Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

RECEIVING AND HANDLING between the rigging lines to prevent damage to the

control center.
The unit should be inspected immediately after receipt On units with side mounted compressors, the unit can
for possible shipping damage. be lifted by the three corner fitting eyes and the
All McQuay centrifugal water chillers are shipped f.o.b. extended eye at the compressor end. The center of
factory and all claims for handling and shipping dam- gravity is located approximately where the discharge
age are the responsibility of the consignee. line enters the upper condenser shell. Adjust cable or
chain lengths accordingly. The compressor support is
Leave the shipping skid in place until the unit is in its not designed to support the full weight of the unit.
final position. This will aid in handling the equipment. Therefore, unit must be lifted so that it is level or
canted to assure that the compressor supports leave
Extreme care should be used when rigging the equip-
ment to prevent damage to the control center, or the ground first and touch down last. Spreader
refrigerant piping. bars are a must. (See Figure 5)

On units with top mounted compressors, the unit can LOCATION AND MOUNTING
be lifted by fastening the rigging hooks to the 4
corners of the evaporator where the rigging eyes are The unit should be mounted o n a level concrete or
located. (See Figure 4). Spreader bars should be used steel base and should be located so as to provide

Figure 4

1. Lifting Eyes
2. Condenser Water - In
3. Condenser Water - Out
4. Evaporator Water - Out
5. Evaporator Water - In
6. Victaulic Coupling or Flange
7. Condenser Relief Valve
8. Oil Fiiter Figure 5
9. Spin Down Piston
10. Control Center

JUNCTION 1
BOX I
THESE POINTS MUST LEAVE
THE GROUND FIRST AND
TOUCH DOWN LAST

3
service clearance at one end of the unit for possible should also be adequately insulated. A cleanable 20
removal of evaporator tubes and/or condenser tubes. mesh water strainer should be installed at both inlets.
Clearances required are 18 feet for units with 16 foot Sufficient shut-off valves should be installed to permit
long shells, 14 feet for units with 12 foot shells, and 10 draining the water from the evaporator or condenser
feet for units with 8 foot long shells. Evaporator without draining the complete system.
condenser tubes are rolled into the tube sheets to
permit replacement if necessary. Clearance at all other NOTE: Neither the evaporator nor the condenser is
self-draining; both must be blown out.
points, including the top is 3 feet.
The piping should also include thermometers at the
Make certain that the floor or structural support is inlet and outlet connections and air vents at the high
adequate to support the full operating weight of the points.
complete unit.
The water heads can be interchanged (end for end) so
that the water connections can be made at either end
Rubber Shear-flex pads, or “lsomode”, are supplied
of the unit. If this is done, new head gaskets must be
with unit, for use under each corner of the base mem-
used.
bers. The unit must be level.
It will not be necessary to bolt the unit to the mounting In cases where the water pump noise may be
slab or framework; but should this be desirable, 1-1/8 objectionable, rubber isolation sections are recom-
mended at both the inlet and outlet of the pump. In
inch mounting holes are provided in the unit supports
most cases, it will not be necessary to provide vibration
at the four corners and under the compressor base on
eliminator sections in the condenser inlet and outlet
the side mounted compressor units.
water lines; but where noise and vibration are critical
(for example, where a pipe chase goes through walls
WATER PIPING adjoining living quarters in an apartment building),
they may be required.
N O T E - AVOID THE USE OF 3600 r.p.m. OR
TWO POLE PUMP MOTORS Where a cooling tower is used to supply condenser
water, a flow balancing valve is required.
It is not uncommon to find these pumps operate with
objectionable noise and vibration. OIL COOLER PIPING
It is also possible to build up a frequency beat due to
PEH063, PEH079, PEH100 and PEH126 are equipped
the slight difference in the operating r.p.m. of the
with factory mounted, water cooled oil coolers with
pump motor and the McQuay centrifugal motor.
the oil piping installed. Water piping for the oil coolers
McQuay encourages the use of 1750 r.p.m. or four
must be installed in the field according to good piping
pole pump motors whenever possible.
practice and should include: stop valves to isolate the
cooler for servicing, cleanable strainer (40 mesh maxi-
EVAPORATOR AND CONDENSER
mum), balancing valve to adjust water flow, solenoid
WATER PIPING
operated water shutoff valve wired in accordance with
All PEH and PFH evaporators and condensers come Field Connection Control Diagram, and a drain valve or
equipped with groove-type mechanical clamp or flange plug. Water supply for the oil cooler may be obtained
connections. The installing contractor must provide from:
matching mechanical connections of the sizes given in a. Chilled Water Circuit (preferred and recom-
the system dimension and capacity tables. NOTE: If mended).
welding is to be performed on the mechanical or flange b. Independent Source, such as City Water.
connections, the solid state temperature sensor and c. Cooling Tower Makeup Water to Condenser.
thermostat bulbs must be removed from the wells to
prevent damage to those’components. When the oil cooler is piped into the chilled water
supply, its water piping should be connected across
Small water pressure test valves or pipe plugs are pro- the chilled water pump so that the full pressure
vided at both the inlets and outlets of the vessel heads. differential of the pump is maintained across the cooler
The test valves permit the water flow pressure drops to system at all times the pump is running. This is the
be checked. The pressure drops and flow rates for the
various evaporators and condensers are shown in
McQuay catalog 950. Refer to the nameplate on the TABLE 1
vessel shell for identification. I 1

