SECOND STAGE WORK FOR

TRACK CONSTRUCTION
LABIS - KLUANG

Azlan
INDEX
1. SECTION 2 (LABIS – PALOH)
a. M2.12 [CS2.3B – CS2.3C - Up]
b. H2.9 [CS2.5A – Point 101A BEKOK O.S - Dn]
c. H2.15 [Point 102A BEKOK O.S – PALOH - Dn]
d. H2.16 [LABIS – CS2.3B – Up]
e. M2.14 [CS2.3C – CS2.5A – Up]
f. H2.20 [Paloh Station - Dn, Up & UL]
g. H2.19 [CS2.3 –CS2.4 – Dn]

2. SECTION 3 (PALOH– MENGKIBOL)


INDEX

a) M2.12 [CS2.3B – CS2.3C - Up]


CH625+525 – CH626+750 – 1.2KM
• Track migration targeted on 08-Feb-22
• Provision of ballast stockpile has been identified at Ch625.500 Up.
*Alternatively if the stockpile located at Down side, future can be
utilized for H2.19 since the previous stockpile at Ch625.380 Dn &
Ch625.xxx Up are not accessible after migration M2.11 & M2.12.
• Working platform – Provision for working platform required no OCS
planted at this area, Ch625+275 – Ch627+000 Up & Dn.
• Proposed for QCS location to be identified (*QCS2.4 - Ch626+750)
• Formation transfer over from infra to track targeted on 03-Jan-22
INDEX

M2.12 [C&S 2.3B – C&S 2.3C]


SEGAMAT JOHOR BAHRU

Ch625+400

Ch626+750
Ch625+275

Ch627+000
ROB10 (✓)
BC92 (✓)
Ch625+520

Ch626+750
Ch625+500

New Permanent Track TTD / CS Track Proposed New Track Proposed TTD / CS Current Train Existing Track Work in Progress Ballast Stockpile
Installed Installed Operation Line
INDEX

b) H2.9 [CS2.5A – Point 101A BEKOK O.S - Dn]


CH637+500 – CH642+550 – 5.1KM
• Track handover targeted on 18-Jan-22
• Entire formation is under Track possession
• Access for RBM via Bekok OS’s point 101A.
• Ballast stockpile provided at Ch638+800 Up line side.
• 42 strings LWR required – Planned for LWR unloading on 6-Dec-21.
INDEX

H2.9 [CS2.5A – BEKOK O.S]


SEGAMAT JOHOR BAHRU
Ch637+700

Ch642+500
Point 101A
Ch638+800

Ch642+405
Point 101B
Ch638+200

Temp.
Bekok O.S
SM Office

New Permanent Track TTD / CS Track Proposed New Track Proposed TTD / CS Current Train Existing Track Work in Progress Ballast Stockpile
Installed Installed Operation Line
INDEX

c) H2.15 [Point 102A BEKOK O.S – PALOH - Dn]


CH643+300 – CH645+305 – 2.0KM
• Track handover targeted on TBA
• Ballast stockpile was identified at Ch645+000.
• RBMs access via Bekok O.S point 102A.
• Formation transfer over from infra to track targeted on 18-Jan-22
INDEX

H2.15 [Point 102A BEKOK O.S – PALOH PL02]


SEGAMAT
Ch643+300 JOHOR BAHRU
Point 102A

Ch645+248
PL 02
645+000

BC 125

Ch645+153
Ch643+397
Point 102B

PL 01
New Permanent Track TTD / CS Track Proposed New Track Proposed TTD / CS Current Train Existing Track Work in Progress Ballast Stockpile
Installed Installed Operation Line
INDEX

d) H2.16 [LABIS – CS2.3B – Up]


CH617+000 – CH625+525 – 8.5KM
• Track handover targeted on 01-Mar-22
• To be construct after migration M2.12 (Kg. Lanek CS2.3B-CS2.3C Up)
and after Labis Station stage 5 completed.
• Access for RBM via crossover LS03-LS04 at Labis Station.
• Formation transfer over from infra to track targeted on 14-Dec-21
INDEX

H2.16 [LABIS – CS2.3B – Up]


