Professional Documents
Culture Documents
Vol IX - PG B210 - IC Works
Vol IX - PG B210 - IC Works
TENDER DOCUMENTS
LOCATION: TITLE:
Western Coast VOLUME IX PART PG-B210
PACKAGE: TECHNICAL SPECIFICATION
INSTRUMENTATION AND CONTROL (I&C)
SCALE: REV:
None Q A 1 0 - H - 0 4 1 0 C
SUBCONTRACTOR:
Sheet 1 of 102
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Disclaimer
The content of this document is intended for the exclusive use of Fichtner’s client and
other contractually agreed recipients. It may only be made available in whole or in part to
third parties with the client’s consent and on a non-reliance basis. Fichtner is not liable to
third parties for the completeness and accuracy of the information provided therein.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Table of Contents
1. General 7
1.1 Codes, Permits and Agency Approvals 8
1.2 Service Conditions and Environmental Requirements 9
1.3 Submittals 10
1.4 Tagging 11
1.5 Packing & Storage 11
1.6 Spare parts list 12
1.7 Familiarization and Development 13
1.8 Technical Requirements 13
1.9 Hazardous Areas 14
1.10 Hazard and Operability Study (HAZOP) 15
3. Instrumentation 22
3.1 General 22
3.1.1 Local instruments 23
3.2 Flow instruments 24
3.2.1 Ultrasonic flowmeters 25
3.2.2 Rotameters 25
3.2.3 Flow switches 26
3.3 Pressure Instruments 26
3.3.1 Pressure & differential pressure transmitters 27
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4. Control System 54
4.1 Availability and Redundancy 55
4.2 Cyber Security 57
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
5. Communication System 86
5.1 General 86
5.2 Telephone System 86
5.3 Clock System 87
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
1. General
This Part of the specification covers the general and technical requirements
to be considered in the design and supply of the instrumentation, control,
monitoring and communications systems, for the new GRS system
providing fuel gas to the Yanbu Power & Desalination Plant.
Reference within this specification does not automatically indicate that the
particular form of instrumentation or equipment is required on this project
or will be acceptable for particular application. This specification does not
however relieve the Contractor of his responsibility for the basic and
detailed design and execution of the instrumentation, control system, and
communication systems as per scope of supply in relevant chapters of this
specification.
The rules of good engineering practice and the relevant approved standards
and regulations shall be observed.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
All systems installed in the plant and their components (e.g. DCS racks,
processors, I/O modules, servers, network components, major panel
accessories, field transmitters, analyzers...) shall have CoO (Certificate of
Origin) to maintain high quality of the product.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
1.3 Submittals
Complete specifications, layouts, dimensional, assembly and installation
drawings, wiring and schematic diagrams, as well as details and technical
data covering the equipment, devices and materials used or installed in the
plant, shall be submitted for review by the Employer.
For following major engineering documents, but not limited to, will be
mandatory to obtain SWCC approval before purchasing or construction:
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
1.4 Tagging
All devices shall be provided with permanent identification tags. The tag
numbers shall agree with Contractor’s equipment drawings and shall be the
tag numbers used on the project drawings and device schedules. All field-
mounted transmitters and devices shall have stamped stainless steel
identification tags. Panel, subpanel, and rack-mounted devices shall have
laminated phenolic identification tags securely fastened to the device. Hand-
lettered or tape labels will not be acceptable. All tags shall be in Arabic and
English language.
The shipping list shall be accessible without exposing the instruments to the
atmosphere. The shipping list shall also contain any cautionary notes
regarding storage of the instruments, including requirements to protect the
instrument from static discharge, chemicals (solvents, paints, etc.), or
ambient atmospheric conditions.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Upon delivery, all equipment and materials shall immediately be stored and
protected by Contractor in accordance with Product Storage and Handling
Requirements section, and in accordance with manufacturer's written
instructions, until installed in the Work. Equipment shall be protected by
Contractor against damage and exposure from the elements. At no time shall
the equipment be stored on earth or grass surfaces or come into contact with
earth or grass. Contractor shall keep the equipment clean and dry at all
times. Openings shall be plugged or capped (or otherwise sealed by
packaging) during temporary storage.
Spare parts list and consumable items shall be, as minimum, as specified
herein, and in any case, shall be enough to assure five years of operation
after guaranteed period:
· Replacement analyzer probes of each type to cover the period.
· Service kits of each type to cover the required period.
· Reagents, Buffers and cleaning agents to cover the required period.
· One Instrument of each type along with mounting accessories.
· One valve actuator of each type along with accessories.
· One Conductivity and pH analyzer assembly.
· Two of each type of DCS processor (CPU’s).
· Two of each type of power supply modules and units used in the project
(DC, AC,).
· Two of each type DCS I/O cards.
· Two of each type DCS network interface cards (including Ethernet).
· Two of each type of Vibration monitoring Systems components,
including sensors and accessories installed in pump’s motors.
· Two of each type of Fire Detection & Alarm System components.
· Two of each type of PLC system components.
Contractor shall guarantee the above listed critical spare parts and any other
recommended and required spare parts for the Plant.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The Contractor will be liable for all defects resulting from non-observance
of these.
Contractor shall provide a full area classification of the GRS and its
connections to interfaces.
The Contractor shall provide drawings to define all the hazardous zones
taking account of all sources of hazards under normal and abnormal
operating conditions, (regardless of whether or not these areas are
specifically listed in the specification). The zoning philosophy shall be in
accordance with the Institute of Petroleum Code/National Electric Code and
will be subject to the approval of the Engineer.
All equipment necessary for mounting in these areas shall meet the
requirements of IEC 60079, SIL and NFPA codes and standards or an
equivalent National Standard. Where required by the Engineer, certification
shall be provided to confirm the suitability of the equipment and devices.
All equipment offered for use in these areas shall have the necessary
certification by the appropriate National Certification Bureau and its
proposed application shall fully comply with all conditions of the certificate.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Final number of controllers per unit shall be defined by the Contractor and
approved by SWCC.
The control system shall be designed so, that the plant can be safely
operated with a minimum number of operators.
All GRS and auxiliary equipment shall be provided with an automatic start-
up, switch-over and shut-down sequences, always subject to the fulfilment
of safety conditions. Switching over shall be carried out bumpless.