III
Figures 4 and 5 show the inlets and outlets of the Maximum Oil Cooler Water Requirements
evaporator and condenser. The evaporator is con-
nected with the warmest water entering at the top.
This reduces the number of tubes required for super-
heating. The condenser is connected with the coolest
water entering at the bottom to maximize subcooling. @ 85 F Entering Oil Coolers Only 1
NOTE: When common piping is used in connection - GPM
with a heating system, care should be taken to insure 8.0
that water flowing through the evaporator cannot ex- 8.0 1.2
ceed 11O’F which can cause the relief valve to dis- 12.25 2.0
charge refrigerant or damage controls. 16.0 6.0”
The piping should be supported to reduce the weight *Pressure drop through two oil coolers with water sides piped in
and strain on the fittings and connections. Piping series - PEH 126 only.

4
Figure 6 On all other PEH centrifugal chillers, a refrigerant
cooled oil cooler is supplied on a special order basis
when water of suitable temperature is not available
either from an external source or at the evaporator.
Subcooled liquid from the condenser is fed to the oil
cooler through an oil temperature control valve whose
control bulb is located on the oil line leaving the oil
cooler. The gas - liquid mixture returns to the inlet of
the evaporator. Refrigerant flow is controlled to main-
tain an oil temperature of approximately 80-lOOoF.

VENT PIPING
As a safety precaution, each system is equipped with
pressure relief valves located on the condenser and on
the evaporator for the purpose of relieving excessive
refrigerant pressure to the atmosphere. Many local
codes require that relief valves be vented to the
outside, and this is desirable installation practice for all
installations. NOTE: Remove plastic shipping plugs (if
installed) from the inside of the valves prior to making
pipe connections. Whenever vent piping is installed,
the lines should be run in accordance with local code
requirements; or where local codes do not apply,
ANSI B9-.1-Sec. 12 code recommendations should be
followed.
recommended arrangement, and most systems will
accommodate it. For those installations where it could Current condenser design incorporates 2 relief valves
be desirable to pipe the oil cooler system across the (1 set) with a 3-Way shutoff valve separating the two
evaporator, this may be done providing the water valves. (See Figure 7). When piping the vent line to a
pressure drop through the evaporator is greater or dual valve set, it may be sized for one relief valve and
equal to the oil cooler pressure drop given in Table 1. piped to both valves. If one relief valve of the two
valve set fails, the shutoff valve may be used to isolate
When supplied with city water, the oil cooler water the faulty relief valve, easing in replacement. On larger
piping should discharge into an open drain to prevent capacity condenser designs, two sets of dual relief
draining the cooler by siphoning. This water may also valves are used. These vents must be sized to the total
be used for cooling tower makeup by discharging it of the two valve sets.
into the tower sump from a point above the highest
possible water level.
Figure 7 Condenser Relief Valve Set
The water flow through the oil cooler must be adjusted
with the balancing valve so that the temperature of oil
supplied to the compressor bearings (leaving the oil
cooler) is not less than 80°F nor more than 1 1 0 On
systems using chilled water for a cooling medium, the
leaving oil temperature should be on the low side of
the acceptable temperature range when operating with
the coldest water. Long shutdown periods will pro-
duce higher than normal chilled water temperatures at
startup and will result in higher oil temperatures until
the chilled water temperature is reduced.

