COMPANY : JOINT OPERATIOS. PROJECT : JO-SC459-MM19 - Maintenance of Tanks, Vessels & Welding Services
CONTRACTOR: GULF SPIC.
PROCEDURE NO: LOCATION:MGC/WAFRA. DATE:
REPORT NO: 01
Description Of Work : TISSUE VIUSAL AND THICKNESS INSPECTION OF BOTTOM PLATE AREA AT TK-103
Instruments Used
DATE TIME DRY DEW POINT RH% ST
Instruments
Instrument No. Calibration Status
Used
Dew Point
E 420236 12/27/2022
Meter
Bacth No
Paint Used Manufacturer Color WFT Avg. DFT Thinner No % Of Thinner
Base Curing Agent
2500 NA NA
SURFACE SAINT GOBAIN SGV-525 WHITE.
TISSUE
Hardness
DFT