Generic Removal Manual - Critical Procedure REV. 4 - Jacket Rigup Methods
Generic Removal Manual - Critical Procedure REV. 4 - Jacket Rigup Methods
9
RIGGING INSTALLATION – JACKET BOTTOM SECTION
Step 1 : Step 2 :
• Lower down rigging arrangement assembly with spreader frame guided by • Set spreader frame on top of cut legs.
ROV. • Prior setting, ROV to make sure that each individual slings are entering
correct quadrant of jacket openings.
10
RIGGING INSTALLATION – JACKET BOTTOM SECTION
Spreader frame
set on top of jacket
leg cut off.
Sling is positioned
at each quadrant
12
RIGGING INSTALLATION – JACKET BOTTOM SECTION
13
RIGGING INSTALLATION – JACKET BOTTOM SECTION
14
RIGGING INSTALLATION – JACKET BOTTOM SECTION
Step 3 : Step 4 :
• ROV to connect rigging for each legs assisted by deck crane. • ROV to connect rigging for each legs assisted by deck crane.
15
RIGGING INSTALLATION – JACKET BOTTOM SECTION
Step 5 : Step 6 :
• ROV to disconnect rigging for spreader frame. • Raise up main block to slightly pick up slack on the riggings.
16
RIGGING INSTALLATION – JACKET BOTTOM SECTION
Step 7 : Step 8 :
• ROV to connect rigging from deck crane and deck tugger. • Raise up the spreader frame supported by deck tugger and deck crane.
• Move barge slightly to clear main block rigging from spreader frame..
17
RIGGING INSTALLATION – JACKET BOTTOM SECTION
Step 9 : Step 10 :
• Deupend the frame by raising up deck crane hoist. • Once deupend, disconnect rigging by deck tugger by ROV
• Lift spreader frame to main deck.
• Proceed with lifting operation.
18
2021 WELLHEAD PLATFORM AND PIPELINE INSTALLATION AND WELLHEAD
PLATFORM REMOVAL CAMPAIGN
19
2021 WELLHEAD PLATFORM AND PIPELINE INSTALLATION AND WELLHEAD
PLATFORM REMOVAL CAMPAIGN
Sling Hanger
20
2021 WELLHEAD PLATFORM AND PIPELINE INSTALLATION AND WELLHEAD
PLATFORM REMOVAL CAMPAIGN
Pre-lay sling
Step 2 :
• Prelay sling for each
18mm Dia. x 6.5 m lg. wire rope
legs on seabed as per
12 T Shackle sling position shown. This
activity can be done as
meanwhile.
• Install sling hanger at
top of each legs cut-off
after pile has been
removed.
• Lower down pulling
sling using crawler
crane.
21
2021 WELLHEAD PLATFORM AND PIPELINE INSTALLATION AND WELLHEAD
PLATFORM REMOVAL CAMPAIGN
12 T ROV Hook
(Typ.)
18mm Dia. x 41 m lg. wire rope sling
Step 3 :
• Lower down pulling
sling at either side of
the horizontal brace.
• The pulling sling is
designed to be 8 m
longer on 1 side to
make it easier to lower
down by ROV
monitoring.
22
2021 WELLHEAD PLATFORM AND PIPELINE INSTALLATION AND WELLHEAD
PLATFORM REMOVAL CAMPAIGN
Step 4 :
• As the pulling sling is
being lowered into
jacket, ROV to grab and
Bring pulling sling out of jacket bring it out of jacket.
• ROV to connect with
the pulling wire on the
main lifting sling.
23
2021 WELLHEAD PLATFORM AND PIPELINE INSTALLATION AND WELLHEAD
PLATFORM REMOVAL CAMPAIGN
Step 5 :
• Slowly pull up the sling
into jacket while ROV
monitoring the path.
• Once the first eye arrive
near sling hanger
elevation, ROV to grab the
hanging wire and slot into
sling hanger.
• The sling weight can be
transferred to sling hanger
by lowering down pulling
sling.
• Once pulling sling slack,
ROV to disconnect the
24 ROV shackle.
2021 WELLHEAD PLATFORM AND PIPELINE INSTALLATION AND WELLHEAD
PLATFORM REMOVAL CAMPAIGN
Step 6 :
• Repeat sling hanging for
other side of the leg.
• Repeat the entire steps for
other 3 remaining legs to
be done as meanwhile as
practically possible.
25
2021 WELLHEAD PLATFORM AND PIPELINE INSTALLATION AND WELLHEAD
PLATFORM REMOVAL CAMPAIGN
Step 7 :
• Once all legs are pre-
rigged with the main
slings, lower down upper
legs sling.
• Make the hydraulic
shackle connection to the
hanging sling eye.
• Once sling eye is inside
shackle body, close the
pin hydraulically.
26
2021 WELLHEAD PLATFORM AND PIPELINE INSTALLATION AND WELLHEAD
PLATFORM REMOVAL CAMPAIGN
Step 8 :
• Connect ROV hook connection on the other side of the leg.
• Repeat the process for other 4 legs.
• If required :
• Upper legs rigging for other 3 legs are tied back to
connector plate first and only release when required to
make connection to lower leg sling.
• Tugger / crawler crane can be used to hold the
hydraulic shackle / rov hook so that it is easier to make
connection to sling eye.
27