On some units, oil cooler water solenoid valves are


1. dl Relief Valve
factory furnished. On those units where the solenoid 2. #2 Relief Valve
valve is required and not furnished, the installing con- 3. Relief Valve 3-Way Shutoff
tractor must supply the solenoid valve. Recommended 4. 3-Way Access Valve
is ASCO type 8210B27 (McQuay Part No. 350A484H45)
or a McQuay approved solenoid valve of comparable
quality. ELECTRICAL
Under no circumstances should the oil cooler be piped POWER WIRING
in parallel with a single pass evaporator. This will result
in inadequate cooling water to the oil cooler. Wiring, fuse and wire size must be in accordance with
information located in the Electrical Data. Standard
N O T E : Water entering the oil cooler should NOT NEMA motor starters require modification to meet
exceed 9O’F. McQuay specifications. Refer to Electrical Data sup-
plied with the unit or McQuay Catalog 950 or 960 for
REFRIGERANT COOLED OIL COOLERS details.
PEH and PFH units equipped with CEO46 /048/050 IMPORTANT: The voltage to these units should be
compressors utilize refrigerant cooled oil coolers within the limitation of plus or minus 10%, and the
mounted inside the compressor crankcase. voltage unbalance between phases must not exceed

5
3%. Since a 3%% voltage unbalance will cause an connect the delta winding, when the motor comes up
approximate 25% increase in motor temperature, it is to speed and before any speed reduction occurs.
most important that the unbalance between phases be
at a minimum. All units are factory equipped with open transition
starters. Closed transition starters are supplied on a
PEH063/079/100/126 POWER WIRING special order basis.
Power wiring to compressor must be in proper phase NOTE: Do not make final power connections to
sequence. Motor rotation is set up for clockwise the starter until wiring has been checked and
rotation facing lead end with phase sequence of l-2-3. approved by an authorized McQuay service repre-
Care should be taken that proper phase sequence is sentative. Under no circumstances should the
carried through the starter to compressor. With the compressor be brought up to speed unless proper
phase sequence of l-2-3 and L1 connected to T1 and phase sequence and rotation have been estab-
T6, L2 connected to T2 and T4 and L3 connected to lished. Serious damage may result if the com-
T3 and T5, rotation is proper. See diagram in terminal pressor starts in the wrong direction. Jog the
box cover. machine to check rotation using the sight glasses
on the rear motor cover to observe direction.
Phase sequence can be determined by using GE
No. 546703265 phase sequence meter or equal. Before CONTROL WIRING
connecting the starter load leads to the compressor
terminals and while checking the field connection The control circuit on the McQuay PEH 063/079/100 &
wiring the transition timer in the starter should be 126 packaged chiller is designed for 115 volts. Power
adjusted to make the transition at approximately 6 to should be supplied from a separate circuit and fused at
15 seconds. This should be reset when the compressor 30 amps. The control circuit on the PEH and PFH 046/
is put on the line. The timer should be adjusted to 048/050 unit is designed for 115 volts A/C. Power is
actuate (disconnect Star winding connection and supplied to the control panel by a .75 or 1 KVA 115
connect Delta) when the motor has come up to speed volt transformer supplied and mounted in the starter
and before any speed reduction occurs. package.
The disconnect switch should be tagged to prevent
CAUTION: Wiring connection to compressor
current interruption. SWITCH IS TO REMAIN ON
terminal studs must be made with copper lugs
AT ALL TIMES IN ORDER TO KEEP OIL
and copper wire.
HEATERS OPERATIVE AND PREVENT REFRIG-
Care should be taken when attaching leads to ERANT FROM ACCUMULATING IN OIL.
compressor terminals. NOTE: Do not make final
The control center off-on switch should be turned to
connections to motor terminals until wiring has
the “off” position any time compressor operation is
been checked and approved by a McQuay repre-
not desired.
sentative.
In the event control voltage is supplied by a trans-
Under no circumstances should compressor be
former, the transformer should be rated at 2 KVA, with
brought up to speed unless proper phase sequence
an inrush rating of 12 KVA minimum at 80% power
and rotation have been established. Serious damage
factor and 95% secondary voltage. For control wire
may result if compressor starts in wrong direction.
sizing, refer to the N.E.C. article 215 and 310. In the
Jog machine to check rotation using sight glasses on
absence of complete information to permit calcula-
the rear motor cover to observe direction.
tions, the voltage drop should be physically measured.
PEH AND PFH046/048/050 POWER WIRING Again the disconnect switch should be marked to pre-
vent control circuit from being de-energized. Water
All PEH and PFH 046/048/050 units are supplied with a flow interlock terminals are provided on the control
factory wired and mounted star delta starter equipped center terminal strip. See field connection diagram in
with ambient compensated quick trip overloads, fac- the Electrical Data or in cover of control center for
tory set at 115% F.L.A. Wiring, fuse and wire size proper connections.
must be in accordance with information located in the
electrical data supplied with the unit or the McQuay The purpose of the water flow interlocks is to prevent
Electrical Data pertaining to your unit. compressor operation until such as time as both the
evaporator water and condenser water pumps are
I M P O R T A N T : The voltage to the unit must be running.
within the limitation of plus or minus 10%, and the
voltage unbalance between phases must not exceed WARNING: Severe damage to the compressor can
3%. Since a 3-1 /2% voltage unbalance will cause an result if the anti recycle timer is turned to the OFF
approximate 25% increase in motor temperature, it is position and the flow switches operate intermittently.
most important that the unbalance between phases be
Operation of the chilled water pump may be to cycle
at a minimum.
the pump with the compressor, operate continously,
The power wiring to the compressor starter must be in or started automatically by a remote source. The cool-
proper phase sequence. Phase sequence can be ing tower pump MUST cycle with the machine. The
determined by using a GE No. 546703265 phase holding coil of the cooling tower pump motor starter
sequence meter or equal. Motor rotation is set up for must be rated at 115 volts 60 Hz with a maximum volt-
clockwise rotation facing the rear end of the compres- amperage rating of 100. If this volt-amperage rating is
sor with a phase sequence of 1-2-3. Care should be exceeded, a control relay is required.
taken that the proper phase sequence is carried
through the starter to the compressor. All interlock contacts must be rated for no less than 10
inductive amps. The alarm circuit provided in the
The transition timer in the starter is factory set at six control center utilizes 115 volts A/C. The alarm used
seconds to disconnect the star winding connection and should not draw more than 10 volt-ampere.

