Professional Documents
Culture Documents
Discharge 02
Discharge 02
1. Inspection and checks before starting the discharging operation (P2-2 to P2-4)
Perform the inspections and checks mentioned below before starting the discharging operation.
After starting the cargo pump, confirm that there are no abnormalities in the various pump components
and then start the tasks mentioned below.
Always confirm that all valves are closed before starting the discharging work and ensure "zero start."
If some valves have been opened for eliminating the liquid-sealed condition, they should be closed
before the discharging work and "zero start" should be ensured. Note however, that the IG branch
The rule commonly-referred to as "zero start" should be adhered to before loading/discharging. "Zero start" refers
to closing all valves except the IG branch valves before commencing valve lineup. Thus, checks should be made
to confirm that all valves are closed before starting the cargo handling operation. Some valves may have been
opened for eliminating the liquid-sealed condition. These valves should always be closed before the cargo
handling operation to ensure "zero start." This rule also applies to work performed when the ship is underway.
The aim of "zero start" is to prevent major accidents such as overflow or contamination of cargo in the tank that
could occur when valves that have been opened for eliminating the liquid-sealed condition are not closed due to
oversight and oil flows through such valves into the tank without anybody being aware of it.
1.2.3 Sealing tape (special seal) for valve operating switches on the cargo console
Measures to prevent operation of unused valves by mistake should be adopted by affixing relevant
seals on their operating switches on the cargo console after fully closing the said switches and capping
them. Care should be taken to affix such seals so that the valve number, valve position and tank number
are clearly visible even after affixing the seals.
To prevent errors in operation of valves at the discharging site, the valve operation is being performed in the
presence of the safety supervisor when a safety supervisor is deputed to the ship. Although check lists are also being
used to ensure correct valve operations, it is impractical to perform all the work by check lists alone.
The cargo handling supervisor should be fully aware of the purpose of the operation before operating
the valve and should perform checks to ensure that there is no mistake. (confirmation by pointing out
and repeating the actions aloud)
1) During ullage measurement and recording of each tank in the CCR before starting the discharging
operation, the measurements should be compared with the records during loading voyages and
checked for abnormalities. Not only should ullage measurement values of each tank be recorded
before starting the cargo handling operation, but they should be displayed in front of the cargo
console so that changes in ullage of tanks that have not been discharged can be immediately
known.
2) Ullage of tanks that have not been discharged varies according to changes in trim and heel.
Therefore, measured values should be compared with values that have been corrected for trim, list,
etc.
3) If the values after applying the necessary correction differ from initial values, it is a sign that major
problems are likely to occur. Such abnormalities should be reported immediately to the Chief
Officer.
4) Major problems mentioned above include simultaneous discharge of cargo other than the cargo to
be discharged and cargo contamination *15. Such problems in addition to causing economic loss
will also cause reliability problems and lead to tangible and intangible losses. When such
phenomena occur, the cause may be due to abnormalities in valves, pipes or other structural
problems in addition to operational errors.
5) Ullage measurement of all tanks should be carried out at least once every hour regardless of
whether the tanks are being loaded or discharged, the measured values until that time should be
compared and changes if any, should be checked. Merely performing checks is not adequate, and
implies maintaining records only. The measured values should always be compared with values
before the start of cargo handling operations.
6) If a large difference in ullage is observed even though the degree of opening of the valve in the tank
being discharged is the same as that of other tanks, then the level gauge may be defective. However,
the difference may also be attributed to closure (opening of valve overlooked) of the IG branch
valve or closure of the valve due to a broken spindle. When discharging is continued with the valve
in the closed condition, major accidents such as denting of the tank may occur.
In such cases, discharging should be stopped immediately and the cause of the abnormality
investigated.
1) Measuring equipment
a) Float
b) MMC *12
c) Tape measure
d) T-square *13 etc.
2) Actually-measured locations
a) Stand for MMC
b) Ullage stand
* What is commingling?
Commingling is different from contamination in that different types of cargo are mixed knowingly
under instructions of the charterer.
1) Check and record the pressures of all tanks, manifold pressure on both sides of the ship, P/V
breaker indication and IGS control pressure. Confirm that none of the recorded values are
abnormal.