All process units shall be controlled, monitored and operated via the DCS,
from the Control Desk in the Control Room of the GRS. Secondary sub-
systems as compressed air system, etc. shall be also controlled, monitored
and operated locally, via the HMI located or directly attached to local
panels.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
At least triple redundant measuring and control loops shall be used for plant
and equipment protection and interlocks. At least dual redundant measuring
and sensing loops shall be applied for modulating control functions. Where
triple redundant measuring loops are applied, the resultant signals may be
commonly used for protection and modulating control. A single fault never
shall cause a trip or loss of performance and shall not cause loss of the
protection system. The redundancy shall be complete including the
processors, interfacing modules, power supply modules, station bus etc.
The data highways system shall be single fault tolerant. One failure in the
data highways shall not reduce the availability of any of the system
components or degrade system performance. Failure recovery shall be
smooth, bump less and automatic. Connection of additional equipment shall
be possible while the system is online without disrupting the running of the
plant. Any data communication failure shall not disrupt process control.
These capabilities shall be proven during the acceptance tests or during trial
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The control ranges of the various individual control systems must not limit
the control range of the plant unit as a whole. The control equipment and
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The design, engineering and layout of the Local Control Room shall comply
with international ergonomic standards.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The ESD valve shall be capable of being operated both from the central
control room and locally without using a selector switch.
The Contractor shall design the local control room in order to provide a
productive and safe environment for operators and on the basis of the
human-centered design approach by balancing efficiency and functionality.
Following aspects shall be considered:
· Plant operation tasks and organization for operation (normal situations
and emergencies).
· Design standards for control rooms (ISO 11064 “Ergonomic design of
control centers, industry standards including customer’s standards)
· Study items based on ergonomics (layout, lighting, coloring, sound,
operator console design, large screen, and selection of furniture and
materials).
Electrical and technical rooms shall have the same environmental conditions
as the CCR (air conditioned, dust free, vibration free, etc.) as defined in
paragraph 1.2.
Cables in the control room(s) shall be routed through a raised floor with
min. 800 mm clear height.
All DCS control cabinets and network panels will be installed in the main
technical room, located in the main plant control facilities building, except
those affecting Electrical system which will be located in the electrical
premises.
Cables shall be routed through a raised floor with min. 800 mm clear height.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
PLC systems shall be of uniform type, compatible with the main DCS
system and shall be built single fault tolerant in all aspects. PLC’s shall be
suitably interfaced with the DCS by hardwiring and additionally in a dual
redundant interface configuration based on one standard protocol.
Bidder shall list and justify the intended use of package PLC for the
ancillary areas. The application and the manufacturer/type of this control
systems shall be subject to Employer/ Engineer's approval.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
3. Instrumentation
This section covers the design, furnishing and installation of an
instrumentation system for the GRS of Yanbu plant.
3.1 General
All components of the instrumentation systems shall be as indicated on the
P&ID drawings, once Contractor have fully developed the detail
engineering and have been approved by SWCC/engineers.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
practice and precautionary measures for safety of the Plant and the operating
and maintaining personnel shall be observed.
Each field mounted instrument or device shall be properly labelled/ tagged
as detailed in the general requirements. All instruments shall be identified
by appropriate tag numbers; permanent non-perishable nameplates attached
to each instrument shall be used for this purpose. Further, every such
instrument or device incorporating an indicator shall also be labelled with its
duty description.
All compression fittings of one dimension used without the plant shall be of
one type and fully compatible to each other.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The Contractor shall provide tapping points before each major flow meter to
allow calibration checking by insertion of a reference flow meter. One
suitable insertion flow meter shall be provided.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Bodies, primary elements and wetted parts shall be suitable for process fluid
and environmental conditions.
Measuring principle shall be ultrasonic transit time and sensor shall be able
to measure accurate bi-directional flow, with a minimum of two parallel
acoustic (beams). Overall accuracy shall be within ±0.5 % of the range with
a repeatability of ±0.2 %.
3.2.2 Rotameters
Rotameters, if applicable, shall be metal type design with conical float.
Float position shall be directly visible through a sealed glass or Plexiglas
viewing window. Flow scale shall be engraved on the viewing window.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Integral local gauge and switch/transmitter units shall not be used. Separate
devices shall be provided for local indication and remote monitoring or
interlocking.
Transmitters shall not be damaged by reverse polarity and they shall have
elevated or suppressed zero. Transmitters will have a turndown ratio of
30:1, or more.
Each transmitter shall be provided with valve manifold with test ports on the
instrument side of the valves. Manifold’s material shall be according
instrument’s wetted parts materials.
All transmitters shall be furnished with LCD type digital indicators and shall
be provided with brackets for wall or pipe-stand mounting.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Switch wetted parts shall be compatible with the process fluid. Where the
process is not defined, all wetted parts shall be Teflon-coated, or Viton and
the connection port shall be stainless steel.
All pressure switches shall be ranged in mbar/bar and all vacuum switches
in mm of water column. Unless otherwise indicated, switches shall have a
fixed dead band and shall be auto-reset type. As a minimum, switches shall
be DPDT, rated 10 amp [A] at 230 V ac.
Each switch shall be provided with a threaded end, ball-type shutoff valve.
Shutoff valve materials shall be compatible with the process fluid. Where
the process is not specified, valves shall have AISI316 wetted parts and
Teflon seals. Multi-port valves shall have all unused ports plugged. Shutoff
valve construction shall be as detailed in the miscellaneous instruments
section.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Gauge dial shall be 100mm size, made in white aluminum, black lettering.
Measured units shall be indicated on the dial face. Pointer travel shall be not
less than 200 degrees or more than 270 degrees of arc.
All pressure gauges shall measure in mbar/bar and all vacuum gauges in
mm water column. All gauges shall have a suitable range to give mid-scale
readings under normal conditions. Gauge accuracy class shall be 1.0.
Each gauge shall be provided with a threaded end, ball-type gauge valve.
Gauge valve materials shall be compatible with the measured process and
wetted parts shall be compatible with the process fluid. Where the process is
not defined, gauge valves shall have AISI Type 316 stainless steel wetted
parts and Teflon seals. Multi-port gauge valves shall have all unused ports
plugged.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
For local indication, gauge glasses or magnetic level indicators may be used.
All level indicators shall be conforming to the rated design criteria for the
vessel and equipped with isolation valves. Connections shall be provided at
the top/side and bottom of the level indicator for draining and venting
purposes.
All types of level device (e.g. indicator, switch, transmitter, etc.) shall be
installed so that removal of the device is possible with the tank or vessel full
and/or with the process in operation, as applicable. This requirement applies
to all types of tanks, both storage tanks and process vessels.
The level sensor shall be suitable for flange connection or bracket mounting,
as required, and shall be weatherproof to IP 65.