6
Figure 10 PEH 050 (Rear View)

1.. Oil Cooler 8. Suction Shutoff Valve


2. Discharge Check Valve 9. Condenser Pressure Relief Valve
3. Discharge Victaulic Coupling 10. Evaporator Pressure Relief Valve
4. Motor Cooling Liquid Line 11. Condenser Water Inlet
5. Motor Terminals 12. Condenser Water Outlet
6. Expansion Valve 13. Evaporator Water Inlet
7. Liquid Line Shutoff Valve 14. Evaporator Water Outlet

TESTING CONTROL CIRCUIT motor control relay should deenergize at the same
time.
Set the (TDR) time delay relay to “0”, manually open
Upon completion of power and control wiring, the the safety controls, one at a time, and observe the
circuit should be tested functionally; but in doing this, starter or MCR. Each switch should interrupt the
the compressor MUST NOT be started. Wire connec- starter or the MCR relay and light an indicating light.
tions to compressor motor terminals on PEH063/079/ Stop the water pump. This also should open the
100/126 units must not be made until wiring has been starter circuit.
approved by a McQuay Service Representative.
Wire connections on PEH and PFH 046/048/050 units REPAIR OF SYSTEM (If Necessary)
must not be made to the starter until wiring has been
approved by a McQuay Service Representative.
PRESSURE TESTING
The first few minutes of compressor operation are
important and require careful observation of all operat- No pressure testing is necessary unless some damage
ing characteristics. was incurred during shipment. Damage may be deter-
mined upon a visual inspection of the exterior piping
The circuits can be completely tested without energiz- assuring no breakage occurred or fittings loosened.
ing the compressor. Panel gauges should show a positive pressure. If no
In cases where a separate control voltage source is pressure is evident on the gauges, a leak may have
furnished, it is only necessary to energize the control occurred discharging the entire refrigerant charge.
circuit with compressor disconnect switch open. In this case, the unit should be leak tested to
determine the location of the leak.
Correct operation of time delays, safety and interlocks
can be determined by observing operation of relay LEAK TESTING
“MCR” (motor control relay) located in starter. (Fur-
nished by starter manufacturer.) In the case of loss of the entire refrigerant charge, the
On systems using a transformer wired from compres- unit should be checked for leaks prior to charging the
sor disconnect to obtain control voltage, it will be complete system. This can be done by charging
necessary to remove load leads from the starter to enough refrigerant into the system to build the
compressor and observe starter operation. pressure up to approximately 10 PSIG and adding
sufficient dry nitrogen to bring the pressure up to a
All field interlock connections should be checked for maximum of 125 PSIG and then leak test with a Halide
proper operation by stopping each pump in order. The or electronic leak detector. Water flow through the
8
vessels should be maintained any time refrigerant is event the refrigerant charge was lost due to shipping
added or removed from the system. CAUTION: DO damage, the system should be charged as follows after
NOT USE OXYGEN TO BUILD UP PRESSURE AS first repairing the leaks and evacuating the system.
A SERIOUS EXPLOSION CAN RESULT. A pressure
regulating valve should always be used on the drum a. Connect the refrigerant drum to the gauge port on
being used to build up the system pressure. Also, do the liquid shutoff valve and purge the charging line
not exceed the test pressure given above. When the between the refrigerant cylinder and the valve.
test pressure is reached, disconnect the gas cylinder. Then open the valve to the mid position.

