KAREN SDN BHD, a toy production company is continually active in designing new toys every
year. Its latest product is going to hit the market before the next new year holiday. The
production is scheduled to commence on the 1 January 2020. As a project manager, you are
required to plan and monitor the production using Microsoft Project software. Details of
summary tasks, subtasks and other relevant information are as follows:
1. Enter all the above information in the newly created Microsoft Project file.
2. Create a new milestone – Begin, before “Market analysis” to indicate the beginning of
the project and another milestone “End” after “Quality Control” at the end of the project.
3. Outlining all the tasks by indenting the sub-tasks from the Summary tasks.
4. Link all tasks accordingly.
5. Set all tasks to “Auto Schedule” and remove any constraints that prevent tasks from
being automatically scheduled.
QUESTION 1:
6. You are required to assign the resources to project tasks according to information
provided in the following table.
7. Both product designers and production engineer are paid based on number of working
hours whereas market analyst, research assistant and accountant receive fixed
payment for each task performed. You are required to assign the following variable costs
and fixed costs to the resources.
QUESTION 2:
8. You are required to create a new Calendar to incorporate the different working time and
assign the resources to this new calendar accordingly.
Resource SH Calendar
Product designer 1 MON-THURS: 8am-12pm, 1pm-5pm
Product designer 2 FRIDAY: 8am -12pm, 3pm-5pm
Production engineer
9. Once all the above have been accomplished you must track and save the baseline for
the project. Set the current date to 30 April 2020 and update the project as scheduled.
QUESTION 3:
In the following table state the tasks that are 100% completed.