Sensor shall be compatible with the process media being measured and
insensitive to mounting location and obstructions. For sensors mounted in
direct sunlight, sunshades must be provided.
When not accessible, transmitter shall be remotely installed from the sensor.
Screened and armored cable between the sensor and the transmitter shall be
supplied by the manufacturer. Transmitter shall be housed in an IP65
enclosure suitable for wall or pipe stand mounting.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The sensor shall be compatible with the process media being measured.
Sensors mounted in direct sunlight shall be provided with sunshades.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
When not accessible, transmitter shall be remotely installed from the sensor.
Screened and armored cable between the sensor and the transmitter shall be
supplied by the manufacturer.
Switches used for low level detection in pump chambers might be float type
(Tilting or fixed-mount float type).
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Connection head shall be threaded to the insert (through neck tube) and
shall be made of appropriated materials for withstanding marine
atmosphere. Protection degree shall be IP66. Process connection for
temperature sensor shall be ½” NPT.
Transmitters shall be, in general, head mounted type and shall accept
thermocouple, RTD (3 and 4 wires), ohms or DC millivolts input signals.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
3.5.2 Thermometers
Filled system and bimetallic type dial thermometers shall be used as
appropriate for local indications in the field. Dial size shall be 100 mm and
casing of the instrument and associated fittings shall be 316SS.
Thermometers shall be provided with adjustable viewing angle to allow the
dial to be positioned for optimum viewing.
Capillary tubing for all filled system thermometers shall be 316SS (if
required).
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
All analyzers shall be single stream, suitable for mounting in ambient plant
conditions, SMART type, and each analyzer shall be provided with
integrated LCD display.
The arrangement shall permit testing of the entire assembly before dispatch
to site and shall be arranged for convenient removal from on-line operation
to facilitate routine maintenance and calibration.
The sampling system shall include but not be limited to all probes, valves,
filters, coolers, pressure regulators, flow-meters, piping, fittings and pumps
as necessary, to give the analyzer a representative and suitably conditioned
sample of real process media requirements.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The on-line vibration measurement system (VMS) shall comply with API
Standard 670, ISO 13373 and ISO 2954 standards. For the protection and
predictive maintenance of major rotating machinery a vibration monitoring
system shall be provided in accordance with ISO 13373.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
· The scanning and resolution time for all vibration channels shall be less
than 1 millisecond.
· The protection signal (Relay contact) shall be initiated in the input
module of the VMS.
· The protection signals for each machinery shall not be shared with other
input module of any other machinery.
· The VMS racks shall be supplied with redundant power supply.
· Portable vibration measurement shall be provided as a scope of supply
(Minimum two).
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
All valves external coating shall be suitable for environment class C5M
according ISO 12944-2.
Valves bodies shall in all cases match the piping pressure and temperature
rating specifications as a minimum, and the operating point on the valve
characteristic should be within the 60 - 70% operating range.
For normal service duties valve bodies shall be made of same material than
the pipe where installed, end connections flanged (raised face), unless
process conditions requires special material or otherwise specified. Flange
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
type connections shall in all cases match the piping specifications, but never
below than ANSI Class 300#.
Hardened and/or stellite plug and seat shall be used for the following
applications:
· erosive service;
· wet steam service with pressure drop above 5 bar;
· general service with pressure drops greater than 5 bar.
For the above applications valves up to and including DN25 shall have their
plug and seat made from solid stellite. For larger sizes, the plug and seat
shall be made from stainless steel (A316) and fully metal coated with
Stellite No.6.
Valves shall be provided with Teflon packing and a lubricator assembly. For
services with fluid temperatures above 200C or below 10C an extended
bonnet shall be provided to keep the packing box at proper temperature.
Bellow seals shall be used for services with dangerous or poisonous fluids.
Suitable valve stem material shall be provided on valves used on chlorine
services or other services which become corrosive when in contact with a
moist atmosphere.
For liquids the exit trim velocity shall not exceed 30m/sec.
For flashing service, the exit trim velocity shall not exceed 22.5 m/sec.
For gas and steam the velocity head in line shall be less than 70 psia.
Supplier shall provide sizing/calculations data sheet for all control valves.
The maximum allowable noise level shall be 85 dB A or less.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The installation shall include isolating valves and a bypass valve for each
control valve on all services. Unless otherwise agreed by the Engineer, the
bypass valve providing tight shut-off shall have the same characteristics and
construction as the control main valve.
3.10 Actuators
This section covers furnishing valves and gate actuators as well as the
accessories specified herein. Each actuator shall be designed to open or
close the valve under all operating conditions. Actuators shall be designed
for the maximum differential pressure across the valve and maximum
velocities through the valve.
Actuators for on-off valves and gates shall be electrical motor driven,
however the use of pneumatic actuators on small valves (DN<200) or
special applications may be considered dependent on duty and subject to the
Employer / Engineer approval.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The various types and sizes of actuators shall be standardized and as far as
possible each type shall be from a common manufacturer to facilitate
interchangeability and spares. The actuators shall be from a reputed
manufacturer with a minimum of 3 years of proven service reliability for
typical applications.
The operation of all actuators, control valves and driven units, shall be so
arranged/ designed as to ensure the safety of the "plant" under failure of
control or actuating supplies.
The failure response of all actuators in the event of the loss of the prime
mover (air pressure, oil pressure, electrical power) shall be indicated on the
Piping and Instrumentation diagrams (P&I), and valve’s specifications.
All electric actuators shall have a handwheel for direct manual operation.
The diameter of the handwheel and geared effort shall be such that they are
reasonably operable by one man.
All actuators shall include a mechanical device to show fully open/ closed
feedback limit. Additionally, limit switches shall be provided for all
electrical and pneumatic valves and gates.
All Actuators shall be light weight and construction materials shall conform
to the requirements of ANSI/AWWA C504 and C540 and shall be suitable
to the corrosive marine environment found on the Site. Actuator material
selection shall be submitted for review and approval to SWCC/Engineers.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Actuators shall be designed for their individual duty but at least for duty
type S4 acc. to IEC 60034-1 and to cycle the valve or gate from the fully
open to the fully closed position or the reverse in approximately 60 seconds.
Actuators for valves or gates listed for modulating service in the valve and
gate schedules (if any), shall be provided with a control module for position
modulating type service. The control module shall be mounted within the
controls compartment.
The control module shall contain adjustments for span, zero, gain, and
deadband.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Power for the remote-control station shall be provided from its respective
actuator unit. The remote-control station shall be rated NEMA 4X.
