practice Thomas Telford
Publishers,’ London.
Sawyer, G.J et. al. 1985, The FIDIC Conditions Digest Of Contractual Relationships And
Responsibilities, Thomas Telford, London.
Jones, P.G., 1975, A New Approach to the ICE Conditions of Contract, The Construction Press Ltd,
Hornby Lancaster.
Han, H.S., et. al. July/August 2001, Approaches For Making Risk-Based Go/No-Go Decision For
international projects Journal Of Construction engineering And Management.
Metropolis P.,et.al.,. May/June 2001, Model; For Understanding, Preventing and Resolving Project
Disputes, Journal of Construction engineering and Management.
Kululanga,G.K. et. al., July/August 2001, Construction Contractors Claim Process Framework,
Journal of Construction engineering and Management.
References 490
Kangari, R.et.al. May/June 2001, Construction Surety Bonding Journal of Construction engineering
and Management.
The WORLD BANK , 1995, Guidelines Procurement Under IBRD Loans and IDA Credits.
ERA Monthly progress report: no.34 Jan 2003, Woldia –Alamata Road Project
Monthly progress report: no.39 Jan. 2003, Harar-Qulubi Road Project
Quarterly progress report: no.36 Dec. 2002, Awash-Hirna Road Project
Hughes, G.A et.al. 1983. claims In Perspective. Longman Scientific And Technical, London
Dinku, A. and Kahsay, G. Claims In International Construction Projects In Ethiopia And A Case
Study Of Selected Projects; Journal of Ethiopian Engineers and Architects, Vol. 20, pp.1-
14, 2003.
Kahsay, G., Claims in International Projects in Ethiopia, MSc thesis, Civil Engineering Department,
Faculty of Technology, Addis Ababa University, July 2003.
Chapter 15
Accidents and Occupational Diseases (Notification) Ordinance (1953).
Booth, R. T. and Lee, T. R., (1995) The Role of Human Factors and Safety Culture in Safety
Management, Journal of Engineering Manufacture, pp. 209.
British Standard Institution (1996) BS 8800, Guide to Health and Safety Management Systems,
London.
Contractors Registration Board (CRB) (2001) Baseline Study to Assess the Situation of Safety in
Tanzanian Construction Sites, Unpublished Report, CRB, Dar es Salaam, Tanzania.
International Labour Office (ILO) (2001), Guidelines on Occupational safety and Health Management
Systems, ILO- OSH 2001,
http://www.ilo.org/public/english/protection/safework/managmnt/guide.htm
[Accessed 10 Dec. 2002].
ISO 8402 (2000) Quality Management and Quality Assurance – Vocabulary, BSI, England.
Occupational Health and Safety Act (OSHA) (2003) Government Printer, Dar es Salaam.
491 Fundamental of Civil Engineering Construction Management
H management skills............................13
management team ......................34, 48
hazard assessments ........................ 162 Managing Director ...........................34
hazard identification ...................... 467 mediation........................................452
head office overheads .................... 450 method statements..152, 156, 162, 257
493 Fundamental of Civil Engineering Construction Management
method ttudy ....................................36 planning . 107, 262, 306, 409, 463, 493
MIGA.............................................118 planning controls ....................... 19, 29
military engineering .......................4, 5 planning engineer ............................ 34
mini-trial ........................................453 plant manager .................................. 34
monetary terms ................74, 104, 107 plant schedule ........................ 164, 168
monitoring and review ...........464, 469 pre-arbitral review board ............... 452
most likely duration .......................209 precedence diagrams ............. 186, 197
motivation ......................... 38, 274, 324 pre-contract stage .......................... 154
mutually exclusive projects .............92 preliminary design......................... 375
negotiations ....128, 129, 353, 365, 366 Premiums....................................... 424
present value (cost) method............. 83
N pre-tender meeting......................... 174
pre-tender planning ....................... 142
network analysis ............................185 pre-tender programme ........... 146, 179
network schedules..................247, 248 Preventive maintenance................. 335
node diagram..................................210 principles of insurance .................. 415
non-financial incentives...................285 professional indemnity insurance .419,
normal cost.....................................227 459
project cycle ............................ 13, 137
O project duration ..................... 211, 228
project evaluation .......................... 133
Occupational Health and Safety... 463, project expenditure ........................ 111
497 project identification ..................... 121
offer and acceptance ......................389 project preparation......... 124, 125, 134
office manager ...............................157 project ranking................................. 76
omissions ...............................361, 362 project stages ................................. 374
open tendering................................377 promoter ............................ 14, 71, 375
opening of tenders..........................384 public sector .................................... 15
operational planning ..............177, 178
operatives .. 27, 51, 159, 202, 277, 476, Q
488
optimistic duration .........................209 Quality and Cost Based Selection . 347
optimum project duration...............226 Quality Based Selection ................ 348
overhead costs..................38, 227, 247 quality management .............. 490, 491
overhead power lines .............473, 482 quantity surveyors ............................. 2
overheads .......................................151 Quantum Meruit ............................ 438
own all plant...................................304
R
P
Rate of Return Method .............. 75, 80
particular ppplication .............397, 404 real terms ....................................... 104
payback method ...............................75 recipient country.................... 109, 117
performance appraisal......................263 Renaissance ....................................... 4
Performance Bond .................406, 422 resident engineer ..................... 15, 441
performance evaluation..................370 resource aggregation ..... 183, 193, 296
personnel officer ..............................34 resource allocation......................... 216
PERT .....185, 208, 209, 210, 211, 212, resource graph ............................... 243
214, 226 resource levelling .......... 227, 238, 239
pessimistic duration .......................209 resource smoothing ....................... 228
References 494
S T