2) If the deck watch detects gas odors or abnormal noise, the breather valve fitted in each tank or the
breather valve of vent riser has probably activated. Crew members should be trained to report such
abnormalities to the officer of the watch immediately upon detection of the same.
3) Efforts should be made to detect abnormalities at an early stage especially in the initial stage of the
discharging operation by frequently checking the pressure of the tank being discharged.
1) Check for negative pressure in the cargo line by observing the suction pressure of the pump.
2) If negative pressure exists, open the gas intake valve installed in the cargo tank, supply gas to the
cargo line using the tank pressure to attain positive pressure in the cargo line. The method of
opening the air cock at the upper part of the strainer tank or the pump casing for attaining positive
pressure is a secondary method presently and is not normally used.
1) Method of bleeding out air in the suction line from delivery tank to pump by opening the pump
discharge valve
2) Bleeding out air using the stripping pump
This method is used when the level of oil in the tank to be discharge is inadequate and priming is not
possible with the available weight of oil.
For details of AUS (Automatic Unloading System), please refer to "2.5 Priming of cargo pump in
AUS-equipped ships" on P2-10 of the "Discharging Section."
1) When oil is delivered from a tank with adequate head*17 with negative pressure in the suction line,
the pump may be damaged due to the water hammer effect. Therefore, take adequate precautions to
prevent negative pressure. Precautions are necessary since damage to pump/line/valve generally
occurs because of the water hammer effect.
2) The air cock on the upper part of the strainer tank or the pump casing is generally not used for
bleeding air from the suction line because of the reasons mentioned below.
a) There is a risk of accidents to workers from gas inhalation especially when the crude oil contains a
high hydrogen sulfide content.
b) Crude oil extracted from the air cock cannot be allowed to remain as it is in the pump room.
c) Piping for gas detector is installed near the cargo pump. The detector monitors the pump room all
the time.
Under such conditions, bleeding of air in the pump room will set off gas detector alarms frequently,
and the awareness for the alarm will be reduced.
3) If the air is not bled out of the pump adequately and the pump is operated (dry operation), the pump
rpm becomes high due to no load or low load. This may cause turbine failure, wear or damage of
the mechanical seal, or damage to the bearing or gland. An overspeed tripping device is provided
for the safety of the pump. If the rpm reaches about 115% of the rated rpm, the pump trips and
initiates an emergency stop.
* 17 What is head?
Refers to the pressure received from the liquid in the tank. When the level of liquid in the tank is high,
that is, when the ullage is small, the tank is said to "have a head." In practice, the pressure due to
weight of a water column of 10 m for water at normal temperature is about 0.1 MPa (1 kg/cm2), or
conversely, a pressure of about 0.1 mPa (1 kg/cm2) is equivalent to a water column of 10 m.
1) Keep open the segregation valve of the cargo line to be used before priming the pump.
2) Crack open *18 the tank main valve and start priming. The pump suction pressure rises. Confirm
that the line from the tank to the pump is fully filled with oil. Then crack open the pump discharge
valve, perform gas purging of cargo tank through the gas intake valve *19 and finish the priming
operation.
2.4.2 Specific example of priming when the oil level is adequate high
(Refer to "Line Diagram" in Fig. D-2-1 of P2-1 and "Line Diagram" in Fig. D-2-2 of P2-2 in the
"Documents Section.)
To discharge 1C/3C/5C using 3 cargo pumps, one tank cleaning pump and three manifolds on the ship,
air is bled according to the procedure described below.
1) If the pressure in the suction line to the pump is negative, open the valves shown below to
eliminate the negative pressure. Use the tank pressure to attain positive pressure in the line.
2) Confirm that the suction gauge pressure of each pump is positive and close the valves shown
below.
When priming the pump, oil should also be filled in the stripping line in principle, and the line should be kept ready
for use whenever required.
3) Open the line segregation valve in the tank to share each group.
4) To prevent opening the bulkhead valve abruptly, repeat the opening and closing operations, and
after confirming no abnormality, open it fully.
Bulkhead valve V111, V121, V131 Open and close repeatedlyÆOpen fully
5) Repeat the opening and closing operations for valve in the stripping line also similarly and open the
valve fully.
Stripping line valve V142, V141 Open and close repeatedlyÆOpen fully
6) Crack open the suction valve of 3C and start oil delivery to the pump. If there is no abnormality at
the crack opening of the suction valve, open the suction valve by 10%.