The actuator body shall be made of rugged, ductile cast iron and shall be
corrosion resistant, IP67. Pneumatic actuators shall be designed for the fail-
safe operation of the process/unit/plant.
All pneumatic control equipment and control drives shall be able to operate
with an air supply pressure between 5 and 7 barg.
Valve controller shall include a LCD display as local user interface, and
provide advanced diagnostic capabilities. Additionally, the controllers shall
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
be furnished with integrated limit switches and valve position transmitter (4-
20mA output). The valve controller shall come with NAMUR mounting.
All actuators which are in critical control loops shall be provided with
separate robust precision position measuring transmitters for operation and
monitoring via DCS. Positioner and position transmitters shall be mounted
in such a way that can be easily removed during maintenance tasks.
All positioners shall be provided with pressure gauges (air supply and
control air output) as well as an air filter regulator set.
External limit switches (e.g. for Open/Close) shall also be provided for
isolation valves and gates. Limit switches shall be heavy duty type, with a
cast NEMA Type 4 enclosure, a spring return roller lever, and four isolated
contacts (two normally open and two normally closed) rated for 10A at 120-
480VAC and 5A at 125VDC.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The instrumentation and control system power supply shall be 24V DC.
Generally, two wire transmitters shall be used (24VDC loop powered), and
all protection and control circuits shall be suitable for operating on 24V DC.
All equipment shall meet all surge withstand capability tests as defined in
ANSI C37.90 without damage to the equipment.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
All major components of the system shall have a low resistance ground
connection.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
· In general, each transducer shall have its own tapping point and sensor,
in particular all transmitters to be used for protection and control shall
have their own separate tapping points.
· Instruments shall be mounted in a height between 1,20 m and 1,60 m so
that they can be easily read and serviced from ground or platforms and so
that all auxiliary devices can be easily operated.
· All transmitters shall be supported in a vibration free manner,
independently from plant connections, and mounted in the right
elevation. No stress shall be imposed through the process connections.
· All type of instruments (indicator, switches, transmitters, etc.) shall be
installed in principle so that removal of the device is possible without
causing shutdown of the process. Attachment method for isolating
valves, vent/test valves and valve manifolds to measuring devices, shall
be such that it is possible to disconnect the device from the connecting
pipework without having to disconnect or drain the pipework.
· All instruments shall be installed and connected so that on-site
calibration using portable test equipment is possible, without removal of
the instrument from the process line.
· All electronic devices shall be protected against transient voltage levels
or short circuits, as well as against vibration, dust or heat which would
damage the device.
· All instruments and junction boxes shall be mounted in locations, which
allow easy and safe access for maintenance without the use of temporary
ladders, scaffolding or similar means.
· Electronic instruments shall not be located close to hot lines, vessels or
other hot equipment. Black bulb temperatures exceeding 80 degrees
Celsius shall not result in calibration difficulties / control module
malfunction nor rapid deterioration of electronic components. For open
locations appropriate sunshades shall be provided.
· All sensors/transmitters mounted in direct sunlight shall be provided with
sunshades.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
All cables shall be flame retardant, low smoke non- Halogen, fully
compliant with IEC standards.
All multipair-cables shall be furnished with single screen (each pair) and
overall screen.
Screen continuity shall be maintained from the instrument, through the field
junction boxes, to incoming screen bar at the marshalling terminals.
Control cables for sensors and actuators shall always be hardwired, field bus
technology shall not be used. Structured cabling shall be applied.
Between the instrument and the local junction box, the cable maybe
supported in metal open conduit system or cable tray; however, for all skid
mounted packages the instrument cable shall be supported in continuous
metal conduit from the instrument to the local panel or junction box, but not
necessarily connected at the ends.
Manufacturer’s data for all cables, materials and fittings shall be approved
by the Engineer prior to purchase.
All cable support systems including trays, fittings and accessories shall be
detailed on instrument electrical hook-up drawings and shall be subject to
the approval of the Engineer.
The cable access to junction boxes, cubicles and marshalling racks shall be
from the bottom. Other kind is subject for approval of Employer / Engineer.
Cable color codes shall be provided for all signals instrument cables. All
cables shall be provided with ferrule for cable identification.
3.11.4.1 Cabling
Prior to installation of cable ladders/trays, the routing shown on the
instrument cable and location layouts shall be checked for interference with
piping, structural and electrical components.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Instrument wiring between the marshalling racks in the technical room (TR)
and field junction boxes shall be wired and connected by means of
identified multipair cables.
All electrical signal cables shall be installed and terminated observing the
following details:
· Special signals cables (such as coaxial cables, fiber optic etc.) shall be
installed in accordance with the seller’s instructions.
· All signal cables shall be individually marked on each side with plastic
markers.
· Special attention shall be paid to the interconnection of cable screens in
such a way that the screening is earthed only at the intended location and
that multiple earthing does not occur.
· Cable glands on equipment in the plant shall preferably be in the bottom
and never in the top, to prevent ingress of water. Where cable glands are
installed in the side wall of the equipment, the cables shall enter from
below. Cables coming from above shall first drop to below the elevation
of the gland.
· All external crevices between cables and cable glands in the plant shall
be sealed with a suitable compound.
· All field single cabling shall be coded with the applicable instrument tag
number close to the junction box.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Where the use of cable glands is not possible for practical reasons, other
systems may be used in consultation with Employer / Engineer. It shall be
ensured that at the cable gland, the cable shields shall be insulated from the
instrument.
All cables should be laid with sufficient length in view of the connections to
be made. For terminal boxes, plug connections and the like, at least one (1)
meter of connection length should be allowed for. For marshalling
racks/boxes, switch fields, control boxes, etc., the cables, if the connection
spot is not known, can be connected up to any spot in the box or any
section.
It is not allowed to connect two (2) or more conductors to one (1) terminal,
unless the terminal is specially equipped for that purpose. For each
deviation, approval from the Employer / Engineer is required.
For special equipment, the cables should be joined in accordance with the
seller’s instructions.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Wire ends shall be identified with closed ring-shaped coding showing the
number of the terminal to which the wire is connected. Color of the ring
coding shall be yellow with black lettering.
For color coding cable conductors/wires refer to IEC 446. For marking of
insulated conductors/wires refer to IEC 391.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The air shall be taken from instrument main air ring and instrument tubing
for pneumatic actuators shall be made of stainless steel (SS316L), plastic
coated (PVC or polyethylene). Tube compression fittings shall double
ferrule type, leak-free, stainless steel (316L).
Compressors provided for instrument air supply shall be of the dry cylinder
type, i.e. which use no oil on the parts exposed to the compressed air.
