Professional Documents
Culture Documents
Salt Point Bridge Cost Estimate 2022-11-29 Updated
Salt Point Bridge Cost Estimate 2022-11-29 Updated
Project Tasks
Support Tasks
Task # Description
01 Picking up material
02 Renting equipment
03 Pre-fabricating
04 Loading trailers
05 Yard clean-up
06 Dispose of Material
Site Tasks
Task # Description
0
1 Mobilization
2 Daily Mob
3 Regrade, Supply and Place Rip-Rap 3 Locations
4 Place and/or Fix Hazard Markers
5 Repair Abutment SU1, Pile P5
6 Repair Pier SU3, Pile P1
7 Repair Pier SU5, Pile P1
8 Site 2: Repair Ashphalt and Seal Cracks
9 Site 2: Epoxy Seal Split Pier Caps
10 Site 2: Repair Railing Connections
11 Put up and Down Signage
12
13
Material Costs
Task # Item
4 Hazard Sign
4 Misc. Lumber
4 Fasteners (Bolts, Screws , Nuts, Etc.)
3 12" Field Stone (Rip-Rap)
3 GeoTextile
5,6,7 Epoxy
5,6,7 FRP Sleeve (QuakeWrap)/Pile Repair Material
8 Asphalt Cold Mix
9 Epoxy
5 Clay
Labour Costs
Support Labour Costs (all labour costs associated with picking up materials. equipment, rentals, etc., and prepping or fabricating material at our yard)
Site Labour Costs (all labour costs associated with site work)
Total Hours
Project Manager Costs
Total Hours
Total Labour Costs
Project Duration
Support Labour Time
Unit Qty Notes
Crew Size 1
Hrs/Day 10
Support Hours 24
Support Days 2.4
Summary
Total Hours 97
Total Days 7.35
Total Weeks 1.795
Total Months 0.57625
Subcontractor Costs
Trade/Type
Contractor Name Task
Mob & Demob
Welding
Trade Subtotal
Trade/Type
Contractor Name Task
Dyck Construction Mob & Demob
Regrade Embankment, Place Riprap Excavation
Regrade Embankment, Place Riprap
Hauling
Delivery Fees
Trade Subtotal
Trade/Type
Contractor Name Task
Ready-Mix Mob & Demob
HydroVac Price Confirmed
Trade Subtotal
Trade/Type
Contractor Name Task
Mob & Demob
On site test
Lab test
Trade Subtotal
Trade/Type
Contractor Name Task
Drafting
Geotechnical
Engineering
Trade Subtotal
Trade/Type
Contractor Name Task
Trade Subtotal
Cost Checks
Item Total Difference
Individual Items 46532.80 0
Subtotals 46532.80 0
Summary
KPI Reference
Target Revenue/Project hr $136 - $153
Target Profit/Project hr $10 - $16
Revenue/Project hr $735.11
Profit/Project hr $119.93
yes
no
Bids Due: 9-Dec-22
p 3 Locations
arkers
e P5
P1
P1
eal Cracks
r Caps
ections
age
Order
Unit Quantity Unit Price Total Supplier Notes
ea $0.00
ea 1 50 $50.00
LS 1 20 $20.00
LS 1 40 $40.00
m3 90 65 $5,850.00
roll 1 600 $600.00
tube 12 30 $360.00
per pile 3 1800 $5,400.00
bag 4 25 $100.00
tube 6 30 $180.00
yard 2 20 $40.00
LS 0 100 $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
PST $884.80
$13,524.80
292
$12,692.00
Notes
Notes
Notes
Welding
Qty Unit Rate Total Notes
$0.00
0 hr $0.00
$0.00
$0.00
$0.00
$0.00
Excavation
Qty Unit Rate Total Notes
4 hr 220 $880.00
20 hr 185 $3,700.00
4 hr 150 $600.00
$0.00
$0.00
$5,180.00
Pile Driving
Qty Unit Rate Total Notes
4 hr 275 $1,100.00
Price Confirmed 10 hr 275 $2,750.00
$0.00
$0.00
$0.00
$3,850.00
Field Testing
Qty Unit Rate Total Notes
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Engineering
Qty Unit Rate Total Notes
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Other
Qty Unit Rate Total Notes
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$9,030.00
EA $0.00
20 Nights 120 $2,400.00
54 Meals 60 $3,240.00 budget $20/meal
4320 KM 0.4 $1,728.00 based on $1.90/L diesel at 21L/100km
2000 KM 0.55 $1,100.00 based on $1.90/L diesel at 29L/100km
60 L 1.7 $102.00 gas
0 L 1.9 $0.00 diesel
400 L 1.9 $760.00 diesel
$9,330.00
Difference Verification
0 Pass
0 Pass
Notes
Markup
% of BID Price Notes
18%
7%
10%
excl. GST
Notes
tes
tes
tes
tes
tes
tes
tes
tes
tes
Notes
l at 21L/100km
l at 29L/100km