7) Continue to deliver oil gradually in this condition until the pump suction pressure increases to the
tank head pressure.
8) Confirm that the pump suction pressure has risen to the tank head pressure.
9) Open the discharge valve of each pump from the crack open position to 10% open position and
bleed out air from the series of suction lines. Perform this operation for each cargo pump at a time,
and not two or three pumps simultaneously.
10) The gas in the suction line and the pump will be pushed into 3C. When the riser is filled with oil,
fully open the pump discharge valve to end the priming operation.
1)
Tank suction line V252, V121, V122 Open
2)
Stripping suction line V561, V525, V164 Open
3)
Stripping delivery line V168, V167, V182 Open
Valves associated
with the stripping V561, V525, V164, V168, V167, V182 Close
pump
6) When the tasks mentioned above have been completed, confirm that the cargo pump discharge
valve is fully closed and the suction valve is fully open. The cargo pump can now be started.
If priming operation for cargo pump equipped with AUS system is not adequately done、serious trouble such as blow off
oil may be occur. To display confirmation and caution which is described in below section 2.5.1 and 2.5.2 and to display
also valve open or shut status board for associated valve.
1) Confirm that the suction line to the cargo pump has been properly connected.
2) Open the bleed main valve (the worker should always standby near the bleed main valve during
this work) and set the N/C selector at the "NORMAL" position.
3) The bleed valve of the separator tank opens automatically, gas in the separator tank is released to
the slop tank through the bleed line and the separator tank level rises. When releasing the gas in the
separator to the slop tank, ensure that the stop valve in the bleed line on top of the separator is
slightly open. If the opening of the stop valve is overlooked, the gas pressure in the bleed line may
rise, the U-seal of the U-sealed pipe in the vacuum pump unit may rupture and inert gas may be
released into the pump room.
4) If the separator tank level does not rise above 50% after performing the operation above, set the
control switch at the "AUTO" position.
5) The vacuum pump starts up automatically (if the separator tank level is below 50%, vacuum pump
starts automatically), and oil is filled in the separator tank.
6) When the separator tank level rises above 70%, the vacuum pump stops automatically.
1) After receiving the request from the CCR, the Engine Department should start the pump at the
minimum rpm (about 50% of the rated rpm, pump rpm about 600).
2) After receiving the notification from the Engine Department that all preparations for using the
pump have been completed (minimum rpm), the operation should be started from the CCR or on
site.The number of oil delivery tanks should be restricted to one, considering the difference in level
between tanks.
3) The proper working of the governor should be confirmed with the pump discharge valve in the
shut-off condition. This operation is to confirm that the pump rpm can be controlled from the CCR,
The governor operation:
* In the clockwise direction when the rpm is raised
* In the counterclockwise direction when the rpm is reduced.
and is generally referred to as "governor works, does not work."
4) Confirm that the discharge valve shut-off pressure at minimum rpm is about 0.4 MPa to 0.5 MPa
(about 4 kg/cm2 to 5 kg/cm2). If the shut-off pressure of the discharge valve is excessively low, then
the bleeding of air generally becomes inadequate when the discharge pressure/rpm fluctuates.
1) Slightly raise the governor of the pump, and slightly open the discharge valve while maintaining
the discharge pressure at about 0.5 MPa (about 5 kg/cm2). By slightly opening the discharge valve,
the intake pressure reduces and the pump rpm also reduces slightly (increase in load), therefore the
governor should be adjusted, if required.
a) The discharge pressure required in a VLCC is about 0.4 to 0.5 MPa (about 4 to 5 kg/cm2).
. From cargo pump to deck line About 30 m (0.3 mPa: 3 kg/cm2 approx.)
. From deck line to topmost part of Chiksan arm About 10m (0.1 mPa: 1kg/cm2
approx.)
. Piping resistance, back pressure, etc. Plus α
b) Differences in pump operation may be observed when discharging starts, depending on the
terminal. An example is described below. In such a case, the discharging should be performed
according to the discharging method of the terminal, except when there is a special reason to do
otherwise. It is important to understand that the operating method specific to a terminal has been
established based on valuable experience and actual implementations in the past.
(1) Set the rpm of all cargo pumps to be used at the minimum rpm at which the governor works
effectively.