Each compressor unit shall be provided with its own control panel, being
part of main control network.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4. Control System
Control System will be designed as a total solution, providing necessary
control and monitoring means for all main systems of the whole plant.
Plant operation, monitoring and control shall be foreseen from a CCR thru
standard operator’s workstations (OWS), Workstations from proprietary
systems shall not be accepted. Local emergency push buttons shall also be
provided for the major plant equipment.
For all control, instrumentation and monitoring systems the latest versions
of proven hardware, firmware and software modules, which are available on
the date of shipping, shall be supplied. This is subject to the approval of the
Engineer. However, prototype equipment will not be accepted, only high-
quality systems from reputable suppliers preferably with established local
back-up for maintenance and after-sales technical and spares supports shall
be offered.
For the system offered, a guarantee shall be given that spare parts will still
be available at least 15 years after commissioning of the plant.
The DCS system shall achieve the functions of data acquisition, signal
conditioning, closed loop control, open loop control, calculation, alarm
processing and annunciation, sequence of event recording, historical and
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
All vital system functions that can affect large part of the plant operation
shall be duplicated with automatic bump less/smooth switch over and fault
reporting and diagnostic facilities. A single fault shall not cause a trip or
loss of performance and shall not cause loss of the protection system.
No single control system fault shall directly cause any of the following
conditions:
· complete loss of one boiler/steam generator unit or more,
· Loss of communication between the HMI in the CCR and the plant
control system such that safe shut down and on-line operation cannot be
maintained from the CCR.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
· Any other element a failure of which will disable large portion of the
plant or create an unsafe operating condition.
The data highway system shall be single fault tolerant; one failure in the
data highways shall not reduce the availability of any of the system
components or degrade system performance. Failure recovery shall be
smooth, bump less and automatic. Connection of additional equipment shall
be possible online without disrupting operation. Any data communication
failure shall not disrupt process control.
The assignment of the various displays on the VDUs shall be flexible and
simple, so that in case of failure of a VDU, any remaining VDU can take
over its function.
The power supply source for all the DCS equipment and Operation Stations
shall be dual-redundant. However, in case of total control system power
interruption the DCS shall set all outputs (analogue or digital) to a
programmed fail-safe position.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The I/O modules in the DCS process controllers shall be provided redundant
as follows:
· Signals for close-loop control shall be connected to non-redundant
modules.
· Signals for open loop control shall be connected to non-redundant
modules.
· Protection system signals and control monitoring signals shall be
connected to different I/O modules.
· Protection system signals shall be connected to dual redundant modules.
· Protection system signals being part of 2 out of 3 voting shall be
connected to three different modules.
In addition to the above measures, for areas of the plant in which proper and
reliable functioning of measurements and process control equipment is
essential for the prevention of human injury or death, fail-safe and type-
approved systems shall be employed. All control subsystems shall have a
demonstration or calculation of the MTBF. The Contractor shall provide
MTBF figures related for each subsystem and the overall figure for the
proposed system.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
DCS shall use purely DCS controllers. It shall not use controllers which are
also sold as PLC. Hybrid systems are not acceptable.
Failures shall be indicated by alarms and LEDs, and logged, including the
hardware address of the failed module. All process and C&I alarms shall be
provided with proper texts to indicate the nature of the fault.
The DCS process controller shall be provided as single fault tolerant and
shall be structured as entirely redundant in all specified aspects, including
the processor modules, power supply modules and communication modules.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The processor shall be programmable using DCS software tools, and shall
include, at least, the following capabilities for programming, debugging of
programs and troubleshooting:
· Off-line development of all DCS-related programming, including user
annotation of the program, and creation and printing of application
programs and I/O cross-reference lists.
· On-line programming including IEC-1311 standards program
modification and monitoring of real-time programming execution.
Removal or disruption of any DCS items for on-line programming or
monitoring will not be acceptable.
· On-line status of data and registers. I/O hardware diagnostic and status
information shall be accessible in on-line mode. For DP and HART
instruments, diagnostic programs shall be installed in DCS and activated
for plant time.
· Input/output forcing.
· Control Loops
· Fast control loops 250 ms
· Slow control loops 500-1000 ms
· Scanning time for processors ≤100 ms
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Wire break and short-circuit supervision shall be provided in the I/O level
for all incoming remote field signals, the faulty signal shall be alarmed.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4.3.3 Marshalling
All DCS input/output signals shall be connected to galvanically isolated
Field Termination Assemblies (FTA). Direct connection of field wiring to
the I/O module terminals is not acceptable.
Terminal connectors on the FTA shall provide the connection points for the
process control wiring. Fuses, relays, and resistors shall protect the FTA
circuitry. The assembly shall also provide surge and ESD protection for the
field wiring terminals. FTA terminal connectors shall be screw-type.
The FTA shall communicate with the associated IO module through pin
connectors (single or redundant). The FTA’s shall be installed at the rear or
front of the dual-access DCS’s cabinets.
Interposing relays shall be provided in the FTA’s for all digital output
signals coming out form DCS cabinets.
All FTA’s shall be fed from dual redundant power supply units.
The communication system shall have all necessary fault diagnostics. The
data transmission shall be continuously supervised. Any errors should be
alarmed and recorded in the CCR.
The speed of the data highway shall not be less than 1Gbit/s. The data
highway shall connect all the systems to perform real time information
exchange between the various DCS components.
Loading of the data highway should not exceed 60% with full load
operation.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The data protocol used shall safeguard against erroneous data transmission
and allow for error detection, recovery and initiate switch-over to the
redundant data highway.
The system shall have the ability to calculate required data from membrane
supplier, simulation for Operation training and functional test for any
control loop.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The function blocks will be linked to build the required control functions.
Control blocks should have individual control database. Implementation of
the control functions shall be easily possible using readily understandable
configuration procedures. All configuration modifications shall be
implemented on-line.
The library of software modules shall contain all the functions required for:
· Closed loop control, such as PID, analogue and step output, multivariable
control, bias, cascade control, adaptive gain, etc.
· Standard software modules for motor/actuator control logic shall be
available, covering the functions described under 'Drive control' in clause
‘Open loop control’.
· Standard software modules for sequence control, such as sequence
header and step modules.
· Standard software module for the selection of the operating and stand-by
units and automatic change-over from a faulty unit to the selected
standby unit.
· Calculating functions such as generator capability curves, operating
characteristics, etc.
· Calculating required data from membrane supplier (Membrane
Performance Normalization).