If any leaks are found in welded or silver soldered b. Turn on both the cooling tower water pump and
joints or it it is necessary to replace a gasket, relieve chilled water pump and allow water to circulate
the test pressure in the system before proceeding. For through the condenser and the chiller. (It will be
copper joints, silver solder is recommended. necessary to manually close the condenser pump
starter).
After making any necessary repair, the system should
be evacuated as described in the section following. C. If the system is under a vacuum, stand the
refrigerant drum with the connection up and open
the drum and break the vacuum with refrigerant
EVACUATION gas.
After it has been determined that there are no d. W ith a system gas pressure higher than the
refrigerant leaks, the system should be evacuated equivalent of a freezing temperature, invert the
using a vacuum pump with a capacity of approximately charging cylinder and elevate the drum above the
3 cu. ft./min. and that will reduce the vacuum to at condenser. With the drum in this position, valves
least 1 millimeter (1000 microns). open, water pumps operating, liquid refrigerant will
flow into the condenser. Approximately 75% of the
A mercury manometer, electronic or other type of total requirement estimated for the unit can be
micron gauge should be connected at the farthest charged in this manner.
point from the vacuum pump. For readings below 1
millimeter, the electronic or other micron gauge should e. After 75% of the required charge has entered the
be used. condenser reconnect the refrigerant drum and
charging line to the service valve on the evaporator.
The triple evacuation method is recommended and is Again purge the connecting line, stand the drum
particularly helpful if the vacuum pump is unable to with the connection up and place the service valve
obtain the desired 1 millimeter of vacuum. The system in the open position.
is first evacuated to approximately 29 inches of
mercury. Enough refrigerant vapor is then added to the
system to bring the pressure up to zero pounds.
Then the system is once again evacuated to approxi-
mately 29 inches of mercury. This is repeated 3 times. IMPORTANT
The first pull down will remove about 90% of the
non-condensables, the second about 90% of that At this point the charging procedure should be
remaining from the first pull down and after the third interrupted and prestart checks made before attempt-
only I-10 of 1% non-condensables will remain. ing to complete refrigerant charge. The compressor
must not be started at this time. (Preliminary check
CHARGING THE SYSTEM must first be completed).
PEH and PFH water chillers are leak tested at the Operation and Maintenance manuals pertaining to the
factory and shipped with the correct charge of re- individual PEH or PFH unit are available from your local
frigerant-12 as indicated on the unit nameplate. In the McQuay Representative.

WARRANTY

The McQuay chiller is covered by a standard published warranty which covers parts only, excluding refrigerant
and oil. A complete published description of that warranty and its limitations is provided in a warranty certi-
ficate included with each unit.
Additional, separate warranty labor and complete maintenance coverage may be purchased separately. Contact
your local McQuay Service Office.
PRE-START SYSTEM CHECKLIST

Not
Yes No Applicable

CHILLED WATER

Piping complete
Water system filled, vented 1 1
Pumps installed, (rotation checked) strainers cleaned
Controls 13.way valves, face and by-pass dampers, by-pass valves, etc.! operable
Water system operated and flow balanced to meet unit design requirements

CONDENSER WATER

Cooling tower flushed, filled and vented _:


Pumps installed, (rotation checked) strainers cleaned
Controls (3.way valves, by-pass valves, etc.) operable
,-I
Water system operated and flow balanced to meet unit requirements I

ELECTRICAL

115.volt service completed, but not connected to control panel


“Power leads connected to starter; load leads run to compressor ready for connectlon when
Service Engineer is on hand for start-up
(Do not connect to starter or compressor terminals)
All interlock wiring complete between control panel and complies with specifications

Starter complies with specifications


*Oil cooler solenoid wired to control panel as shown on wiring diagram
Pump starter and interlock wired ! I
Cooling tower fans and controls wired 1:
Wiring complies with National Electrical Code and local codes I ’
*Condenser pump starting relay (HWRI installed and wired.

MISCELLANEOUS

Oil cooler water piping complete. (Units with water cooled oil coolers only) I
Relief valve piping complete
Thermometer wells, thermometers, gauges, control wells, controls, etc. installed
A minimum system load of 25% of machine capacity is available for testing and adjusting controls I 1

10

You might also like