(2) Gradually open the discharge valve while monitoring the manifold pressure.
(3) When there is no abnormality on the ship and on the shore, and when the inflow to the shore
reception tank is confirmed, open the discharge valve fully.
(4) Raise the pump rpm to adjust the pressure to the required manifold pressure.
(5) Check the flow rate on the receiving terminal side and make fine adjustments to the pump rpm.
(6) When the required discharging rate and the manifold pressure are attained, set the pump.
2) Confirm that the cargo oil has passed through the manifold (discharging has started), and has
flowed into the shore reception tank. Also confirm that there are no abnormalities in the manifold
pressure, oil leaks and vibrations.
If gas is mixed in the ship's discharge line or until the balance between the ship and the shore
stabilizes, vibrations may occur in the Chiksan arm. The discharging rate should not be increased until
this condition disappears.
3) If there is no abnormality in the ship and on shore, closely observe the pump rpm, the discharge
pressure, the intake pressure and the steam chest pressure. Raise the pump rpm while maintaining
the discharge pressure at 0.5 MPa (about 5 kg/cm2). Raise the pump rpm in steps of about 20,
which is the normal value. If the pump is operated abruptly, major problems such as tripping of the
boiler or generation of black smoke may occur. Therefore, operate the pump carefully.
4) Raise the pump rpm using the governor while opening the discharge valve in small steps.
The pump rpm when the discharge valve is fully open is about 850 to 900.
5) When the discharge valve has been opened to about 50%, no change in pressure occurs even if it is
opened further. If such a condition is observed, the discharge valve may be opened fully without
any problems. The butterfly valve should be operated based on the understanding that the pressure
changes abruptly in proportion to the flow rate due to the opening of the valve up to about 50%
opening of the valve.
The flow rate is restricted by the pressure when the discharge pressure is constant. Even if the discharge valve
is opened from 50% to 100%, no change in the flow rate is observed. However, if one of the two cargo pumps
in operation trips due to some reason, the discharge pressure of the pump in operation reduces, therefore the
discharge flow rate increases. (Refer to curves of pump characteristics in Fig. D-2-6.)
6) After fully opening the discharge valve, set the required rpm and manifold pressure while carefully
observing the intake pressure.
7) The operating method varies depending on various conditions from the start of pump operation
until the operation reaches a steady state. Consequently, the pump and the discharge valve should
be operated depending on the condition. For instance:
a) When the oil level in the ship's tank is adequate and back pressure exists (line up to the shore
terminal is filled with oil)
• The method of setting the pump at the minimum rpm, gradually opening the
discharge valve fully, raising the pump rpm if no abnormality exists and attaining the planned flow
rate or pressure
b) When the oil (water) level in the tank is adequately high and there is no back pressure (overboard
discharge, shore reception tank and lines are empty or nearly empty, clean ballast filled condition,
etc.)
• The method of operating while adjusting both the pump rpm and the discharge valve
c) If the oil level in the ship's tank is adequately high and the back pressure is extremely high (shore
reception tank installed at a high location, no non-return valve in the receiving line and back
pressure is acting up to the ship's manifold)
• The method of increasing pressure while adjusting both the pump rpm and the
discharge valve, opening the gate valve when the back pressure from the shore tank becomes the
same as the pressure and starting the discharging operation.
d) If the oil level in the ship's tank is low or very low, back pressure exists or it is very high
• The method of operating while adjusting both the pump rpm and the discharge valve
e) If the oil level in the ship's tank is low or very low, back pressure exists or does not exist
• The method of operating while adjusting both the pump rpm and the discharge valve
The guideline for discharge pressure for the operation while adjusting both pump rpm and discharge
valve is 0.5 MPa (about 5 kg/cm2). In this method, the operation is performed while maintaining this
pressure.
1) After starting the pump and 1-2 minutes after discharging, crack open the pump discharge valve at
the minimum rpm at which the governor works effectively, and confirm that there is no
abnormality.
2) If the pump discharge pressure, intake pressure, rpm and steam chest pressure start fluctuating,
close the discharge valve temporarily at the minimum rpm at which the governor works effectively.
Then repeat the procedure "crack open/shut" two to three times and remove the gas.