The configuration control software shall include provisions for setting each
loop's scan rate. The configuration software should also be able to be
implemented by means of fill in the blank templates or other user-friendly
approaches that allow the user to easily create and modify control strategies
by lining the predefined algorithms.
The DCS system shall have provision to develop sequences and shall be
capable of being programmed directly from logic flow charts using an
operator-oriented language.
The system shall be furnished complete with working programs. All
software design, development, debugging, reprogramming tasks and final
configuration backups which are required to achieve operation in
accordance with this specification shall be provided and shall be
Contractor’s responsibility.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
For each final control element (FCE), it is preferred that automatic single-
channel closed-loop control shall be provided to ensure that a failure in one
loop will have only limited effect on the plant. This does not apply if the
control loop hardware is in a fully redundant arrangement.
The closed-loop controls shall permit control actions from the open-loop
control functions or systems, such as automatic MANUAL/AUTO
switchover and controlled OPEN/CLOSED actions of the control valve and
shall issue corresponding check-back signals to the open-loop control.
Control loop gain shall be automatically adjusted through parameter control
when the number of effective Final Control Elements (FCE) changes, e.g.
with one or two pumps under closed-loop operation.
Faults in the power supply shall not result in any unwanted or dangerous
switching actions.
Besides the modulating control function PID, the controllers shall contain
facilities for bumbles transfer, anti-reset windup, auto/manual switching,
parameter scheduling, cascading, feed forward control, signal exchange with
open loop controls, etc. Advanced control algorithms shall be provided
wherever they would result in advantages of process control. Due to a better
control quality self-adjustment of control parameters, use of state controllers
also with observer, adaptive controllers or multiple input multiple output
controllers shall be available.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4.4.1.2.1 General
Open loop control shall be hierarchically organized and shall contain
individual drive controls and sequential controls. Protection and safety
interlocks of the drives shall be provided by the open loop control system.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Group controls shall be capable of being switched 'on' and 'off' and shall
have defined commands for 'automatic' and 'manual'.
Any faults in the control system, which could cause the control sequence to
stop, have to be confined to one control sequence. Any faults in the control
system or in the plant equipment shall lead to an automatic changeover from
a faulty unit to an appropriate standby unit.
For this reason, jump conditions shall be foreseen. Before entering in the
step, the sequence logic shall check the status of the jump condition. If the
jump conditions are fulfilled the respective step commands will not be
executed and the control sequence will be continued with the next step of
the sequence. Jump conditions shall not violate any protections or process
safety.
In case if the sequence control stopped and the plant went for a safe
shutdown the cause of the failure shall be indicated in the DCS.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
At least functional groups should be considered for all main pumps. All
necessary function group controls shall be provided, which are necessary for
the intended automatic start of the Plant.
To this module all orders i.e. from the operator station via the keyboard,
step signals of the control sequences, interlocks or protection as well as all
check-back signals of the drive or switchgear shall be connected. After the
processing of these signals the control module shall issue the order to the
switchgear via coupling relays. Drive control in the I/O level of the DCS
shall be utilized for the motorized control actuators and the protection. The
functions of the drive control shall be integrated in a dedicated multichannel
hardware module.
The Contractor shall describe in his offer the hardware and software
modules he intends to use for the drive control. Drive control modules shall
meet the following minimum requirements:
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
In the event of any tripping or failure, a group signal must be passed via the
annunciation equipment and the fault status must be displayed individually
for each drive in the appropriate operation display on the operator station.
The local controls shall act only if selected by a local/remote key on the
local control point. The local/remote signal shall be sent to the drive control
where the selection of the control mode shall be processed. If local
operation is selected, it shall be displayed on the VDU in the CCR and no
operation from other place shall be possible. The command from the
emergency stop push-button of the local control point shall be transmitted
directly to the switchgear.
For unidirectional motor drives (pumps, fans) the issued command shall be
an impulse (e.g. reset by switchgear feedback signal) which shall be
memorized in the switchgear by latching, so that the interposing relays shall
not be permanently energized.
The control command shall be reset by stroke end or by torque switches for
reversing drives (actuators for valves, dampers). Drives/actuators with
intermediate positions shall be designed either with a stop command or for
inching operation.
Solenoid valves that do not exceed the drive control module power limit
may be energized directly from the drive control module.
Individual controls of reversing drives shall be so designed that upon
withdrawing of the control cable plug connector the drive actuator will stop
and it will not be possible to set it in motion.
The control commands from the drive control module to the switchgear
shall be transmitted to the switchgear through two interposing relays at 24 V
DC, one for the ON and one for the OFF command. The coils of the
interposing relays shall be connected with freewheeling diodes.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Active and passive interlocks must not be capable of being switched off
operationally from the control room. All protections have to work fully
automatically and independent of the operator and always have to be
effective for all procedures (manual, partial automatic, fully automatic).
After a stop or close action by protection, the restart of the equipment shall
be possible only after the fault is rectified and the protection signal is reset.
Every safety related loop has to be verified according to the standard IEC
61508, IEC 61511 that the requested and necessary Safety Integrity Level
(SIL) is fulfilled for the individual loop. The Contractor has to assess all
safety related loops to ensure compliance with the related requirements and
has to submit the report of these studies to the client.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The software shall include a DCS simulation and training tools which allow
operators to train on a computer in an environment identical to the control
room.
Through the operating consoles it shall be possible to start or stop the plant's
equipment, control the various valves, pumps, solenoids etc., change modes
and setpoints of controllers. All necessary information concerning process
behavior, control instrument and controller integrity for modulating control,
sequential control and alarm function should be immediately available to the
operator at the operator station.
All analogue signals from field equipment shall be shown on the VDUs, in
the dynamic graphic displays or/and other displays. It shall be possible to
provide a historical and real-time trend display for analogue and status
signals.
For high availability of the plant redundant connection to data highway shall
be provided in all operator stations. The number of operator’s stations shall
assure that in case one operator station fails, the normal operation of the
plant would still be possible using the remaining operator stations.
At any operator station the operator shall be able to choose any kind of
display and execute control on any of the VDUs from any of the keyboards.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The shift supervisor, Engineers and Plant Manager shall have access to all
systems of the Plant for monitoring. It is not foreseen that they will operate
the Plant.
The system shall be provided with the main and bulk memories of adequate
size including 40% spare capacity, i.e. 40% of the installed memory shall be
free for future extended functions after commissioning. If during execution
of this project, memory sizes prove inadequate, Contractor shall increase
memory at no cost.
Bulk memory shall be provided with redundant hard disk drives (RAID 10).
CD/DVD may be used only to load and to extract or store programs or data.
