RENCANA ANGGARAN BIAYA

NAMA PROJECT : SINARJAYA ECOPARK


NAMA PEKERJAAN : PEMBANGUNAN AULA / BALE BADANTEN
LOKASI PEKERJAAN : CARINGIN - KAB GARUT
LUAS BANGUNAN : 60.00 m2
VOL.
NO URAIAN PEKERJAAN SAT. BAHAN UPAH
PEKERJAAN
A PEKERJAAN PONDASI
1 Pek. Bouplank m 60.00 43,000.00 2,580,000.00
2 Pek. Galian Tanah
Pek. Galian Tanah Tapak m3 1.58 88,000.00 138,600.00
Pek. Galian Tanah Pondasi m3 5.12 88,000.00 450,560.00
3 Pas.Pondasi Batu Kali m3 7.68 680,000.00 5,222,400.00
4 Urugan Tanah Peningi Lantai m3 40.00 69,300.00 2,772,000.00
5 Urugan Pasir m3 4.00 282,200.00 1,128,800.00
JUMLAH 12,292,360.00
B PEKERJAAN STRUKTUR BETON
1 Pek Footplat Titik 14.00 -
- Beton K225 m3 1.05 680,000.00 714,000.00
- Pembesian Besi 12" Batang 8.17 64,000.00 522,666.67
- Kawat Beton Kg 0.89 22,000.00 19,673.50
2 Pek. Kolom Pedestal Titik 14.00 -
- Beton K225 m3 1.26 680,000.00 856,800.00
- Pembesian Besi 12" Batang 8.40 64,000.00 537,600.00
- Sengkang Besi 8" Batang 7.00 28,000.00 196,000.00
- Kawat Beton Kg 0.20 22,000.00 4,400.00
3 Pek. Pas. Sloof m 32.00 -
- Beton K225 m3 0.48 680,000.00 326,400.00
- Pembesian Besi 12" Batang 10.67 64,000.00 682,666.67
- Sengkang Besi 6" Batang 8.00 28,000.00 224,000.00
- Papan Bekisting m3 0.62 1,700,000.00 1,054,000.00
- Kawat Beton Kg 2.74 22,000.00 60,280.00
4 Pek. Kolom Buah 14.00 -
- Beton K225 m3 2.63 680,000.00 1,785,000.00
- Pembesian Beton 12" Batang 14.47 64,000.00 925,866.67
- Sengkang Besi 6" Batang 6.42 28,000.00 179,666.67
- Papan Bekisting m3 0.34 1,700,000.00 578,000.00
- Kawat Beton Kg 2.16 22,000.00 47,458.95
5 Pek. Ring Balok m 158.00 -
- Beton K225 m3 3.16 680,000.00 2,148,800.00
- Pembesian Beton 12* Batang 52.67 64,000.00 3,370,666.67
- Sengkang Besi 6" Batang 46.08 28,000.00 1,290,333.33
- Papan Bekisting m3 0.33 1,700,000.00 561,000.00
- Kawat Beton Kg 2.95 22,000.00 64,914.30
6 Pek Rabat Beton Lantai 12 Cm m3 38.76 -
- Beton K225 m3 21.60 520,000.00 11,232,000.00
JUMLAH 27,382,193.42
C PEKERJAAN LAPISAN PAPAN KAYU
1 Lapisan Papan Kayu Tiang
a. Papan Kayu Kls II Setara
lembar 36.00 22,000.00 792,000.00
Borneo 1x20x300 Cm
b. Cat Kayu Melamik m2 18.00 122,000.00 2,196,000.00
2 Lapisan Papan Kayu Ringbalk
a. Papan Kayu Kls II Setara
lembar 24.00 22,000.00 528,000.00
Borneo 1x20x300 Cm
b. Cat Kayu Melamik m2 28.80 122,000.00 3,513,600.00
D PASANGAN BALOK KAYU / RINGBALK ANAK
a. Kayu Balok setara Borneo
1 Batang 35.00 65,000.00 2,275,000.00
6x12x300 Cm
b. Cat Kayu Melamik m2 22.00 122,000.00 2,684,000.00
JUMLAH 11,988,600.00
E PASANGAN RANGKA ATAP KAYU

Pas Balok Utama Rangka, Kayu


1 Batang 20.00 65,000.00 1,300,000.00
Balok setara Borneo 6x12x300 Cm

Pas Kayu Gording, Kayu Balok


2 Batang 76.00 65,000.00 4,940,000.00
setara Borneo 6x12x300 Cm
Pas Kayu Usuk setara Borneo
3 Batang 64.00 32,000.00 2,048,000.00
4x6x300 Cm
4 Reng Kayu Batang 220.00 4,000.00 880,000.00
5 Lisplank Kayu Batang 60.00 26,000.00 1,560,000.00

6 Pebgecatan Cat Kayu motif Kayu ls 1.00 12,000,000.00 12,000,000.00

JUMLAH 22,728,000.00
F PEKERJAAN PENUTUP ATAPATAP
Pas Penutup Atap Genteng
1 m2 142.00 62,000.00 8,804,000.00
Palentomg Jatiwangi Super
Pas Bubungan Genteng Palentong
2 m1 58.00 38,000.00 2,204,000.00
Jatiwangi Super
3 Pas Plafond anyaman Kayu m2 142.00 35,000.00 4,970,000.00
JUMLAH 15,978,000.00
G PEKERJAAN LANTAI
Pek. Pas. Kramik Lantai 40x40
1 m2 110.00 90,000.00 9,900,000.00
Corak kayu
JUMLAH 9,900,000.00
H PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Titik Lampu Titik 3.00 275,000.00 825,000.00
2 Pek Instalasi Stop kontak Titik 3.00 275,000.00 825,000.00
Pek. Pas. MCB + Box pengaman
3 Titik 1.00 250,000.00 250,000.00
presto
4 BP Listrik PLN 1300 Watt unit 1.00 5,000,000.00 5,000,000.00
JUMLAH 6,900,000.00
JUMLAH ANGGARAN BIAYA 107,169,153.42
DIBULATKAN 107,000,000.00