1) At the start of the discharging operation, confirm that cargo oil passes through the manifold and
flows into the shore reception tank. It is also very important to check for changes in ullage in tanks
other than the delivery tank, manifold pressure and presence of vibrations or oil leaks.
2) Confirm that the operation can be performed normally after starting the pump and that the oxygen
concentration is less than 5%vol in the IGS. Push the IG supply button and change over to tank
supply. Make preparations beforehand for using the required number of inert gas fans since a
CASE 1 CASE 2
Start pump Start pump
↓ ↓
Check for pump abnormalities Check for pump abnormalities
↓ ↓
Complete terminal reception Complete terminal reception preparations
preparations
↓ ↓
Discharge to terminal OK Discharge to terminal OK
↓ ↓
Open gate valve Open pump discharge valve (adjust
degree of opening)
↓ ↓
Open pump discharge valve (adjust Increase pressure up to the ship side gate
degree of opening) valve
↓ ↓
Fully open pump discharge valve Confirm same pressure at ship and shore
↓
Open gate valve
↓
Fully open pump discharge valve
5) The cargo pump and ballast pump are centrifugal pumps. In principle, abnormal noise or vibrations
should not occur when these pumps are operating. The precaution for pump operation should be
considered based on : "Large abnormal noise or vibrations indicate that the permissible operating
range of the pump is being exceeded."
1) The method of starting the discharging operation sequentially at or near the minimum rpm soon
after starting the pump, and to raise the discharging rate to the specified rate after starting the
third and final pump.
2) If the time until the start of the final pump is short, run at no-load operation and raise the
discharging rate to the specified rate by running all pumps in parallel.
However, it may sometimes by required to operate additional pumps and perform the discharging
operation when discharging has already started with the operation of the first cargo pump. In such
a case, the conditions below may be considered.
1) When oil is required to be circulated in the discharge lines of the ship before starting
the discharging operation and there are restrictions in the number of pumps to be operated
2) When one-pump operation is required soon after the start of the discharging operation.
In both cases mentioned above, the procedure for starting the second and third pumps is the
same,, but adequate precautions mentioned later (refer to "2.1 Pump no-load operation" on P3-21
of the "Discharging Section) should be taken.
1) Fully open the pump discharge valve and start the pump.
2) Lower the rpm of the first pump already in operation to the minimum rpm, close the discharge
valve fully and run the pump at no-load operation. In this case, if an abnormality such as
suspension of the discharging operation occurs, the discharge valve should not be fully closed but
opened to about 10%.
3) When discharging is being continued with the first pump, back pressure acts on the outer side of the
discharge valves of the second and third pumps. Raise the rpm of the second pump slightly above
the minimum rpm, ensure a discharge pressure of slightly above 0.05MPa (about 0.5 kg/cm2) for
the first pump and then slightly open the discharge valve. Subsequently, adjust the discharge
pressure to coincide with the discharge pressure of the first pump.
4) Start the third pump by a procedure similar to that of the second pump.
5) After the third pump has started, make the discharge pressures of all the pump the same, check the
manifold pressure and flow rate, and adjust to obtain the planned discharge flow rate.
6) When two or more pumps are to the operated in parallel, all the pumps to be operated should be
adjusted to have the same discharge pressure.
1) Make the rpm of all pumps the same and avoid any unbalance.
2) Make the discharge pressures of all pumps the same. If the rpm is unbalanced because of intake
pressure, throttle the discharge valve of the pump with the low rpm and equalize the discharge
pressures.
3) If the parallel operation of the pumps is difficult (if the unbalance in the rpm and discharge
pressures of the pumps cannot be eliminated), stop one of the pumps and isolate the suction line.
After isolating the suction line, reduce the rpm of the pump with low intake pressure, throttle the
discharge valve, and equalize the discharge pressures of all the pumps.
1) Throttle the discharge valve. If the discharge or intake pressure varies, then the pump can
perform the discharging operation.
2) Even at the same rpm, the "defeated" phenomenon can be observed because of the relationship
between discharge pressure and line pressure. In this case, the steam chest pressure reduces (load
is small) since the "defeated" pump is not discharging the cargo.
1) Case 1
From main suction of slop tank (p/s) or 5C tank to pump
↓
Deck line
↓
Crossover line
↓
Eductor line in pump room
↓
Purge to the same tank
2) Case 2
Method of delivering oil from the cargo line to the same tank other than slop tank and 5C tank and
purging using the stripping line.