All CPU computers shall be industrial workstation, rack mount type (19”)
and shall be installed in appropriated network rack panel provided with a
KVM switch for keyboard/mouse extension. KVM switch shall allow to
control, switch and manage any PC’s (CPU’s computers) from any
keyboard, monitor and mouse.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The keyboard should have standard operator control keys. All keyboards
used for control of the process should be identical, clearly labelled, and it
shall be provided with a mouse.
All data entry and operator commands should be subject to two steps of
operating action so as not to cause any inadvertent actions. Regularly used
keys shall be of extra rugged design.
For this purpose, graphic elements (plant displays, curves, loop displays,
alarm displays, operating windows etc.) arranged in a hierarchic order shall
display easily, quickly and transparently the status of the plant, of the
control equipment and of the control loops.
The highest demand in the designing of the HMI shall be placed on user
friendly displays. For the control room operator displays for monitoring,
information and control functions shall be provided. The displays shall
present process sequences and statuses in a functionally related manner.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
When particular operator input has been accepted by the DCS, this
condition shall be indicated to the operator by a change of color, short
blinking, short audible tone etc.
In all cases the current and the entered data shall be shown separately.
Standard displays shall be used for adjustment of drives and open/closed
loop controls, e.g. for selection of remote manual operation. All relevant
values of the open loop or the closed loop controller (actual value,
manipulated variable, etc.) shall be displayed. All operator inputs shall be
transferred to the automation system only after the ´Execute´ key has been
pressed.
The grouping of the control loops shall be done based on the system or
equipment mode of operation and is subject to Engineer's approval.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The detailed information shall be card coded or access code word protected
from unauthorized alteration.
All new alarm messages shall be displayed on the next available line and
shall flash until acknowledged from the keyboard. Every new alarm shall
activate a bell for 2 seconds to call the attention of the operator. If more
alarms are detected than are to be shown on the VDU, more recent ones
shall be displayed, and the earlier messages shall be shifted to the alarm
backlog memory. In this case a special message on the screen will indicate
presence of messages in the backlog memory. Recall of backlog messages
on the VDU display shall be provided.
The alarm condition of each point should be displayed on the group display
by color change and blinking. Alarms acknowledge should be possible only
from the relevant (assigned) operator station. For all alarms a direct access
to the dedicated graphic display shall be provided.
On request the system shall list all the alarms implemented in the system,
grouped by equipment or function (i.e. common equipment, electrical etc.),
showing the alarm status of each alarm.
It shall be possible to transfer each VDU from one operator station by the
keyboard in alarm mode or monitoring mode. However, while in the latter
mode, occurrence of any new alarm shall activate the bell and the new alarm
shall be shown on the existing display.
Alarm acknowledgement and first failure resetting shall always be from
VDU’s. Local alarms acknowledge from any equipment or a panel is not
acceptable.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The available storage should be sufficient for all analogue points for a
period of 1 month at a sampling rate of 1 second or better. Varying the
sampling rate or producing averages such as 1 minute, 2 minutes etc. should
make it possible to store more points or for longer periods.
The system should also have a multi-trend feature from which it should be
able to display the set point, measured variable and output of any
combination of variables on the same trend variable.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4.5.1.10 Logging
The system should be able to assemble data and print various kinds of
standard reports.
The system should provide the following basic types of reports as a
minimum:
· Event lists,
· Incident (trip) review log,
· Operator action reports,
· Custom reports with fixed and variable formats.
The above reports should use real time data, historical data, or calculated
data generated, by any node in the system or any connected device to the
system such as PLCs or plant management system. All points in the system
should be available for reporting.
A report generation function should be available at the engineering
workstation for free-format reports generation of text and data.
These reports should be archived for further recall. Schedule assignment for
reports shall be flexible. Demand for immediate output of a report must not
affect any scheduled reports that have been set up previously.
The types or classes of data used by the report generator shall include:
· Analogue variables and associated parameters,
· Operator entered values,
· Status of multi state variables,
· Alarm and event messages,
· Calculated variables,
· Historical data values and status, and
· Other retrievable tagged items.
The report generator shall also be able to incorporate text supplied for report
titles, explanations, messages, etc. Data validity indicators have to be
propagated throughout report production to provide information on the
reliability of requested values.
Math functions to provide more complex reports (more than list of totals
and averages) shall be a standard tool of the report package. The software
package shall be easy to use and not require programming skills.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
· Daily Operating Report: A daily report, listing the major plant variables
(up to 100 variables) shall be provided. The report shall include hourly
values and minimum/maximum/average values where appropriate. A
minimum of 10 separate daily reports shall be provided.
· Monthly Operating Report: A monthly operating report, which averages
the values from the above daily reports, shall be provided. The report
shall include monthly minimum / maximum / average values where
appropriate.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
Alarms should be presented on the alarm display, the first being the newest
non-acknowledged alarm. It shall be possible to implement the first out
alarm in graphical display for the unit/major equipment. Different selection
criteria should be available at least:
· Acknowledged/unacknowledged alarms;
· Priorities or states,
· Period of time,
· Systems or groups, and
· Sources of alarms.
Process alarms and 'return to normal' messages should be shown with a time
stamp as and when they occur. Alarm printing shall be on request of the
operator. The alarm archiving shall be done continually.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The display shall be aesthetically integrated in a panel and into the CCR
environment in a manner that maximizes operator ergonomics. The system
shall be capable of displaying any graphic screen available in the DCS and
special graphic displays created for the large screen projection system. The
system shall be supplied with dedicated keyboards and mouse.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The system shall monitor itself continuously for failures by means of self-
diagnostics. Diagnostic routines shall be applied for each control module.
Detailed diagnostic messages shall be displayed on the engineering
console’s VDU and printer, and group alarms shall be given at the process
operator's desk. The diagnostic display shall clearly identify in graphical
manner the faulty component, the nature of the fault and the component
location (at least panel number, rack number and slot number).
Remote accessibility shall be possible via DSL to allow the specialist for
example to troubleshoot all the DCS components for routine maintenance or
system repair or configuration.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
PMS server shall provide all data information through the office LAN to
following PC clients:
· Shift supervisor office,
· Engineers office, and
· Plant manager office.
PMS server shall provide protected remote access functionality from web
browser.
Configuration and diagnosis of the system shall be possible from the
centralized PC to be located in the Engineering desk of the CCR.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The system shall provide maintenance information and alarms for the O&M
crew to perform predictive maintenance activities.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
5. Communication System
5.1 General
This section of the specification covers all relevant services for the proper
installation of all these communication systems:
· Complete data network fully compliant to Volume IX, Part-B218 Data
network,
· Telephone System (extension of existing one),
· Portable radio system,
· Clock system.