SEGAMAT
Ch643+300 JOHOR BAHRU
Point 102A

Ch617+097
Ch616+965

Ch625+275
LS13
LS12

BRV 16 (✓)
BRV 15 (✓)

BRV 16 (✓)
BRV 17 (✓)
ROB9
ROB8
LABIS
STATION

LS14
Ch617+191
LS11
Ch616+871

Ch625+520
Ch643+397
Point 102B

*622+000

New Permanent Track TTD / CS Track Proposed New Track Proposed TTD / CS Current Train Existing Track Work in Progress Ballast Stockpile
Installed Installed Operation Line
INDEX

e) M2.14 [CS2.3C – CS2.5A – Up]


CH626+750 – CH638+020 – 11.3KM
• Track handover targeted on 01-Mar-22
1. Infra
▪ Outstanding work – Box culvert construction on progress for BC95, BC96,
BC103, BC104 & BC109.
▪ Ground treatment on progress from CS2.3C (Ch627+000) until Bekok PLC
(Ch633+000). Infra target to handover to track by 9-Jan-22.

2. Track
▪ Proposed to bring-in RBM via 2 QCS – QCS2.5A at Ch638+000 & QCS2.4
Ch627+000.
▪ To identified new location for ballast stockpile for north side (*proposed
previous stockpile at Ch628 or new location next to ROB11)
INDEX

H2.14 [CS2.3C – CS2.5A]


SEGAMAT JOHOR BAHRU

Ch637+700
Ch626+750

Ch627+000

Temp.
Bekok
Station

BRV 20 (✓)
BRV 19 (✓)

BRV 21 (✓)
ROB11

BC109
BC96
BEKOK
STATION
Ch626+750

Ch638+200
*Ch628+000 **Ch632+000 Ch637+000

New Permanent TTD / CS Track Proposed New Proposed TTD / CS Current Train Existing Track Work in Progress Ground Treatment Ballast Stockpile
Track Installed Installed Track Operation Line – Infra work
INDEX

f) H2.20 [Paloh Station - Dn, Up & UL]


CH645+200 – CH646+975 – 1.8KM
• Track handover targeted on 15-Feb-22
• T/O PL01 & PL07 to be used for RBM access into CRO area
• Track Down main between PL06 to PL10 to be completed until final
tamping & ballast profiling due ballast train not accessible to stockpile
CH645+250(hence small stockpile on Up main formation to be
created temporarily)
• Formation transfer over from infra to track targeted on 20-Jan-22
INDEX

H2.20 [PALOH STATION – DN, UP & UL]

Ch645+771
SEGAMAT JOHOR BAHRU

PL07

Ch647+553
Ch645+268

Ch646+665

Ch647+533
Ch645+248

Ch645+575

PL13
PL03

PL10

PL12
PL02

PL06

PALOH
STATION

PL11
Ch647+439

PL14
Ch647+648
PL09
Ch646+665
PL01
Ch645+153

PL04
Ch645+362
PL05
Ch645+575

645+250

PL08
Ch646+468
Road Access

New Permanent Track TTD / CS Track Proposed New Track Proposed TTD / CS Current Train Existing Track Work in Progress Ballast Stockpile
Installed Installed Operation Line
INDEX

g) H2.19 [CS2.3 –CS2.4 – Dn]


CH625+525 – CH626+750 – 1.7KM
• Track handover targeted on 03-May-22
• To Identify new ballast stockpile for Down Line
• To Identify location for QCS
• To Identify working platform for both connection at C&S2.3B &
CS2.3C
• Formation transfer over from infra to track targeted on 25-Apr-22
INDEX

M2.19 [C&S 2.3 – C&S 2.4]


SEGAMAT JOHOR BAHRU

Ch625+400

Ch626+750
Ch625+275

Ch627+000
CS2.3 CS2.4

ROB10 (✓)
BC92 (✓)
Ch625+520

Ch626+750
New Permanent Track TTD / CS Track Proposed New Track Proposed TTD / CS Current Train Existing Track Work in Progress Ballast Stockpile
Installed Installed Operation Line