Professional Documents
Culture Documents
Site Supervsion Class Note
Site Supervsion Class Note
Introduction
2
1
5/21/2013
…Continued …Continued
5 6
If the cost per unit of quantity changes, or if the nature or timing of the work in the
Variation does not correspond with items in the Bill of Quantities, the quotation by the Clause 41: Cash flow forecast
Contractor shall be in the form of new rates for the relevant items of work.
When the Program is updated, the Contractor shall provide the
For both Admeasurement and Lump Sum Contracts, if the Contractor’s quotation is
unreasonable, the Engineer may order the Variation and make a change to the
Engineer with an updated cash flow forecast.
Contract Price, which shall be based on the Engineer’s own forecast of the effects of Clause 42: Payment Certificates
the Variation on the Contractor’s costs.
For both Admeasurement and Lump Sum Contracts, if the Engineer decides that the The Contractor shall submit to the Engineer monthly statements
urgency of varying the work would prevent a quotation being given and considered of the estimated value of the work executed less the cumulative
without delaying the work, no quotation shall be given and the Variation shall be amount certified previously
treated as a Compensation Event
For both Admeasurement and Lump Sum Contracts, the Contractor shall not be The Engineer shall check the Contractor’s monthly statement
entitled to additional payment for costs that could have been avoided by giving and certify the amount to be paid to the Contractor.
early warning.
The value of work executed shall be determined by the
Engineer.
…Continued …Continued
7 8
The value of work executed shall comprise the value of: Clause 43: Payments
a) The quantities of the items in the Bill of Quantities completed in the Payments shall be adjusted for deductions for advance
case of Admeasurement Contracts; or payments and retention
b) Completed activities in the Activity Schedule in the case of Lump If an amount certified is increased in a later certificate or as
Sum Contracts. a result of an award by the Adjudicador or an Arbitrator,
the Contractor shall be paid interest upon the delayed
The value of work executed shall include the valuation of payment as set out in this clause
Variations and Compensation Events.
Unless otherwise stated, all payments and deductions will be
The Engineer may exclude any item certified in a previous paid or charged in the proportions of currencies comprising
certificate or reduce the proportion of any item previously the Contract Price.
certified in any certificate in the light of later information. Items of the Works for which no rate or Price has been
entered in will not be paid for by the Employer and shall be
deemed covered by other rates and prices in the Contract.
2
5/21/2013
…Continued …Continued
9 10
Clause 44: Compensation event Clause 47: Price Adjustments
Clause 45: Tax Price Adjustments formula
Unless otherwise specified in the SCC, the Engineer shall not Ln Mn En
adjust the Contract Price if taxes, duties, and other levies are pn = A + b +c +d + etc .
changed that subsequently affect the Contract Price. Lo Mo Eo
Clause 48: Retention
Clause 46: Currencies
Clause 49: Liquidated damage
Where payments are made in currencies other than Ethiopian
Clause 50: Bonus
Birr, the exchange rates used for calculating the amounts to be
paid shall be the exchange rates stated in the Contractor’s Bid. Clause 51: Advance Payment
Clause 52: Securities
Clause 53: Day work
Clause 54: Cost of repair
3
5/21/2013
shall review the records and drawings and either confirm or (b) any other items in the Bill of Quantities including those for Contractor’s
vary them. Equipment, Temporary Works, day works and the like,
Method of Measurement57.1 (c) the percentage of the invoice value of listed materials, all as stated in the
The Engineer shall, within 28 days of receiving such statement, deliver to the Employer
an Interim Payment Certificate stating the amount of payment to the Contractor which
Correction of Certificates60.4
the Engineer considers due and payable in respect of such statement, subject: The Engineer may by any Interim Payment Certificate make any
(a) firstly, to the retention of the amount calculated by applying the Percentage of Retention
stated in the Appendix to Tender, to the amount to which the Contractor is entitled under
paragraphs (a), (b), (c) and (e) of Sub-Clause 60.1 until the amount so retained reaches
correction or modification in any previous Interim Payment
the Limit of Retention Money stated in the Appendix to Tender, and
(b) secondly, to the deduction, other than pursuant to Clause 47, of any sums which may have
Certificate which shall have been issued by him and shall
become due and payable by the Contractor to the Employer.
Provided that the Engineer shall not be bound to certify any payment under this Sub
have authority, if any work is not being carried out to his
Clause if the net amount thereof, after all retentions and deductions, would be less than satisfaction, to omit or reduce the value of such work in any
the Minimum Amount of Interim Payment Certificates stated in the Appendix to
Tender. Interim Payment Certificate
Notwithstanding the terms of this Clause or any other Clause of the Contract no
amount will be certified by the Engineer for payment until the performance security, if
required under the Contract, has been provided by the Contractor and approved by
the Employer.
4
5/21/2013
17
Introduction Introduction
19 20
5
5/21/2013
6
5/21/2013
…cont’d
27
After Three and half months the following works has been
accomplished
Site clearing 100% Completed
Excavation 100% Completed
Foundation 100% Completed
Fencing 100% Completed
Electric 100% Completed
Framing 50% Completed
Plumbing 75% Completed
Paving 50% Completed
The Actual cost incurred till the date of reporting is 152,000 ETB.
What is the status of the project in terms of schedule and Budget?
Is the project behind the schedule or ahead of the schedule?
Is the schedule under budget or over budget?