The specified systems will be state of the art and proven for the specified
application. Wherever applicable, the systems shall meet the approval
standards of the local regulatory authorities for the specified application.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The master clock shall provide for highly reliable, accurate and stable real-
time information. It shall be provided with necessary interface for
synchronizing form standard GPS time signal.
The DCS shall have a redundant real time master clock which will be
synchronized by standard GPS time signal.
The real time clock is used for time synchronization for all the DCS and
PLCs components, etc. In case of GPS failed, one of the master clocks shall
lead for the synchronization of all the plant DCS components and other
systems.
The master clock in turn shall provide necessary safe synchronizing signals
to the following:
· The slave clocks (wall mounted, double face, etc.),
· Specified DCS,
· Maintenance/data management system,
· All supplied PLCs,
· All other systems, which requires time synchronizing
.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The DCS shall include as a minimum, but not limited to the following
systems/equipment:
· Redundant Single fault tolerant fiber optical plant bus/highway (Ethernet
TCP/IP in accordance with IEEE 802.3, at least 1 Gbitps), ring topology.
· Redundant Processing Units and Server Units shall be provided to
connect the Plant Bus/highway bus to the Operation Stations.
· Operator stations and large screen monitor in CCR, which are specified
somewhere else in the specification.
· Local operator stations, which are specified somewhere else in the
specification.
· Engineering stations, which are specified somewhere else in the
specification.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
· GRS shall be provided with its own DCS process control stations for
control and protection. In order to maximize the availability and the
reliability of the plant/ units/process, the total number of process control
stations will be defined at beginning of the engineering phase based on
the final plant configuration.
· Redundant interface modules and serial data links to the Package’s PLC
control panels, which are specified elsewhere and subject to the
Employer/ Engineer’s approval.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The necessary data exchange between Package’s PLC’s and PMS shall be
part of the scope Contractor.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
All control desks shall be supplied with audible/ visual equipment for the
DCS alarms and annunciations which shall be of different tones for different
systems.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
At least 20% free space shall be available in all cabinets, junction boxes and
marshalling racks after final commissioning for future ad-on items. This free
space shall be distributed inside the cabinets in such a way that additional
terminals, equipment or modules may be added to any group of controls. At
least 20% spare cores shall be provided in each control and monitoring
cable. All spare cores shall be terminated.
Each module shall be sized such that no more than 60% of its installed
capacity is utilized during normal operation and shall not exceed 80% even
under extreme load condition.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The Contractor is responsible for the overall DCS layout and design of the
entire plant, as well as for the coordination of the interfaces and overall
design of all package control equipment or other control equipment supplied
by other sub-contractors and for making sure that the design of this
equipment and the submitted documentation is in line with the General
Project Requirements and Technical Specification.
As far as the final execution of the work is concerned all design data,
interlocking conditions, control loops and logic diagrams supplied by the
various sub-contractors shall be checked, verified and closely coordinated
with the other sub-contractors of the corresponding equipment. For this
purpose, close collaboration with all sub-contractors supplying control
equipment shall be arranged.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
6.8 Documentation
Bidder to prepare and provide all information and documents necessary for
review and assessment by the Owner / Engineer. Bidder shall use overviews
and zoom into details, represent structures, split, concentrate and use further
methods to simplify comprehension of each equipment, function system and
the plant at large.
· The Bidder shall provide a listing of all DCS hardware and software to be
scheduled, indicating make and type.
· The Bidder shall provide a detailed DCS architecture drawing of the
proposed system. The drawing shall include interconnection of all DCS
components and interfaces with equipment provided by others. All
Process Control Units (PCU) shall be identified with their functional
distribution. Bidder shall state in their bid which of auxiliary and
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
examples filled with data, and associated time schedule for the drawing
approval procedure at the beginning of the design phase. Owner / Engineer
reserve themselves the right to require further documents to be integrated in
the MDL and require additional details to be included in each document.
Out of the finally agreed MDL the Engineer will select the important
documents and the interval for submission.
For each equipment, Bidder shall indicate the Stock Keeping Unit (SKU)
identifier of the equipment manufacturer and a SKU identifier to be agreed
with the Owner. The SKU system for the Owner shall be set up by the
Bidder acc. to Owner’s requirements.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The Contractor shall be, in all cases, fully responsible for the correct
installation and erection with regard to the measuring and control functions
of all the supplied equipment.
The Contractor shall make all necessary provisions for the site testing and
commissioning of the control and instrumentation systems which include
but shall not be limited to the following:
· Test calibration of all instruments prior to installation. The
instrumentation used for calibration or check of operational
instrumentation shall carry a valid test certificate from an approved
authority and not from the contractor.
· Functional test of instruments once installed.
· Loop testing of all measurement and control loops.
· Site demonstration test required confirming that all control and
supervisory function conform to their respective functional specification.
All tests performed on site, including the results and deficiencies, shall be
recorded and the test protocols shall be submitted to the Engineer for
approval.
All cabling for the field equipment shall be supplied, laid, labelled and
terminated. For the supplied field cabling all necessary cable routes,
supporting tray work and intermediate marshalling shall be provided.
Loosely attached nameplates by wires are not acceptable. Label material and
writing shall be selected to withstand the environmental conditions where
they are mounted. The label size and fixing place shall be selected to allow
easy reading.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
6.11 Documentation
All documents and information requiring checking and approval by the
Engineer in accordance with Part 1.3 of this specification shall be submitted.
All-important design documents shall be submitted for approval to the
Engineer as per approved procedure.
6.12 Training
The Tenderer shall include in his offer the provision for training for all I&C
systems and equipment to the client's management, operation and
maintenance staff in accordance with the requirements specified under
Volume VI.
The training shall cover the main control systems like all DCS hardware and
software components, different PLC systems, field instruments
(transmitters, analyzers…), vibration monitoring system, as well as all
communication systems.
4871A95/S133Doc-801060045-7064
CONSTRUCTION OF SALES GAS SUPPLY PIPELINE TO YANBU PLANT
PHASE-3 PROJECT
The Tenderer shall include a list with individual prices of all spare parts he
recommends should be held by the employer to enable the plant to be
operated efficiently considering maintenance and repair.
Any parts ordered must be strictly interchangeable and suitable for use in
place of the corresponding parts supplied with the contract works. Each
spare part item shall be marked with the equipment name and designation
number corresponding to the appropriate section of the operation and
maintenance manuals.
4871A95/S133Doc-801060045-7064