Furthermore, details of the method under the tentative conditions of oil circulation for purging gas are
described below (4.2.1 to 4.2.4).
6) Adjust the pump rpm and degree of opening of the discharge valve appropriately. Since more
attention is to be paid to the flow rate than the pressure during this work, the discharge valve will
be opened to a large extent. A pump discharge pressure of 0.4 mPa (about 4 kg/cm2) is adequate.
Therefore, care should be taken to prevent increasing the pump rpm excessively. An rpm of about
700 is a suitable value.
7) Adjust the pump rpm and the discharge pressure.
8) Each deck watch should lightly strike the pipe using a wooden hammer and confirm from the sound
that the all the ship's discharging lines have been filled with oil. At the same time, the terminal staff
should perform independent checks. Thus, both sides should confirm that gas purging has been
properly completed.
Check that ullage changes no longer occur and confirm that gas has been removed by observing the
steady suction pressure of the eductor in the CCR.
9) The gas in the pipeline is purged to 5C. There is no risk of overflow in this method since the oil
delivery tank and the oil receiving tank is the same tank. No abnormality due to mixing of gas
occurs in this tank because the suction bell mouth and the discharge line are installed at a safe
distance from each other.
Discharge valve of no. 1 and no. 2 cargo pumps V113, V123 Slightly open
6) The gas in the pipeline is purged to 3C. There is no risk of overflow in this method since the oil
Discharge valve of no. 1 and no. 2 cargo pumps V113, V123 Adjustment
8) Perform adjustments of pump rpm, discharge pressure, degree of opening of discharge valve
appropriately similar to the adjustments in Case 1.
9) Confirm the completion of gas purging similar to the procedure given in Case 1.
V.313 may be fully opened at the commencement of pump operation since the flow rate can be
adjusted using the direct filling valve.
4) Start the No. 1 cargo pump
5) Slightly open the discharge valve with the rpm of the cargo pump raised to 50 rpm above the
minimum rpm
6) Slightly open the discharge valves of No. 2 and No. 3 pump sequentially while monitoring the
pump discharge pressure.
7) Perform adjustments of pump rpm, discharge pressure, degree of opening of discharge valve
There is no risk of overflow in this method since the oil delivery tank and the receiving tank are the same.
However, since the suction valve and the discharge valve are the same, a part of the gas/liquid mixture is
probably returned to the tank with another part returned to the suction line. From our experience until now, no
problem has occurred in this method. A method that takes slightly more time than usual is a safe method.
Also, no abnormal changes have been observed in the pump during the work.
6) Purge the gas in the pipeline to the 3C tank and the suction line.
7) Adjust the pump rpm and the discharge valves V.113, V.123 and V.133.
1) If the grade of oil to be discharged in that in the slop tank is the same, the method of using the slop
tank as the suction tank and returning the oil to the same slop tank via the eductor line may be
adopted.
This method is commonly adopted when the slop tank can be used.
(Refer to "4.2.1 Oil circulation method Case 1" on P2-27 of the "Discharging Section.")
2) Another method is the purging of gas from the 3P/S tank via the drip line of the manifold. It is
commonly used for instance, during the line pressure tests but it can only be used with the
permission of the terminal. Also, it can be used only when the 3P/S is to be discharged first.
3) Although the method of purging gas from the gas intake valve installed at the crossover of the
manifold can be considered, it is extremely dangerous since the diameter of this line is very small.
This method should not be used. Moreover, the 3C tank should be discharged first.
1) After oil circulation, if the flow is to be stopped temporarily to review the valve lineup, throttle the
discharge valve while maintaining the pump at the minimum rpm, then close the valve to the
receiving tank. In this case, close the discharge valve first and then close the valve to the receiving
tank to prevent pressure surge.
2) Change over to valve lineup for discharging oil.
3) When valve lineup for receiving oil in shore tanks and valve lineup on the ship side have been
completed, open the gate valve and start discharging oil while communicating with the terminal.
4) According to MARPOL, the gas purging of lines should be performed by branching out a part of
the discharge when discharging from the slop tank or when discharging fresh oil at the final stage
of the discharging operation.